Overview
Managing Contract Risks on Green Projects The Rise of Green Buildings Project Delivery Methods Mastering Form Agreements Drafting and Negotiating Contract Terms Understanding Insurance and Bonding
Approximately $8 billion worth of green construction in 2006 Grew to approximately $60 billion in 2010 Estimated $100-140 billion in 2013 Next three years:
By 2015
$554 billion to the national economy Green jobs will quadruple to 7.9 million
International Green Construction Code released last March Released last winter - commercial green building standard Replaces Standard 90.1-2007
Design-Bid-Build
Design-Build
Importance of Contract Forms Design and construction organizations are moving quickly to prepare standardized forms
Promote an industry standard Increase revenue
Forms vary significantly from organization to organization Hasty preparation = missing terms and concepts Understanding forms means opportunity to avoid green pitfalls
April 10, 2012
D503-2011 Sustainable Projects Guide Not a contract document, exhibit, or addendum that can be incorporated in whole into project contracts. Provides an overview of some of the key legal and contractual issues that can arise on projects that incorporate sustainable goals. Includes model contract language that can be added to:
B101-2007 Owner-Architect Agreement A101-Owner-Contractor Agreement A201-2007 General Conditions
April 10, 2012
AIA New Sustainable Projects Documents Set to be released in April or May 2012 Incorporation of model language into:
A101-2007 SP Owner/Contractor B101-2007 SP Owner/Architect A201-2007 SP General Conditions C401-2007 SP Architect/Consultant A401-2007 SP Contractor/Subcontractor
ConsensusDOCS - 310
Not a stand alone contract Assumes design-bid-build Invents new nomenclature: Green Building Facilitator
Default = Architect
Green Measures
Physical those incorporated in Plans and Specs as part of design. Procedural means and methods in performance of work.
ConsensusDOCS - 310
Remedy Provision: Moves all tax and financial consequences (i. e. the cost savings) into the category of consequential damages that are subject to waivers of such damages in other construction documents. Missing Terms: Green Guarantee Disclaimer of warranties Payment of GBF Completion Issues
Failed Green Certifications Green construction is regular construction risk with a twist.
April 10, 2012
Lack of Precedent
No appellate case law to date. Limited LEEDigation: Only a few reported cases containing green issues:
Southern Builders v. Shaw Development (MD) Tax credits Poor contract drafting DestinyUSA (NY) Tax/Bond credits, False promises ACHRI v. City of Albuquerque (NM) ACHRI sued to prevent ordinance imposing energy eff. stds. Gidumal v. Site 16/17 Development (NY) Misrepresentation of LEED goals and energy performance
April 10, 2012
Is it an objective standard?
It should be!
Sample Provision: Owner's Desired LEED Certification is LEED Certification at the Gold Level under the USGBCs LEED for New Construction Rating System, version 3.0 - 2009. The LEED Responsibility Matrix [Dated/Version], which is attached hereto as Exhibit A identifies the Prerequisites applicable to the Project as well as the Credits the Owner has decided to pursue for the Project.
April 10, 2012
Green Guarantees
Owners Perspective:
A guarantee is ideal (but may not be realistic) Any contract with the word guarantee creates an uninsurable risk and cannot be accepted. Do not guarantee any level of certification. There are too many factors outside the contractors control. At most, contractors should accept responsibility for the contractor responsible credits.
Designers Perspective:
Contractors Perspective:
Green Guarantees
Often guarantees are not express or clear:
Example: Southern Builders, Inc. v. Shaw Development LLC
Project Specs: Project is designed to comply with a Silver Certification Level according to the U.S. Green Building Councils Leadership in Energy & Environmental Design (LEED Rating System, as specified in Division 1 Section LEED Requirements.
The Contractor shall perform the Sustainable Measures required to be performed by the Contractor in accordance with the Contract Documents, however, nothing contained in this Section 3.5 shall be construed as a guarantee or warranty by the Contractor that the Project will achieve the Sustainable Objective.
April 10, 2012
lost rents, loss of tax credits, damage to reputation, down or idle time, interest and finance charges, material escalation costs, depreciation, rental costs, additional energy costs, loss of productivity and efficiency
Contractors Perspective: Contractors should insist upon a mutual waiver on green projects. Shaw Development is a good example of the exposure a contractor may face (i.e. tax credits)
Substantial Completion
Owners Perspective: Will try to tie certification to substantial completion. Designers Perspective: LEED Certification is on a different timeline from building completion and occupancy. Contractors Perspective: Contractors should not allow substantial completion to be tied to certification. Certification could take months and include appeals. This may occur while the owner is occupying the building and receiving the benefit of its use.
April 10, 2012
Substantial Completion
Sample provision:
Substantial Completion:
This provision specifically overrides any and all provisions dealing with Substantial Completion in other Contract Documents. Substantial Completion is the stage in the progress of the Project when the Project or designated portion thereof is sufficiently complete so that the Owner can occupy or utilize the Project for its intended use. Substantial Completion does not depend upon achieving the Desired LEED Certification.
Sample provisions:
Final Completion:
Final Completion occurs when the Project reaches final completion under the Contract Documents, however, Final Completion does not depend upon achieving the Desired LEED Certification. The Owner may retain 2.5% of the entire Project cost until the Green Building Certification Institute determines Certification, if any.
Only agree to part two if the owner insists upon some protection.
April 10, 2012
Standard of Care
Changes with the profession as practices and competencies change. Best practices of yesterday are the minimum standards of today As green products and processes surge, A/Es saddled with working knowledge of these New AIA ethics standard: promote sustainable design and development principles in their professional activities.
Single ply TPO roof (10 years) vs. BUR (30 years)
Standard of Care
Derived from statute:
P.E. must use reasonable professional skill, judgment and diligence normally rendered by professional engineers in the practice of professional engineering implied in every contract
Material Substitutions
Do not allow material substitutions without written change from all necessary parties (Owner/Architect). Risk of inadvertently losing LEED credits. Designers and Contractors - be cautious in proposing material changes. Make sure you know how it will affect credits. Proposed language in AIA - D503:
Burden on contractor to determine affect Architects entitled to rely on contractors statements
Contractors should get specific approval from Owner and Designer BEFORE substituting materials.
April 10, 2012
Material Substitutions
Beware of brand name or its equivalent specifications Consider using standard form to evaluate material substitutions:
Sample Matrix
Sample Matrix #2
Could be as simple as:
EXHIBIT A LEED CERTIFICATION RESPONSIBILITY MATRIX Prerequisite or Credit Design Responsibility Contractor Responsibility Owner Responsibility Documentation Responsibility
Provide that a subcontractor/subconsultant is bound to the contractor/DPOR in the same fashion as the contractor/DPOR is bound to the owner in the prime contract. Help to ensure that the subcontractor's obligations to the contractor mirror the contractor's obligations to the owner. Flow Down Mistake:
Subcontractor brings high VOC paint on site; Unable to obtain EQ Credit 4.2 which costs the project Silver Certification; Owner needed at least LEED Silver for tax credits and sues; If Sub was not bound to same standards, contractor may end up holding the bag
Indemnification Provisions
Owners unrealized expectations = claims and lawsuits Attempt to pass liability to the party most responsible for the loss Indemnify: To protect against damage, loss, or injury Best used in conjunction with a flow down provision Be aware of embedded indemnification provisions
Indemnification Provisions
Green/Sustainable Project. Subcontractor shall defend and indemnify Contractor against all costs, expenses, damages and liability, including without limitation, legal fees and expenses resulting from any failure of the Project to achieve the Owners desired green or sustainable building certification or goals, but only to the extent that such failure to achieve certification or goals results from any fault or neglect or act of the Subcontractor in the performance of the Work, or the fault or neglect or act of any entity for
Bond companies are taking position that green certifications are not covered by bonds. Insurance companies are taking position of wait and see according to the 2010 Marsh Report Coverage for green product failures?
Questions?
Thank You
Logan A. Hollobaugh, LEED AP Ogletree, Deakins, Nash, Smoak & Stewart, P.C. (312) 558-1429 logan.hollobaugh@odnss.com Matthew J. Straub Ogletree, Deakins, Nash, Smoak & Stewart, P.C. (312) 558-1424 matthew.straub@odnss.com