Portfolio Area
Project location
The project is developed through the SPV Green Solar Power;
The location is represented by one land plot with an area of 15 Ha; The estimated installed capacity is 8 MWp; Average GHR radiation in site is of 1443 KWh/m; The access to the site is assured by a European road (E574/DN65) and a exploitation road (2,4 KM from asphalt to the entry in the site);
Site photos
The solution study for grid connection has been approved and the grid connection permit (ATR) has been issued at the End of February 2012;
Prefeasibility Study
Land rights
Certificate of urbanism
Environmental Approval
The project has obtained all the necessary permits and approvals;
Location Permit
Technical Details
Bobicesti Location/SPV Installed Capacity (MW) 8.0
15
0.8
1400-1480
1250-1270
Mounting System
fixed tilt
Transmission Line
UGL
Substation
20 kV
The Developer
is one of the most important producers of LV and MV equipment as well as and integrated solutions. The company is structured in several business units: Low Voltage, Medium Voltage, Power Distribution Equipment, Turnkey Projects, Steel parts, Maintenance
Over 36 Mil Euro turnover and over 350 employees at the end of 2011 As secondary fields of activity the company operates in: Industry (Chemical and petrochemical, Metal processing , Industrial appliances, Food processing, Transportation and others) Real Estate (Industrial and Residential) Entered the renewable energy market in 2010 with the intention of capitalizing on the electrical works and project management expertize The company holds the following certificates: Certificate for electrical works issued by National Authority for the Energy Regulation (ANRE); Certificate of registered supplier for TRANSELECTRICA, ELECTRICA and E-ON Moldova; Authorization for land improvement projects (civil works and installation and commissioning works) issued by the Agriculture, Woods and Rural Development Ministry Turnover evolution (MIL. EURO)
Project structure
INVESTOR 1
Developers
INVESTOR 2
New investor at fully permitted stage
Project Companies
The deal structure can be flexible as the projects can be acquired individually or as a pipeline depending on the investors
Power Suppliers
Penalty for quota unfulfillment
Quotas for the post-2020 period will be defined later by the Government, but will be no lower than the 2020 quota; Penalty for electricity suppliers that are unable to fulfill the mandatory quotas is set at EUR 110; Currently there is a significant undersupply of GCs needed to achieve the renewable share in generation mix; Secondary legislation elaborated by ANRE (The National Regulatory Authority) was approved in early November 2011; Thus for the first time Romania has an attractive and applicable supporting mechanism for renewables.