Infrastructure projects are complex, capital intensive and with long gestation period, posing multiple and unique risks to project financiers. Private investment in infrastructure in India over the past decade has not been up to the expectation, and there is a need for Public-Private Partnerships (PPPs) to play a much greater role than before. The paper analyzes the reasons for private financing not making its way into the different infrastructure segments, and examines the key constraints to private financing. It also suggests ways to mitigate these constraints for a sustained private investment in the Indian infrastructure.
Introduction
Infrastructure projects are complex, capital intensive, having long gestation period and involve multiple risks to the project participants. In many countries shortage of public funds have forced the government to enter into a long-term contractual agreement for financing construction and operation of infrastructure projects. A Public-Private Partnership (PPP) can be defined as private sector financiers of construction and operation of infrastructure projects, which would have been otherwise provided by the public sector. PPP structures are typically more complex than the traditional public procurement projects, and their complexity is due to the number of parties involved and the mechanism used to share the risk. PPP projects are characterized by non-recourse or limited-recourse financing, where lenders are repaid from only the revenues generated by the projects. The concessionaire is a special purpose vehicle in which the sponsoring entities are not responsible for the repayments of loans. These projects have a capital cost during constructions and a low operating cost afterwards, which implies that the initial financing costs are very large compared to the total cost. Further, a mix of financial and contractual arrangements amongst the multiple parties including the commercial banks, project sponsorers, domestic and international financial institutions and government agencies makes it further complex.
* ** Research Scholar, JIIT, A-10, Sector 62, Noida 201303, Uttar Pradesh, India. E-mail:gitmcollege@yahoo.co.in Associate Professor and HOD, JIIT, A-10, Sector 62, Noida 201303, Uttar Pradesh, India. Email: aayushi.gupta@jiit.ac.in *** Former Vice Chancellor, RGPV, Bhopal, and Director, AHL, Bhopal, HX 95 E7 Arera Colony, Bhopal, India. Email: mcgupta2000@yahoo.co.in 52 2011 IUP. All Rights Reserved. The IUP Journal of Infrastructure, Vol. IX, No. 1, 2011
In recent years, efforts have been made by the Government of India to increase the private investment in infrastructure. While Indias performance in increasing the investment is encouraging, about two-thirds of the investment has gone to the telecommunication sector since 2001. India realized sufficient investment in the transport sector but the investment in energy, water supply and sanitation has not yet picked up noticeably. Even at this rate India is well behind the other countries in attracting private investment. Financing gaps in infrastructure up to the year 2010-2011 have been estimated by the Planning Commission of India, and are provided in Table 1. To meet this funding gap, innovative financing models are needed to make economically essential projects commercially viable and allow active private sector participation to facilitate private sector efficiency in Indias infrastructure development. The paper examines key constraints to private financing of infrastructure, fiscal barriers and deficiencies in the government policies and regulatory framework. It further suggests practical ways to attract sustained private investment in infrastructure development. Table 1: Overall Financing Gap in Infrastructure Up To 2010-11( Billion)
Sectors Roads Power Telecommunications Railways Airports Ports Total Investment Needed 4,670 10,591 2,143 1,242 191 306 19,143
Source: Planning Commission
Shareholder Agreement
Lenders
Loan Agreement
Franchisee
Suppliers
Design-Construct Consortium
Major risks a project sponsor faces are: political, financial, constructional, operational, and market risks. The risks can be broadly classified into: (1) Elemental risks comprising physical, design, construction, operation and maintenance, technology, finance and revenue generation risks; and (2) global risks comprising political, legal, commercial and environmental risks (Merna and Smith, 1996). BOT type project assumes a much broader scope of risks than a mere contractor in a traditional design-bid-build contract. It is because of many responsibilities undertaken and the broad scope of risks assumed by the concessionaire, and the characteristics of nonrecourse or limited-recourse financing. A strong financial capability and ability of the concessionaire to manage the long-term financing of the project through innovative financing strategies is an important prerequisite for the successful development of a BOT type project.
Equity can be provided by project promoters or financial investors. In an infrastructure project, financing equity mainly shoulders the greatest level of operational, financial and market risks. In the initial stages, mostly it comes from the sponsors but the ability of the sponsors to get it from the primary market remains limited. In the longer term, equity finance from financial investors such as venture capital funds and other institutional investors can prove to be critical as the sponsors equity is consumed at early stages and not recycled quickly enough due to lack of refinancing options. At present equity financing by institutional investors has the following major constraints. Limited Exit Options: While investing in infrastructure, financial investors are interested to know the exit options. The best route to exit from the equity is to sell the stake to the sponsors through a put option. However, in India such agreements are not easy and require the permission from the government for an unlisted company. This creates uncertainty. Exit option prevents investors in financing a privately managed infrastructure project. Shallow Capital Market and Corporate Governance Issues: Infrastructure project developers are mostly construction companies, equipment suppliers or operational services companies. Return for these companies on their investment comes from additional business generated from the project and not by the project. Transparency in disclosures and misuse of corporate assets are key problems for retail investors to keep them away from such projects. Minority shareholders, therefore, suffer and lose out in such situations.
the estimates of the Bank for International Settlements (BIS), the size of Indias corporate bond market was 0.3% of nominal GDP in Dec 2003, much lower than that of Malaysia 43.3% or South Korea 27.7% (World Bank, June 2006, p. 31).
Other Constraints
The financial sector related factors which have been identified as above mainly prevent private investment in infrastructure. However, the sector policy and regulatory framework are also closely linked to these funding issues. The main constraints other than financial sector related are as under:
Fiscal barriers to private financing of infrastructure. Approvals, red tape and inadequate administrative capacity. Multiple clearances. Lack of coordination between departments. Delays in award of contract. Limited capacity within government to execute PPPs in infrastructure. Poor infrastructure regulations. Recommendations for Private Financing to Infrastructure
PPPs can play much important role in bridging the financial gap for building the requisite infrastructure. Suggestions for mitigating the key constraints to private financing of infrastructure are given as under:
Developing a well developed government bond market. Investment policy and regulatory guidelines to insurance companies, pension
funds, mutual funds and other financial institutions for participation in infrastructure financing.
Make transactions transparent, clear, predictable and competitive. Government should create a stable, transparent and fast acting regulatory
environment.
Conclusion
India faces large financing gap which can be bridged only by active private participation in building the necessary infrastructure. Reforms that facilitate the use of various financing instruments by investors are needed. However, the funding issues are closely linked to sector policies and regulatory frameworks and therefore, private investment will also require that the fiscal barriers, red tape and professional inefficiencies should also be addressed properly. Increased private financing for infrastructure on a sustained basis will require governments proactive role and policies to provide wide spread reforms in infrastructure that will go beyond the financial sector.
Bibliography
1. Merna A and Smith N J (1996), Guide to the Preparation and Evaluation of Build-Own-Operate-Transfer (BOOT) Project Tenders, Asia Law and Practice, Hong Kong. 2. Shen L Y, Li Q M, Drew D and Shen Q P (2004), Awarding Construction Contracts on Multicriteria Basis in China, Journal of Construction Engineering and Management, ASCE, Vol.130, No. 3, pp. 385-393. 3. Tiong R L K and Alum J (1997), Evaluation of Proposals for BOT Projects, International Journal of Project Management, Vol. 15, No. 2, pp. 67-72. 4. World Bank (2006), Financing Infrastructure: Addressing Constraints and Challenges, World Bank, p. 6.
Reference # 27J-2011-03-03-01
57
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.