On the completion of this unit you will be able to: Coordinate and supervise the preparing of a progress claim Select an appropriate method for evaluating a progress claim Assess and verify a sub-contractors progress claim
Progress Claims
The aim of a progress claim is to claim for the progressively increasing value of work completed to date. There will be many progress claims during a project. On a job of short duration there may be only two or three payments claimed by a builder: First, maybe a deposit, secondly, a progressive payment for work complete to that point. finally, the total value of work completed. You can see why the middle or interim payment is called a progress payment.
Progress Claims
Who would prepare a progress claim: The progress claim is prepared by the builder and submitted to the proprietor. The builder may delegate the actual work of preparation to a building cadet, leading hand, general foreman or contract administrator. A progress claim would also be prepared by a subcontractor and submitted to the head contractor or builder. The subcontractor may also delegate actual preparation or gathering of information to a responsible employee. Regardless of who carries out the work, the same process is adopted as described in this section.
Progress Claims
Time for issuing a progress claim The claim would be completed ready for submission to the proprietor, or to the builder in the case of a subcontractor, at the time stated in the contract conditions. Often this is on the 28th day of the month, because every month has a 28th day. The contract conditions may state that where that day is either a Saturday, Sunday or public holiday, the progress claim should be submitted on the preceding working day.
Progress Claims
It is necessary to closely consult the contract conditions for this information. Usually a progress claim will be submitted once a month. This allows valuation of the whole of the work up to that point. The end of the month is a very convenient point in time to value completed work. The end of the month may coincide with the end of the financial or calendar year.
Progress Claims
In the housing industry it is common practice to agree on the completion of a stage of construction as the time for submitting a progress claim. It is also common practice to agree on the value of the claims prior to signing a contract. Appendix 2 HIA Residential Building Contract Item 13 Progress Payments Clause 12 In the housing industry many sub-contractors submit progress claims more frequently than monthly. This needs to be considered in the builders cash flow programme, as some payments will need to be made before the builder receives a progress payment from the client
Progress Claims
Information required for a progress claim:
There is much basic information required before cost information is required. Building companys name Proprietors name Project name and address Date Progress claim number.
Progress Claims
Building companys name The building companys name must be the same as that shown on the contract conditions. Some companies have a different trading name to the company namefor example, OTEN Building Pty Ltd trading as Strathfield Builders. Here, OTEN Building Pty Ltd is a legal entity recognised by the Australian Securities Commission (ASC) and the Australian Taxation Office (ATO). Strathfield Builders may be a registered business name, but does not have the same legal standing and should not be used.
Progress Claims
Proprietors name The proprietors name must always be used. If there is an architect supervising the project, you must still address the progress claim to the proprietor. In this instance the architect will be acting as the proprietors agent and will not be making payment. Therefore, address the progress claim to the person or company that will be making the payment and whose name appears as the other party on the contract conditions.
Progress Claims
Project name and address It is important to distinguish between similar projects. For example, the company could be upgrading two different premises in the same street. The reference number given to the project would help when entering project cost and payment details in a computer record. Date The date of preparation and submission should be shown to prove compliance with the contract conditions. Should there be any delay in payment, the date of submission can be seen for the possible calculation of interest on late payments.
Progress Claims
Progress claim number Showing the claim number distinguishes one claim from another. This allows quick reference to be made in communications. It is also useful in ensuring that payments to subcontractors are made from the correct claim. For example, if a subcontractors claim was included in the builders claim No. 12, no payment should be made to that subcontractor until payment for claim No.12 is received. This ensures that the builder does not overspend. Note in some instances the proprietor may request an affidavit stating that all payments have been made in relation to the claim prior to making the payment
Progress Claims
Progress Claims
Methods of assessing the value of work completed Work may be valued by a number of methods: Measure the work completed since the last progress claim. Measure the total work completed since the commencement of the works. Determine a percentage of each work item completed since the commencement of the works. Determine a percentage of large areas of the works since the works commenced.
Progress Claims
Methods of assessing the value of work completed Method 1 Measure the work completed since the last progress claim should be avoided, because it is often very difficult to establish where the work was measured to at the last claim unless drawings are kept, and colour or some other method has been used to mark in each new measurement.
Progress Claims
Methods of assessing the value of work completed Method 2 Measure the total work completed since the commencement of the works is very accurate but it is a long and time-consuming measuring exercise to establish a value. This is likely to be warranted in many circumstances where accurate payment for work is necessary.
Progress Claims
Methods of assessing the value of work completed Method 3 Determine a percentage of each work item completed since the commencement of the works is similar to method 2. This does not have the same degree of accuracy but requires substantially less time. This method is the most efficient methodtime is reduced and little accuracy is sacrificed. Experience is required to adequately assess percentages speedily but work missed in a previous valuation may easily by included.
Progress Claims
Methods of assessing the value of work completed Method 4 Determine a percentage of large areas of the works since the works commenced is very quick and should only be carried out by those with long experience of the trades involved. It is best used as a check of claims carried out by others (eg a clerk of works checking through a builders progress claim).
Progress Claims
Methods of assessing the value of work completed Method 5 Agreed value of stage complete This progress payment method is common to the housing industry. It requires a schedule of an agreed value to be paid at predetermined stages of construction, eg 30 % of the total construction value payable at the completion of the floor slab. See item 13 Appendix 2
Progress Claims
Methods of assessing the value of work completed Set-out of a progress claim The progress claim should contain three components: A covering letter The progress claim summary A complete breakdown showing detail of how the figures on the summary were achieved.
Progress Claims
Methods of assessing the value of work completed Set-out of a progress claim The progress claim should contain three components: A covering letter The progress claim summary A complete breakdown showing detail of how the figures on the summary were achieved.
Progress Claims
Bills of quantities provided by the client are not common to the housing industry. A bill of quantities is prepared as part of the estimating process by the builder. It is good practice to use this as a check on as built quantities.