Drying of pipelines prior to commissioning

DRYING OF PIPELINES PRIOR TO COMMISSIONING


The water inside the operating pipeline is a source of many problems. The company CEPS can perfectly dry itdrying of pipelines it performs prior to putting it into operation by the extremely pre-dried air and also vacuum.

ON THIS PAGE

Reasons for drying of gas pipelines after construction Sources of water inside pipelines Pipeline drying using deeply predried air Vacuum drying
GO TO THE RELATED ITEMS

Reasons for drying of gas pipelines after construction


Water inside a gas pipeline in operation causes a number of problems. In medium-pressure gas pipelines, house pressure regulators tend to freeze in winter, which is very unpleasant both for the customer, who is suddenly deprived of heating and for the gas company because emergency crews need to go out to the field to repair this, which influences the economics of gas supplies. In high-pressure pipelines, complications with natural gas hydrates tend to form in addition to the problems with pressure regulating stations. The hydrates may clog even a large diameter pipe. In addition to this operational trouble, water in highpressure pipelines primarily poses a direct risk of failure. Internal corrosion caused by free water has been already detected in many pipelines. However, it is only recently that a much more dangerous consequence of free water has been proved in gas pipelines transporting normally treated natural gasinternal stress corrosion cracking ( SCC) which, in a relatively short time of operation (several

Products Information about Company Contacts


DOWNLOADS

Product catalogue PDF for screen (464 kB) Product catalogue PDF for print (1746 kB)

www.ceps-as.cz/en/products/drying-of-pipelines.html

1/6

3/25/13

Drying of pipelines prior to commissioning CEPS a.s.

years), may cause a complete failure of extensive stretches of the line. At the same time there is no reliable method at present to detect the creation and beginnings of SCC development on the inside of the pipe wall.

Sources of water inside pipelines


Water enters a pipeline before putting into operation usually due to lack of discipline at work during construction. In some cases, the reason may be the construction technology itself, for example where underground river crossings are laid which requires that the pipe is flooded with water. Hydrotests or stresstests are another stage of construction when water enters a pipe. This is evident when the tests are carried out using water but we should not ignore tightness-tests using air when water contained in air condenses in the pipe after the air is compressed. Although some of the water is removed from the pipeline when it is cleaned, a significant proportion of water cannot be removed from the pipeline even when repeatedly applying mechanical cleaning techniques using water-absorbing cleaning pigs because the water adheres to the pipe walls due to capillary forces. This water can only be removed by special drying techniques. CEPS carries out pipe drying before commissioning, using both methods that are currently used throughout the worlddeeply pre-dried air and vacuum drying. Both of these technologies can also be deployed for drying other pipelines facilities (metering stations, interconnecting nodes, etc.) or even pieces of equipment requiring a high level of dryness (chemical apparatuses, high-performance steam turbines, etc.).

Generator of very dry air JUV 3600 allows to dry up to 3600 m of air per hour pipeline DN 1000 with a length of 10 to 15 km can be dried in one to two days

pipeline drying using deeply pre-dried air

Pipeline drying using deeply pre-dried air


This technique is suitable for pipes made of steel and plastic materials, and also for process equipment. At first step the air is dried to a temperature of water dew point below 80 C in a special unit based on a molecular sieve, and then blown into the pipeline for being dried. The water, which is present in the line evaporates into the pre-dried air, and in this air is carried to outside the pipeline. CEPS has two big units available. Each unit has a drying capacity of one cubic metre

www.ceps-as.cz/en/products/drying-of-pipelines.html

2/6

3/25/13

Drying of pipelines prior to commissioning CEPS a.s.

of air per second, i.e. 3,600 cu. m/hour. This is sufficient capacity to dry a pipeline having a nominal diameter DN 1000 (40 in.) and a length of 10 to 15 km in one or two days. In case of need (particularly to speed up the drying process) both units can be connected in parallel. Both units are housed in containers and are transported on off-road vehicles capable to manage the navigation throughout the difficult terrain, and therefore can be transported over the construction strip (r.o.w). The third one, smaller unit has a capacity of drying 650 cubic metre of air per hour and is used for drying of low profile pipelines.

Very dry air generator JUV 650 The units operating pressure of 4 to 8 bar is strong enough to push porous cleaning pigs through the pipe during the drying process, which helps to achieve the high rate of drying. At forked/branched pipelines or those whose dimension changes significantly, or in process equipment, i.e. wherever the porous elements cannot be pushed through the equipment, the drying takes a proportionately longer time. The drying of a complex pipeline node, after the hydrotest or stresstest water has been simply released, would take several days. Pipes are dried to the standard level of the temperature of water dew point in the pipe of minus 20 C. However, in case of need, particularly for process equipment, up to minus 70 C can be achieved.

vacuum drying

Vacuum drying
Vacuum drying is based on a generally known physical phenomenonas the pressure drops, also the boiling point of liquids drops. At an absolute pressure of about 2 kPa, water boils at the temperature of the soil that surrounds the pipe.

www.ceps-as.cz/en/products/drying-of-pipelines.html

3/6

3/25/13

Drying of pipelines prior to commissioning CEPS a.s.

The drying process by this method should be very carefully followed because at too high pumping speed of the out coming air, pipeline is not sufficient to complement the evaporative heat of water supply through the wall of pipe, but instead the evaporative heat is taken from the water inside the pipe, which causes its cooling. This phenomenon consequently does not lead to the evaporation of water but water inside pipe freezes. The pipeline then apparently acts as dry, but after putting into operation ice gradually melts and the problems with water appears again. Therefore it is necessary follow carefully process of drying, including control dead time. This dwell time when pumping is stopped, which is repeated according to pipeline diameter prevents water freezing. These dwell times the other hand significantly prolong the drying time.

Vacuum drying is also suitable for a complicated internal piping The vacuum drying is suitable particularly for branched steel pipes and pipeline facilities. For pipes having a nominal diameter of more than DN 500 (20 in.), the geometric stability of the pipes under deep vacuum always needs to be assessed. This technique now cannot be employed with plastic pipesapplication of method for this purpose requires to perform the certification tests that are currently carried out. In comparison with drying based on deeply pre dried air supported by porous pigs pushed through the pipe, vacuum drying is slower. However, where the porous elements cannot be used, vacuum drying may even be faster for more complex pipeline nodes. CEPS operates several vacuum units, each one with the capacity of up to 200 cu. m/hour. In case of need, the units can work in parallel. Vacuum drying is very appropriate for drying complexly shaped distribution network pipes, because in addition to the drying itself, it also makes the first gas admittance into the pipes much easier. The gas is flowing into vacuum and therefore there is no risk of forming an explosive mixture in the pipe, and the pipe does not need to be deaerated. Both technologies of pipeline drying used by CEPS, meet the requirements of TPG 702 13.

related products
Together with this product are usually
www.ceps-as.cz/en/products/drying-of-pipelines.html

Cleaning and gauging of pipelines

Stresstests and hydrotests of high-pressure pipelines

4/6

3/25/13

Drying of pipelines prior to commissioning CEPS a.s.

provided the following products and services all products

High-pressure steel pipelines rehabilitation after long-time of operation

Decontamination of pipelines transporting petroleum liquids before repairs or shutdowns

Products and services show all products and services

related documents
More documents and other information, see the section about the company CEPS all about company

ISO 9001:2008 ISO 14001:2004 OHSAS 18001:2007 ISO 3834-2:2005

About CEPS company show everything about the company CEPS

contact
If you have any questions, do not hesitate to contact technical experts and business persons of CEPS Contact us

Ing. Ale Brynych executive director phone +420 241 021 547 ceps@ceps-as.cz

Ing. Bc. Ale Crha commercial director and welding engineer phone +420 241 021 549 ceps@ceps-as.cz

Head office of CEPS a.s. phone +420 241 021 511 fax +420 241 021 512
www.ceps-as.cz/en/products/drying-of-pipelines.html 5/6

3/25/13

Drying of pipelines prior to commissioning CEPS a.s.

e-mail ceps@ceps-as.cz all contacts and maps

2013 CEPS a.s. / RSS Contacts ba ck to top

/ Genera l terms a nd condi ti ons CZ / Techni ca l s peci fi ca ti ons CZ /

www.ceps-as.cz/en/products/drying-of-pipelines.html

6/6

Anda mungkin juga menyukai