O.S.P.I. 2 Aspen Court Boynton Beach, FL. 33436 Tele: 561-734-6127 Fax: 561-736-7919
03A
Sub Bids
12,402,442 3,472,786 2,858,581 1,133,408 3,253,865 Ticket Total
O.P.S.I. Budget
12,402,442 3,500,781 2,869,560 1,271,297 3,325,366
15
23,369,447
Subcontractor Used
23,369,447
23,121,082
"A"
Sub/Supplier Addendums MWBE Status Base Quote Description Off-Site Parking Condo Insurance Layout and survey from control points Lifting, hoisting and material placement Install Safety Cabeling at decks Excavate for this Scope of Work. Submittals / Engineering Excavation / Backfill / Compaction / Fine Grading Foundations / Footings / Pads / Mats Keyways at Footings D/A8.6 Elevator pit / Keyway / Water Stop 6 Mil Visqueen and WW Mesh Soil Poisoning & Certificate Material Handling Equipment Scaffolding Slab on Grade / Construction Joints / Saw Cuts Expansion Joints Form, Place & Finish Crane/Hoist Pads Form, Place & Finish Equip. Pads Garage Ramps Form Columns / Shearwalls Pool Deck / Planters Secondary pour at pool deck and planters Clock Tower Concrete Masonry Walls & Planters Fill Masonry Cells / Bond Beams / Lentils with Grout Beams / Curbs / Knee walls / Parapets / Window Sills Elevated Decks / Mezzanines Quantity UOM U$
Budget
"A"
"B"
"C"
23,051,000 Cost $
24,120,000
26,861,617
$ 3,523 $ $
15,000
such as: Subcontractor Scope Reviews, Pre-constructibility Reviews with R.F.I. publishings and Change Order Management.
1,400.00 sqft $ 3,523 $ $ 25,000 3,523 $
3,523
25,000
3,253,865
SCOPE SHEETS
O.S.P.I. 2 Aspen Court Boynton Beach, FL. 33436 Tele: 561-734-6127 Fax: 561-736-7919
Page 2
Budget "A" In Paving $ $ No No 134,091 21,996 "B"
03A
"C"
15
2,567
2,567
2,567
tons $ tons tons tons sqft lbs 25,000 $ 1,313 3,000 tons
1,313
205,690
1,140
each
75
SCOPE SHEETS
O.S.P.I. 2 Aspen Court Boynton Beach, FL. 33436 Tele: 561-734-6127 Fax: 561-736-7919
Page 3
Budget "A" "B"
03A
"C"
15
Styrofoam Forming where indicated HSS-1 (4" x 4" x 1/4") Balcony Columns Sheath Roof Trusses Units Wood Fascia Seat Wall Site Planter Masonry
$ $ $
20,877 94,080
SUBTOTALS TOTALS
$ $ $ $
$ $
23,369,447 23,369,447
$ $
24,291,334 24,291,334
$ $
30,503,626 30,503,626
$ $
$ -
Accept
23,369,447
24,291,334
30,503,626
Adjusted Total
23,369,447
24,291,334
30,503,626
SCOPE SHEETS
O.S.P.I. 2 Aspen Court Boynton Beach, FL. 33436 Tele: 561-734-6127 Fax: 561-736-7919
Reinforcing
Alternates:
03B
Ticket Total
16
0
Subcontractor Used Budget
Sub/Supplier Addendums MWBE Status Base Quote Description Quantity UOM U$ $ 12.19 ton 0.80 ton 0.90 ton 2.50 ton 6.72 ton 0.39 ton 10.80 ton 1.05 ton 0.25 ton 35.60 ton $ $ $ $ $ $ $ $ $ $ 15,236 999 1,121 3,125 8,400 488 13,500 1,308 317 44,494 $ $ $ $ 3.08 ton 4.62 ton 3.90 ton 0.49 ton 9.03 ton 649 sqft 21.12 ton $ $ $ $ $ $ $ 3,850 5,775 4,875 608 8,126 117 23,351 $ $
Budget
"A"
"B"
"C"
2,478,000
2,535,280
Site Work
Reinforcing steel @ Planter foundation footings & Walls Reinforcing steel @ foundation & WallsClock Tower footings Reinforcing steel @ foundation & walls- Seat Wall Reinforcing steel @ structure - Fountains Reinforcing steel @ structure - round columns Reinforcing steel @ structural beams Reinforcing steel @ structure - 2 sided planter wall Reinforcing steel @ structure - 2 Side Fountain Wall Reinforcing steel @ structure - elevated slab Site Work SUBTOTAL Site Work TOTALS
$ $ 2,535,280 2,535,280 $ $ $ $ -
117 117 $ $
117 117 $ $ -
SCOPE SHEETS
O.S.P.I. 2 Aspen Court Boynton Beach, FL. 33436 Tele: 561-734-6127 Fax: 561-736-7919
Reinforcing - Continued
Page 2
03B
16
Sub/Supplier
Budget
"A"
"B"
"C"
$ $ $
23,351
117
117
1,313 $ 11,907
$ 1,333,108 $ 5,438 $ $ $ $ $ $ $ $ $ $ $ 21,253 295,486 35,792 97,213 249,527 40,906 138,841 214,999 17,860 10,619 11,907
Bldg. & Garage SUBTOTAL Bldg. & Garage TOTALS Total Tons Total Rebar Material Total Wire Mesh & Accessories Subtotal Materal Cost Sales Tax Total Material Cost Labor to Install Revised Pricing Total without Alternates
2,824.12 ton
$ 3,432,936
$ $
$ $
$ $
$ $
$ $
$ 174,132 $
169,342
179,065
867,527
$ $ $
867,527
ton
$ 3,500,781
3,546,477
3,622,376
Adjusted Total
3,546,477
3,472,786
3,622,376
SCOPE SHEETS
O.S.P.I. 2 Aspen Court Boynton Beach, FL. 33436 Tele: 561-734-6127 Fax: 561-736-7919
Concrete Material
Alternates:
03D
Ticket Total
17
0
Subcontractor Used "C"
Sub/Supplier Addendums MWBE Status Base Quote Description 3000 REGULAR 3000 PRPM 4000 REGULAR 4000 PRPM 5000 REGULAR - Crane/Hoist Pads 5000 REGULAR 5000 PRPM Quantity UOM cyds cyds cyds cyds cyds cyds cyds U$ $
Budget
"A"
"B"
"C"
Cost 2,869,560
Site Work
$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $
2,869,560 2,869,560 -
$ $
3,343,267 3,343,267
$ $
2,858,581 2,858,581
$ $
$ $
$ $
$ $
$ $
$ $
$ $
$ $
$ $
$ $
$ $
$ $
$ $
2,869,560
3,343,267
2,858,581
Adjusted Total
2,869,560
3,343,267
2,858,581
SCOPE SHEETS
O.S.P.I. 2 Aspen Court Boynton Beach, FL. 33436 Tele: 561-734-6127 Fax: 561-736-7919
03F
Ticket Total
18
1,133,408
Subcontractor Used "A"
Sub/Supplier Addendums MWBE Status Base Quote Description Shop Drawings Post Tension Calculations (Max of Eight (8) Sets Tendons - Cut To Length, Coiled, Location Mark Plastic Support Chairs 14" Slab Standeez Post Tension Support Slabs Over 14" Calibrated Stressing Equipment Three (3) Machine Sets @ Three (3) Months Equipment Insurance General Liability Insurance Encapsulated Anchoring System Delivery Rebar Materials Sales Tax Concrete, Formwork, Shoring or Grouting of Stress Pockets Shear Stud Rails Hoisting Equipment Tenplates, Tie Wire Field Taping of Tendons Quantity UOM U$
Budget
"A"
"B"
690,000 Cost No $ $ $ $ $ $ No
804,400
Site Work
$ $
0 690,000 $ 690,000 $
804,400 804,400
$ $
$ $
$ $
SCOPE SHEETS
O.S.P.I. 2 Aspen Court Boynton Beach, FL. 33436 Tele: 561-734-6127 Fax: 561-736-7919
Page 2
Budget "A" "B"
03F
18
$ $
$ $
$ $
$ $
$ $
$ $ $ $
$ $ $ $
$ $
$ $
$ $
$ 1,271,297
1,133,408
1,247,808
Adjusted Total
1,133,408
1,247,808
SCOPE SHEETS
O.S.P.I. 2 Aspen Court Boynton Beach, FL. 33436 Tele: 561-734-6127 Fax: 561-736-7919
Masonry
Alternates:
04A
Ticket Total
19
3,253,865
Subcontractor Used "B"
Sub/Supplier Addendums MWBE Status Base Quote Description Grouting of cells (3000PSI) / bond beams / lentils Grout hollow metal frames Fence piers / pilasters (CMU and Concrete) Planter Walls Elevator pit walls High Strength CMU Shoring Rebar Material Rebar placement Layout Masonry Non-Bearing (f,m 2000 PSI) Masonry Bearing (f,m 2800 PSI) Motar Type M (2500 PSI) Float finish exposed block Strike joints at exposed block Control Joints Lintels (4000 PSI) Horizontal reinforcement Dovetail anchors Rebar Blockout Placement Scaffolding Bracing Hoisting Doorframe installation Clean-up OSHA Saftey for all Working Floors CMU Materials & accessories Off-Site Parking Bondable Quantity UOM U$
Budget
"A"
"B"
"C"
"D"
"E"
3,450,000 Cost
3,189,865
3,500,000
3,387,000
In 03A
In 03A No block $ 0.20 $ N/A In 03A, B 1900 psi 1900 psi No N/A No In 08A N/A No In 08A No 64,000 $ N/A In 03A, B
64,000
No N/A No In 08A
SCOPE SHEETS
O.S.P.I. 2 Aspen Court Boynton Beach, FL. 33436 Tele: 561-734-6127 Fax: 561-736-7919
Masonry - Continued
Sub/Supplier
Page 2
Budget $ 71 15 29 71 15 29 3,840 702 520 35.60 cuyd cuyd cuyd cuyd cuyd cuyd sqft sqft sqft Tons $ $ $ $ $ $ $ $ $ $ $ 2,979 635 1,210 6,827 1,456 2,773 30,720 5,616 4,160 12,460 68,836 $ $ $ $ 300 300 7,185 4,854 9.00 cuyd cuyd sqft sqft Tons $ $ $ $ $ $ 12,567 28,800 57,479 38,830 3,150 140,826 $ $ $ 5,898 381 381 5,898 307 263,611 cuyd cuyd cuyd cuyd lnft sqft $ 247,059 $ 1,307 $ 36,567 $ 566,208 $ 3,070 $ 2,108,888 $ $ $ 53,994 83,611 15,000 $ $ $ 303,365 each 13,839 each $ 3,325,366 $ 12.23 $ 11.85 $ $ $ $ 15,600 390,600 390,600 $ $ 375,000 $ $ $ $ $ $ 3,150 78,983 78,983 $ $ 5,586 12,768 57,479 $ $ $ $ $ $ $ $ $ $ $ $ 2,979 635 1,210 6,827 1,456 2,773 30,720 5,616 4,160 12,460 3,582,836 3,582,836 $ $ "A" "B" 3,253,865 3,253,865
04A
"C" "D"
19
"E"
Site Work
Place Masonry Grout - Planter Walls Place Masonry Grout - Clock Tower Place Masonry Grout - Seat Wall 3000 PSI Grout Mix - Planter Walls 3000 PSI Grout Mix - Clock Tower 3000 PSI Grout Mix - Seat Wall Concrete Block 8" - Planter Walls Concrete Block 8-12" - Clock Tower Walls Concrete Block 12" - Seat Wall Install Reinforcing steel @ masonry walls Site Work SUBTOTAL Site Work TOTALS
$ $ $ $ $ $ $ $ $
2,979 1,210 6,827 2,773 30,720 4,160 12,460 3,561,129 3,561,129 $ $ $ 1,210
2,773
4,160
3,459,143 3,459,143 $ -
$ $ $ $
$ $ -
$ $ -
1374 cyds
$ $ $
$ 3,115,704
Adjusted Total
4,052,419
3,253,865
3,561,129
3,474,743