Anda di halaman 1dari 110

Alcatel-Lucent WiMAX

9710 C-WBS Installation and Commissioning Manual

BS Document Installation & Dismantling Manual Release W3 from MR1

3BK 17435 3011 RJZZA Ed.12

BLANK PAGE BREAK

Status Short title

RELEASED bscom
All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from Alcatel.

2 / 110

3BK 17435 3011 RJZZA Ed.12

Contents

Contents
Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 1.1 Presentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 1.1.1 9710 C-WBS Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 1.1.2 Dimensions and Weight . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 1.1.3 Common 9710 C-WBS Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 1.1.4 Restriction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 1.1.5 Initial State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 1.1.6 Final State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 1.1.7 Grouped Task Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18 1.1.7.1 Grouped Task Sequence for 9710 C-WBS Installation . . . . . . . . . . 18 1.1.7.2 Grouped Task Sequence for 9710 C-WBS Commissioning . . . . . . 19 1.2 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 1.2.1 Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 1.2.1.1 Prerequisites for 9710 C-WBS Installation . . . . . . . . . . . . . . . . . . . . . 20 1.2.1.2 Prerequisites for 9710 C-WBS Commissioning . . . . . . . . . . . . . . . . . 20 1.2.2 Site Specific Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21 1.2.2.1 Site Specific Information for 9710 C-WBS Installation . . . . . . . . . . . 21 1.2.2.2 Site Specific Information for 9710 C-WBS Commissioning . . . . . . 21 1.2.3 External Task . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22 1.3 Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22 1.3.1 Scheduling for 9710 C-WBS Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22 1.3.1.1 Scheduling for 9710 C-WBS Installation on a Wall . . . . . . . . . . . . . . 22 1.3.1.2 Scheduling for 9710 C-WBS Installation on a Mast . . . . . . . . . . . . . 23 1.3.2 Scheduling for 9710 C-WBS Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 1.3.2.1 Scheduling for 9710 C-WBS Commissioning without Commissioning Wizard . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 1.3.2.2 Scheduling for 9710 C-WBS Commissioning with Commissioning Wizard . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 1.4 Telecom/Supervision Outage and Operating Impact . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 1.5 Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 1.5.1 Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 1.5.1.1 Hardware Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 1.5.1.2 Software Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 1.5.1.3 Forms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 1.5.2 Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 1.5.2.1 List of Installation Kits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 1.5.2.2 Consumable Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30 1.5.3 Applicable Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30 Scenario for 9710 C-WBS Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31 2.1 Initial Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32 2.1.1 Before Going Onsite . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32 2.1.2 Before You Start . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32 2.1.2.1 Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32 2.1.2.2 Required Knowledge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33 2.2 Site Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33 2.2.1 Install Cable Tray . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33 2.2.2 Option: Install the Cable Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34 2.3 Option: Install and Connect the External Alarm Board and CEBOX . . . . . . . . . . . . . . . . . . . . . 35 2.3.1 Install and Connect WAIN . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35 2.3.1.1 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35 2.3.1.2 Install the WAIN Board . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35 2.3.1.3 Install CEBOX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36

3BK 17435 3011 RJZZA Ed.12

3 / 110

Contents

2.4

2.5

2.6

2.3.1.4 Connect WAIN Cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.1.5 Run and Connect the External Alarm Lines . . . . . . . . . . . . . . . . . . . . 2.3.2 Install and Connect WAIN-UL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.2.1 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.2.2 Install the WAIN-UL Board . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.2.3 Install CEBOX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.2.4 Connect WAIN-UL Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.2.5 Run and Connect the External Alarm Lines . . . . . . . . . . . . . . . . . . . . 2.3.3 Install and Connect WAING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.3.1 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.3.2 Install the WAING Board . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.3.3 Install CEBOX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.3.4 Connect the WAING Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.3.5 Run and Connect the External Alarm Lines . . . . . . . . . . . . . . . . . . . . Run and Connect Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.1 Run and Connect Earth Cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.2 Run and Connect Hybrid Cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.2.1 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.2.2 Connect Hybrid Cable to 9710 C-WBS . . . . . . . . . . . . . . . . . . . . . . . . 2.4.2.3 Connect Hybrid Cable to Hybrid Connection Box . . . . . . . . . . . . . . . 2.4.2.4 Option: Connect Hybrid Cable to the CEBOX . . . . . . . . . . . . . . . . . . 2.4.2.5 Option: Connect Hybrid Cable to Site Connection Box . . . . . . . . . . 2.4.3 Run and Connect the Ethernet Cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.4 Option: Connect Ethernet Cable in the CEBOX . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.5 Run and Connect Optical Fiber Cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.5.1 Run and Connect Optical Fiber Cable - Indoor Application . . . . . . 2.4.5.2 Run and Connect Optical Fiber Cable - Outdoor Application . . . . . 2.4.6 Run and Connect the Antenna Jumpers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.7 Run and Connect GPS Antenna Cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.7.1 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.7.2 Run and Connect GPS Antenna Cable . . . . . . . . . . . . . . . . . . . . . . . . 2.4.7.3 Option: Connect GPS Antenna Cables to WAING . . . . . . . . . . . . . . Position and Fix Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.1 Option: Fix MOFRA and Cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.1.1 Fix MOFRA to Back Cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.1.2 Fix MOFRA on Wall . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.1.3 Fix Back Cover and MOFRA on Wall . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.2 Option: Fix MOFRAL and Cover V2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.2.1 Fix MOFRAL to Back Cover V2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.2.2 Fix MOFRAL on Wall . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.2.3 Fix Back Cover V2 and MOFRAL on Wall . . . . . . . . . . . . . . . . . . . . . . 2.5.3 Option: Fix Back Cover and MOFRA on Mast . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.3.1 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.3.2 Using Clamps . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.3.3 Using Metal Bands . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.4 Option: Fix Back Cover V2 and MOFRAL on Mast . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.4.1 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.4.2 Using Metal Bands . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.5 Lift 9710 C-WBS on Top of Mast or Tower . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.5.1 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.5.2 Install Lifting Ring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.5.3 Lift 9710 C-WBS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Option: Install the Fan Hat . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.6.1 Option: Install the Lock Plate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.6.1.1 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.6.1.2 Install the Lock Plate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.6.2 Fix the Fan Hat on the Cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

36 37 38 38 38 38 39 40 40 40 40 41 41 41 42 42 43 43 43 46 49 50 52 54 55 56 57 59 62 62 62 64 65 65 65 66 67 68 68 69 70 71 71 72 73 76 76 76 78 78 78 79 80 80 80 80 81

4 / 110

3BK 17435 3011 RJZZA Ed.12

Contents

2.6.3 Connect Fan Hat . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83 2.6.4 Put Front Cover on 9710 C-WBS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84 2.6.5 Put Front Cover V2 on 9710 C-WBS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84 2.7 Finish Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85 2.7.1 Close Cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85 2.7.2 Before You Leave . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86 Scenario for 9710 C-WBS Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87 3.1 Initial Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88 3.1.1 Before Going Onsite . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88 3.1.2 Before You Start . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88 3.1.2.1 Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88 3.1.2.2 Required Knowledge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89 3.2 Cabling Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89 3.2.1 Check Earth and Hybrid Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89 3.2.2 Check Antenna Jumpers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89 3.3 Check Power Up (On) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90 3.4 Commissioning Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90 3.4.1 Install NEM-B Software on LMT PC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90 3.4.2 Connect LMT on 9710 C-WBS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91 3.4.3 Allocate Configuration Rights . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92 3.4.4 Edit Additional Modules (Optional) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92 3.4.4.1 Edit External Alarm Module . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92 3.4.4.2 Edit Top Cover with Fan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 93 3.5 Commissioning without Commissioning Wizard . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94 3.5.1 Check 9710 C-WBS Software Version . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94 3.5.2 Initial Parameters Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94 3.5.2.1 9710 C-WBS Identity Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94 3.5.2.2 Change 9710 C-WBS IP Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95 3.5.2.3 Edit Basic Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95 3.5.2.4 Edit Antenna Ports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 96 3.5.2.5 Edit Clock Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 97 3.5.2.6 Edit External Alarms (Optional) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 97 3.5.3 Commissioning Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98 3.5.3.1 Transmitter Power Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98 3.5.3.2 VSWR Measurement Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99 3.5.3.3 External Alarm Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100 3.5.3.4 Fan Hat Alarm Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101 3.6 Commissioning Using Commissioning Wizard . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102 3.7 Final Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109 3.7.1 Check Hardware Modules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109 3.7.2 Site Inventory . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109 3.7.3 Connection to Network . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110 3.8 Before You Leave . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110

3BK 17435 3011 RJZZA Ed.12

5 / 110

Figures

Figures
Figure 1: 9710 C-WBS Hardware with MOFRA, Cover V1 and Fan Hat . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 Figure 2: 9710 C-WBS Hardware with MOFRAL, Cover V2 and Fan Hat . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 Figure 3: Example of 9710 C-WBS in Indoor Environment (without Cover) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 Figure 4: Example of 9710 C-WBS in Indoor Environment (with Cover) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16 Figure 5: Example of 9710 C-WBS in Outdoor Environment (Wall Installation) . . . . . . . . . . . . . . . . . . . . . . . . . 16 Figure 6: Example of 9710 C-WBS in Outdoor Environment (Mast Installation) . . . . . . . . . . . . . . . . . . . . . . . . 17 Figure 7: Grouped Task Sequence for 9710 C-WBS Installation on a Wall / Mast . . . . . . . . . . . . . . . . . . . . . . 18 Figure 8: Grouped Task Sequence for 9710 C-WBS Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19 Figure 9: External Alarm Board (WAIN) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35 Figure 10: 9710 C-WBS with CEBOX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36 Figure 11: External Alarm Cable Routing Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36 Figure 12: Alarm 2 Cable Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37 Figure 13: 9710 C-WBS with CEBOX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39 Figure 14: WAIN-UL Cables Routing Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39 Figure 15: 9710 C-WBS with CEBOX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41 Figure 16: Earth Cable Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42 Figure 17: The Star Configuration - Fast Ethernet Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43 Figure 18: The Hybrid Cable Connectors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44 Figure 19: Connection the Hybrid Cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44 Figure 20: The Hybrid Cable Connection at 9710 C-WBS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45 Figure 21: Hybrid Connection Box . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46 Figure 22: Junctions of the Hybrid Connection Box . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47 Figure 23: DDF Hybrid Cable Diagram . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48 Figure 24: Hybrid Cable CEBOX Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49 Figure 25: The Hybrid Cable Connection at Site Side . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51 Figure 26: The Daisy Chain Configuration - Fast Ethernet Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52 Figure 27: The External Interfaces of the CEBOX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53 Figure 28: Daisy Chain Configuration - Ethernet Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53 Figure 29: Ethernet CEBOX Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54 Figure 30: The Star Configuration - Gigabit Ethernet Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56 Figure 31: CEBOX Connectors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56 Figure 32: The Daisy Chain Configuration - Gigabit Ethernet Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57 Figure 33: Typical Daisy Chain Mast Architecture . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58 Figure 34: Daisy Chain Configuration - Optical Fiber Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58 Figure 35: Antenna Jumper Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60 Figure 36: Antenna Feeder Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60 Figure 37: Connector Positions: [a] AAS, [b] 9710 C-WBS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61 Figure 38: GPS Connector . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63 Figure 39: GPS Splitter . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63

6 / 110

3BK 17435 3011 RJZZA Ed.12

Figures

Figure 40: GPS Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64 Figure 41: GPS Cable Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64 Figure 42: Fixing MOFRA to Back Cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65 Figure 43: Dimensions (in mm) between Fixation Holes on MOFRA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66 Figure 44: Fixing MOFRA on the Wall . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67 Figure 45: Fix MOFRA and Back Cover on Wall . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68 Figure 46: Fixing MOFRAL to Back Cover V2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68 Figure 47: MOFRAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69 Figure 48: Fixing MOFRAL on the Wall . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70 Figure 49: Fixing the Clamps to MOFRA + Back Cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72 Figure 50: Fixing MOFRA and Back Cover on Mast . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72 Figure 51: Mastfix Support . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73 Figure 52: Fix MOFRA with Back Cover onto Mastfix Support . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73 Figure 53: Ear-locked Buckles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73 Figure 54: Metal Band with Buckle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74 Figure 55: Fix Metal Band with Mastfix Support on Mast . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74 Figure 56: Fixing the Hand Tool . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74 Figure 57: Roll Tool . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75 Figure 58: Hold Band with Thumb . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75 Figure 59: Buckle Ears Down . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75 Figure 60: Fixing MOFRAL and Back Cover V2 on Mast . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 77 Figure 61: Lifting Ring Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 78 Figure 62: Install 9710 C-WBS on the MOFRA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79 Figure 63: Install Lock Plate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80 Figure 64: Fixing Fan Hat on Back Cover V1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81 Figure 65: Fixing Fan Hat on Back Cover V2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82 Figure 66: Connecting Fan Hat Cable on 9710 C-WBS Unit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83 Figure 67: Fix Cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84 Figure 68: Fix Cover V2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84 Figure 69: Fix Front Cover onto Back Cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85 Figure 70: Close Bottom Cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85 Figure 71: Information Window . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91 Figure 72: Leave Commissioning Window . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102 Figure 73: Enter Commissioning Window . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102 Figure 74: Leave Commissioning Window . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108

3BK 17435 3011 RJZZA Ed.12

7 / 110

Figures

8 / 110

3BK 17435 3011 RJZZA Ed.12

Preface

Preface
Purpose
The following naming conventions are used in this document: The Alcatel-Lucent 9710 Compact WiMAX Base Station will be later referred as 9710 C-WBS(former A9116 WiMAX BS) The Alcatel-Lucent 9740 WiMAX Access Controller will be later referred as 9740 WAC (former A9160 WAC) The Alcatel-Lucent 9753 WiMAX Operation and Maintenance Center will be later referred as 9753 OMC (former A1353-WR OMC-R). Where the procedure refers to both Cover Version1 and Cover Version2, the common Cover name will be used. This document describes how to install and commission 9710 C-WBS equipment.

Whats New

In Edition 12
Improvements in section Change 9710 C-WBS IP Settings (Section 3.5.2.2) (regarding to VLAN Tagging). A note was introduced in section Before You Start (Section 2.1.2) . In section Run and Connect the Antenna Jumpers (Section 2.4.6) step 2 was change with step 3.

In Edition 11
General improvements.

In Edition 10
First official release of document for W3MR1.

3BK 17435 3011 RJZZA Ed.12

9 / 110

Preface

Audience

This document is intended for: Installers Site administrators Supervisors Project managers Field service technicians Occasional users.

Assumed Knowledge

The reader must have: Basic knowledge of Alcatel WiMAX equipment Network architecture principles Commissioning tools Operations and maintenance concepts for 9710 C-WBS Basic knowledge for scheduling. Experience of electrical un/mounting and cabling.

Installers must be entitled to work either on 230 V AC or 48 V DC equipment. Interventions on antenna masts, roofs and in other dangerous situations is restricted to trained and authorized people.

10 / 110

3BK 17435 3011 RJZZA Ed.12

1 Overview

1 Overview
This section provides general information concerning the operating principle and requirements of the installation procedure.

3BK 17435 3011 RJZZA Ed.12

11 / 110

1 Overview

1.1 Presentation
1.1.1 9710 C-WBS Configuration
The concept supports maximum four 9710 C-WBS configuration. In whole document, for information, are presented three 9710 C-WBS configuration. The hardware consists of following modules: 9710 C-WBS without Cover V1(Version 1) or Cover V2(Version 2) Mounting frame (MOFRA / MOFRAL) Optional covers: Without top fan With top fan.

Figure 1: 9710 C-WBS Hardware with MOFRA, Cover V1 and Fan Hat

Figure 2: 9710 C-WBS Hardware with MOFRAL, Cover V2 and Fan Hat

12 / 110

3BK 17435 3011 RJZZA Ed.12

1 Overview

1.1.2 Dimensions and Weight


9710 Without C-WBS CEBOX C-WBS Without cover C-WBS +MOFRA Without cover C-WBS +MOFRAL With cover V1 and without fan hat C-WBS+ MOFRA+ Cover V1 With cover V1 and fan hat C-WBS+ MOFRA +Cover V1+Fan With cover V2 and without fan hat C-WBS+ MOFRAL +Cover V2 Dimension (mm) Width Height Depth Weight (kg) 9710 23.7 C-WBS unit CEBOX MOFRA MOFRAL Cover V1 Cover V2 Top Fan for Cover V1 Top Fan for Cover V2 23.7 23.7 23.7 23.7 23.7 23.7 395 645 140 395 745 170 395 745 170 450 818 190 450 960 190 440 782 201 440 970 201 With cover V2 and fan hat C-WBS+ MOFRAL +Cover V2+Fan

1 2.8 -

1 1.3 -

1 2.8 5.8

1 2.8 5.8

1 1.3 -

1 1.3 -

1.9

1.9

2.5

22 Maximum (kg)

27.5

26

33.3

36.3

27.9

30.4

3BK 17435 3011 RJZZA Ed.12

13 / 110

1 Overview

1.1.3 Common 9710 C-WBS Data


9710 C-WBS Installation On the wall without cover (indoor) On the wall with cover (indoor/outdoor) On the mast with cover (indoor/outdoor) Position 9710 C-WBS must be installed only in vertical position for air cooling. Installation at minimum 2.5 m height in public places Installation at minimum 1.0 m height in places not open to the public Output for antennas In/Out for external cables Clearance Bottom side of 9710 C-WBS housing Bottom side of 9710 C-WBS housing Left, right: 0.1 m. Top: 0.4 m above top fixation points of basic unit to the MOFRA/MOFRAL. Bottom: 0.25 m Front: 0.8 m Site Fuse 6 A (in AC power).

1.1.4 Restriction
None.

1.1.5 Initial State


Before starting the installation check that: The site is prepared according to SPP-62 Specification for 9710 C-WBS Site Preparation The power suplly is provided with a readily accessible disconnect device with over current protection rated 15A The installation kits are packed and delivered onsite. Before starting the commissioning phase: The 9710 C-WBS unit is not plugged into the MOFRA/MOFRAL Antennas and feeders are installed and tested (including VSWR) NEM-B direct connection to 9753 OMC is installed and tested, or the Data Communication Network (backbone) is configured, to allow testing of the O&M connection between the 9710 C-WBS and 9753 OMC.

14 / 110

3BK 17435 3011 RJZZA Ed.12

1 Overview

1.1.6 Final State


After finishing the installation: The site is tidy The equipment is ready for commissioning. After finishing the commissioning: The 9710 C-WBS is installed, powered and an inventory file is done The 9710 C-WBS is disabled and locked, without current alarms The WiMAX modules inside the 9710 C-WBS are enabled and unlocked, without current alarms The WiMAX site specific parameters are set The 9710 C-WBS communication state is online (ready to be managed by the 9753 OMC) The 9710 C-WBS is ready for radio network introduction, without another onsite intervention.

: The power supply can be AC or DC

Figure 3: Example of 9710 C-WBS in Indoor Environment (without Cover)

3BK 17435 3011 RJZZA Ed.12

15 / 110

1 Overview

: The power supply can be AC or DC

Figure 4: Example of 9710 C-WBS in Indoor Environment (with Cover)

: The power supply can be AC or DC

Figure 5: Example of 9710 C-WBS in Outdoor Environment (Wall Installation)

16 / 110

3BK 17435 3011 RJZZA Ed.12

1 Overview

Figure 6: Example of 9710 C-WBS in Outdoor Environment (Mast Installation)

3BK 17435 3011 RJZZA Ed.12

17 / 110

1 Overview

1.1.7 Grouped Task Sequence


1.1.7.1 Grouped Task Sequence for 9710 C-WBS Installation
The following figure shows the grouped task sequence for this scenario.

Figure 7: Grouped Task Sequence for 9710 C-WBS Installation on a Wall / Mast

18 / 110

3BK 17435 3011 RJZZA Ed.12

1 Overview

1.1.7.2 Grouped Task Sequence for 9710 C-WBS Commissioning


The following figure shows the grouped task sequence for this scenario.

Figure 8: Grouped Task Sequence for 9710 C-WBS Commissioning

3BK 17435 3011 RJZZA Ed.12

19 / 110

1 Overview

1.2 Preparation
1.2.1 Prerequisites
In order 9710 C-WBS IP discover to reach DHCP for NE server, the routers connecting the 9710 C-WBS to the WiMAX Radio Access Network, must have the Bootp Relay function enabled.

1.2.1.1 Prerequisites for 9710 C-WBS Installation


The following prerequisites apply: The site must be compliant with General Safety Instructions The site is ready to receive the 9710 C-WBS, according to the SPP-62 Specification for 9710 C-WBS Site Preparation Check that the power source is compliant with the type indicated on the marking label The hybrid connection box, used to split the hybrid cable, must be used in indoor conditions. LAN connectivity is mandatory. The Site Connection Box is required if there is no external hybrid connection box. The equipment is delivered onsite (packed) with the associated kits (the 9710 C-WBS unit will be put in position during the commissioning phase) The cable tray is mandatory for installation The GPS antenna splitter must be installed.

1.2.1.2 Prerequisites for 9710 C-WBS Commissioning


The following prerequisites apply: The site must be compliant with the General Safety Instructions The 9710 C-WBS is successfully installed (the installation CCL is available) Antennas are installed, tested and connected to the feeder or ready for connection (if no antennas are available use loads) The 9710 C-WBS is successfully provisioned (the provisioning CCL is available) The 9710 C-WBS and 9715 L-WBS Service Reference Sheet is available and correctly completed; refer to the Site Specific Information for 9710 C-WBS Commissioning (Section 1.2.2.2).

20 / 110

3BK 17435 3011 RJZZA Ed.12

1 Overview

1.2.2 Site Specific Information


1.2.2.1 Site Specific Information for 9710 C-WBS Installation
You must have the following specific information to complete the scenario (refer to the 9710 C-WBS and 9715 L-WBS Service Reference Sheet ): Site: Position of the 9710 C-WBS onsite Address of the site and access to the site (key holder) Power supply distribution on the customer side Cable tray GPS antenna position GPS antenna signal splitter (if the splliter is used). Equipment: CEBOX (yes or not) External alarm board (yes or not) Optical kit (yes or not) Cover V1/Cover V2 (yes or no) Fan hat (yes or no).

1.2.2.2 Site Specific Information for 9710 C-WBS Commissioning


You must have the following specific information to complete the scenario (refer to the 9710 C-WBS and 9715 L-WBS Service Reference Sheet ): Site Arrangement: 9710 C-WBS position Position of the site power cabinet and fuse breakers labeling corresponding to the 9710 C-WBS Antenna feeders position. Equipment Configuration: 9710 C-WBS hardware configuration Sector azimuth and corresponding feeder labeling (for physical connection) Clock synchronization mode. Transmission: 9710 C-WBS logical name, location name and network identity. Test Parameters: TX power level (dBm) TX frequency (MHz).

3BK 17435 3011 RJZZA Ed.12

21 / 110

1 Overview

1.2.3 External Task


If other radio transmitting equipment is present on the site (such as GSM BTS, UMTS Node B), this radio transmission must be stopped (leading to a telecom outage) during 9710 C-WBS installation near the antenna (for safety reasons). If antenna jumpers must be connected to feeder cables, the feeder loss must be given by the antenna installation team before or during the 9710 C-WBS installation.

1.3 Scheduling
Time based on technical constraints. The number of resources shown in the following tables does not take into account individual customer or safety requirements. These procedures requires at least two people onsite. All tasks are done on the 9710 C-WBS site, with an installation team comprising at least two people. Typical duration: One day for two people. The time is given in hours (hours), minutes (min) and seconds (sec).

1.3.1 Scheduling for 9710 C-WBS Installation


1.3.1.1 Scheduling for 9710 C-WBS Installation on a Wall
Task/Duration (min.) Initial Checks Before going onsite Before you start Site Preparation Install Cable Tray Option: Install Cable Protection Optional: Install and Connect the External Alarm Board and CEBOX Run and Connect the Cables Run and Connect the Earth Cable Run and Connect the Hybrid Cable Option: Run and Connect the Ethernet Cable Option: Connect Ethernet Cable in the CEBOX 2 hours 1 hour 30 min. 10 min. 4 hours 3 hours 20 min. 10 min. 10 min. 20 min. 20 min. 2nd Person 1st Person

2 hours 5 min. 5 min. 10 min. 10 min. 10 min.

4 hours 10 min. 10 min. 20 min. 20 min. 20 min.

22 / 110

3BK 17435 3011 RJZZA Ed.12

1 Overview

Task/Duration (min.) Option: Run and Connect the Optical Fiber Run and Connect the Antenna Jumpers Run and Connect the GPS Antenna Cable

2nd Person 1 hour 5 min. 20 min. 10 min.

1st Person 2 hours 10 min. 40 min. 20 min.

Task/Duration (min.) 9710 C-WBS Installation Option: Fix the MOFRA on the Back Cover V1 Option: Fix the MOFRAL on the Back Cover 2 Option: Fix the MOFRA on Wall Option: Fix the MOFRAL on Wall Option: Fix the Back Cover V1 and MOFRA on Wall Option: Fix the Back Cover V2 and MOFRAL on Wall Lift 9710 C-WBS on Top of Mast or Tower Option: Install the Fan Hat Finish Installation

2nd Person

1st Person

5 min. 5 min. 30 min. 20 min. 40 min. 30 min. 30 min. 15 min. 10 min.

10 min. 10 min. 60 min. 40 min. 1 hour 20 min. 60 min. 30 min. 20 min.

1.3.1.2 Scheduling for 9710 C-WBS Installation on a Mast


Task/Duration (min.) Initial Checks Before going onsite Before you start Site Preparation Option: Install Cable Tray Option: Install Cable Protection Optional: Install and Connect the External Alarm Board and CEBOX Run and Connect the Cables Run and Connect the Earth Cable 2 hours 1 hour 30 min. 10 min. 4 hours 3 hours 20min. 10 min. 10 min. 20 min. 20 min. 2nd Person 1st Person

2 hours 5 min. 5 min.

4 hours 10 min. 10 min.

3BK 17435 3011 RJZZA Ed.12

23 / 110

1 Overview

Task/Duration (min.) Run and Connect the Hybrid Cable Option: Run and Connect the Ethernet Cable Option: Connect Ethernet Cable in the CEBOX Option: Run and Connect the Optical Fiber Cable Run and Connect the Antenna Jumpers Run and Connect the GPS Antenna Cable 9710 C-WBS Installation Option: Fix the MOFRA on the Back Cover V1 Option: Fix the MOFRAL on the Back Cover V2 Option: Fix Back Cover V1 and MOFRA on Mast Option: Fix Back Cover V2 and MOFRAL on Mast Option: Fix the Back Cover V1 and MOFRA on the Mast using the clamps Option: Fix the Back Cover V2 and MOFRA on the Mast using the band Lift 9710 C-WBS on Top of Mast or Tower Option: Install the Fan Hat Finish Installation

2nd Person 10 min. 10 min. 10 min. 1 hour 5 min. 20 min. 10 min.

1st Person 20 min. 20 min. 20 min. 2 hours 10 min. 40 min. 20 min.

5 min. 5 min. 15 min. 15 min. 15 min.

10 min. 10 min. 30 min. 30 min. 30 min.

15 min.

30 min.

30 min. 15 min. 10 min.

30 min. 20 min.

24 / 110

3BK 17435 3011 RJZZA Ed.12

1 Overview

1.3.2 Scheduling for 9710 C-WBS Commissioning


1.3.2.1 Scheduling for 9710 C-WBS Commissioning without Commissioning Wizard
Grouped Task / C-WBS site Initial Checks (Section 3.1) Cabling Checks (Section 3.2) Commissioning Preparation (Section 3.4) Commissioning without Commissioning Wizard (Section 3.5) Final Checks (Section 3.7) Before You Leave (Section 3.8) TOTAL TIME 2nd Person 30 min. 5 min. 28 min. 48 min. 1st Person 30 min. 5 min.

13 min. 5 min. 2 hour 15 min.

1.3.2.2 Scheduling for 9710 C-WBS Commissioning with Commissioning Wizard


Grouped Task / C-WBS site Initial Checks (Section 3.1) Cabling Checks (Section 3.2) Commissioning Preparation (Section 3.4) Commissioning Using Commissioning Wizard (Section 3.6) Final Checks (Section 3.7) Before You Leave (Section 3.8) TOTAL TIME 2nd Person 30 min. 5 min. 28 min. 48 min. 1st Person 30 min. 5 min.

13 min. 5 min. 2 hour 15min.

3BK 17435 3011 RJZZA Ed.12

25 / 110

1 Overview

1.4 Telecom/Supervision Outage and Operating Impact


Radio transmission must be stopped during human intervention near the antenna. If any other systems are present on the same site (such as GSM BTS, UMTS Node B), they must also be stopped. The commissioned 9710 C-WBS is still not in traffic.

1.5 Resources
1.5.1 Tools
The following tables describe the necessary hardware tools, software tools, and forms.

1.5.1.1 Hardware Tools


Kit name Basic tools set Reference OUT 001

Refer to the Tools Catalogue for content checking.

1.5.1.2 Software Tools


Item Customer Documentation CD with the version associated with the current document edition. Remember that the document you are reading cannot be used as a paper version. It is online documentation using hypertext links which take you to other parts of a document on the same CD-ROM. All words in italics are hypertext links. Part Number Use at... 9753 OMC

1.5.1.3 Forms
Item Completion Check List (CCL) 9710 C-WBS Delivery Note Restriction List WiMAX W3MR1 3BK 11275 0139 QTZZA BS site Part Number 3BK 17435 0009 QZZZA Use at ... BS site

26 / 110

3BK 17435 3011 RJZZA Ed.12

1 Overview

1.5.2 Supplies
1.5.2.1 List of Installation Kits
Use the following table to check, onsite, the mandatory or optional delivery item kits. Type Kits A - Basic Installation Kits M M M Standard installation kit for WBS unit Basic Installation kit for WiMAX Mounting frame MOFRA MOFRAL M M M Basic installation kit for optical fiber Wall fixing kit Mast fix kit, (80 mm < Mast 180 mm) Mast fix metal band kit Metal band OFC3SEC KIT-MMKT MMFI MMKT 3BK 07653 ABXX 3BK 27769 ABXX 3BK 08272 ABXX 3BK 28008 AAAA 3BK 27700 AAXX 3BK 07653 ABAA 3BK 07637 ABXX 1 1/C-WBS 1 1 1 1/C-WBS 1/C-WBS Mnemonic Code Quantity

M TC

MMFI Stainless Steel band Buckle Ear-lockt Style WAIN WAIN-UL(AC) WAIN-UL(DC) WAIN-G

3BK 07637 ACAA 1AD 13225 0001

1/C-WBS 2/C-WBS

TC

Ear-locked Buckles

1AD 13225 0002

2/C-WBS

TC

External Alarm Kit

3BK 28094 AAXX 3BK 28095 AAXX 3BK 28095 BAXX 3BK 28096 AAXX 3BK 07653 AB AD 01960 0003

1/C-WBS

M M

Earth Cable Kit Label Kit for Indoor Feeder Identification Label Kit for Outdoor Feeder Identification Labels kit for outdoor cables identification Kit labels : power, Ethernet Label for terminal block B - Basic Installation Kits

KIT-MMKT

1/C-WBS 1

1AD 02370 0002

1AD 02370 0004

M M

3BK 25932 ACAA 1AD 02853 0001

1 1

3BK 17435 3011 RJZZA Ed.12

27 / 110

1 Overview

Type Kits M Ground cable 10mm for AC power (max. 100m) Hybrid Cable for WBS AC version: 10m 20m 40m 60m 80m TC Hybrid Cable for WAIN-UL version AC Hybrid Cable for WAIN-UL version DC Hybrid Cable for WBS DC version: 10m 20m 40m 60m M Ethernet Cable
2

Mnemonic GRD

Code 1AC 00730 0003

Quantity 1/C-WBS

ETHAC 3BK 27397 AEXX 3BK 27397 AAXX 3BK 27397 ABXX 3BK 27397 ACXX 3BK 27397 ADXX ETHAC-UL 3BK 28075 AAXX

1/C-WBS

1/C-WBS

TC

ETHDC-UL

3BK 28076 AAX

1/C-WBS

ETHDC 3BK 28007 AEAA 3BK 28007 AAAA 3BK 28007 ABAA 3BK 28007 ACAA CA-CA120S4 100m cable L907 4x2 MMFI 3BK 08942 AAAA

1/C-WBS

1/C-WBS

TC

Mast fix SUPPORT GPS Splitter

3BK 27745 AAAA

1/up to 4 C-WBS 1

TC TC

Indoor standard splice box Outdoor optical distribution box OPTOSM*ST/PC

1AB 34975 0002 1AB 34351 0001

TC

Fibre Cleaver tool

OPTOSM*ST/PC

1AD 13080 0001

TC TC

Mechanical splice Compact fusion splicer machine

OPTO-SM*MU Soldering

1AB 35209 0001 1AC 03866 0001

6/C-WBS 1

28 / 110

3BK 17435 3011 RJZZA Ed.12

1 Overview

Type Kits TC Patch cord cable with connectors LC : 1m 2m 3m TC Outdoor 6 optical fibres cable in roll: 250m 500m 1000m TC TC Optical cable 6 fibers (10m) Outdoor optical distribution box

Mnemonic OPTIC AL*1*SM

Code

Quantity 1/C-WBS

1AC 03809 0001 1AC 03809 0002 1AC 03809 0003

6OPTFC 3BK 27554 AAXX 3BK 27554 ABXX 3BK 27554 ACXX 6OPTFC OPTOSM*ST/PC 3BK 30405 AA 3AB 343510001

1/C-WBS

1/C-WBS 1

TC

Antenna jumper cable 1m 2m 3m

MACC 3BK 07928 AB 3BK 07928 AD 3BK 07928 AE 3BK 27207ACAA 1AB 352090 0001 MSTC tbc MFCC 3BK 08640 AAxx 3BK 08640 AAxx 3BK 08681 BAXX 3BK 27396 BAxx 1AB 35296 0001 PBA WAIN PBA WAIN-UL PBA WAIN-G 3BK 27741 AAXX 3BK 28022 AAAA 3BK 27741 BAXX

1/ant 1/ant 1/ant

TC TC TC TC TC TC TC TC

Data cable 4 pairs UV in 100m roll Tools for mechanical splice 9710 C-WBS Cover V1 9710 C-WBS Cover V2 Top cover with fan CEBOX Splicing KIT for Hybrid Cable 4pairs External Alarm Board

1/C-WBS 1/C-WBS 1/C-WBS 1/C-WBS 1/C-WBS 1/C-WBS 1/C-WBS

C - Optional Kits for Site Preparation CO GPS Splitter 1AF 14584 AAAA 1

3BK 17435 3011 RJZZA Ed.12

29 / 110

1 Overview

Type Kits CO Wire mesh cable trays 6m x 0.1m, indoor site Screwing tube Wire mesh cable trays 6m x 0.05m, indoor site
: mandatory kit : technical choice kit : customer option kit

Mnemonic MCTW

Code 3BK 04753 AB

Quantity 1

CO CO

1AB 34048 0001 MCTN 3BK 04753 AA

1 1

M TC CO

1.5.2.2 Consumable Supplies Note:


The consumable supplies must be qualified according to environment use. The installer or subcontractor must supply (not included in Alcatel-Lucent kits): A set of screws, nuts and washers to connect power cables to the site power box and to the earth plate A set of tie wraps to fit cables Indelible markers, blank labels and adhesive tape.

1.5.3 Applicable Documents


You must have the following documents or have electronic access to the following documents: Completion Check List (CCL) 9710 C-WBS and 9715 L-WBS Maintenance Handbook 9710 C-WBS and 9715 L-WBS Description Tools Catalogue SPP-62 Specification for 9710 C-WBS Site Preparation 9710 C-WBS and 9715 L-WBS Service Reference Sheet General Safety Instructions NEM-B User Guide.

30 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

2 Scenario for 9710 C-WBS Installation


This scenario presents all checks needed before beginning the scenario, and all detailed tasks to be performed on each site.

3BK 17435 3011 RJZZA Ed.12

31 / 110

2 Scenario for 9710 C-WBS Installation

2.1 Initial Checks


2.1.1 Before Going Onsite
Before going onsite, you must check that the following information and supplies are available: All Prerequisites for 9710 C-WBS Installation (Section 1.2.1.1) are met The customer has been informed of the: Date and time Site name and address Purpose of operation. Personnel are available (refer to Scheduling (Section 1.3)) Site Specific Information for 9710 C-WBS Installation (Section 1.2.2.1) is available Tools (Section 1.5.1) are available and ready for operation. Verify the calibration label when indicated in tool kit list. Supplies (Section 1.5.2) are available and ready for operation Supplies (Section 1.5.2) are available.

2.1.2 Before You Start


Read the WiMAX Delivery Notes and Restriction List WiMAX W3MR1 document for the possible workarounds and patch installations (refer to Forms (Section 1.5.1.3).

Note: 2.1.2.1 Checks

For WBS parameters namimg rules refer to Naming Rules for ASN Hosts from 9753 OMC Configuration Handbook.

Perform the following operations: Check that all Prerequisites for 9710 C-WBS Installation (Section 1.2.1.1) are met Check the availability of all necessary Tools (Section 1.5.1) and Supplies (Section 1.5.2) Check that safety precautions are taken according to the General Safety Instructions Complete the header field of the Completion Check List (CCL). The CCL must be completed as each installation instruction is carried out. Refer to the Tools Catalogue and note down measurement accuracy when indicated in the tool kit list (Tools (Section 1.5.1) ) Check that equipment is not damaged when it is unpacked Inform the operator, and ask him if you can start now.

32 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

2.1.2.2 Required Knowledge


You must be familiar with the following: Safety rules and precautions; refer to the General Safety Instructions Grouped Task Sequence for 9710 C-WBS Commissioning (Section 1.1.7.2) Telecom/Supervision Outage and Operating Impact (Section 1.4).

2.2 Site Preparation


2.2.1 Install Cable Tray
This section describes the required conditions for cable protection installation for the 9710 C-WBS. This is an option for installation in an indoor environment. The wire mesh cable trays are available in the installation kit for indoor sites. For a general view of the position of cable trays relative to the 9710 C-WBS, power box and DDF, refer to Final State (Section 1.1.6). Required conditions: The cable trays must reach: The middle-bottom part of the 9710 C-WBS housing Site Connection Box and power supply box Hybrid Cable (power supply and Ethernet) GPS cable Antenna feeders Room ground plate. The distance between the cable tray and 9710 C-WBS housing must be maximum 15 cm.

The cable ways will be isolated or several cable ways will be installed in order to separate the various electrical supply systems. Alternatively, a space of 30 cm must be left between two signal types.

3BK 17435 3011 RJZZA Ed.12

33 / 110

2 Scenario for 9710 C-WBS Installation

2.2.2 Option: Install the Cable Protection


This section describes the required conditions for cable protection installation for the 9710 C-WBS. For outdoor installation (wall or mast), use the conduit kit for outdoor sites (see Supplies (Section 1.5.2)). For a general view of the position conduits relative to the 9710 C-WBS, Site Connection Box, and power supply box, refer to Final State (Section 1.1.6)). Required conditions for wall installation: When the distance between the 9710 C-WBS and Site Connection Box is less than 70 cm, use only flexible metallic pipe for wall installation On the 9710 C-WBS side, the conduit must reach the middle-bottom end of the 9710 C-WBS cover and stops at 40 cm below the cover On the Site Connection Box sides, the conduit stops 25 cm above On the conduit end, use flexible metallic pipe for guiding the cables inside the covers (9710 C-WBS, Hybrid Connection Box / Site Connection Box) Use two different conduits: One for hybrid and ground cables One for alarms cables. Required conditions for mast installation: For installation on a mast, only use flexible metallic pipe On the 9710 C-WBS side, the flexible metallic pipe must reach the middle-bottom of the 9710 C-WBS cover and run into the cover On the Site Connection Box side, the flexible metallic pipe must reach the top of the covers and run into the covers Use two different flexible metallic pipes: One for hybrid cable and ground cables One for alarms cables.

The cable ways will be isolated or several cable ways will be installed in order to separate the various electrical supply systems. Alternatively, a space of 30 cm must be left between two signal types.

34 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

2.3 Option: Install and Connect the External Alarm Board and CEBOX
This section describes how to install the external alarm board to the 9710 C-WBS.

2.3.1 Install and Connect WAIN


This external alarm board is used for European area.

Note: 2.3.1.1 Materials


Description PBA-WAIN Flat cable Screw Cable gland Label

The WAIN must be mounted in the CEBOX (3BK 27396 BAxx) before the CEBOX is mounted onto the WBS.

Reference 3BK 27741 AAxx 3BK 27796 AAxx 1AD 009840012 1AD 046730001 3BK 27044 AAAA

Qty 1 1 6 2

Kit WAIN

Optional

2.3.1.2 Install the WAIN Board


To install external alarm board to the 9710 C-WBS: 1. Open CEBOX. 2. Take the external alarm board and mount it in the CEBOX.

Figure 9: External Alarm Board (WAIN) 3. Tighten the WAIN and CEBOX with the six fixation screws . Tighten the all six screws with recommanded torque 1Nm.

3BK 17435 3011 RJZZA Ed.12

35 / 110

2 Scenario for 9710 C-WBS Installation

2.3.1.3 Install CEBOX


Description CEBOX Reference 3BK 27396 AAAA Kit Optional

To install CEBOX: 1. Take the CEBOX with external alarm board assembled. 2. Remove NEMOCON cover. 3. Tighten the CEBOX and 9710 C-WBS with the 4 fixing screws. Tighten the all four screws with recommanded torque 6Nm.

Figure 10: 9710 C-WBS with CEBOX

2.3.1.4 Connect WAIN Cable


To connect the external alarm cable: 1. Open CEBOX. 2. Insert one side of the alarm cable routing in the NEMOCON connector and the other side of the cable to the 9710 C-WBS. This is shown in the following figure.

Figure 11: External Alarm Cable Routing Connection

36 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

2.3.1.5 Run and Connect the External Alarm Lines


To connect the external alarm cable: 1. Remove cap from cable entry hole. 2. Install two cable gland. 3. Run cables through the cable glands. 4. Insert alarm cable into the clamp strips. 5. In the next figure is shown the clamp strip for Alarm 2 (Alarm Switch Closed).

Figure 12: Alarm 2 Cable Connection 6. Close the CEBOX. Tighten the all four screws with recommanded torque 3,5Nm.

3BK 17435 3011 RJZZA Ed.12

37 / 110

2 Scenario for 9710 C-WBS Installation

2.3.2 Install and Connect WAIN-UL


This external alarm board is used for USA and Canadian areas.

Note: 2.3.2.1 Materials


Description PBA-WAIN-UL Flat cable Screw Cable Plate Cable gland adapter M16 to M20 Cable gland M20 Cable gland Label

WAIN-UL must be mounted in the CEBOX (3BK 27396 BAxx) before the CEBOX is mounted onto the 9710 C-WBS.

Reference 3BK 28022 AAAA 3BK 27796 AAxx 1AD 009840012 3BK 28078 AAxx 3BK 28077 AAAA 1AC xxxxx yyyy

Qty 1 1 6 2 1 1

Kit WAINUL

1AD xxxxx yyyy 1AD 046730001 3BK 27044 AAAA

1 4 Optional

2.3.2.2 Install the WAIN-UL Board


To install WAIN-UL board to the CEBOX: 1. Open CEBOX. 2. Take the external alarm board and mount it in the CEBOX. 3. Tighten the WAIN-UL and CEBOX with the six fixing screws . Tighten the all six screws with recommanded torque 1Nm.

2.3.2.3 Install CEBOX


Description CEBOX Reference 3BK 27396 AAAA Kit Optional

To install CEBOX: 1. Take the CEBOX with external alarm board assembled. 2. Remove NEMOCON cover. 3. Tighten the CEBOX and 9710 C-WBS with the 4 fixing screws. Tighten the all four screws with recommanded torque 6Nm.

38 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

Figure 13: 9710 C-WBS with CEBOX

2.3.2.4 Connect WAIN-UL Cables Note:


The CEBOX must be mounted to the 9710 C-WBS (see section Install CEBOX (Section 2.3.1.3)). To connect the WAIN-UL cables: 1. Insert one side of the flat cable in the NEMOCON connector and the other side of the cable to the 9710 C-WBS. 2. To connect cables for Ethernet I/F: Insert one side of the cable for Ethernet I/F in the NEM connector of the WAIN-UL board and the other side of the cable in the NEM connector of the 9710 C-WBS Insert one side of the other cable for Ethernet I/F in the TRANS1 connector of the WAIN-UL board and the other side of the cable in the TRANS1 connector of the 9710 C-WBS.

Figure 14: WAIN-UL Cables Routing Connections

3BK 17435 3011 RJZZA Ed.12

39 / 110

2 Scenario for 9710 C-WBS Installation

2.3.2.5 Run and Connect the External Alarm Lines Note:


The CEBOX must be mounted to the 9710 C-WBS (see section Install CEBOX (Section 2.3.1.3)). To connect the external alarm cable: 1. Install cable gland. 2. Install M16/M20 adaptor and cable gland. 3. Run cable through the cable gland. 4. Insert alarms cable into the clamp strips from the alarm input connector interface (see Figure (4)). 5. Close the CEBOX. Tighten the all four screws with recommanded torque 3,5Nm.

2.3.3 Install and Connect WAING


The WAING (Glonass the Russian satellite system) is used for Russian area.

Note: 2.3.3.1 Materials


Description PBA-WAING Flat cable Screw Cable NEMOCON MCX Cable DSUB NEMOCON Cable gland Label

WAING must be assembled in the CEBOX (3BK 27396 BAxx) before the CEBOX is assembled onto the 9710 C-WBS.

Reference tbc 3BK 27796 AAxx 1AD 009840012 tbc tbc 1AD 046730001 3BK 27044 AAAA

Qty 1 1 6 1 1 3

Kit WAING

Optional

2.3.3.2 Install the WAING Board


To install WAING board to the CEBOX: 1. Open CEBOX. 2. Take the external alarm board and mount it in the CEBOX. 3. Tighten the WAING and CEBOX with the six fixing screws . Tighten the all six screws with recommanded torque 1Nm.

40 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

2.3.3.3 Install CEBOX


Description CEBOX Reference 3BK 27396 AAAA Kit Optional

To install CEBOX: 1. Take the CEBOX with external alarm board assembled. 2. Remove NEMOCON cover. 3. Tighten the CEBOX and 9710 C-WBS with the 4 fixing screws. Tighten the all four screws with recommanded torque 6Nm.

Figure 15: 9710 C-WBS with CEBOX

2.3.3.4 Connect the WAING Cables Note:


The CEBOX must be assembled to the 9710 C-WBS (see section Install CEBOX (Section 2.3.1.3)). To connect the WAING cables: 1. Insert one side of the flat cable in the NEMOCON connector and the other side of the cable to the 9710 C-WBS. 2. Insert one side of the MCX cable to the WAING board and the other side of the cable to the 9710 C-WBS. 3. Insert one side of the DSUB cable to the WAING and the other side of the cable to the 9710 C-WBS.

2.3.3.5 Run and Connect the External Alarm Lines Note:


The CEBOX must be assembled onto the 9710 C-WBS (see section Install CEBOX (Section 2.3.1.3)). To connect the external alarm cable: 1. Remove cap from cable gland. 2. Install two cable glands. 3. Run cables through the cable glands. 4. Insert alarms cable into the clamp strips from the alarm input connector interface. 5. Close the CEBOX. Tighten the all four screws with recommanded torque 3,5Nm.

3BK 17435 3011 RJZZA Ed.12

41 / 110

2 Scenario for 9710 C-WBS Installation

2.4 Run and Connect Cables


In the case of an indoor application, the cables can also be run and connected after Position and Fix Equipment (Section 2.5).

Do not work under power. Open the circuit breakers to ensure that the power supply is disconnected. Annotate the circuit breakers with a ticket to prevent mistakes.

2.4.1 Run and Connect Earth Cable


This section describes how to connect the Earth Cable from the 9710 C-WBS to the site earth plate. Description Earth Cable Label Reference 3BK 07653 AB 3BK 27398 AAAA ETHLP Kit

To connect the earth cable: 1. Cut the earth cable to the required length. 2. Fit shrinking sleeve. 3. Crimp a 8mm terminal lug at each end of the earth cable. 4. Connect the earth cable to the site earth plate and put a label. 5. Connect the other end of the earth cable to the 9710 C-WBS.

Figure 16: Earth Cable Connection 6. Arrange the cable alongside the CEBOX.

42 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

2.4.2 Run and Connect Hybrid Cable


This section describes how to connect the Hybrid Cable from the 9710 C-WBS to the site connection box. Do not work under power. Open the circuit breakers to ensure that the power supply is disconnected. Annotate the circuit breakers with a ticket to prevent mistakes.

2.4.2.1 Materials
The maximum hybrid cable length plus extra Ethernet cable length must be up to 80m in case of AC power and up to 60m in case of DC power. Description Label Reference 3BK 27044 AAAA Kit tbc

2.4.2.2 Connect Hybrid Cable to 9710 C-WBS


Use the Hybrid Cable in the following cases: Star Configuration Daisy Chain Configuration. The following figure shows the Star Configuration for Fast Ethernet connection.

Figure 17: The Star Configuration - Fast Ethernet Connection

3BK 17435 3011 RJZZA Ed.12

43 / 110

2 Scenario for 9710 C-WBS Installation

On the 9710 C-WBS side, the hybrid cable must reach the left-top side of the CEBOX, as shown in Figure 18.

Figure 18: The Hybrid Cable Connectors

Figure 19: Connection the Hybrid Cable The hybrid cable comprises: 3 wires (blue, black and yellow / green); cross-section = 2.5 mm for power supply 4 twisted pairs (Cat5) for connecting two electrical interfaces Fast Ethernet LAN1 and LAN2.
2

44 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

To connect the hybrid cable: 1. Remove the protective cap from the hybrid connector. 2. Push the hybrid cable into the connector and block the action switch.

Figure 20: The Hybrid Cable Connection at 9710 C-WBS 3. Run the cable through the cable tray for cable passing. 4. Label the cable at both sides. 5. If there are more than one 9710 C-WBS on the site, check that the power supply circuit breakers are labeled.

3BK 17435 3011 RJZZA Ed.12

45 / 110

2 Scenario for 9710 C-WBS Installation

2.4.2.3 Connect Hybrid Cable to Hybrid Connection Box


The hybrid connection box must be used in the indoor conditions or protected conditions.

Description AC Power Cable DC Power Cable Wiring tool OSA3

Reference 3BK 25561 AAXX tbc 1 AD 0160 40001

Kit 3BK 27769 ABAA 3BK 27769 ABAA

To connect the hybrid cable to the hybrid connection box: 1. Run the hybrid cable from 9710 C-WBS to the hybrid connection box.

Figure 21: Hybrid Connection Box 2. Remove the cable insulation. Hybrid cable assignment: AC Power Cable L (line) N (null) G (ground) DC Power Cable Positive (+) Negative (-) PE (Ground) Color Black Blue Green/Yellow

Table 1: AC or DC Power Cable Colors

46 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

Pin (as seen at RJ45 in the hybrid cable connector on the 9710 C-WBS side) 4 5 2 1 6 3 8 7 Table 2: Ethernet Cable Wires Color

Color

Pair

Dedicated to... NEM-TX

blue solid white/blue stripe orange solid white/orange stripe green solid white/green stripe brown solid white/brown solid

Transmission-TX

Transmission-RX

NEM-RX

3. Open the hybrid connection box. 4. Remove the external metal shield from the cable. Ensure that the cable is cut in order to reach the grounding point. After cutting the cable, roll the rest of it and connect it to the grounding point (cut the cable as short as possible). 5. Ensure that the power cable is connected to the corresponding points into the hybrid connection box on the electrical junction block. 6. Before inserting the Ethernet cable in the data junction block, remove the external metal shield from the Ethernet cable. 7. Insert the Ethernet pairs into the data junction block using the wiring tool OSA 3. 8. Connect one side of the power cable inside the hybrid connection box and the other side to the power box. 9. Connect one side of the grounding cable inside the hybrid connection box and the other side to the grounding point.

Figure 22: Junctions of the Hybrid Connection Box 10. Connect one side of the data cable inside the hybrid connection box and the other side of the data cable to the DDF. The figure below shows the overall cabling diagram.

3BK 17435 3011 RJZZA Ed.12

47 / 110

2 Scenario for 9710 C-WBS Installation

Figure 23: DDF Hybrid Cable Diagram

48 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

2.4.2.4 Option: Connect Hybrid Cable to the CEBOX Note:


Description Power Cable material 2.5 Flexible conduit 1/2 Junction Box Wire nuts (3 in CEBOX and 3 in the junction box) This section must be performed when is used the WAIN-UL board . Reference tbc tbc tbc tbc Kit

To connect the hybrid cable to the CEBOX: 1. 2. Run the hybrid cable from the 9710 C-WBS to the CEBOX. 3. Remove cable insulation. 4. Remove the external metal shield from the cables. 5. Insert the cables of the hybrid cable into the CEBOX through the cable gland. 6. Insert the power cable from the site into the cable gland M20. 7. Connect the hybrid cables to the corresponding cables from the CEBOX plate. 8. Ensure that you make the right connections inside the CEBOX.

Figure 24: Hybrid Cable CEBOX Connection

3BK 17435 3011 RJZZA Ed.12

49 / 110

2 Scenario for 9710 C-WBS Installation

2.4.2.5 Option: Connect Hybrid Cable to Site Connection Box


To connect the hybrid cable to the site connection box: 1. Run the hybrid cable from the 9710 C-WBS to the site. 2. Remove the cable insulation (see mark point 1 on Figure 25). 3. Remove the external metal shield from the cable. Ensure that the cable is cut in order to reach the grounding point. After cutting the cable, roll the rest of it and connect it to the grounding point (cut the cable as short as possible). 4. Insert the rest of the cable into the power box through the cable gland. 5. Connect the power cable to the corresponding points in the power box. The following table lists the colors of the cables (L, N, G). AC Cable L (line) N (null) G (ground) DC Cable Positive (+) Negative (-) PE (ground) Color Black Blue Green/Yellow

Table 3: The Colors of the AC or DC Power Cables 6. Run out the Ethernet cable from the power box (see mark point 2 from the Figure 25). 7. Before inserting the Ethernet cable into the site connection box, remove the external metal shield from the Ethernet cable. Ensure that the cable is cut in order to reach the grounding point (see mark point 3 from Figure 25). 8. Insert the Ethernet pairs into the site connection box through the cable gland. 9. Ensure that you make the right connections inside the site connection box. 10. The following table lists the wire pair assignments.

50 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

Pin (as seen at RJ45 in the hybrid cable connector on the 9710 C-WBS side) 4 5 2 1 6 3

Color

Pair

Dedicated to...

blue solid white/blue stripe orange solid white/orange stripe green solid white/green stripe

NEM-TX

Transmission-TX

Transmission-RX

8 7

brown solid white/brown solid

NEM-RX

Table 4: Standard Colors

Figure 25: The Hybrid Cable Connection at Site Side

3BK 17435 3011 RJZZA Ed.12

51 / 110

2 Scenario for 9710 C-WBS Installation

2.4.3 Run and Connect the Ethernet Cable


This section describes how to install the Ethernet cable from the 9710 C-WBS. Description Label Ethernet cable Reference 3BK 27044 AAAA 3BK 27207 ACXX Kit

Use the Ethernet cable only in the indoor Daisy Chain Configuration. The Daisy Chain Configuration has the following connections: Fast Ethernet connection Gigabit Ethernet connection.

Note:

The physical connections between the 9710 C-WBSs are Gigabit Ethernet connection, but the rate between 9710 C-WBS and 9740 WAC is limited to Fast Ethernet. The following figure shows the Daisy Chain Configuration and the two connection types.

Figure 26: The Daisy Chain Configuration - Fast Ethernet Connection

52 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

The external interfaces of the 9710 C-WBS are: TRANS1 is for 9740 WAC or 9753 OMC connection TRANS2 is for daisy chain connection NEM connector is for LMT connection AUX connector is for Antenna Tilt connection.

Figure 27: The External Interfaces of the CEBOX To connect the Ethernet cable: 1. Open the CEBOX. 2. Insert the Ethernet cable in the CEBOX through the cable gland. 3. Insert the cable in the TRANS1 connector. 4. Run the Ethernet cable from the CEBOX to the site connection box. 5. The following rules apply when the daisy chain configuration is used (see Figure Daisy Chain Configuration - Ethernet Connection (28)): The TRANS2 connector of the Master 9710 C-WBS is linked to the TRANS1 connector of the Slave1 9710 C-WBS The TRANS2 connector of the Slave1 9710 C-WBS is linked to the TRANS1 connector of the Slave2 9710 C-WBS.

Figure 28: Daisy Chain Configuration - Ethernet Connection

3BK 17435 3011 RJZZA Ed.12

53 / 110

2 Scenario for 9710 C-WBS Installation

2.4.4 Option: Connect Ethernet Cable in the CEBOX


Note:
This section must be performed when is used the WAIN-UL board . To connect the Ethernet cable in CEBOX: 1. Remove the external metal shield from the Ethernet cable. 2. Insert the Ethernet pairs into the corresponding clamp strips, from the Ethernet input connector interface, using the wiring tool OSA3. Clamp strip (as seen at clamp strps from the CEBOX) 4 5 2 1 6 3 blue solid white/blue stripe orange solid white/orange stripe green solid white/green stripe 3 Transmission-RX 2 Transmission-TX 1 NEM-TX Color Pair Dedicated to...

8 7

brown solid white/brown solid

NEM-RX

Table 5: Standard Colors 3. The figure below shows the cabling diagram.

Figure 29: Ethernet CEBOX Connections

54 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

2.4.5 Run and Connect Optical Fiber Cable


CLASS 1 LASER PRODUCT! This section describes how to install the optical fiber cable from the 9710 C-WBS to the site connection box.

Description Indoor WBS 9116 Optical Fiber Access Kit

Reference CON-OPTO-SM*LC-PC Duplex CON-OPTO-SM*ST/PC

Kit 3BK 30406 AA

Outdoor WBS 9116 Optical Fiber Access Kit WBS 9116 Optical Fiber Daisy Chain Kit Label

1AB 34351 0001 3BK 30406 AC 3BK 27044 AAAA

Use the Optical Fiber in the following cases: Indoor/outdoor Star Configuration when a Gigabit Ethernet connection is used Outdoor Daisy Chain Configuration.

3BK 17435 3011 RJZZA Ed.12

55 / 110

2 Scenario for 9710 C-WBS Installation

2.4.5.1 Run and Connect Optical Fiber Cable - Indoor Application


The following figure shows the indoor Star Configuration with a Gigabit Ethernet connection.

Figure 30: The Star Configuration - Gigabit Ethernet Connection To connect the optical fiber: 1. Open the CEBOX. 2. Run the outdoor optical fiber cable (from the Indoor Optical Fiber Access) though the cable gland of the 9710 C-WBS. 3. Connect the optical cables to the SFP1 connectors of the C-WBSs (see Figure CEBOX Connectors (31)).

Figure 31: CEBOX Connectors

56 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

4. Connect the others side of optical cables to the optical fiber access box. 5. Close the CEBOX. Tighten the all four screws with recommanded torque 3,5Nm.

2.4.5.2 Run and Connect Optical Fiber Cable - Outdoor Application


The following figure shows the outdoor Daisy Chain Configuration with a Gigabit Ethernet connection.

Figure 32: The Daisy Chain Configuration - Gigabit Ethernet Connection

3BK 17435 3011 RJZZA Ed.12

57 / 110

2 Scenario for 9710 C-WBS Installation

To connect the optical fiber cable: 1. Open the CEBOX. 2. Run the outdoor optical fiber (outdoor 6 optical fiber) cables (from the Indoor Optical Fiber Access or from Outdoor Optical Fiber Distribution) through a cable gland of the 9710 C-WBS.

Figure 33: Typical Daisy Chain Mast Architecture 3. The following rules apply when the optical daisy chain configuration is used (see Figure 34): The SFP1 connector of the Master 9710 C-WBS is linked to optical fiber distribution The SFP2 connector of the Master 9710 C-WBS is linked to optical fiber distribution The SFP1 connector of the Slave1 9710 C-WBS is linked to optical fiber distribution The SFP2 connector of the Slave1 9710 C-WBS is linked to optical fiber distribution The SFP1 connector of the Slave2 9710 C-WBS is linked to optical fiber distribution.

Figure 34: Daisy Chain Configuration - Optical Fiber Connection

58 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

4. In optical fiber distribution the next connections have to be done: The SFP2 cable of the Master 9710 C-WBS is linked with SFP1 cable of the Slave1 9710 C-WBS The SFP2 cable of the Slave1 9710 C-WBS is linked with SFP1 cable of the Slave2 9710 C-WBS 5. Close the CEBOX. Tighten the all four screws with recommanded torque 3,5Nm.

2.4.6 Run and Connect the Antenna Jumpers


This section describes how to install the antenna jumpers from the 9710 C-WBS to the Adaptive Antenna System (AAS). The following rules apply: The antenna connectors must be dry before connection The connection of antenna jumpers to the antenna feeders will be done during the commissioning.

Description Vinyl electrical tape Linerlees Rubber Splicing Tape Label Kit for Indoor Feeder Identification Label Kit for Outdoor Feeder Identification

Reference 1AC 01556 0001 1AC 01595 0001 AD 01960 0003 1AD 02370 0002

Kit Optional Optional

On the 9710 C-WBS side, the antenna jumpers must reach the bottom part of the 9710 C-WBS housing and have a provision of 30 cm for connection. The antenna feeders must have the same length. To run and connect antenna jumpers: 1. Connect the antenna jumpers to antenna feeders: For indoor sites

3BK 17435 3011 RJZZA Ed.12

59 / 110

2 Scenario for 9710 C-WBS Installation

1 2

: Antenna feeder : Antenna jumper cable

Figure 35: Antenna Jumper Connection For outdoor sites.

Note:

Use the auto-vulcanisant (3) tape first, then cover with scotch (2) tape.

1 2 3 4

: Antenna feeder : Tape scotch : Tape auto-vulcanisant : Antenna jumper cable

Figure 36: Antenna Feeder Connection 2. Connect the antenna jumper to the adaptor. To connect antenna jumper to the adaptor: Remove the plastic cap Screw the antenna jumper to the adaptor. 3. Connect the antenna jumper with adaptor to the C-WBS antenna connector, as shown in Figure Antenna Jumper Connection (35). 4. Label the antenna jumper. 5. Connect the adaptor with the antenna jumper to the AAS connector.

60 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

Figure 37: Connector Positions: [a] AAS, [b] 9710 C-WBS 9710 C-WBS antenna configuration WBSAxy 9710 C-WBS antenna connector ANT1 ANT2 ANT3 ANT4 Table 6: 9710 C-WBS Antenna Configuration AAS connector

ANT1 ANT2 ANT3 ANT4

3BK 17435 3011 RJZZA Ed.12

61 / 110

2 Scenario for 9710 C-WBS Installation

2.4.7 Run and Connect GPS Antenna Cable


This section describes how to connect the GPS antenna cable to the 9710 C-WBS.

2.4.7.1 Materials
Description Splitter Coaxial antenna cable Connector side Alcatel-Lucent 9117 L-WBS unit Connector side antenna unit Connector side head of feeder Reference GPS Source S14WI LCF 1/2 Quick N female N female N male for feeder 1/2 Kit

2.4.7.2 Run and Connect GPS Antenna Cable


The GPS connectors must be dry before connection.

The following rules apply: The GPS antenna must be oriented parallel to the horizon to provide maximum visibility for the satellites The GPS antenna must be mounted with a 140 (minimum 120) visibility of the sky and no shadow area. The GPS antenna must be mounted approximately 2m above any reflecting surface (to reduce errors caused by reflections) The antenna has included a lightening protective device. To achieve vertical antenna isolation, a separation of 4m is required The GPS antenna must be mounted on top of the tower/mast and 4 meters above any other antenna. When the 1/.2 feeder is used, it must be connected directly to the antenna or to the 9710 C-WBS Maximum cable length between the 9710 C-WBS and the GPS antenna is: Without splitter and 1/2 feeder 50m for direct connection With splitter and 1/2 feeder 100m when the GPS splitter is used. The splitter can be used in two cases: For indoor installations when long cables are needed to the roof to have unobstructed sky visibility

62 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

For outdoor installations when 9710 C-WBSs are collocated and is difficult to find four locations on the tower to mount individual GPS antennas with enough decoupling with other systems. In standard outdoor installations when the above conditions are not met, one GPS antenna for each 9710 C-WBS is the basic scheme. To connect GPS antenna cable (without GPS splitter). 1. Remove protective cap from GPS connector. 2. Connect the coaxial antenna cable to the 9710 C-WBS, in the GPS connector.

Figure 38: GPS Connector 3. Connect the other side of the coaxial antenna cable directly to the GPS antenna. 4. Grounding GPS antenna. To connect the GPS antenna cable (with GPS splitter): 1. Remove protective cap from GPS connector. 2. Connect the coaxial antenna cable to the 9710 C-WBS, in the GPS connector. 3. Remove protective cap and water protection caps from GPS splitter connectors.

Figure 39: GPS Splitter 4. Connect the other side of the coaxial antenna cable to the GPS splitter.

3BK 17435 3011 RJZZA Ed.12

63 / 110

2 Scenario for 9710 C-WBS Installation

In case of 4 9710 C-WBS In the second case, all 4 9710 C-WBSs are connected at one GPS splitter.

Figure 40: GPS Connection 5. Grounding GPS antenna.

2.4.7.3 Option: Connect GPS Antenna Cables to WAING Note:


This section must be performed when is used the WAIN-G board . To connect the GPS cable to WAING: 1. Open the CEBOX. 2. Remove the external metal shield from the GPS cable. 3. Insert the GPS pairs into the corresponding clamp strips, from the GPS input connector interface, using the wiring tool OSA3. 4. The figure below shows the cabling diagram.

Figure 41: GPS Cable Connections

64 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

2.5 Position and Fix Equipment


2.5.1 Option: Fix MOFRA and Cover
2.5.1.1 Fix MOFRA to Back Cover
This section describes how to assemble the cover to the MOFRA, if supplied. Description Cover V1 Reference 3BK 08640 AAXX Kit MSTC

To fix the MOFRA to the back cover: 1. Open the bottom part of the front cover and loosen the two screws. 2. Detach the front cover. 3. Assemble the back cover to the MOFRA, as shown in the following figure.

Figure 42: Fixing MOFRA to Back Cover

3BK 17435 3011 RJZZA Ed.12

65 / 110

2 Scenario for 9710 C-WBS Installation

2.5.1.2 Fix MOFRA on Wall


This section describes how to fix the equipment on the wall, in the case of indoor environments, without using the back cover. Description 4 * Expanding wall-plug (D12mm * L60mm) 4 * Screw (M10 * 80mm) Reference 1AD 00755 0007 1AD 0050 0030 Kit MMKT

To fix the equipment on the wall without using the back cover: 1. Identify the position where the equipment is to be installed, as described in Site Specific Information (Section 1.2.2). 2. Use a spirit level and mark the position of the four fixation holes, using the dimensions from the installation drawing and as shown in the following figure.

Figure 43: Dimensions (in mm) between Fixation Holes on MOFRA 3. Punch and drill the four holes in the wall and put the expanding wall-plug (S12 dowels) in the hole, as shown in Figure 44. 4. Mount the MOFRA on the wall with the screws (M10 * 80), without tightening them, as shown in Figure 44. 5. Tighten the fixation screws.

66 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

Figure 44: Fixing MOFRA on the Wall

2.5.1.3 Fix Back Cover and MOFRA on Wall


This section describes how to fix the equipment on the wall in the case of indoor/outdoor environments, including the back cover. Description 4 * Expanding wall-plug (D12mm * L 60mm) 4 * Screw (M10 * 80mm) Reference 1AD 00755 0007 1AD 0050 0030 Kit MMKT

To fix the equipment on the wall, using the back cover: 1. Fix the back cover to the MOFRA, as described in Fix MOFRA to Back Cover (Section 2.5.1.1). 2. Identify the position where the equipment is to be installed, as described in Site Specific Information (Section 1.2.2). 3. Mark the position of the four fixation holes, using the dimensions from Figure 43. 4. Punch and drill the four holes in the wall and put the expanding wall-plug (S12 dowels) in the hole. 5. Mount MOFRA with back cover V2 on the wall with the screws (M10 * 80) without tightening them. 6. Level the ensemble using a spirit level. 7. Tighten the MOFRA and back cover V2 with the four fixing screws.

3BK 17435 3011 RJZZA Ed.12

67 / 110

2 Scenario for 9710 C-WBS Installation

MOFRA

: Mounting Frame

Figure 45: Fix MOFRA and Back Cover on Wall

2.5.2 Option: Fix MOFRAL and Cover V2


2.5.2.1 Fix MOFRAL to Back Cover V2
This section describes how to assemble the cover V2 to the MOFRAL, if supplied. Description Cover V2 Reference 3BK xxxxx AAAA Kit tbc

To fix the MOFRAL to the back cover V2: 1. Open the bottom part of the front cover V2 and loosen the two screws. 2. Detach the front cover V2. 3. Assemble the back cover V2 to the MOFRAL, as shown in the following figure.

Figure 46: Fixing MOFRAL to Back Cover V2

68 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

2.5.2.2 Fix MOFRAL on Wall


This section describes how to fix the equipment on the wall, in the case of indoor environments, without using the back cover. Description 4 * Expanding wall-plug (D12mm * L60mm) 4 * Screw (M10 * 80mm) Reference 1AD 00755 0007 1 AD 0050 0030 Kit MMKT

To fix the equipment on the wall without using the back cover: 1. Identify the position where the equipment is to be installed, as described in Site Specific Information (Section 1.2.2). 2. Use a spirit level and mark the position of the four fixation holes, using the dimensions from the installation drawing and as shown in the following figure.

Figure 47: MOFRAL 3. Punch and drill the four holes in the wall and put the expanding wall-plug (S12 dowels) in the hole. 4. Mount the MOFRAL on the wall with the screws (M10 * 80), without tightening them. 5. Tighten the fixation screws.

3BK 17435 3011 RJZZA Ed.12

69 / 110

2 Scenario for 9710 C-WBS Installation

2.5.2.3 Fix Back Cover V2 and MOFRAL on Wall


This section describes how to fix the equipment on the wall in the case of indoor/outdoor environments, including the back cover V2. Description 4 * Expanding wall-plug (D12mm * L 60mm) 4 * Screw (M10 * 80mm) Reference 1AD 00755 0007 1AD 0050 0030 Kit MMKT

To fix the equipment on the wall, using the back cover V2: 1. Fix the back cover V2 to the MOFRAL, as described in Fix MOFRAL to Back Cover V2 (Section 2.5.2.1). 2. Identify the position where the equipment is to be installed, as described in Site Specific Information (Section 1.2.2). 3. Mark the position of the four fixation holes, using the dimensions from Figure 47. 4. Punch and drill the four holes in the wall and put the expanding wall-plug (S12 dowels) in the hole. 5. Mount MOFRAL with back cover on the wall with the screws (M10 * 80) without tightening them. 6. Level the ensemble using a spirit level. 7. Tighten the MOFRAL and back cover V2 with the four fixing screws.

Figure 48: Fixing MOFRAL on the Wall

70 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

2.5.3 Option: Fix Back Cover and MOFRA on Mast


This section describes how to fix the equipment on a mast in the case of outdoor environments, using the cover. When the diameter of the mast is >180mm, the back cover and MOFRA must be fixed on the mast using a metal band.

2.5.3.1 Materials
The following table lists the materials required to fix the back cover and MOFRA on a mast, using the clamps. Description 2 * Fixing Parts-Front 2 * Fixing Parts-Rear 4 * Screws fix to MOFRA (M6 * 35mm) 4 * Screws (M10 * 160 mm) (80 mm Mast 130 mm) 4 * Screws M10 * 220mm (thread=75mm, with hexagonal head TH ) (130 mm < Mast 180 mm) 1AD 002150118 Reference 3BK 07650 AAAA 3BK 07649 AAAA 1AD 002150033 1AD 002150117 Kit MMFI

The following table lists the materials required to fix the back cover and MOFRA on a mast, using the metal band. Description 4*Screws (M10x40) 4*Nuts M4 4*Washers for M4 screws Reference Kit MMFI

3BK 17435 3011 RJZZA Ed.12

71 / 110

2 Scenario for 9710 C-WBS Installation

2.5.3.2 Using Clamps


To install the MOFRA and back cover using the clamps: 1. Fix the back cover to the MOFRA, as described in Fix MOFRA to Back Cover (Section 2.5.1.1). 2. Identify the position where the equipment is to be installed, as described in Site Specific Information (Section 1.2.2). 3. Assemble the MOFRA with the back cover onto the mast, using the other two half clamps.Select the screws as follows: M10*160mm if the diameter of the mast is between 80mm and 130mm M10*220mm if the diameter of the mast is over 130mm and up to 180mm.

Figure 49: Fixing the Clamps to MOFRA + Back Cover 4. Adjust to the required height and orientation. 5. Tighten the all four screws with torque 30Nm.

Figure 50: Fixing MOFRA and Back Cover on Mast

72 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

2.5.3.3 Using Metal Bands


To install MOFRA and back cover using the metal band: 1. Fix the back cover to the MOFRA, as described in Fix MOFRA to Back Cover (Section 2.5.1.1). 2. Assemble the MOFRA with the back cover onto the two mastfix support and the four M10x40 screws, as shown in the following figure.

Figure 51: Mastfix Support

Figure 52: Fix MOFRA with Back Cover onto Mastfix Support 3. Identify the position where the equipment is to be installed, as described in Site Specific Information (Section 1.2.2). 4. Run the metal band through the two bracket band-IT of the mastfix support. 5. Fix the ear-locked buckle to end of the metal band by running the band thought the buckle orifice and bending it (taking care to leave few cms for safety reasons).

Figure 53: Ear-locked Buckles

3BK 17435 3011 RJZZA Ed.12

73 / 110

2 Scenario for 9710 C-WBS Installation

Figure 54: Metal Band with Buckle 6. Fix the metal band with the mastfix support on the mast by running the end of the band through the buckle.

Figure 55: Fix Metal Band with Mastfix Support on Mast 7. Place the band in the opening of the tool nose and gripper block. Move it into slot as far as possible, to avoid the buckle sliding into the tool nose. Apply tension by turning the tension handle of the tool.

Figure 56: Fixing the Hand Tool 8. Place a finger on the band-it band at the buckle bridge while tensioning with the tool handle. When you feel band stop moving through the buckle, stop turning the tension handle. 9. Roll the tool over the buckle.

74 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

Figure 57: Roll Tool 10. Release the band gripper and push the tool nose away from the buckle approximately 3cm. Pull the cutting bar handle to cut the band. 11. Remove the tool and hold the stub of band down with your thumb.

Figure 58: Hold Band with Thumb 12. Hammer down the buckle ears.

Figure 59: Buckle Ears Down

3BK 17435 3011 RJZZA Ed.12

75 / 110

2 Scenario for 9710 C-WBS Installation

2.5.4 Option: Fix Back Cover V2 and MOFRAL on Mast


This section describes how to fix the equipment on a mast in the case of outdoor environments, using the cover V2.

2.5.4.1 Materials
The following table lists the materials required to fix the back cover V2 and MOFRAL on a mast, using the metal band. Description 4*Screws (M10x40) 4*Nuts M4 4*Washers for M4 screws Hand tool Hammer Reference Kit MMFI

2.5.4.2 Using Metal Bands


To install MOFRAL and back cover V2 using the metal band: 1. Fix the back cover V2 to the MOFRAL, as described in Fix MOFRAL to Back Cover V2 (Section 2.5.2.1). 2. Assemble the MOFRAL with the back cover V2 onto the two mastfix support and the four M4x10 screws, as shown in the Figure 51. 3. Identify the position where the equipment is to be installed, as described in Site Specific Information (Section 1.2.2). 4. Run the metal band through the two bracket band-IT of the mastfix support. 5. Fix the ear-locked buckle to end of the metal band by running the band thought the buckle orifice and bending it (taking care to leave few cms for safety reasons). 6. Fix the metal band with the mastfix support on the mast by running the end of the band through the buckle (see Figure Fix Metal Band with Mastfix Support on Mast (55)). 7. Place the band in the opening of the tool nose and gripper block. Move it into slot as far as possible, to avoid the buckle sliding into the tool nose. Apply tension by turning the tension handle of the tool (see Figure 56). 8. Place a finger on the band-it band at the buckle bridge while tensioning with the tool handle. When you feel band stop moving through the buckle, stop turning the tension handle.

76 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

9. Roll the tool over the buckle (see Figure Roll Tool (57)). 10. Release the band gripper and push the tool nose away from the buckle approximately 3cm. Pull the cutting bar handle to cut the band. 11. Remove the tool and hold the stub of band down with your thumb (see Figure 58). 12. Hammer down the buckle ears (see Figure 59).

Figure 60: Fixing MOFRAL and Back Cover V2 on Mast

3BK 17435 3011 RJZZA Ed.12

77 / 110

2 Scenario for 9710 C-WBS Installation

2.5.5 Lift 9710 C-WBS on Top of Mast or Tower


This section describes how to lift the 9710 C-WBS to the top of a mast or tower, using the lifting ring.

2.5.5.1 Materials
The following table lists the materials required to lift 9710 C-WBS on top of mast or tower: Description Lifting Eye Bolt M8 Reference 3BK 08947 AAAA Kit

2.5.5.2 Install Lifting Ring Note:


The lifting ring has the following measurements: 14mm long thread 20mm internal diameter 8mm thickness. To install the lifting ring on the 9710 C-WBS, screw the lifting ring into the M8 thread on top of the 9710 C-WBS unit, down to the internal screw-thread stop, as shown in Figure 61. Do not tighten the screw.

Figure 61: Lifting Ring Installation When the optical fiber cable is used, Run and Connect Optical Fiber Cable (Section 2.4.5) before lifting the 9710 C-WBS onto the top of a mast or tower.

78 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

2.5.5.3 Lift 9710 C-WBS


To lift the 9710 C-WBS: 1. Move the 9710 C-WBS to the position where it will be mounted. 2. Lift the 9710 C-WBS to the required level, using the lifting ring. 3. Move the 9710 C-WBS nearer to the MOFRA/MOFRAL. 4. Install the 9710 C-WBS on the MOFRA/MOFRAL. Put the hanger onto the hook of the MOFRA/MOFRAL.

Figure 62: Install 9710 C-WBS on the MOFRA 5. Fix the 9710 C-WBS with the two clamps, from the lower side. Do not damage the connectors during the operation.

3BK 17435 3011 RJZZA Ed.12

79 / 110

2 Scenario for 9710 C-WBS Installation

2.6 Option: Install the Fan Hat


2.6.1 Option: Install the Lock Plate
2.6.1.1 Materials
The following table lists the materials required to fix the lock plate on the CEBOX. Description Lock Plate Reference 3BK 27638 AAAA Kit MPP-Lock Plate

2.6.1.2 Install the Lock Plate


To install the lock plate 1. Close the CEBOX. 2. Install the lock plate in the bottom part of the CEBOX.

Figure 63: Install Lock Plate

80 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

2.6.2 Fix the Fan Hat on the Cover


This section describes how to fix the fan hat on top of the cover. To fix the fan hat on the cover: 1. Unpack the fan hat. 2. Assemble the back cover on the 9710 C-WBS. 3. Assemble the fan hat together with the back cover and fix them with three screws, as shown in the following figure.

Figure 64: Fixing Fan Hat on Back Cover V1

3BK 17435 3011 RJZZA Ed.12

81 / 110

2 Scenario for 9710 C-WBS Installation

Figure 65: Fixing Fan Hat on Back Cover V2 After the Fan Hat is assembled to the 9710 C-WBS, the Fan Hat cable must be connected to the 9710 C-WBS; see section Connect Fan Hat (Section 2.6.3).

82 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

2.6.3 Connect Fan Hat


This section describes how to run and connect the fan hat cable to the 9710 C-WBS. To connect the fan hat: 1. Run the fan cable along the 9710 C-WBS, on the bottom side. 2. Remove from the 9710 C-WBS unit the fan hat connector cover. 3. Connect the fan hat cable to the 9710 C-WBS unit and screw up it, as shown in the following figure.

Figure 66: Connecting Fan Hat Cable on 9710 C-WBS Unit After the Fan Hat is connected to the 9710 C-WBS, the fans starts automatically; the fans speed is adjusted in function of the temperature.

3BK 17435 3011 RJZZA Ed.12

83 / 110

2 Scenario for 9710 C-WBS Installation

2.6.4 Put Front Cover on 9710 C-WBS


This section describes how to assemble the fan hat front cover. To put the front cover on the 9710 C-WBS: 1. Put the front cover on the 9710 C-WBS. 2. Assemble the back and front covers together. 3. Tighten the screws at the bottom of the cover.

Figure 67: Fix Cover

2.6.5 Put Front Cover V2 on 9710 C-WBS


This section describes how to assemble the front cover V2. To put the front cover V2 on the 9710 C-WBS: 1. Put the front cover V2 on the 9710 C-WBS. 2. Assemble the back and front covers together. 3. Tighten the screws at the bottom of the cover V2.

Figure 68: Fix Cover V2

84 / 110

3BK 17435 3011 RJZZA Ed.12

2 Scenario for 9710 C-WBS Installation

2.7 Finish Installation


2.7.1 Close Cover
To close the cover: 1. Close the cover using the two screws provided. 2. Fix the front cover onto the back cover, if necessary, as shown in the following figure.

Figure 69: Fix Front Cover onto Back Cover 3. Close and lock the bottom cover and the fan cover. 4. Close and lock the power box (if necessary).

Figure 70: Close Bottom Cover

3BK 17435 3011 RJZZA Ed.12

85 / 110

2 Scenario for 9710 C-WBS Installation

2.7.2 Before You Leave


Before leaving the site: 1. Clean the site. 2. Lock the door. 3. Return the keys to the key owner.

86 / 110

3BK 17435 3011 RJZZA Ed.12

3 Scenario for 9710 C-WBS Commissioning

3 Scenario for 9710 C-WBS Commissioning


This Scenario presents all checks needed before beginning the scenario, and all detailed tasks to be performed on each site.

3BK 17435 3011 RJZZA Ed.12

87 / 110

3 Scenario for 9710 C-WBS Commissioning

3.1 Initial Checks


3.1.1 Before Going Onsite
Before going onsite, you must check that the following information and supplies are available: All Prerequisites for 9710 C-WBS Commissioning (Section 1.2.1.2) are met The customer has been informed of the: Date and time Site name and address Purpose of operation. Personnel are available (refer to Scheduling (Section 1.3)) Site Specific Information for 9710 C-WBS Commissioning (Section 1.2.2.2) is available Tools (Section 1.5.1) are available and ready for operation. Verify the calibration label when indicated in tool kit list. Supplies (Section 1.5.2) are available and ready for operation Applicable Documents (Section 1.5.3) are available.

3.1.2 Before You Start


3.1.2.1 Checks
Perform the following operations: Check that all Prerequisites for 9710 C-WBS Commissioning (Section 1.2.1.2) are met Check the availability of all necessary Tools (Section 1.5.1) and Supplies (Section 1.5.2) Check that safety precautions are taken according to the WiMAX General Safety Instructions Complete the header field of the Completion Check List (CCL). The CCL must be completed as each commissioning instruction is carried out. Refer to External Task (Section 1.2.3) for the additional tasks Check that the resistance of the antistatic wrist strap is greater than 1 M . Connect the antistatic wrist strap to the earth rack. Inform the operator, and ask him if you can start now.

88 / 110

3BK 17435 3011 RJZZA Ed.12

3 Scenario for 9710 C-WBS Commissioning

3.1.2.2 Required Knowledge


You must be familiar with the following: Safety rules and precautions; refer to the WiMAX General Safety Instructions Grouped Task Sequence for 9710 C-WBS Commissioning (Section 1.1.7.2) Telecom/Supervision Outage and Operating Impact (Section 1.4). How to document faults and anomalies.

3.2 Cabling Checks


Note:
For a first time installation, the tasks in this section have already been performed. Perform this section only for a separate commissioning.

3.2.1 Check Earth and Hybrid Cables


Check if the Earth and Hybrid cables are correctly installed.

Help:

For more information about Earth and Hybrid cable connection, refer to Run and Connect Earth Cable (Section 2.4.1) and Run and Connect Hybrid Cable (Section 2.4.2).

3.2.2 Check Antenna Jumpers


Check if: The antenna jumpers are connected to the antenna feeders The other end of the antenna jumper is connected to the 9710 C-WBS The antenna feeder is connected to the AAS The GPS antenna cable is connected to the 9710 C-WBS.

Help:

For more information about antenna jumper, refer toRun and Connect the Antenna Jumpers (Section 2.4.6).

3BK 17435 3011 RJZZA Ed.12

89 / 110

3 Scenario for 9710 C-WBS Commissioning

3.3 Check Power Up (On)


This section describes the 9710 C-WBS power checks. Before checking that the 9710 C-WBS is powered up, ensure that the Safety Precautions have been taken according to the WiMAX General Safety Instructions. The protective earth is connected to the equipment earth terminal. To check that the 9710 C-WBS is powered up: 1. Check the site power panel to ensure that the breakers are OFF. 2. Disconnect the hybrid cable from the 9710 C-WBS. 3. Using a multimeter, check at the hybrid connection box or power box that there is no voltage between L (line) and N (neutral) , N and PE (protective earth), L and PE. 4. Switch ON the circuit breakers at the site power panel. 5. Check the voltage between line (L) and neutral (N) on the hybrid cable. 6. Check that there is no voltage between N and PE. 7. Check that there is full voltage between L and PE. 8. Switch OFF the circuit breakers at the site power panel. 9. Run and Connect Hybrid Cable (Section 2.4.2) to the 9710 C-WBS unit. 10. Switch ON the breakers.

3.4 Commissioning Preparation


This section describes how to prepare commissioning.

3.4.1 Install NEM-B Software on LMT PC


This section describe how to prepare the LMT PC, if it is not already done. Note Input Task Description Install NEM-B Software on LMT PC (if not done) Site 9710 C-WBS To do 5 min. Outage None

To install the NEM-B software on the LMT PC: 1. Install NEM-B Application on the LMT PC. See Tools (Section 1.5.1) for the necessary supplies. 2. If needed, Upgrade NEM-B Software from CD-ROM.

90 / 110

3BK 17435 3011 RJZZA Ed.12

3 Scenario for 9710 C-WBS Commissioning

3.4.2 Connect LMT on 9710 C-WBS


Note Task Description LMT connection on 9710 C-WBS Site 9710 C-WBS To Do 2 min. Outage None

To connect the NEM-B to the 9710 C-WBS: 1. Open the CEBOX. 2. Use an Ethernet cable to connect (locally) the NEM-B to the 9710 C-WBS NEM port (Figure 27). When the 9710 C-WBS is installed on tower/mast, connect (locally) the NEM-B to the 9710 C-WBS using the NEM connector from DDF. 3. Start the NEM-B Application. 4. Type the 9710 C-WBS IP address (according to the 9710 C-WBS and 9715 L-WBS Service Reference Sheet). 5. Click on [ Connect ]. 6. Type the 9710 C-WBS User and Password (according to the 9710 C-WBS and 9715 L-WBS Service Reference Sheet). 7. Click on [ Continue ]. For a first commissioning an information window appears. In this case, only the 9710 C-WBS software replacement is possible.

Figure 71: Information Window Click on [ OK ].

3BK 17435 3011 RJZZA Ed.12

91 / 110

3 Scenario for 9710 C-WBS Commissioning

3.4.3 Allocate Configuration Rights


Note Task Description Allocate configuration rights Site 9710 C-WBS NEM-B To Do 1 min. Outage None

To allow the commissioning mode, the BS CommunicationState must be in offline mode. From the NEM-B menu, select Configuration->Allocate Configuration Rights.

3.4.4 Edit Additional Modules (Optional)


This section describe how to edit additional modules with Remote Inventory. MNEMO WAIN WAIN-UL WAING MFCC
xx, yy

Reference 3BK 27741 AAxx 28022 AAxx tbc 08681 BA xx

ICS 01 01 01 yy

Comments External alarm External alarm External alarm Top cover with fan

Nbr. 1 1 1 1

: Depending on the versions installed onsite

Table 7: Additional Modules List and Part Numbers

Note:

Functional variants (AA, AB, BA, ...) and ICS could be change without manual update.

3.4.4.1 Edit External Alarm Module


Note Task Description Add external alarm module Site 9710 C-WBS NEM-B To Do 5 min. Outage None

To add the external alarm module: 1. From the NEM-B selection bar select the Tree View. 2. From the Tree View select the Hardware Modules. 3. In the right window click on the Remote Inventory tab. 4. Right click on the C-WBS unit and select Edit Additional Modules. 5. The "Additional Modules" window opens.

92 / 110

3BK 17435 3011 RJZZA Ed.12

3 Scenario for 9710 C-WBS Commissioning

6. In the "Additional Modules" window click on the [ Add ] button to add the module. 7. Type the following module data: How many Part number ICS. 8. Click on [ OK ] to accept the settings.

3.4.4.2 Edit Top Cover with Fan


Note Task Description Add top cover with fan Site 9710 C-WBS NEM-B To Do 5 min. Outage None

To add the external alarm module: 1. From the NEM-B selection bar select the Tree View. 2. From the Tree View select the Hardware Modules. 3. In the right window click on the Remote Inventory tab. 4. Right click on the C-WBS unit and select Edit Additional Modules. 5. The "Additional Modules" window opens. 6. In the "Additional Modules" window click on the [ Add ] button to add the module. 7. Type the following module data: How many Part number ICS. The Part number and the ICS number can be tacked from the label of the equipment. 8. Click on [ OK ] to accept the settings.

3BK 17435 3011 RJZZA Ed.12

93 / 110

3 Scenario for 9710 C-WBS Commissioning

3.5 Commissioning without Commissioning Wizard


3.5.1 Check 9710 C-WBS Software Version
For a first commissioning, perform only the 9710 C-WBS software replacement, as described in 9710 C-WBS and 9715 L-WBS Software Replacement.

Note

Task Description Check 9710 C-WBS software version

Site 9710 C-WBS NEM-B

To Do 10 min.

Outage None

To check which 9710 C-WBS software version is installed: 1. From NEM-B, open the General BS Status window. 2. Display Software Configuration. 3. Compare the current software version with the software version required for commissioning. 4. If needed, replace the 9710 C-WBS software with the 9710 C-WBS software version needed for commissioning, as described in 9710 C-WBS and 9715 L-WBS Software Replacement.

3.5.2 Initial Parameters Settings


3.5.2.1 9710 C-WBS Identity Information
Note Task Description Edit 9710 C-WBS identity information Site 9710 C-WBS To Do 2 min. Outage None

To edit the basic configuration: 1. From the NEM-B menu, select Configuration->Edit Basic Configuration. 2. Type the following 9710 C-WBS logical parameters; refer to the 9710 C-WBS and 9715 L-WBS Service Reference Sheet: BS Logical Name BS Location Name Network Identity.

94 / 110

3BK 17435 3011 RJZZA Ed.12

3 Scenario for 9710 C-WBS Commissioning

3.5.2.2 Change 9710 C-WBS IP Settings


Note Task Description Change 9710 C-WBS IP settings Site 9710 C-WBS To Do 2 min. Outage None

To change 9710 C-WBS IP settings: 1. From the NEM-B menu, select Configuration->Change Base Stations IP Settings. 2. Select the DHCP mode (according to the 9710 C-WBS and 9715 L-WBS Service Reference Sheet).In case of VLAN Tagging select the DHCP mode Not-used and type the following addresses; refer to the 9710 C-WBS and 9715 L-WBS Service Reference Sheet: Manual OAM IP Address Manual OAM Netmask Manual OAM IP Gateway Manual Trans IP Address Manual Trans IP Netmask Manual Trans IP Gateway 3. Click-on [ OK ]. The addresses must be inline with the 9753 OMC site. Contact the 9753 OMC team for confirmation. Refer to the 9710 C-WBS and 9715 L-WBS Service Reference Sheet.

3.5.2.3 Edit Basic Configuration


Note Task Description Edit basic configuration Site 9710 C-WBS To Do 2 min. Outage None

To edit the basic configuration: 1. From the NEM-B menu, select Configuration->Edit Basic Configuration. 2. Select values for the next parameters (if the 9710 C-WBS is not alone): BS Topology (starTopology or chainTopology) Position in Chain (first, second, or third) BS Mount Type (atGroundLevel, onMast or inCabinet)

Note:

If the Ethernet cable from the Hybrid cable is used, in the BS Mount Type field, select onMast.

3BK 17435 3011 RJZZA Ed.12

95 / 110

3 Scenario for 9710 C-WBS Commissioning

Enable Ethernet Taging. In case of VLAN Tagging from the drop down menu, select true. OAM VLAN ID. 3. Type the name of Antenna Model. 4. Select the AAS Antenna Model: RFS:W4A25-90ANV when the frequency band is between 2.3GHz and 2.7GHZ RFS:W4A35-90ANV when the frequency band is between 3.3GHz and 3.8GHZ ANDREW:APW425-12014-ON when the frequency band is between 2.3GHz and 2.7GHZ ANDREW:APW435-12014-ON when the frequency band is between 3.3GHz and 3.8GHZ.

3.5.2.4 Edit Antenna Ports


Note Task Description Edit antenna ports Site 9710 C-WBS To Do 2 min. Outage None

To edit antenna: 1. From the Tree Navigation Window , click on the [ Antennta Ports ]. 2. Select the General tab. 3. Right-click on the ANT1 and select Edit. 4. Type the next parameters (refer to the 9710 C-WBS and 9715 L-WBS Service Reference Sheet): Antenna Gain Antenna Feeder Loss Adress type of atcId Antenna Device Controller Id Antenna Tilt Device Id. 5. Repeat the steps (3) and (4) for each antenna (ANT2, ANT3 and ANT4). 6. Click-on [ OK ]. To edit antenna port assignment: 1. From Tree Navigation Window , click on Display General Antenna Status and Assign/Unassign Sector. 2. Select the General tab. 3. Right-click on the ANT1and select Assign Sector->Sector1. 4. Right-click on the ANT2 and select Assign Sector->Sector1.

96 / 110

3BK 17435 3011 RJZZA Ed.12

3 Scenario for 9710 C-WBS Commissioning

5. Right-click on the ANT3 and select Assign Sector->Sector1. 6. Right-click on the ANT4 and select Assign Sector->Sector1. To edit transmitter modules: 1. From Tree Navigation Window , click on Display General Antenna 2. Select the General tab. 3. Right-click on the ANT1and select Assign Transmitter->26. 4. Right-click on the ANT2 and select Assign Transmitter->27. 5. Right-click on the ANT3 and select Assign Transmitter->28. 6. Right-click on the ANT4 and select Assign Transmitter->29.

3.5.2.5 Edit Clock Configuration


Note Task Description Edit clock configuration Site 9710 C-WBS To Do 2 min. Outage None

To edit the Clock Configuration: 1. From the NEM-B menu, select Configuration->Clock Configuration. 2. In the clock configuration window, select the Clock Synchronization Source: If a GPS antenna is used, gps-synchronised If a GPS antenna is not used, free-running. 3. Click-on [ OK ]. The 9710 C-WBS resets.

3.5.2.6 Edit External Alarms (Optional)


Note Task Description Edit external alarms Site 9710 C-WBS To Do 5 min. Outage None

To edit external alarms: 1. From the Tree View, select Alarms -> External Alarms. 2. Right click on port number, select Edit. 3. The "Edit External Alarms" window opens. 4. Click on the Monitored Attribute part and declare the external alarm name. 5. Click OK. The external alarm is declared. 6. Repeat all steps for all four external alarms port.

3BK 17435 3011 RJZZA Ed.12

97 / 110

3 Scenario for 9710 C-WBS Commissioning

3.5.3 Commissioning Tests


3.5.3.1 Transmitter Power Test
During the transmitter power test nobody should stay close to the beam antenna (see WiMAX General Safety Instructions manual.

Note

Task Description Transmitter power test

Site 9710 C-WBS

To Do 3 min.

Outage None

To perform transmitter power tests: 1. From the NEM-B menu, open the Power Test window. 2. Type the following parameters: TX power level, in dBm, at antenna connectors (between 25.0 and 35.0dBm)

Note:

Use the maximum TX power level for test: 35.0 dBm. Test frequency: For 9710 C-WBS at 2.3GHz choose the frequency between 2300000 and 2400000kHz For 9710 C-WBS at 2.5GHz choose the frequency between 2496000 and 2690000kHz For 9710 C-WBS at 3.5GHz choose the frequency between 3400000 and 3600000kHz Test duration: between 1 and 10080minutes. 3. Select the test bandwidth: bw5MHz, bw7MHz, bw8MHz or bw10MHz. 4. Select the test mode: disabled, mode1, mode2, mode3, mode4. 5. In the FEU Selection part, click on [ >> ] to move all Available FEUs to Selected FEUs. 6. Click on [ Start ] and then confirm with [ Yes ] to run test. 7. Check in the Test Status field if the test-ok message appears after the test duration is finished. 8. Click on [ Close ] to quit the test.

98 / 110

3BK 17435 3011 RJZZA Ed.12

3 Scenario for 9710 C-WBS Commissioning

3.5.3.2 VSWR Measurement Test

RESTRICTION

The VSWR measurement test is currently not implemented.

Note

Task Description VSWR Measurement Test

Site 9710 C-WBS

To Do 6 min.

Outage None

To perform the VSWR measurement test: 1. From the NEM-B menu, open the VSWR Measurement Test window 2. Type the test parameters: Test power level, in dBm, at antenna connectors (between 15.0 and 35.0 dBm) Test frequency: For 9710 C-WBS at 2.3GHz choose the frequency between 2300000 and 2400000kHz For 9710 C-WBS at 2.5GHz choose the frequency between 2496000 and 2690000kHzz For 9710 C-WBS at 3.5GHz choose the frequency between 3400000 and 3600000kHz VSWR Warning Threshold Margin (leave default 5 dB) VSWR Urgent Threshold (leave default 30dB) 3. In Selectable Antennas, select the antennas [ ANT 1/ANT 2/ANT 3/ANT 4 ]. 4. Click on [ Start Measurement ]. 5. Click on [ Yes ] to run the test. 6. After a successful test, confirm the new VSWR Warning Threshold with [ YES ] to store the values in the 9710 C-WBS. The results appear in the NEM-B window 7. Click on [ Close ] to quit the test. Use the maximum TX power level for test: 35,0 dBm The recommended value for the VSWR test is the maximum TX Power.

3BK 17435 3011 RJZZA Ed.12

99 / 110

3 Scenario for 9710 C-WBS Commissioning

Display the Antenna Ports VSWR view and, for each antenna port, modify the VSWR threshold values in order to have: 1. Warning Threshold = "5". 2. Urgent Threshold = "30". If the VSWR Measurement Test is not successful, use this task to modify the Threshold.

3.5.3.3 External Alarm Test


Before starting the external alarm test the WAIN / WAIN-UL / WAING board must be added at the 9710 C-WBS (see Edit Additional Modules (Optional) (Section 3.4.4)).

Help:

In the 9710 C-WBS, the external alarm are connected to WAIN / WAIN-UL / WAING board (inside the CEBOX) (see Run and Connect the External Alarm Lines (Section 2.3.1.5)). Site 9710 C-WBS To Do 16 min. Outage None

Note

Task Description External alarm test

To perform external alarm test: 1. Open the Alarms. 2. View and check in External Alarm that all used ports are connected (declared).

3. Connected external alarm, check if the alarm appears (after about 10 seconds). 4. Undo all changes for external alarm test and check in the Alarms view if the external alarm disappears (after about 10 seconds).

100 / 110

3BK 17435 3011 RJZZA Ed.12

3 Scenario for 9710 C-WBS Commissioning

3.5.3.4 Fan Hat Alarm Test


Note Task Description Fan hat alarm test Site 9710 C-WBS To Do 16 min. Outage None

To perform fan hat alarm test: 1. Remove the fan hat cable from the 9710 C-WBS unit. 2. Open the Alarms. 3. View and check in External Alarm. The fan hat alarm appear. 4. Reconnect the fan cover cable to the 9710 C-WBS (see Connect Fan Hat (Section 2.6.3)) and check in the Alarms view if the alarm disappear (after about 10 seconds).

3BK 17435 3011 RJZZA Ed.12

101 / 110

3 Scenario for 9710 C-WBS Commissioning

3.6 Commissioning Using Commissioning Wizard


Note:
For a first commissioning, the commissioning wizard is not available. UseCommissioning without Commissioning Wizard (Section 3.5) to perform 9710 C-WBS commissioning. To perform commissioning using commissioning wizard: 1. From the NEM-B, click on Commissioning Wizard button. 2. A warning window appears. Click on [ OK ]. In the left part of the window appears commissioning tree with all steps which have to be performed. 3. In the "Commissioning" window click on [ Next ]. 4. In the "Wizard" window click on [ Next ]. 5. After software replacement the commmissioning wizard must be restarted. To restart commissioning wizard: Click on the General BS Status button The "Leave Commissioning Wizard" window appear. This window informs you If you left the commissioning wizard window all data will be lost.

Figure 72: Leave Commissioning Window Click on [ OK ]. Click on again the Commissioning Wizard button A warning window appears.

Figure 73: Enter Commissioning Window Click on [ OK ].

Note:

The commissioning is open again and now in the commissioning tree appears all the steps required to perform commissioning. In the "Commissioning" window click on [ Next ]. In the "Wizard" window click on [ Next ]. 6. The "Load Configuration" window appears. Verify the current values and if is necessary modify target values. To load a commissioning wizard configuration previously saved: Click on [ Load ]

102 / 110

3BK 17435 3011 RJZZA Ed.12

3 Scenario for 9710 C-WBS Commissioning

Load configuration as is described in Load Existing Configuration (Option) section from NEM-B User Guide manual. Click on [ Apply ] Click on [ Next ] to continue the commissioning. 7. The "Running Software" window appears. Click on [ Apply ]. Click on [ Next ]. 8. The "Hardware Modules" window appears. Click-on [ Apply ]. To configure hardware modules refer to Configure Hardware Modules section from NEM-B User Guide. Click on [ Next ]. 9. The "Remote Inventory" window appear. In this window you can edit the remote inventory information for a specific module or commissioning dates for all modules. To edit the remote inventory, refer to Remote Inventory Data from NEM-B User Guide manual. Click on [ Apply ] to submit the settings. Click on [ Next ] to continue the commissioning wizard. 10. The "Network Interfaces" window appear. In this window you can lock/unlock the network interfaces.To unlock the network interfaces: In the "Target Values" window, right click on the target interface and select Unlock Click on [ Apply ] to submit the settings. Click on [ Next ] to continue the commissioning wizard. 11. The "Basic Configuration" window appear. In this window you can edit basic configuration.To edit 9710 C-WBS identity information: Click on [ Edit ] button Type the following 9710 C-WBS logical parameters (refer to the 9710 C-WBS and 9715 L-WBS Service Reference Sheet and ): BS Logical Name BS Location Name Network Identity Select values for the next parameters (if the 9710 C-WBS is not alone): BS Topology (starTopology or chainTopology) Position in Chain (first, second, or third) BS Mount Type (atGroundLevel or onMast).

Note:

If the Ethernet cable from the Hybrid cable is used, in the BS Mount Type field, select onMast.

3BK 17435 3011 RJZZA Ed.12

103 / 110

3 Scenario for 9710 C-WBS Commissioning

Enable Ethernet Taging. In case of VLAN Tagging from the drop down menu, select true. OAM VLAN ID Type the name of Antenna Model. Select the AAS Antenna Model: ANDREW:APW425-12014-ON when the frequency band is between 2.3GHz and 2.7GHZ ANDREW:APW435-12014-ON when the frequency band is between 3.3GHz and 3.8GHZ. Click on [ OK ]. Click on [ Apply ] to submit the settings. Click on [ Next ] to continue the commissioning wizard. 12. The "IP Settings" window appear.To edit IP settings: Click on [ Edit ] button Select Imperative-usage for DHCP mode Click on [ OK ] Click on [ Apply ] to submit the settings Click on [ Next ] to continue the commissioning wizard. 13. The Antenna Ports window appear. Click on [ Next ] to continue with the general parameters commissioning. 14. The "General Parameters" window appear.To edit antenna: In the "Target Values" window, right-click on the ANT1and select Edit Type the next parameters (according to the 9710 C-WBS and 9715 L-WBS Service Reference Sheet): Antenna Gain Antenna Feeder Loss. Repeat the steps for each antenna (ANT2, ANT3 and ANT4). Click-on [ OK ]. To edit antenna port assignment: In the "Target Values" window, right-click on the ANT1and select Assign Sector->Sector1 Right-click on the ANT2 and select Assign Sector->Sector1 Right-click on the ANT3 and select Assign Sector->Sector1 Right-click on the ANT4 and select Assign Sector->Sector1 To edit antenna transmitter assignment:

104 / 110

3BK 17435 3011 RJZZA Ed.12

3 Scenario for 9710 C-WBS Commissioning

In the "Target Values" window , right-click on the ANT1and select Assign Transmitter->26 Right-click on the ANT2 and select Assign Transmitter->27 Right-click on the ANT3 and select Assign Transmitter->28 Right-click on the ANT4 and select Assign Transmitter->29 Click on [ Apply ]. Click on [ Next ]. 15. The "VSWR Parameters" window appears.To modify the VSWR threshold settings: In the "Target Values" window, double click on the target antenna The Antenna Port VSWR dialog box opens. Enter the threshold values required (max. 30). When the VSWR is activated, the threshold values can be entered. When the VSWR is deactivated, threshold values cannot be entered. Click on [ OK ] to submit . Click on [ Apply ]. Click on [ Next ]. 16. The "Sectors Configuration" window appears. Click on [ Next ]. 17. The "Clock Configuration" window appears.To edit clock: In the "Target Values" window, click on [ Edit Clock ] In the "Clock Configuration" window, select the Clock Syncronization Source: If a GPS antenna is used, gps-syncronised If a GPS antenna is not used, free-running Click on [ OK ]. Click on [ Apply ]. Click on [ Next ]. 18. The "Alarms" window appears. Click on [ Next ]. 19. The "External Alarm" window appears.To perform external alarm test: View and check in External Alarm that all used ports are connected (declared). Connected external alarm , check if the alarm appears (after about 10 seconds). Undo all changes for external alarm test and check in the Alarms view if the external alarm disappears (after about 10 seconds).

3BK 17435 3011 RJZZA Ed.12

105 / 110

3 Scenario for 9710 C-WBS Commissioning

To perform fan cover alarm test Remove the fan hat cable from the 9710 C-WBS unit Open the Alarms View and check in External Alarm. The fan hat alarm appear Reconnect the fan hat cable to the 9710 C-WBS (see Connect Fan Hat (Section 2.6.3)) and check in the Alarms view if the alarm disappear (after about 10 seconds) 20. The "Alarm Filtering Options" window opens. Click on [ Apply ]. Click on [ Next ]. 21. The "Alarm Severity Definitions" window opens. Click on [ Apply ]. Click on [ Next ]. 22. The "Save" window appears.To save commissioning in a .xml file: Click on [ Save ] A browser window to select the configuration file appears. Select the file and click on the [ Save ] button to save the selected file After successfully saved, the Save Configuration tab will be marked OK. Click on [ Next ] to continnue the commissioning. 23. The "Tests" window appears. Click on [ Next ] to continnue the commissioning. 24. The "Transmitter Test" window appears.To perform transmitter power test: Click on [ Start ] Type the following parameters: TX power level, in dBm, at antenna connectors (between 15.0 and 35.0dBm)

Note:

Use the maximum TX power level for test: 35.0 dBm. Test frequency: For 9710 C-WBS at 2.3GHz choose the frequency between 2300000 and 2400000kHz For 9710 C-WBS at 2.5GHz choose the frequency between 2496000 and 2690000kHzz For 9710 C-WBS at 3.5GHz choose the frequency between 3400000 and 3600000kHz Test duration: between 1 and 10080minutes. Select the test bandwidth: bw5MHz, bw7MHz, bw8MHz or bw10MHz Select the test mode: disabled, mode1, mode2, mode3, mode4 In the FEU Selection part, click on [ >> ] to move all Available FEUs to Selected FEUs

106 / 110

3BK 17435 3011 RJZZA Ed.12

3 Scenario for 9710 C-WBS Commissioning

Click on [ Start ] and then confirm with [ Yes ] to run test Check in the Power Test Result field if the test-ok message appears after the Test duration is finished (2 minutes) Click on [ Close ] If the test was performed, click on [ Test OK ] or on [ Test NOK ]. Click on [ Next ] to continue commissioning. 25. The "VSWR Measurement Test" window appears. The VSWR measurement test is currently not implemented. Click on [ Next ]. To perform VSWR measurement test: Click on [ Start ] Type the test parameters: Test power level, in dBm, at antenna connectors (between 15.0 and 35.0 dBm) Test frequency: For 9710 C-WBS at 2.3GHz choose the frequency between 2300000 and 2400000kHz For 9710 C-WBS at 2.5GHz choose the frequency between 2496000 and 2690000kHzz For 9710 C-WBS at 3.5GHz choose the frequency between 3400000 and 3600000kHz VSWR Warning Threshold Margin (leave default 5dB) VSWR Urgent Threshold (leave default 30dB) In Selectable Antennas, select the antennas[ ANT 1/ANT 2/ANT 3/ANT 4 ] Click on [ Start Measurement. ] Click on [ Yes ] to run the test. After a successful test, confirm the new VSWR Warning Threshold with [ YES ] to store the values in the 9710 C-WBS. Click on [ Close ] If the test was performed, click on [ Test OK ] or on [ Test NOK ]. Click on [ Next ] to continue commissioning. 26. The "Set Commissioning Date" window appears. In the "Target Values" window select a row, right-click and select [ Set Commissioning Date for all Modules ] to trigger the date setting. Click on [ Apply ]. Click on [ Next ].

3BK 17435 3011 RJZZA Ed.12

107 / 110

3 Scenario for 9710 C-WBS Commissioning

27. The "Results" window appears. 28. To leave the commissioning wizard: Click on the General BS Overview button The "Leave Commissioning Wizard" window appear. This window informs If you left the commissioning wizard window all data will be lost.

Figure 74: Leave Commissioning Window Click on [ OK ].

108 / 110

3BK 17435 3011 RJZZA Ed.12

3 Scenario for 9710 C-WBS Commissioning

3.7 Final Checks


3.7.1 Check Hardware Modules
Note Task Description Check hardware modules Site 9710 C-WBS To Do 2 min. Outage None

To check the hardware modules: 1. From the NEM-B, display the Hardware Modules view and check that all is correct and the status is enabled for all modules (except for the 9710 C-WBS, which is disabled because the 9710 C-WBS is not connected to the 9740 WAC). 2. In Alarms, check that there are no alarms.

Note:

The Signalling Links are disabled because the 9710 C-WBS is not connected to the 9740 WAC.

3.7.2 Site Inventory


Note Task Description Site inventory Site 9710 C-WBS To Do 4 min. Outage None

To perform the site inventory: 1. From the NEM-B, display the Remote Inventory Data view (from the Hardware Modules view). 2. Right click on the row of the module and select Edit. 3. Save the inventory data with Write Remote Inventory File to the LMT PC. The location and name of the generated file appears on the bottom of the NEM-B screen. If needed, Setup NEM-B Preferences (the directory where the remote inventory file is saved). 4. Finish the Site Inventory: Complete the CCL with the required information (site name, operator name, ...) Save the completed file to a CD.

3BK 17435 3011 RJZZA Ed.12

109 / 110

3 Scenario for 9710 C-WBS Commissioning

3.7.3 Connection to Network


Note Task Description Connection the 9710 C-WBS to the Network Site 9710 C-WBS To Do 7 min. Outage None

To connect the 9710 C-WBS to the network: 1. Connect the 9710 C-WBS to the network; refer to Run and Connect Cables (Section 2.4). 2. Check Hardware Modules (Section 3.7.1). 3. If the 9710 C-WBS - 9753 OMC connection is ready, contact the 9753 OMC teams and ask them to ping the 9710 C-WBS from the 9753 OMC (using the client PC).

3.8 Before You Leave


Note Task Description Finish the commissioning Site 9710 C-WBS To Do 5 min. Outage None

Before you leave: 1. From the NEM-B menu, Release Configuration Rights (online) to exit the commissioning mode. 2. Exit NEM-B Software and disconnect the cable between the PC and the 9710 C-WBS. 3. If the access to Alcatel-Lucent 9117 L-WBS is possible check if the GPS LED is blue and blink once per sec. 4. Close the CEBOX. Tighten the all four screws with recommanded torque 3,5Nm. 5. Complete the CCL and the site log book. 6. Clean the site (remove packaging and remaining materials). 7. Close the site and hand the keys to the key holder. Return the CCL, with the floppy disk supporting the final inventory file, to base.

110 / 110

3BK 17435 3011 RJZZA Ed.12

Anda mungkin juga menyukai