Anda di halaman 1dari 10

December Edition

2012

MINISTRY OF EDUCATION, MALAYSIA VOCATIONAL COLLEGE STANDARD CURRICULUM MODULE INFORMATION

MODULE CODE LEVEL CREDIT UNIT CONTACT HOUR

: : : : :

SHALLOW AND DEEP FOUNDATION CCT 105 1 SEMESTER 1 2.0 FACE TO FACE NON FACE TO FACE : 4.0 HOURS/WEEK :

MODULE TYPE PREREQUISITE CORE REQUISITE

: : :

VOCATIONAL -

Last Edited Module Page

03 06 Dec 2012 1/10 Document Page 1

December Edition

2012

MODULE OUTCOMES: At the end of the module, students should be able to:1. 2. 3. 4. 5. 6. 7. 8. 9. avoid workplace hazards. maintain cleanliness of work area and equipment. follow basic security procedure. setting out and excavate trenches for shallow trench. provide pest control services. construct timbering and shoring. pour and screed lean concrete on the trenches bed. perform piling works. perform pile cap works.

MODULE DESCRIPTION This module is designed as an introduction to students about shallow trenches set up and excavation, pest control services, timbering and shoring construction, the pouring and screeding of lean concrete on trenches bed, piling work and pile cap work. Students will be exposed to the instructions and procedures of the work that suit the current industrial needs. They will learn how to use all the necessary plans, tools and equipment so that the work can be proceeded according to the work specifications. They will also be introduced to the roles of supervisory. Workplace safety guidance material is also included in this module that contributes to the state of knowledge about hazards and risks and the ways of removing or reducing the hazard and risk.

Last Edited Module Page

03 06 Dec 2012 2/10 Document Page 2

December Edition

2012

CONTENT AND LEARNING STANDARDS COURSE MODULE CODE : : : CONSTRUCTION TECHNOLOGY SHALLOW AND DEEP FOUNDATION CCT 105

CONTENT STANDARD 1. SETTING OUT AND EXCAVATING TRENCHES FOR SHALLOW TRENCH 1.1

LEARNING STANDARD Set out measurements for excavation 1.1.1

PERFORMANCE CRITERIA Set out the measurements for shallow trench excavation.

1.2

Identify and select tools for manual excavation Perform manual excavations Arrange the machinery for excavation work Maintain the tools after an excavation work Keep the record for daily excavation work progress

1.2.1 Choose appropriate manual digging tools for shallow trenches

1.3 1.4

1.3.1 Perform excavation for shallow trenches manually 1.4.1 Identify the type of machines for digging deep trenches

1.5

1.5.1 Cleans and maintain the tools after work for maintenance purposes. 1.6.1 Read the daily work progress on the excavation work performed

1.6

Last Edited Module Page

03 06 Dec 2012 3/10 Document Page 3

December Edition

2012

CONTENT AND LEARNING STANDARDS COURSE MODULE CODE : : : CONSTRUCTION TECHNOLOGY SHALLOW AND DEEP FOUNDATION CCT 105

CONTENT STANDARD

LEARNING STANDARD

PERFORMANCE CRITERIA

2. PROVIDING PEST CONTROL SERVICES

2.1

Determine the areas that require pest control treatment. Keep records of areas being serviced

2.1.1 2.1.2

Identify the areas that need pest control treatment. Mark the areas that need pest control treatment.

2.2

2.2.1 Record details of pest control services for the serviced area. 2.3.1 Perform site supervision of the serviced area.

2.3

Perform site supervision

Last Edited Module Page

03 06 Dec 2012 4/10 Document Page 4

December Edition

2012

CONTENT AND LEARNING STANDARDS COURSE MODULE CODE : : : CONSTRUCTION TECHNOLOGY SHALLOW AND DEEP FOUNDATION CCT 105 LEARNING STANDARD LEARNING STANDARD

CONTENT STANDARD

3. CONSTRUCT TIMBERING AND SHORING

3.1 Determine the size of timber to shore up the bank of the shallow trenches.

3.1.1 3.1.2

Determine the type of wood used for shallow trenches based on the detail blueprint. Determine the size of the wood used for the work concerned as specified in the detail blueprint.. Determine adequate materials needed for timbering and shoring construction as stated in the work specification. Transpot the selected timber to the worksite.

3.2 Supply and deliver timber to the work site

3.2.1

3.2.2

3.3 Prepare, measure and cut timbering and shoring materials correctly

3.3.1 Prepare the measurement and cutting of the timbering and shoring materials based on the blueprint. 3.4.1 Install wooden struts in the shallow trench in accordance to the detail blueprint.

3.4 Place the timbering and shoring materials accordingly 3.5 Clear debris and generate good work areas
03 06 Dec 2012 5/10

3.5.1 Clear debris at the site after the completion of the required work.

Last Edited Module Page

Document Page

December Edition

2012

CONTENT AND LEARNING STANDARDS COURSE MODULE CODE : : : CONSTRUCTION TECHNOLOGY SHALLOW AND DEEP FOUNDATION CCT 105 LEARNING STANDARD 4.1 Prepare work surface for pouring of the concrete. 4.2 Prepare the area for mixing of lean concrete. 4.3 Prepare the equipment and tools for the mixing of the lean concrete manually. 4.4 Mixing the lean concrete at the mixing place. LEARNING STANDARD 4.1.1 Prepare work surface for pouring of concrete at the location specified. 4.2.1 Prepare the area for mixing of the lean concrete at the location specified. List and prepare equipment and tools for mixing of the lean concrete manually.

CONTENT STANDARD

POUR AND SCREED LEAN CONCRETE ON THE TRENCH BEDS

4.3.1

4.4.1 4.4.2 4.4.3

State the materials and mix ratio for the lean concrete. Mix the lean concrete at the mixing place. Practise safety precautions while handling hand tools.

4.5 Pour and level the lean concrete to the required trench beds (on site mixing or ready-mixed concrete)

4.5.1 Pour and screed lean concrete on the trench beds by using appropriate tools so that a good and clean surface of screed lean can be obtained.

Last Edited Module Page

03 06 Dec 2012 6/10 Document Page 6

December Edition

2012

4.6 Maintain and generate a good work area

4.6.1 Clean the waste at the site after the completion of the work carried out.

Last Edited Module Page

03 06 Dec 2012 7/10 Document Page 7

December Edition

2012

CONTENT AND LEARNING STANDARDS COURSE MODULE CODE : : : CONSTRUCTION TECHNOLOGY SHALLOW AND DEEP FOUNDATION CCT 105 LEARNING STANDARD 5.1 Mark of the piling points 5 PERFORM PILING WORK PERFORMANCE CRITERIA 5.1.1 Interpret the blueprint given to locate the piling points 5.1.2 Perform the marking of piling points according to the blueprint given 5.2.1 Set up the piling rings frame while ensuring safety measures 5.3.1 Stake the piling materials on the project site while ensuring safety measures 5.3.2 Understand and communicate with the supervisor and machine operator using sign language 5.4.1 Perform the piling work with the supervision of the supervisor while ensuring safety measures 5.5.1 Check and mark the required level of the piles for cutting purposes 5.5.2 Perform the cutting of piles using appropriate machinery
Document Page 8

CONTENT STANDARD

5.2 Set up the piling rings frame

5.3 Stake the piling materials on project site

5.4

Perform piling work with the supervision of supervisor

5.5

Cut the piles according to the specification

Last Edited Module Page

03 06 Dec 2012 8/10

December Edition

2012

CONTENT AND LEARNING STANDARDS COURSE MODULE CODE : : : CONSTRUCTION TECHNOLOGY SHALLOW AND DEEP FOUNDATION CCT 105

CONTENT STANDARD

LEARNING STANDARD 6.1 Excavate earth for pile cap work according to the required area and depth. 6.2 Cut the pile to the cut off level.

PERFORMANCE CRITERIA 6.1.1 Demonstrate the excavation of earth surface for pile cap work to the required area and depth.

6. PERFORM PILE CAP WORK

6.2.1 Cut the pile to the cut off level by using proper power tools. 6.3.1 Prepare the work area to carry out cleaning work to install formwork. 6.4.1 Place and shape the formwork by referring to the blueprint given. 6.4.2 Place the lean concrete by using proper procedures and techniques. 6.5.1 Prepare the reinforcement bar for the pile cap

6.3 Prepare the work area for the placing of formwork. 6.4 Place the lean concrete to the required level.

Last Edited Module Page

03 06 Dec 2012 9/10 Document Page 9

December Edition

2012

6.5 Place reinforcement bar for the pile Cap.

according to the size needed. 6.5.2 Place reinforcement bar correctly. 6.5.3 Use and place spacer blocks under the reinforcement bar appropriately.

Last Edited Module Page

03 06 Dec 2012 10/10 Document Page 10

Anda mungkin juga menyukai