How to Develop a Work Breakdown Structure (WBS)

Andreas Apostolopoulos

Agenda

Apr 2013

www.esi-intl.co.uk

Objectives
By the end of this session youll be able to Identify WHERE and HOW WBS fits into the project cycle Understand WHAT a WBS is and WHY to use it in a project

Develop a WBS of a project that is assigned to you

Apr 2013

www.esi-intl.co.uk

Where a WBS fits into the project cycle ?

Apr 2013

www.esi-intl.co.uk

What is the Work Breakdown Structure (WBS)?


The WBS is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables PMBOK 4th Edition Guide pg. 116
Apr 2013 www.esi-intl.co.uk
Hierarchical Decomposition Work to be Executed Project Team

Project Objectives & Deliverables

WBS
5

Why the WBS Organizes & Defines Total Scope of the Project ?
Inputs
Project Scope Statement Requirements Documentation Organizational Process Assets

Tools & Techniques

Decomposition

Outputs

WBS WBS Dictionary Scope Baseline Project Document Updates


6

Apr 2013

www.esi-intl.co.uk

WBS vs WBS Dictionary

WBS

WBS Dictionary

Apr 2013

www.esi-intl.co.uk

Discussion Topic
As an Abbey IT project manager you are assigned a project to Install a computer network into an enterprise. You plan to create the WBS. For what information and resources you will ask for? How do you start?
Apr 2013 www.esi-intl.co.uk 8

WBS Styles

Top-down Tree

Mind Map

Outline
Apr 2013 www.esi-intl.co.uk 9

How Many Decomposition Levels?


Level 1
Project Level/ Summary Level Project

Level 2
Deliverable or Phase

Task 1

Task 2

Level 3
Sub-deliverables or Sub-phases Subtask 1 Subtask 2

Level 4
Work Package (Activity Level)
Apr 2013 www.esi-intl.co.uk

Work Package 1

Work Package 2
10

Common Mistakes to Avoid?


Using the WBS as a task list Organizing the WBS by organizational structure Time-phasing the WBS

A lack of traceability to the WBS

No leverage for change control

No support activities

Apr 2013

www.esi-intl.co.uk

11

Independent Case Study: Develop a WBS for your Personal Web site

Apr 2013

www.esi-intl.co.uk

12

IT Project Group Case Study Marconi Intranet Project

Apr 2013

www.esi-intl.co.uk

13

Review

Apr 2013

www.esi-intl.co.uk

14

Questions - Feedback Questions ??

Apr 2013

www.esi-intl.co.uk

15

Software Tools
Mind Mapping

Further Study
PMBOK 5th Edition Practice Standard for Work Breakdown Structures

Post-it

WBS Tools

Ms-Visio

http://www.matchware.com

http://www.pmi.org

Ms-Excel

MsWord

Apr 2013

www.esi-intl.co.uk

16

Thank You

Andreas Apostolopoulos aaposto62@gmail.com www.aaposto.weebly.com

Apr 2013

www.esi-intl.co.uk

17

Appendix A: Solution to Independent Case Study


About Me

Carrier History

Education

Skills

Interests

Contact

Company 1

Company 2

Company 3

MSc

Bachelor

IT

Languages

Role A

Role B

Java

C++

Unix

French

Greek

Apr 2013

www.esi-intl.co.uk

18

Appendix B:
WBS diagram for practical exercise (BLANK)

Apr 2013

www.esi-intl.co.uk

19

Appendix C: Solution to Group Case Study


Marconi Web site

About us

Products/Services

Purchase

Contac us

History

Mission

Employment

How to Order

Order Form

Price List

Telephone

Fax

Online

Apr 2013

www.esi-intl.co.uk

20

Anda mungkin juga menyukai