Parkway International Contracting (LLC)

Document No : FP-MS-003 Revision :0 Date : February 1, 2007 Page : 1 of 5

Index

1. Scope 2. References 3. Responsibilities 4. Procedures/Methods 5. Manpower Requirement 6. Material Requirement 7. Health & Safety Provision 8. Distribution 9. Check List

Parkway International Contracting (LLC)

Document No : FP-MS-003 Revision :0 Date : February 1, 2007 Page : 2 of 5

1. Scope /Objective/Purpose
The Scope of this Method Statement covers the application of Painting. The Purpose of this procedure is to ensure that the correct methods are employed during the application of paint and to achieve compliance with the contract specifications and manufacturers recommendations.

2. References
a) b) c) d) e) f) Approved material submittals for painting works. Quality system procedure material receipt and inspection. Approved project safety plan & procedures. Engineers' instructions. Project specifications. Manufacturers recommendations/Data sheet.

3. Responsibilities
The Project Manager & the Construction Managers are responsible for the over all operation of this procedure & its revision when deemed necessary and to delegate the responsibility to nominated Site Engineer to directly supervise the works on site. The nominated Site Engineers are responsible for ensuring that all the painting works are executed in accordance with the manufacturers paint application procedure and project specifications. The foreman responsible for painting works shall ensure that all the painting works are as per the procedure. The QC Inspector will be responsible for painting, compliance with QC requirements, including submission of inspection request and the documentation is signed-off by the concerned parties and filed in the quality department filing system.

4. Application Procedures/Method
Work shall be in accordance with Project specification section 09900, ITP, Schedule, mockup and Approved manufacturers method statement for each paint systems. 1) Painting shall not be commenced until the clearance to be obtained from ALEC 2) Shall protect the surfaces not to be painted from paint spatters, markings and other damages. 3) All surfaces to be painted shall be cleaned from dust, dirt and other surface debris.

Parkway International Contracting (LLC)

Document No : FP-MS-003 Revision :0 Date : February 1, 2007 Page : 3 of 5

4) Rinse scrubbed surfaces with clean water until foreign materials are flushed from surfaces and allow surfaces to dry thoroughly prior painting activities. 5) Shall prevent contamination of cleaned surfaces before prime coat is applied and between applications of remaining coats. 6) Surfaces shall be sanded to provide adequate adhesion and to remove visible defects 7) Shall apply primer or paint as soon as possible after cleaning and before deterioration occurs. 8) Provide protection to prevent damage from droppings, over spray, wind blown particles, etc. 9) Safe access shall be provided to the location for materials and work force. 10) Surface preparation shall be checked by QC Inspectors and offer for consultants approval. 11) Paint that has been approved by consultant shall be used and apply as per manufactures application method/paint system 12) Complete each specified coat of paint on an entire surface. 13) Care shall be taken for drying time between coats as per manufacturers recommendation. 14) Finish coat shall be smooth, free of brush marks, pile-up of paint, skipped or missed areas. 15) Make edges of paint adjoining other materials or colours without over lapping the colours.

5. Delivery and Storage


1) All paint and related material shall be delivered to the site in manufacturers sealed containers with manufacturers labels which shall bear name, brand, type of paint, colour of paint and instructions for use. 2) All paint materials shall store away from heat generating devices and in a well ventilated area 3) Storage of paints and other related materials used on job shall be in a single place and shall keep such storage place clean and in order. 4) Oily or solvent soaked rags shall be removed from storage area and all necessary precautions shall be taken to reduce fire hazard.

6. Manpower Requirements
a) Foremen b) Painters c) Helpers

Parkway International Contracting (LLC)

Document No : FP-MS-003 Revision :0 Date : February 1, 2007 Page : 4 of 5

7. Material Requirements
a) As per manufactures paint System

8. Health & Safety Provisions


a) Suitable access shall be provided for the work and shall provide safe scaffolding if required for painting activities as per the contract. b) High standard of house keeping shall be observed to prevent falling materials. c) The effect of weather conditions shall be considered and appropriate allowance will be made. Suitable personnel protective equipments shall be provided to prevent skin contact with paint and to prevent falls. d) Care shall be taken for the protection of all the works and removing the surplus material and waste from site and cleaning the working area during and after the completion of work e) All the safe practices will be adopted during painting activities for the safety, health and environment as per the manufactures recommendation.

9. Distribution
Copies of this method statement shall be issued to the following for information and action. 1) Project Manager 2) Construction Managers 3) Site Engineer 4) QA/QC 5) Safety Engineer

= = = = = END OF THE PROCEDURE = = = =

Parkway International Contracting (LLC)

Document No : FP-MS-003 Revision :0 Date : February 1, 2007 Page : 5 of 5

CHECK LIST FOR PAINTING

Project: Dubai Marina Mall & Hotel/Apartments


Location Area: Activities / Items to be Inspected QCI Verifications Check the area released for 1 Painting. Check surface preparation-no dampness, scratches, broken or 2 damages on the surfaces and shall be cleaned with out any loose particles. Check for paint materials 3 approval. Check manufacturer and expiry 4 dates for all the paints. Check equipments/tools for 5 painting. Check protection for all related 6 services. 7 Check application of primer. Check application of stucco/skim 8 coat. Check application of first coat 9 paint and colour. Check application of final coat 10 paint and colour. Check paint system is as per 11 manufacturers recommendation. Comments and Discrepancies (if any): fino/Parkway QA/QC Approval Name: Signature: Date: SR.NO