Anda di halaman 1dari 5

OWNER:

IPP:

KIMANIS POWER SDN BHD

(842208-H)

(A joint venture company between PETRONAS Gas Berhad and NRG Consortium (Sabah) Sdn Bhd)

PROJECT MANAGEMENT CONSULTANT: KIMANIS POWER PROJECT ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) FOR 300MW COMBINED CYCLE POWER PLANT CONTRACTOR: CTCI Corporation, CTCI Overseas Corporation Limited, CTCI Malaysia Sdn Bhd, Synerlitz (Malaysia) Sdn Bhd, SCHB Engineering Services Sdn Bhd CONSORTIUM KECSB/ABB-KIMANIS/MOS/0213/04 REV. B

VEN. DOCUMENT NO:

TITLE:

275/132KV KIMANIS SWITCHYARD ITP FOR STEEL STRUCTURE ERECTION


DOCUMENT NO:

KPP-000-XK91C-009-0060

REV. B

B A Rev.

CHANGES IN ATTACHMENT ISSUE FOR APPROVAL Description

6/3/2013 20/02/2013 Date

ABB ABB By Chk. App. Page No. 1 of 5

THIS DOCUMENT CONTAINS CTCI CORPORATION CONFIDENTIAL INFORMATION OF A PROPRIETARY NATURE. THIS INFORMATION MUST NOT BE COPIED OR DISCLOSED IN WHOLE OR IN PART TO OUTSIDE PARTIES NOR USED FOR OTHER THAN THE PURPOSE FOR WHICH PROVIDED WITHOUT PERMISSION OF MANAGEMENT. ()

CONTENT 1.0 PROPOSE 2.0 SCOPE 3.0 PROJECT DESCRIPTION

PAGE 3 3 3

4.0 ACTIVITIES

5.0 ATTACHMENTS

275/132KV KIMANIS SUBSTATION METHOD OF STATEMENT STRUCTURE ERECTION

KPP-000-XK91C-009-0060
DATE

2 OF 5

6/3/2013
REV.

1.0 PURPOSE The purpose of this Procedure is to define the items that must be inspected and tested during the construction and to set the Hold Points or Witness Points for certain inspection items including required examination and test, so as to ensure that the entire construction quality complies with the requirements of the contract and project specifications. 2.0 SCOPE The examination and testing items must comply with the requirements of relevant drawings, specifications and statutory codes. This inspection and test items listed in the appendixes are the most basic requirements. 3.0 PROJECT DESCRIPTION Project: Kimanis 275/33kV Consumer Main Intake Main Contractor: ABB Malaysia Sdn. Bhd. Sub Contractor: KARISMA Energy & Construction Sdn. Bhd./SKT Semarak Sdn. Bhd.

275/132KV KIMANIS SUBSTATION METHOD OF STATEMENT STRUCTURE ERECTION

KPP-000-XK91C-009-0060
DATE

3 OF 5

6/3/2013
REV.

4.0 ACTIVITIES 4.1 Before starting the work, the Project Manager shall assign the Supervisor to compile the relevant document and shall submit to the Client for review, if required. 4.2 The Contractor shall prepare the inspection and test plan, using specific forms to set all hold points/witness points according to the contractual requirements, project specifications and statutory codes.

4.3 QC manager and the Site Supervisor shall review the proposed inspection and test plans and compile the relevant inspection and test items to form a complete set of Inspection and Test Plan. It should be submitted for approval.

4.4 The approved Inspection and Test Plan shall be handed over to the responsible appointed QC Manager.

5.0 ATTACHMENTS ATTACHMENT ATTACHMENT ATTACHMENT ATTACHMENT ATTACHMENT ATTACHMENT ATTACHMENT 1: 2: 3: 4: 5: 6: 7: INSPECTION AND TESTING PLAN FLOWCHART STEEL STRUCTURE ERECTION CHECK LIST ELEVATION OF COLUMN FOUNDATION STRUCTURE STEEL ERECTION CHECK LIST GROUT/POUR CARD PUNCH LIST QUALITY MANAGEMENT STANDARD

275/132KV KIMANIS SUBSTATION METHOD OF STATEMENT STRUCTURE ERECTION

KPP-000-XK91C-009-0060
DATE

4 OF 5

6/3/2013
REV.

ATTACHMENT 1 INSPECTION AND TESTING PLAN FLOWCHART

275/132KV KIMANIS SUBSTATION METHOD OF STATEMENT STRUCTURE ERECTION

KPP-000-XK91C-009-0060
DATE

5 OF 5

6/3/2013
REV.

Anda mungkin juga menyukai