,
10.1' Protective treatment shaH be applied to the whole of The words "as described in the con tract "
the exposed concrete surface and repairs as described in should be deleted if ail of the exposed
the mntract. concrete is ta be trealed. Otherwisedraw
ings which indicate the locations to be
treated should be included.
10.2 Protective treatments shall be mixed and applied
strictlyin accordancewith the manufacturer' s instructions.
,- Thinning.ordiluting in excess of the manufacturer's rec
ommendtions shaH not be permitted.
10.3 AB surfaces shaH be dry before and during the appli Instruments which indicatesurface mois
cation of protective treatment. Ambient and surface tem lure condition, though not on an abso
peratures/ ambient relative humidity and the surface
lu!e seale, are available and values are
moisture condition shaH be measured and recorded by the
quo!ed in sorne coating manufacturer's
specifications.
Contractor on each day before coating commences and
during coating. No coating shaH be applied unless the
conditions meet the coating manufacturer' 5 specification.
10.4 Where repair mortars or fairing mats or surface fillers
and mating systems are supplied by different manufac
turers, the repair mortar shaH be subjected to trials by the
coating manufacturer and repar material manufacturer to
ensure compatibility between the various elements and
eviden shall be provided of acceptable performanceelse
where on simiJar structures under similar conditions.
10.5 Records of application rates shall be submitted by the
Contractor to the Engineer on a daily basis indca ting batch
numbers, the area covered by each coat and the amount of
coating material used.
30
w Mff'GRDMh a
10.6 Items or areaS which are not to be coated shall be
suitably protected or masked before application of the
protective treatment.
10.7 Trial sample panels of protective treatment shaH be
prepared in the works for approval by the Engineer. Pro
tective treatment application shaH not be carried out until
a trial sample panel has been approved by the Engineer.
The trial sample shan be used as a standard against which
the rest of the work will be judged.
.: :-.
MHE Q%& F PMM' <,.tiW_lWif'f
11. TRIAL SAMPLEREPAIRS
General Notes
The need for sample repairs will depend ta a certain extent on the size of the contract and the avallable time. If possible the size
and location should be shown on the drawings or described in the Specification.
Pull-off testing could be specified for the cores and used as a basis for assessing pull off values achieved in the works.
11.1 Trial sample repairs for approval shaH be undertaken
for each type ofdesigna ted repair not less than three weeks
before the related work is scheduled to start. Trial sample
repairs shaH be carried out using materials of the same
formulation as that to be used in the works. If the formu
lation of materials is changed during the course of the
works, additional trial sample repairs shan be carried out.
11.2 Trial repairs shaH be assessed by the Engineer to check
that the required standard will be achieved by the materi
aIs and methods proposed by the Contractor. Trial repair
areas shall be used asa standard against which subsequent
work shaH be judged.
11.3 Trial sample repairs shaH be chosen, as far as it 1S
reasonably possible to encompass the majority of the posi
tions and orientations of the surfaces to be repaired.
11.4 During the trial repairs six cubes for each type of
mortar shaH be made and three tested at 7 and three at 28
days. Cubes shaH be made cured and tested. generally in
accordance with BS 6319 Part 2 andlor the manufacturer' s
recommendations.
11.5 After reinstatement six number 50mm diameter cores Coring should not be undertaken until 3
shaH be cut through each trial repair area to a depth such days after repair for resin mor/arS and 14
that each core penetra tes the substrate by approximately days after repar for cementitious mor
25mm. The cores shaH be visuaHy examined by the Engin fars. These periods may have ta be ex
eer to determine the degree of compaction and
tended in periods of cold weather.
adhesion achieved. '. :..
The cores could be used used for pull-oft
tests as described in Clause 12.8.
11.6 On completion of the coring a section of the trial
samplerepairs shaH becarefully broken out in the presence
of the Engineer to demonstrate that adequate compaction
and adhesion have been achieved.
11.7 Approval for trial repairs shaH be based on the fol Acceptance criteria may have ta be ad
lowing: justed in the light ofexperience.
i)
Cube results shaH demonstrate an average If necessary add ta 11.7:
strength which exceeds 90% of the
iv) Colour match and surface texture
manufacturer's stated strength with no single
match with adjacent concrete.
result less th an 75% of the manufacturer' s
Where the repair material is required to
reach aparticular strength for structural
stated strength.
ii)
reasons il will be necessary to use this
Visual inspection of the trial area shaH indicate
strength as the acceptance criterion
that the area is free from excess voidage and has
rather than the manufacturer's quoted
good bond to the substrate/reinforcement.
strength.
Iii)
Cores are weIl compacted and free from entrapped
If a characteristic strength has been spe
air with good inter-layer adhesiDn.
cified in 13.3add ta 11.7a reference to the
characteristic strength and the amount
by which the result shall exceed the spe
cified characteristic strength.
32
12 MMMM 1N,., ,aa' Ahfi
12. TESTING
General Notes
Clauses 12.8. la 12.12 ta be omitted if pull-off testing is not specified. Also amend sequence of operations in Clause 1.4.
Alternative forms of testing could be substituled or added.
A European Standard on testing of repair mate rials is in the early course of preparation but may not be available for several
years.
12.1 One sample of mortar for repairs shaH be taken for
every three days on which repair mortar is used unless
otherwise specified by the Engineer. The strength result
from the sample shaH represent mortar placed on the pre
vious day, the day on which the sample was taken and the
following day. Three cubes shall be made and tested from
each sample. For cement based mortar, the cubes shaH be
tested at 28 days. The average of the three 28 day values
shall be taken as a strength result. For resin based mortar
the cubes shaH be tested at an age agreed by the Engineer
and the average value for those cubes shaH be taken as a
strength result.
12.2 Sampling and testing of repair mortars shall be in
accordance with BS 6319 Part 2 unless otherwise specified
by the Engineer
12.3 AlI testing shan be carried out by a NAMAS ac
credited labo ra tory.
12.4 Test cubes sha1l be stored and cured in a manner Cubes oJ pa/ymer modified morlar should
appropria te ta the materials under test in accordance with be placed in sealed polylhene bags imme
the manufacturer's instructions but generally in accord
diately after making and struckfrom Iheir
ance with BS6319. They shalI be delivered properly ident
mould at an age ofl day. Thereafter they
should he air cured al a temperature of
ified to the approved laboratory.
approximately 2fYC until they are tested.
12.5 Cube results shaH be judged for compliance against Where the repair material is required ta
the manufacturer's quoted strength. Each strength result comply with a "char.acteristic" slrength
shall exceed 80% of the manufacturer's stated typical
for slructural reasqns it will be necessary
strength.
la use Ihis strerigth as the acceptance
12.6 The repairs at risk due to non compliance shaH in Adjust this clause ta clearly identify
dude aIl repairs executed on days represented by any which repairs are at risk if a "charac
strength result which fails to achieve compIiance.
leristic" strength luis been specified in
13.3. The repairs at risk will depend an
the form af the acceptance criteria speci
fied in 12.5.
12.7 As a consequence of non-compliance in the tenns of
the above, the Contractor shaH be directed to take such
remedial action as the Engineer may consider necessary.
This action may include removal of material in repairs at
risk as described above and/or further testing required to
establish the acceptability or otherwise of the repair mor
tar. The Contractor shall.bear: the cast of any such addi
tional testing and removal and reinstatement of repirs.
33
H H ~ W i'ri*ee
-
12.8 During the course of the works the Engineer will carry
out approximately x No pull-off tests on repaired areas.
The tests wiII be carried out fourteen days after reinstate
ment of the area under test. The Contractor shaH cu t 50mm
diameter cores through the repair and 50mm into the
original concrete at locations directed by the Engineer. The
Contractor shaH make good the core hoIes after completion
of the test using the repair methods and materials de
scribed in this specification.
12.9 Three No. pull-off tests shaH be carried out on each
selected area. The average of the three values shaIl be taken
as a pull-off strength result.
12.10 Each pull-off strength result on an area shaH be at
least 0.8 N/mm
2
unless failure occurs within the parent
concrete at a lower value.
12.11 The mode of failure shaH be recorded i.e. within
substrate, within repair material.
12.12 As a consequence of non-compliance with the puII
off strength requirement, the Contractor shaH be directed
to take such remedial action as the Engineer may consider
necessary.
Add number of pull-off tests. Pull-off test
locations have to avoid reinforeement.
Sorne authorities advocale using a disc
cutler to cut a 50mm square rather than
co ring prior to the pu/l-off test. The ac
cep/ance value ofO.8Nfmm
2
may have to
be revised (upwards or downwards) in
the light of experience.
34
J'
Aseem_
13. MATERIALS
General Notes
Alternative clauses could be drafled to allaw site batching of repar mortar using po/ymer latex or the use of flowng concrete.
These are felt to be applicable only ta larger contracts. The clauses shauld inc/ude requirements for strict quality cantrol and the
Engineer should consider modifications to the testing regime. The Contractor should be required ta demonstrate that he can
exert effective co.ntrol over the sile batching operation.
The properties of repaiT materials need to match those of the concrete in the structure under repar. Hgh shrinkage valuesl
differenees in elastic modulus and thermal coefficient can lead ta high stresses in the patch and the surrounding concrete which
could cause debonding and premature failure.
At present there are few national standards which are directly applicable ta repar materiais. Many manufacturers have carried
out comprehensive test programmes but il is nol possible ta compare materials because different test methods may have been
used. Work is at present being undertaken by CEN ta produce European Standards for test rnethods and eventually repair
materiais. At present it is considered that the best approach is ta include the narnes ofl say, three repair system manufacturers
based on Experience of past sa tisfact ory performance in similar conditions.
A schedule of proposed repair materials, ta be completed by tenderers, is given in Appendix C.
13.1 AlI materials for repair and protection of concrete Add narnes and addresses of manufac
structures shaH be obtained from a single manufacturer turers.
from the list given below. Alternative manufacturers may
be proposed by the Contractor prior to commencement of
Repair systems are available from a large
work at site but their materials shaH not be used without
number of manufacturers of widely va
rying resourees and track record. Mem
the prior approval of the Engineer.
bers of the Working Party were strongly
a)
of the opinion that where circumstanees
b)
permit this Clause should be amended ta
c)
inc/ude referenee ta FeRFA or other such
. etc)
body. Sorne materials have British Board
of Agrment Certification.
ft is recommended that aIl elements of a
repair and protection system (reinforee
ment protective system, bonding aid or
primer, repair mortar, surface filler, fair
ing coat and protection system) are ob
tained from a single manufacturer.
O/herwise there can be divided responsi
: :..
bilities ifproblemsarise. Ifuseof products
from more than one manufacturer is un
avoidable then the combination should be
the subject of trials by bath manufac
turers ta check compatibility. Evidence
of previous successful use ofthe materials
in combination would also be useful.
13.2 AlI materials shaH be used strictly in accordance with
the manufacturers' instructions and this Specification.
Manufacturers' instructions shall be available to ail opera
tives at site.
13.3 Repair mortars, fairing coats and pore fillers shaH be Add any strength or other requirements
factory pre-batched materials. The chloride ion content of for the repair mortar. If the term "charac
cement based materials shaH not exceed 0.1 % by weight of tenstic strength" is used this would have
cement. The ingredients and their proportioning shan be
ta be defined as say "that strength below
such that disruptive alkali aggregate reaction does not
which only 5% ofsamples are expected ta
occur.
fall". Add ta the clause if colaur and
surface lex/ure match VJith tlu::: existing
concrete are required.
25
13.4 Mixing and application of repair and protection ma
terials shaH be carried out strictly in accordance with the
manufacturer's instructions. Mixing of part bags or other
containers of components shall be allowed only with the
prior permission of the Engineer and the manufacturer.
13.5 Ail materials and the manner in which they are used
shaH conform to the relevant Health and Safety and Con
trol of Substances Hazardous to Health Regulations.
13.6 Materials shall be stored in an environment which
conforms with the requirements of the manufacturer. Ma
terials shaH not be removed from store until immediately
prior to mixing or use. Matenal from damaged containers
shaH be discarded.
Storage facilities are required ta be stated
in the information provided by the Con
Iractor with his tender.
* MG HM ....?
APPENDIXA
SURVEY AND LOCATION OF DEFECTS
(ALTERNA TIVE FORM WHERE SURVEY 15 CARRIED OUT BY THE ENG1NEER
DURING THE CONTRACT)
: ;.
1. ..
37