ENSCO 84 STRUCTURAL WORK COMPLETION STATUS

JOB DESCRIPTION NEW 4TH MAIN ENGINE INSTALLATION 4th EMD installation Air duct extension Walk way platform BALANCE ACTIVITIES 1. Installation of new air duct extension for the 4th EMD 2. Installation of new walkway platform for the 4th MD 3. Removal of temporary supports provided IWO the deck access opening for lowering the EMD 4. Provide 06 nos. collar plates on main deck transverse frame # 14, 15,& 16 IWO deck access cutout. 5. Painting of the coaming plate around 4th EMD and burn marks inside the tank. 6. Final inspections by client 7. Functional test of fire and gas dampers 8. Painting of burn marks inside the accommodation spaced below the Egen room 9. Insulation and panel works completion in accommodation spaces below EGEN room 10. Paint touch ups IWO pipe and electrical penetrations 11. Installation of battery box 12. Installation and commissioning of the CO2 system for emergency generator room. 13. Installation of pipe supports for fuel and air lines PERCENTAGE COMPLETION SCHEDULED COMPLETION REMARKS New air duct installed but fouling with the 4th EMD exhaust bellow.

INSTALLATION OF NEW EMERGENCY GENERATOR Removal of existing emergency generator and installation of new caterpillar generator. Structural modification to the EGEN room for installation of new control panel. Relocation of fuel tank.

HILLMAN ROLLER INSTALLATION Structural modification IWO skid rails Installation of Hillman roller assembly

14. 2 nos. drain relocation and 01 no. drain line penetration inside tank no. 27 (cut due to structural modification for Hillman roller) 15. Pain touch up in tank no 27 and applying of eureka gel inside tank 28 and 29 ( removed for hot work) 16. Painting of main deck and Hillman roller structure

above main deck 17. Final inspection and tank closing INSTALLATION OF REVERSE OSMOSIS UNIT Installation of the unit on foundation Installation of chemical injection skid 18. Welding of the RO unit skid to the foundation 19. Installation of the chemical injection unit skid foundation and installation of the same. 20. Closing of the access opening above the RO unit. 21. Final structural inspection by client. 22. Paint touchups IWO paint damaged areas. 23. Relocating the emergency breathing stations and tubing termination. 24. Removal of old A/C tubing penetration & MCT and installation of inserts on the deck in the same locations. 25. Heavy duty hand rail fabrication and installation 26. Paint touchups inside the accommodation spaces IWO platform support and MCT penetrations. 27. Insulation and panel work completion inside accommodation spaces removed for hot work. 28. Final inspection by client. 29. Radiator platform, container platform and hull paint touchups IWO new structure and paint damaged areas. 30. Container platform access stair ways installation 31. Removable and fixed handrails installation for the container platform 32. Plating of the container platform above the first two radiators 33. Installations of container hold down locks. 34. Final inspection by client 35. Installation of grating for the new platforms 36. Installation of new access stair ways 37. Cropping of old platform fouling IWO new access route and modification of the access ladder to the

RELOCATION OF 07 A/C CONDENSER UNIT Platform extension IWO FWD jack house top. Relocating the AC condensers Relocating the emergency breathing stations.

NEW PLATFORM FOR 4TH EMD RADIATOR AND CONTAINER PLATFORM ABOVE THE RADIATORS. Platform extensions for the new radiator Container platform installation above radiators with access way and handrails ACCESS FOR CRANE CABS PORT AND STBD Installation of new platform

New stair ways and hand rails

sheave assembly. 38. Cropping off the old access stair for the crane cabs. 39. Access extension connecting the Jack house platform stbd side ony. 40. Required NDT and client inspection 41. Pain touchups of the new structure and paint damaged areas

SHALE SHAKER HOUSE ROOF TOP MODIFICATION Platform extension Modification of access stair ways Necessary hand rails provision. INSTALLATION OF KING POST AND BURNER BOOM PORT AND STBD Installation of owner supplied prefabricated items of the king post foundation. Installation of the king post base and support eye pads

42. Plating of the extended platform 43. Reposition and extending the existing heavy duty hand rails to the far end of the platform 44. Relocating 01 no. light post fouling IWO stair way. 45. Necessary NDT and client inspection 46. Painting of the structural modification areas and the paint damaged areas 47. Completion of fitup and welding of under deck stiffening for port and stbd king post foundation 48. Welding completion of king post foundation 49. Installation of king post base and holding eye pads 50. Modification of the heavy duty hand rails cut for installation of the foundation 51. Installation of the fire line cut IWO king post foundation 52. Necessary NDT and client/class inspection 53. Painting of the structure and paint damaged areas 54. Fabrication and installation of air receiver foundation and under deck stiffening 55. Fabrication and installation of booster pump foundation 56. Fabrication completion and testing of Air receiver 57. Installation of air receiver and booster pump

Class inspection completed

Canceled

PROVISION FOR AIR STARTING OF THE EMERGENCY GENERATOR Fabrication and installation of air

receiver 660 gals Installation of booster pump

58. Required NDT and client inspection 59. Paint job completion on the foundations and paint damaged areas 60. Structural modification IWO aft smit bkts 61. Fit up and welding of aft towing bkts 62. Required NDT and client/class inspection 63. Load test of all smit bkts witnessed by class and client 64. Painting of structure above deck and reapplying of eureka gel inside the tanks under the smit bkts. Canceled - NDT reports and strength calculations to be submitted Class inspection completed

RELOCATION OF 04 NOS. TOWING SMIT BKTS Strengthening of deck structure @ new location of towing arrangement Relocation of smit bkts Load test

MODIFICATION OF ACCOMMODATION EXTERNAL STAIRS AND PLATFORM PORT AND STBD Cropping the existing platform Installation of new platform and stair ways Extension of old stair ways

65. Cropping of the existing platform and stair ways 66. Fabrication of new platform and stair ways 67. Installation of new platform, stair way and supports port side 68. Installation of new platform, stair way and supports stbd side 69. Installation of lights port and stbd 70. Necessary NDT and client inspection. 71. Final painting of new structure and damaged areas. 72. Reinsulating the insulating and paneling of accommodation spaces IWO hot work. 73. Relocating the the air compressor an the new extended platform and welding the skid to the deck 74. New hand rail installation 75. Necessary NDT and client Inspection 76. Paint touchups of the damaged areas.

RELOCATION OF AIR COMPRESSOR ON THE EXTENDED JACK HOUSE PLATFORM Platform extension Relocation of air compressors

BULK AIR DRYER ON WELD ROOF Installation of the foundation for the dryer Installation of the bulk air dryer unit

77. Installation and welding of the bulk air dryer unit foundation and under deck stiffening. 78. Installation of the unit and welding. 79. NDT of the foundation and under deck stiffening to be done. 80. Inspection of the structure. 81. Painting of the new structure and damaged surfaces. 82. Fabrication and installation of the new access platform extension 83. Fabrication and installation of the new stair ways 84. Fabrication and installation of new handrails 85. Structural inspections 86. NDT of the new structure 87. Painting of the new structure and damaged surfaces

NEW HELIDECK EMERGENCY ACCESS PLATFORM PORT/STBD Fabrication and installation of new access platform extensions Installation of new stair ways Installation of new hand rails NDT

88. 89. 90. 91. 92. 93.