8 BETA
Authors: Tom Heath, Philip Tibenderana, Richard Carter,Kerstin Danert & Etsegenet Berhe 2009 Macros need to be enabled Password: borehole Navigate using the buttons on the top Instructions: Water Well Reference No: Field note Location: St Gallen Date 2/24/2009 Coordinates/GPS
Stage A: Unit Costs 1. Fill in Fixed Costs 2. Update Rig Database 3. Update Casing Database
Go
Go Go
Description: This is the test run for the costing and pricing field note.
Stage 2: Borehole Specifications 1. Fill in Home data 2. Fill in Mobilisation 3. Fill in Drilling 4. Fill in Completion
St Gallen
Enter Data Editable data Dark blue cell = formulas Light Blue = local currency Red = Summed variables for each section
Go Go Go
1 2 3
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
All of the staff work and are paid for all stages of the job and the hourly rate remains constant Rig lifetime (years) is calculated by lifetime (hours)/(Utilisation (days) * Working Hours in Day) Rig deprecation is based on the straight line method (equal amounts each year) incorporating the utilisation of the rig. It is calculated by taking the value/(lifetime (years)*365*utilisation/365 then converted into an hourly figure by dividing it by the number of working hours in day The residual value of the rig is zero Depreciation is the same for each hour of mobilisation, drilling, completion and development Short vehicle trips are not included in the model (pick up lunch, drop off at accommodation etc) as very small amount The vehicles used are present for the entire duration of the boreholes construction The average fuel consumption is the same as the values set in the fixed cost The distance travelled to get to the site during mobilisation is the same during demobilisation (leaving the site) The mobilisation and demobilisation takes the same amount of time and has the same labour costs The depreciation is equal for the mobilisation and demobilisation The total mobilisation is the sum of depreciation, fuel, vehicles and labour for the mobilisation and demobilisation The total depth equals the thickness of the overburden plus the thickness of the rock The time to drill the hole is equal to the depth divided by the drilling speed The depreciation (straight line method) for the compressor is constant The compressor fuel consumption rate is constant throughout drilling The cost of fuel for the rig is a fixed cost per hour The cost of mud and foam is constant per hour The drilling fixed cost takes into account the rig's drilling lifetime. It is calculated taking the Rig value/lifetime (hours * (1+maintenace%). It assumes the rig residual value is zero and is an additional cost of top of fixed Rig deprecation
During delays the cost is calculated by the cost the hourly depreciation, labour and vehicle costs The maintenance cost is a fixed percentage of the fixed drilling cost The Drilling String has no residual value and will be replaced after its lifetime The Drag Bit has no residual value and will be replaced after its lifetime The Hammer has no residual value and will be replaced after its lifetime The Hammer Bit has no residual value and will be replaced after its lifetime The cost of drilling through overburden is the sum of the cost per meter of the drilling string and the Drag bit (cost per meter = Replacement cost/lifespan (m)) 27 The cost of drilling through rock is the sum of the cost per meter of the drilling string, hammer and hammer bit (cost per meter = Replacement cost/lifespan (m))
28 The total drilling cost is the sum of the fixed overburden and rock costs multiplied by their respective depths, plus the hourly cost of depreciation, fuel, lube, mud foam, labour and fixed drilling multiplied by the number of hours to drill the hole 29 The volume of the annulus equals the area of the hole minus the area of the casing multiplied by the depth 30 If the hole is screened/cased then the entire hole is cased/screen 31 The casing and screen are the same diameter 32 If the hole is screened/cased then the entire hole has backfill/gravel pack/a sanitary seal 33 The density is the same for all of the backfills (set in fixed costs) 34 The bags of backfill are all the same size (set in fixed costs) 35 The time to screw casing/screen together is constant with depth 36 The time to weld casing/screen is constant with depth 37 The volume of material required to backfill the borehole is calculated based on the size on the annulus plus 10% 38 39 40 41 42 43 44 45 Total completion cost is the sum of the screening, casing, backfill, sand, cement, rig depreciation and labour The compressor is running for all of development The compressor fuel consumption rate is constant throughout development The compressor depreciation cost is constant The pump and generator fuel consumption rate is constant throughout development The pump and generator depreciation cost is constant The pump is running for all of the pumping test period Total development and test pumping is the sum of development, pumping, labour and depreciation
46 The number of working hours in a day is constant (specified in results) 47 48 The yearly loan amount is calculated using the PMT function to calculate the monthly repayments and converts this into a yearly amount. PMT calculates the payment for a loan based on constant payments and a constant interest rate. The cost of overheads is converted into a daily fee based on the number of working days in a year
Local Currency
Working Hours in Day
Local Currency
8
GB
Working Hours in Day 1 2 Cost per hour $33.33 $6.67 $13.33 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.07 $53.33 52 10 21 0 0 0 0 0 0 0 83 Vehicles Rig Transport Truck Mounted Rig Pick Up and Trailer Truck and Trailer Compressor Transport Truck Mounted Compressor Pick Up and Compressor Truck and Compressor None (towed) Extra Vehicles Truck Pick Up 2 Pick Ups Hire/Upkeep per day $66.67 $6.67 $0.00 $33.33 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 104 10 0 52 0 0 0 0 0 0 Fuel litres/km 1.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00
Local Currency
8
GB
Exchange Rate 1 USD = Mobilisation Fuel $/litre Labour Hydrologist Driller Assistant Driller 1 Assistant Driller 2 Driver 1 Driver 2 Driver 3 Labourer Security Person Other Total Hourly Rate Drilling Fuel for Rig (litres per hour) Lubricant for Rig ($ per hour) Mud pump ($ per hour) Compressor depreciation ($ per hour) Fuel for Compressor (litres per hour) Lubricant (and foam) for Comp. ($/hour) Completion Bag Density (kg/m3) Bag Weight (kg) Time to Install Casing (minutes/m) Time to Weld Casing (minutes/m) Test Pumping
Pump & generator depreciation ($ per hour) Pump & generator fuel use (litre per hour) Labour for pumping ($ per hour)
1.56 $1.33 No 1 1 1 0 0 0 0 0 0 0
Mobilisation Fuel per litre Labour Hydrologist Driller Assistant Driller 1 Assistant Driller 2 Driver 1 Driver 2 Driver 3 Labourer Security Person Other Total Hourly Rate Drilling Fuel for Rig (litres per hour) Lubricant for Rig ($ per hour) Mud pump ($ per hour) Compressor depreciation ($ per hour) Fuel for Compressor (litres per hour) Lubricant (and foam) for Comp. ($/hour) Completion Bag Density (kg/m3) Bag Weight (kg) Time to Install Casing (minutes/m) Time to Weld Casing (minutes/m) Test Pumping
Pump & generator depreciation ($ per hour) Pump & generator fuel use (litre per hour) Labour ($ per hour)
2.00 No 1.0 1.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Cost per hour 50.00 10.00 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.10 80.00
Vehicles Rig Transport Truck Mounted Rig Pick Up and Trailer Truck and Trailer Compressor Transport Truck Mounted Compressor Pick Up and Compressor Truck and Compressor None Extra Vehicles Truck Pick Up 2 Pick Ups
Hire/Upkeep per day Fuel litres/km 100.00 10.00 0.00 50.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00
Fixed Costs
2.00 $0.67 $1.33 $0.67 1.00 $1.33 1500 25 3 7 $1.50 1.00 $25.00
1 1 2 1 1 2 1 1 1 1 2 1 39
Instructions Enter fixed data into white cells. The light blue cells are the value in local currency. If have values in local currency enter in table on right then click on button to convert to USD, the values will then be converted based on the set exchange rate
Enter the values in local currency then click on grey button to convert to US$. The values must be converted as the model runs in US $
2 1 2.00 1.00 1.00 2.00 0 0 0 0 0.00 0.00 4.00 Legend: White = Enter Data Grey = Data Used in Mobilisation Lilac = Data used in Drilling Pale Blue = Data Used in Completion Light Blue = Value in Local Currency Dark blue cell = formulas
Legend: White = Enter Data Grey = Data Used in Mobilisation Lilac = Data used in Drilling Pale Blue = Data Used in Completion Light Blue = Value in Local Currency Dark blue cell = formulas
Instructions: Fill in the details just for the Rigs that you use - either update those already given, or add a new line. If you have the values in the local currency enter them into the table on the right and click on the button to convert to USD. All data needs to be filled in for the left table
Rig Database
Date
Location:
Rig Name
Rig Type
Location
Rig Cost
Rig Loan
C&P Field Note Rig A C&P Field Note Rig B C&P Field Note Rig C
0 0 0 0 0 0 0 0 0 0 0 0 0
$ $ $
$ $ $ $ $ $ $ $ $ $ $ $ $
10 10 10 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
5 5 5
0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
$ $ $ $ $ $ $
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0
Replacement Lifespan Replacement Cost Drilling Drilling Cost Hammer string String (m)
Lifespan of Replacement Lifespan Hammer Cost Hammer Hammer (m) Bit Bit (m)
5% 5% 5%
$ $ $
$ $ $
$ $ $
$ $ $
0 0 0 0 0 0 0 0 0 0 0 0 0
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
$ $ $ $ $ $ $ $ $ $ $ $ $
0 0 0 0 0 0 0 0 0 0 0 0 0
$ $ $ $ $ $ $ $ $ $ $ $ $
0 0 0 0 0 0 0 0 0 0 0 0 0
$ $ $ $ $ $ $ $ $ $ $ $ $
0 0 0 0 0 0 0 0 0 0 0 0 0
$ $ $ $ $ $ $ $ $ $ $ $ $
0 0 0 0 0 0 0 0 0 0 0 0 0
0 Selected 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0% 0% 0% 0% 0% 0% 0%
0% 0% 0% 0% 0% 0% 0%
$ $ $ $ $ $ $
0 0 0 0 0 0 0
$ $ $ $ $ $ $
0 0 0 0 0 0 0
$ $ $ $ $ $ $
0 0 0 0 0 0 0
0 0 0 0 0 0 0
Local Currency
Rig Name Rig Type Location
GB
Rig Cost Rig Lifetime (years) Rig Finance Period Rig Loan Rig Loan Rig Interest rate Lifetime (hours)
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Rig Maintenance
Replacement Lifespan of Replacement Lifespan Replacement Cost Hammer Hammer Cost Hammer Hammer Bit Cost Drag Bit (m) Bit (m)
Current Rig
0 Selected 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Instructions: Fill in the details just for the casing/screen/backfill type that you need - either enter them into the table on the right and click on the button to convert to USD. The local cu
Casing Database
Date
Location:
Casing
Type UPVC (heading) 4 inch casing 110mm casing 5 inch casing 6 inch casing Steel (heading) 65/8 inch casing 150 mm casing 95/8 inch casing 135/8 inch casing 155/8 inch casing Diameter Inches 4.0 4.3 5.0 6.0 7.5 6.0 9.5 13.5 15.5 Price Per m $ $ $ $ $ $ 9.00 11.00 15.00 20.00 69.00 64.00 0 0 Used 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Screen
Type UPVC (heading) 4 inch screen 110mm screen 5 inch screen 6 inch screen Steel (heading) 6 inch 20-23 bar stainless steel screen 6 inch 60- 72 bar stainless steel screen 150 mm screen
backfill type that you need - either update those already given, or add a new line. If you have the values in the local curr ton to convert to USD. The local currency tables don't need to be filled in only the tables in USD
n
Diameter Inches 4.0 4.3 5.0 6.0 6.0 6.0 6.0 Price Per m $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 10.00 0 0
Annulus Fill
Type Graded Gravel Pack Formation stabiliser (washed gravel/sand backfill) Drill Cuttings Cement Bentonite Price per 25 kg bag $ 7.00 $ 3.00 $ $ $ 20.00 35.00
Local Currency
GB
Casing
Type UPVC (heading) 4 inch casing 110mm casing 5 inch casing 6 inch casing Steel (heading) 65/8 inch casing 150 mm casing 95/8 inch casing 135/8 inch casing 155/8 inch casing 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Diameter Price Per Inches m 4.00 4.30 5.00 6.00 0.00 7.50 6.00 9.50 13.50 15.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15.00 17.00 20.00 25.00 50.00 60.00 100.00 100.00 150.00 0 0 0 Used 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Screen
Type UPVC (heading) 4 inch screen 110mm screen 5 inch screen 6 inch screen Steel (heading) 6 inch 20-23 bar stainless steel screen 6 inch 60- 72 bar stainless steel screen 150 mm screen 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
een
Diameter Inches Price Per m 0 4 15.00 4.3 5 6 0 6 6 6 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 20.00 25.00 28.00 60.00 100.00 110.00 0 0 0 Used 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Annulus Fill
Type Graded Gravel Pack Formation stabiliser (washed gravel/sand backfill) Drill Cuttings Cement Bentonite Price per kg bag 5.00 2.00 0.00 20.00 25.00
Rig Specifications Rig Rig Value Rig Life (Years) Rig Utilisation Rig Depreciation ($/hour) Total Rig Depreciation Labour & Fuel Time to Travel to Site and Set Up (hours) Labour Cost Fuel $/Litre Distance (km) 10 $1,067 $1.33 260 Hire/Real upkeep
1 4 1
1,664 2.08
Step 2: Mobilisation
Vehicles 1. Rig Transport 2. Compressor Transport 3. Extra Vehicles Mobilisation Vehicle Costs Hourly Vehicle Cost Mobilisation Fuel Costs Mobilisation Hire Costs Mobilisation Vehicle Costs $8.33 $693.33 $166.67 $860.00 13 1,082 260 1,342
260 0 0
Total Mobilisation
2,267
3536
Step 3: Drilling
Drilling Spec Total Depth (m) 50.0 Thickness of Overburden (m) 40.0 Thickness of Rock (m) 10.0 Average Speed of Drilling (m/hour) 4.0 Diameter of Hole (inches) 6.0 Time to Drill Hole (hours) 12.5 Supplies Rig Total Fuel and Lubric $41.67 Compressor and Fuel (rock drilling) $8.33 Mud Pump (overburden drilling) $13.33 Total Labour cost $666.67 Vehicle costs $104.17 Temporary Casing $150.00 Rig Details Rig C&P Field Note Rig B Rig Cost $170,000 Rig Life (hours) 10,000 Maintenance 5% Rig Equipment Replacement Cost Replacement Cost Lifespan of Equipment (m) Time Delays Length of Delays (hours) Cost of Delay Drilling String $15,000 23,400 20,000
Drilling Unit Rates Rig Depreciation (/hour) Maintenance (per hour) Overburden Cost (per m) Rock Costs (per m)
$ $ $ $
27 1 4 12
265,200
$1,457
2,273
$79
2,273
Hole Hole Diameter (inches) Hole Depth (m) Is the hole Cased/Screened? Casing Diameter (inches)
6 50 Yes 1 4.3
No
Rig Depreciation ($/hour) Labour Cost Vehicle Cost for Casing Tick if Casing sections are welded together
0 0 Casing (including sump) Screen Type of Casing/Screen Length (m) Unit Price ($/m) Total Cost 5 40 $11.00 $440.00 1.Backfill Backfill or Gravel pack Type Length (m) Volume Required (m3) No. Bags required (bag = 25 kg) Cost per Bag Total Cost Total Fill 2 35 0.34 20.5 $3.00 $61.49 $110.68 12 0.12 7.0 $7.00 $49.19 4 17.16 686.40 10 $12.00 $120.00 2. Gravel Pack 1 4
0
18.72 187.20
Step 4: Completion
0.00
10.92 76.74
Length Sanitary Seal (m) Cost per Bag Cement Bags of Cement (bag 25 kg) Cost per Bag Bentonite Bags of Bentonite (bag =25 kg) Total Cost
Total Completion
$957
1,493
Development Time to Develop Borehole (hours) Compressor Fuel Cost Compressor Depreciation Cost Development Total Pumping Test Pumping Test Length (hours) Pump and Generator Fuel Cost Pump and Generator Depreciation Pumping Test Total
Time equip, labour, vehicles on site (hr)
$5 $3
$8.00
8 4 12
12
$16 $18
$34.00 8
25 28 53
Labour and Rig Is the Rig on Site for Pumping Test? Total Rig Depreciation Total Labour Cost Vehicle costs
Yes
No
$623
972
$623.33, 12%
Mobilisation $2,266.67
Drilling $1,456.79 2272.595 $2,266.67, Completion $957.35 1493.4636 $957.35, 18% 43% Development $623.33 972.4
$1,456.79, 27%
Mobilisation
Drilling
Completion
Development
Borehole Cost
$17.85 $53.33 $3.33 $3.33 $1.33 $8.33 $150.00 $78.67 $7.42 $2.42 $11.00
$ GB
5,304 8,274
Name Field note Location: St Gallen Date
Step 6: Results
m 25 kg bags
$12.00 3.00
Step 6: Results
Development
2/24/2009
Gravel Pack Sanitary Seal (Bentonite) Sanitary Seal (cement) Labour: Casing Vehicle running costs Rig Depreciation Development and Pumping Test Borehole Development (Compressor depreciation) Borehole Development (Compressor fuel) Pumping Test (Depreciation) Pumping Test (Fuel) Labour Development Labour Test Pumping Vehicle running costs
8 5.5
3.9 4 4.1
2. Minimum Timescale
Task Mobilisation Drilling Completion Development and TP Demobilisation Duration Duration (hours) (Days) 10.0 13.5 2.5 12.0 10.0 1.3 1.7 0.3 1.0 1.3 Start (Days) 0 1.3 2.9 3.3 4.3 Finish (Days) 1.3 2.9 3.3 4.3 5.5
Rig Depreciation
Mobilisation
Drilling
Completion
Development and TP
Demobilisation
GB Bill of Quantities
Quantity 20.00 520.00 20.00 20.00 Amount ($) $2,267 $340 $693 $167 $1,067 $1,457 $223 $667 $8 $42 $13 $104 $150 $79 $74 $97 $957 $440 $120 $61 No 1 1.1 1.2 1.3 1.4 2 2.1 2.11 2.12 2.13 2.14 2.15 2.16 2.17 2.18 2.2 2.21 2.22 3 3.1 3.2 3.3 Description Mobilisation/Demobilisation Rig Depreciation Fuel Vehicle running costs Labour: Mobilisation Drilling Per Hour: Drilling + Rig Depreciation Labour: Drilling Compressor Fuel Rig Fuel and Lubric Mud & foam Vehicle running costs Temporay Casing Delays Per Metre: Rock Drilling Costs Overburden Drilling Costs Casing and Completion Casing: 110mm casing Screen: 110mm screen Backfill Unit GB/hour km GB/hour hours Unit Rate Quantity 26.52 2.08 13.00 83.20 20.00 520.00 20.00 20.00 Amount 3536 530 1082 260 1664 2273 348 1040 13 65 21 163 234 123 116 151 1493 686.40 187.20 96
12.50 12.50 2.50 12.50 10.00 12.50 1.00 1.00 10.00 40.00
27.85 83.20 5.20 5.20 2.08 13.00 234.00 122.72 11.57 3.77
12.50 12.50 2.50 12.50 10.00 12.50 1.00 1.00 10.00 40.00
40.00
m m 25 kg bags
10.00 20.50
3.4 3.5 3.6 3.7 3.8 3.9 4 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8
Gravel Pack Sanitary Seal (Bentonite) Sanitary Seal (cement) Labour: Casing Vehicle running costs Rig Depreciation Development and Pumping Test Borehole Development (Compressor depreciation) Borehole Development (Compressor fuel) Pumping Test (Depreciation) Pumping Test (Fuel) Labour Development Labour Test Pumping Vehicle running costs Rig Depreciation
$5,304 $6,382
GB GB
8274 9956
3. Cost Breakdown
Equipment Fuel Labour Vehicles Consumables
Total US $
GB
16%
18%
8%
$ $ $ $ $ $
43%
No of Days of Trip Working Days in a year Rig Rig Loan Lifetime (years) Rig Loan Interest Rig Loan Yearly Repayments
5.5 240
C&P Field Note Rig B 10 20.00% $170,000 $39,424.16
Office Cost Item Stationery Bills other 265,200 61,502 Cost for Trip (local) 0 0 0 0 57 215 1,409 1,681 8274.458573 9,956
1600 Per year ($) Per Year (GB) 100 156 500 780 1000 1,560 0 0 0 0 0
Yearly Fee
Cost for Trip ($) $0.00 $0.00 $0.00 $0.00 $36.67 $137.50 $903.47 $1,077.64 $5,304 $6,382
$1,600.00 $6,000.00
$39,424.16
Total Overheads for Borehole Cost of Borehole Total Cost for Borehole
0 0 0 0 0 0 0
Office Staff
6000
Item Per year ($) Per Year (GB) Receptionist 1 500 780 Receptionist 2 500 780 Manager 5000 7,800 0 0 0 0 0
0 0 0 0 0 0 0
GB Bill of Quantities
No 1 1.1 1.2 1.3 1.4 2 2.1 2.11 2.12 2.13 2.14 2.15 2.16 2.17 2.18 2.2 2.21 2.22 3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 Description Mobilisation/Demobilisation Rig Depreciation Fuel Vehicle running costs Labour: Mobilisation Drilling Per Hour: Drilling + Rig Depreciation Labour: Drilling Compressor Fuel Rig Fuel Mud & foam Vehicle running costs Temporay Casing Delays Per Metre: Rock Drilling Costs Overburden Drilling Costs Casing and Completion Casing: 110mm casing Screen: 110mm screen Backfill Gravel Pack Sanitary Seal (Bentonite) Sanitary Seal (cement) Labour: Casing Unit GB/hour km GB/hour hours Unit Rate Quantity 26.52 2.08 13.00 83.20 20.00 520.00 20.00 20.00
GB/hour GB/hour GB/hour GB/hour GB/hour GB/hour GB/hour GB/hour m m m m 25 kg bags 25 kg bags 25 kg bags 25 kg bags GB/hour
27.85 83.20 5.20 5.20 2.08 13.00 234.00 122.72 11.57 3.77 17.16 18.72 4.68 10.96 54.60 31.20 83.20
12.50 12.50 2.50 12.50 10.00 12.50 1.00 1.00 10.00 40.00 40.00 10.00 20.50 7.00 2.00 1.00 2.50
GB/hour GB/hour
13.00 26.52
2.50 2.50
Development and Pumping Test Number of Days (based on set number of hours in a day) Minimum Borehole Development (Compressor 1.04 4.00 0 1 2 GB/hour 3 4 depreciation) Borehole Development (Compressor fuel) GB/hour 2.08 4.00 Mobilisation Pumping Test (Depreciation) GB/hour 2.34 12.00 Pumping Test (Fuel) GB/hour 2.08 12.00 Labour Development and Test Pumping GB/hour 83.20 8.00 Drilling GB/hour 13.00 12.00 Vehicle running costs Rig Depreciation GB/hour 26.52 4.00 Total (excluding overheads) GB Completion GB Total (including overheads)
Development and TP
Demobilisation
Amount ($) $2,267 $340 $693 $167 $1,067 $1,457 $223 $667 $8 $42 $13 $104 150 $79 $74 $97 $957 $440 $120 $61 $49 $70 $20 $133 $21 $43 $623 $3 $5 $18 $16 $213 $200 $100 $68
er of hours in a day)
6
$5,304 $6,382
Amount 3536 530 1082 260 1664 2273 348 1040 13 65 21 163 234 123 116 151 1493 686 187 96 77 109 31 208
Local Currency