Activity : On-going 900mm wide RCU DraIn Top Slab Formwork installation Location : New Road Northbound MC01 CH 60~ CH 90 Date: 03/06/2013
Activity : On-going installation of Welded Wire Mesh for 900mm wide RCU Drain
5 6
Activity : On-going installation of Welded Wire Mesh and Drain Cover for 900mm wide RCU Drain Location : New Road Northbound MC01 CH 60~ CH 75 Date : 04/06/2013
Activity : On-going Finsihing Works of top slab of 900 mm wide RCU Drain Location : New Road Northbound MC01 CH 60~ CH 75 Date : 04/06/2013
Activity : On-going Spiking of cable at Upper Changi Road On-going installation of formworks for 900mm wide RCU Drain Location : Westbound near the existing Bus Stop MC02 CH 125 Date:5/06/2013
Activity : On-going Casting of Top Slab Location : New Road Northbound MC01 CH 140~ CH150 Date:7/06/2013
Activity : On-going casting of 1400mm x 1200mm RC Sump Base Foundation Location : New Road Northbound MC01 CH 140~ CH150 Date:18/06/2013
Activity : On-going Compaction of Sub base Construction. Location : New Road Northbound MC01 CH 140~ CH150 Date:29/06/2013
Activity : On-going installation of formworks for 900mm wide RCU Drain Location : New Road Northbound MC01 CH 140~ CH150 Date:25/06/2013
Activity : On-going RCBC casting of wall and Top slab Location : New Road MC01 CH 30 Date:28/06/2013
Activity : On-going installation of formworks for 900mm wide RCU Drain Location : New Road Northbound MC01 CH 140~ CH150 Date:29/06/2013
Activity : Casting of Kerb Foundation and installation of K2 Kerb Location : New Road CH 40 ~ CH 60 Northbound Date:29/06/2013
Activity : On-going Soil Disposal Location : New Road CH 60 ~ CH 40 West Bound Date:29/06/2013