400KV SWITCHYARD PROGRESS

33KV DATE MAN POWER PCC RCC BOLTING 33KV SWITCHYARD 400KV CABLE TRENCH (In Mtr) CONTROL ROOM STRINGING

29-Sep-11

(129+49) = 178

----

------

10

Door & window Fixing, Painting work in control building. Wall painting work, Tiles fixing.

-----

30-Sep-11 1-Oct-11

(120+49) = 169 (161+49) = 210

3 1

9 3

--6

-------

3 Nos CT erection work Aux Mat 1 no laying, Alignment work of CT & CVT.

10 15

-----

-----

2-Oct-11

(115+39) = 164

----

4 Nos CT erected, AC KIOSK Beam casting.

10

Corridor wall painting, Battery room tiles fixing, 4 nos door glass fixing. Battery room Tiles work, Door & Window fixing.

-----

3-Oct-11

(112+49) = 161

11

----

2 Nos CT erected, Gantry beam erected.

10

-----

4-Oct-11

(26+53) = 79

----

----

----

----

2 Nos CT erected, 5 Nos PT & 1 no LA erected.

-----

Door & window Fixing, Painting work in control building. Door & window Fixing.

-----

5-Oct-11

(27+53) = 80

----

5 nos PI erected,

----------------60

6-Oct-11 7-Oct-11 8-Oct-11 9-Oct-11

----(30+53)=83 (45+46)=91 (87+56)=143

-----------------

--------3 -----

--------3 3

----1 no tower erected -------

----1 Aux mat 1 Tower beam erected, 1 no of Aux mat. 1 set of isolator erected.

------------10

--------Door fixing Switch & Light fitting

10-Oct-11

(76+53)=129

1 no tower erected, 1 no beam erected.

1 no Aux mat, AC KIOSK fixing. 1 no Aux mat, One column CB erected

----

Corridor wall Painting, Battery room tiles fixing Painting, Door fixing & Tile fixing. Door fixing, Tiles fixing, lighting, Painting. Tiles fixing, POP work in under progress. Tiles fixing, POP work in under progress. Polishing work, Tiles Fixing work under progress. Polishing work, Tiles Fixing work under progress. Tiles work & False Ceiling work under progres. Tiles work, Painting & False Ceiling work under progres.

----

11-Oct-11

(104+29+54)=187

----

----

12-Oct-11

(124+54)=178

1 no tower beam, 2 no's CT erected, 8 no's equipment pipe 1 pole of CB erected, AC structure errected. Kiosk misc work. 8 no's equipment pipe structure & 1 num tower beam erected.

15

----

13-Oct-11

(107+32+54)=193

1 pole of CB erected.

15 pcc

---124 Mtr in Twin conductor. 108 Mtr guard conductor stringing. 54 Mtr stringing in one phase

14-Oct-11

(110+54)=164

--

--

14 no's pipe structure 2 no's CT, CVT erected. erected. 16 no's pipe structure erected. 6 no's pipe structure erected. 17 no's equipment pipe structure erected. 2 no's CT erected. 13 nos pipe structure & 1 num ct erected. 1 num Aux mat, 4 no's CVT erected.

25 pcc

15-Oct-11

(155+50)=205

40

16-Oct-11

(175+50)=225

----

25

17-Oct-11

(194+51)=245

2 no's LA erected, AC Kiosk erectcion under progress

15

----

18-Oct-11

(193+53)=246

--

1 LA & 1 Isolator erected.

(30mtr PCC + 20 mtr RCC + 12mtr wall)

----

19-Oct-11 20-Oct-11

(193+51)=244 (176+47)=223 ( 96+49)=145

21-Oct-11

EARTHMAT (In Mtr)

----

150 120

100

100

-----

-----

-----------------

200

120

160

160

140

80

----

250

250

400KV SWITCHYARD PROGRESS DATE MAN POWER PCC 33KV RCC BOLTING
6nos RCC AC KIOSK Spacer fixing work

33KV SWITCHYARD

1-Nov-11

65+52 =117

2-Nov-11 3-Nov-11 4-Nov-11 5-Nov-11

70+48 =118 99+52 =151 77+50 =127 104+50 =154 3 6

pipe str-12nos

6-Nov-11 7-Nov-11 8-Nov-11

109+42=152 107+27=134 136+74=210

3 3

6 4 3 pipe str-12nos

9-Nov-11

140+62=202

pipe str=12no

10-Nov-11

154+62=216

9nos pipe str,

11-Nov-11

105+62= 167

12-Nov-11

101+62=162

10nos pipe str,LA=3nos

13-Nov-11

102+64=166

LA =3nos

14-Nov-11

144+64=178

3 in BTG area

3nos CT, 3nos LA erected in 33 kv,

15-Nov-11

113+62=175

3 in BTG area

ISO-1 set , 3nos CT,

16-Nov-11

128+62=188

3nos CT,3nos pipe str,

17-Nov-11

125+57 =182

pipe str=6nos

18-Nov-11

104+67=161

pipe str=3nos,pt=6no

19-Nov-11

100+54=154

PT=3no ,Iso=3set in 33kv

20-Nov-11

88+50=138

21-Nov-11

96+49=145

22-Nov-11

111+49=160

23-Nov-11

96+43=139

ISO -3 set , suspention disk insulator=6set, CT JB=4nos,

24-Nov-11

109+44=153

1no ct jb & 1no pt jb fixing,9set suspention insulator erected,

25-Nov-11

84+44=128

1no PT JB fixing,6set suspention insulator erected 2set iso topcontact erected,1no CT JB fixing,panel shifting in kiosk3 1no CB foundation casting,1no CT,1set Isolator

26-Nov-11

114+47=161

27-Nov-11

106+46=152

28-Nov-11

114+45=159

9set jumpering,4nos BPI erection

29-Nov-11

119+43=162

12set jumpering,9nos BPI erection,panel erection in Kiosk3

30-Nov-11

105+45=150

9nos BPI erection,3nos jumpering,2set Iso erection

00KV SWITCHYARD PROGRESS 400KV CABLE TRENCH (In Mtr)


30mtr

CONTROL ROOM

STRINGING

EARTHMAT (In Mtr)

FCBC CHARGER-3NOS,

Tower-1(BTG ) BPI-6

60mtr wall 10mtr rcc 10mtr rcc FCBC CHARGER-1NOS Main mat=130mtr 2 aux mat

2nos panel erected in 15mtr wall,12mtr AC KIOSK rcc,20mtr pcc 33mtr wall,8mtr rcc,10mtr pcc Iso=1set,3nos panel ercted in AC KIOSK T.beam1no(400kv),panel erection in kio 3 2 set insulator of iso ,panel alignment in ACKIOSK. 7nos piep str, 2set ISO. 15mtr wall,30mtr rcc,35mtr pcc 20mtr pcc,25mtr wall,(33kv-8mtr wall,10mtr rcc,) 22mtr wall,27mtr rcc in 400 kv,5mtr rcc in 33kv, 5.5mtr wall,10mtr rcc in 33 kv,5mtr rcc in 400 kv. 25mtr wall in 400 kv 17mtr wall in 33 kv,10mtr rcc,10mtr pcc 10mtr wall,10mtr rcc,17mtr pcc in 33 kv 5nos light fitted Main mat=80mtr Main mat=140mtr

5nos light fitted light,tiles fixing,& AC out door work is under progress.

Aux mat=2nos

Main mat=40mtr,Aux mat=1no

stringing 40mt

Aux mat =1no

Iso-1set

stringing 40mtr

17mtr rcc,10mtr pcc,7mtr wall in 33 kv,10mtr pcc,10mtr wall in 400 kv 13mtr wall both side casting,10mtr rcc,12mtr pcc in 33 kv,40mtr pcc in 400 kv

40mtr stringing ,

Main mat=150mtr

Structure of LM erection is u/p

27 nos earthing strip

32mtr wall,22mtr pcc, 10mtr rcc.

48mtr u band laying in cable trench,Aux mat2nos

Bolting=3nos in BTGarea

(17mtr pcc,17mtr wall,15mtr raft) in 33kv, 40mtr pcc in 400kv 200mtr main mat laying ,Aux mat-4no(in 33kv) 26mtr main mat lalying & aux mat=8 nos(33kv),

Pcc=4 no(Aux foundtion of SRT 1)

17mtr pcc in 33kv,24mtr raft in 400kv

AC out door unit fixing,painting u/p in control room,

24mtr raft pipe str =3no(LA),in in400kv,10mtr Painting & wiring work u/p BTG area, pcc=2no(btg in control room, wall &17mtr raft area) in33kv

Raft=4nos(SRT 1 aux foundtion),2nos raft &4no pcc in BTG area

7mtr raft &15mtr wall in 33kv

wiring & acid proof painting work u/p in control room

stringing-22.8mtr in 33kv

Breaker=1set, 2nos raft in BTG area,

18mtr raft & 17mtr wall in 33kv,12.5mtr wall in 400kv

painting& wiring u/p in control room,road work u/p

Aux mat=2no(400kv) Stringing=50mtr(3 , 3kv) 1no(33kv),Main mat laying22mtrs

Breaker=2 pole, 5nos 10mtr wall in bolting in BTG 33kv, 30mtr pcc in area,road work u/p 400kv Breaker=1pole,Iso=2s 32mtr wall (33kv) et,Earth removal work & 15mtr raft in u/p(from main cable 400kv. trech side) 15mtr rcc & 12mtr wall in 33kv,20mtr RCC &10mtr one sidewall castingin 400kv

Painting u/p in control room,

Stringing=160mtr( 33kv)

100mtr

Painting u/p in control room,

Stringing=126mtr( 33kv),42mtr quad stringing in 400kv

2set iso erected

painting & lighting work u/p

stringing=250mtr in 400kv

2set ISO erected,2no BPI str erected

20mtr RCC

painting & lighting work u/p

stringing=52mtr twin conductor

10mtr pcc in 1set isolator erection, 33kv,7mtr raft in 400 kv

painting & lighting work u/p

stringing=(52*2)m Aux tr of twin mat=2nos(400k conductor in v) 400kv

3no CT erection

12mtr rcc in 33kv,10mtr rcc in 400kv

painting work u/p

String=30mtr(33kv 106mtr main ) mat in400kv 102mtr main mat in 400kv,25mtr in 33kv

17mtr pcc& 15mtr 2no Aux foundation wall casting in casting of SRT,1set Iso 33kv,15mtr rcc in erection 400kv 17mtrRCC &12.5mtr wall in 33kv,24mtr wall in 400kv 15mtr pcc&10mtr wallcasting in 400kv,25mtr pcc in 33kv

painting & AC work u/p

painting & AC work u/p

130mtr main mat laying in 400kv

1set CB pole erected

Stringing=62mtr painting & Ac wiring work quad moos u/p in400kv

Aux mat=2no(33kv), 1no(400kv)

OTHER

Road work to SRT2 u/p

Road work to SRT2 u/p

Road work to SRT2 u/p

3no PCC inBTG area

3nos RCC&1no pcc in BTG area

400KV SWITCHYARD PROGRESS DEC-11 DATE MAN POWER PCC 33KV RCC BOLTING 33KV SWITCHYARD 400KV CABLE TRENCH (In Mtr)

1-Dec-11

112+48=160

1no CB erected,9no iso pipe structure erected

22mtr wallcasting in33kv,37.5mtr wall casting in400kv

2-Dec-11

98+55=153

1no pole CB erected,spacer fitting in 12nos pipe strs erected quad moose u/p,LM no2 erection u/p

10mtr wall casting in 400kv

3-Dec-11

123+54=177

14nos pipe strs erected,1no CB erected,30mtr nose engle fixing .

1pole CB erected,20nos 12mtr Raft & 15mtr Wall spacer fitted in line casting in 33kv,50mtr dia,LM2 erection u/p Pcc in 400kv

4-Dec-11 5-Dec-11 10mtr Raft & 35mtr wall in 33kv,28mtr wall casting in 400kv

6-Dec-11

82+56=138

2no CTJB &1no PTJB fixing

1no WT erected

7-Dec-11

92+57=149

1no WT erected,3no 47mtr Raft in 2no ISO eligment & 6no jumper insulator 400kv,12mtr wall & jumpering erected,LM2 erection 38mtr nose angle casting u/p of cable trench in 33kv

8-Dec-11

90+58=148

6nos jumpering of CT in 33kv,2no ISO alignment

1set CB pole erection,2no Quad moos jumpering

20mtr raft in 400kv & 20mtr wall casting in 33kv

9-Dec-11

71+58=129

1no CB pole erected,LM 2 erection 24mtr Raft in 400kv u/p

10-Dec-11

107+59=166

3 nos PT , 1 nos Iso 30mtr R.C.C in 400kv, 10 2 nos CB pole erected, erected, 2 nos Iso mtr PCC in 33kv, cable alignment & 40 mtr IPS 2 nos quad moose tray support work u/p. jumpering, LM 2 tube erection u/p 20 mtr PCC and 10 mtr RCC in 400kv, 3 mtr 2 nos Iso alignment, 2 3 nos CT erected, LM 2 PCC,5mtr one side wall nos jumpering erection u/p casting and 7mtr RCC, cable tray support work u/p in 33 kv

11-Dec-11

101+59=160

12-Dec-11

13-Dec-11

133+60=193

6nos suspension jumpering, 2 nos Isolator alignment

6 nos suspension erection, 10mtrx4nos IPS tube welded u/p, LM 2 u/p

12 mtr RCC ,10 mtr PCC, cabletray supprot work u/p,50mtr PCC in 400kv

14-Dec-11

136+61=197

6nos equipment pipe structure erected,

WT=2nos erected,6nos suspension disk erected,LM2 erection u/p

10mtr Rcc,17mtr Raft,15mtr Wall casting in 33kv,40mtr pcc in 4ookv

15-Dec-11

135+62=197

10

9 nos pipe strs erected,3no Ips tube erected,cable tray support welding u/p,

2nos CTJB fixing,LM2 erected,IPS tube welding u/p,9nos mechanism box fixing .

15mtr PCC,7mtr RCC &9mtr wall casting in 33KV,50mtr PCC in 400kv.

16-Dec-11

123+62=185

2set Isolater erected,1set iso 40mtr Pcc in Isolater Mech box stand eligment,6nos 400kv,10mtr wall casting fixing=5nos, suspension disc in 33kv insulater erection,2no CT JB fixing

17-Dec-11

127+64=191

16mtr PCC,16mtr RCC IPS tube welding u/p,2 &27mtr wall casting in 3nos IPS tube CT JB & 2nos CVT JB 33kv,27mtr PCC & 3omtr erected,6no BPI erected fixing wall casting,20nos precast slap casting

18-Dec-11

135+66=201

2no ISO mecha box fixed

6nos ISOmechanism box fixed

35mt RCC in 400kv,15mtr wall casting & 5mtr Rcc in 33kv

19-Dec-11

134+66=200

3no grouting ,6nos BPI erected,3no IPS tube erected,1set ISO eligment

35mtr wall casting in 33kv,10mtr rcc in 20nos BPI clamp fixing 400kv,20no precast slab in main BUS 1,6no ISO in 400kv. mechanism box fixing,

20-Dec-11

136+66=202

10

27mtr Al tube erected on main bus,5nos ISO 3nos IPS tube mechanism erected,1no CB box&3noE/S casting,cable tray mechanism box support fixing work u/p, fixing,1no BPI erected,4no bpi clam fixing

20mtr Rcc in 400kv

21-Dec-11

143+66=209

2set Iso contact fixing,2no LA clamp fixing,30mtr nose angle fixing in cable tranch

2no of 27mtr IPS tube erected on main bus,2no BPI erected ,2no ISO mechanism box fixing

13mtr wall casting in 33kv,25no precast slab ,8mtr Rcc in 400kv

22-Dec-11

135+65=200

1no CB foundation casting,leveling work u/p

30mtr pcc& 7.5mtr wall 3 span spacer casting in 33kv,10mtr fixing,3no jumpering in pcc & 30mtr raft in line dia & Isolater 400kv.13 precast slab in eligment u/p 400kv.

23-Dec-11

102+66=168

6.5mtr of 4no Al pipe tube erected on main bus,suspention jumper erected=6nos,7no BPI ereted 18mtr of 2no Al tube erected on main Bus,6.6mtr of 3no AL tube erected on o/g fidder ,5mtr of 1no Al tube erected on inter connecting.6no BPI erected,1no ISO eligment.

2no BPI erected,27mtr of 3noAI tube pipe 12.5mtr wall casting & erected ,2no quad 10mtr nose angle casting moos jumpering,6no in 33kv,15mtr Rcc in ISO mechanism box 400kv. fixing,

24-Dec-11

152+66=218

27mtr *2no AL tube erected on main bus2,3no pipe str 17mtr RCC in 33kv,35mtr erected,2no LA PCC in 400kv erected,8no Light fitting erecte on LM1

25-Dec-11

154+65=219

SRT1 soak pit PCC of one side, 3 nos pipe 15mtr RCC & 17mtr nose 44 mtr IPS tube Erected, structure erected, 1 angle work in cable 1 nos ISO alignment. nos LA erected, 40 mtr trench, IPS tube erected

26-Dec-11

176+17=193

18mtr of 3no Al pipe erected on main bus.

6no clamp connectors fixing,1no Iso eligment.

7mtr Raft & 15mtr wall casting in 33kv,20mtr Pcc in 400kv

27-Dec-11

129+60=189

7mtr Rcc & 30mtr wall 1no CB foundation 3nos LA erected,7nos casting in 33kv,30mtr casting,60mtr AL tube clamp connector of ct Pcc in 400kv,20mtr nose erected,6nos pipe str & 5no clamp connector angle casting in 33kv & erected of ISO fixing 40mtr nose angle fixing in 400kv.

28-Dec-11

117+63=180

12no equipment base 54 mtr AL tube erected grouting,3no PI pipe ,6no clamp connector structure & 3 nos ISO of CT& 6nos of ISO pipe str erected,6nos PI fixing,1no ISO ercted, erected.

25mtr Pcc ,20mtr wall casting &30mtr nose angle casting in 33kv.

29-Dec-11

137+67=204

1set CB pole 40mtr Pcc in 3no pipe structure erected,LM 3 erection 400kv,34mtr Pcc &15mtr erected,10mtr of 3no Al complete,6no ISO & wall casting in 33kv,5no tube erected,3no PI 6no CT link clamp foundation of Iso erected,6nos pipe str connector fixing ,27mtr mechanism box alignment of 2no Al tube erected stand.10mtr nose angle on main bus. casting in 33kv.

30-Dec-11

106+69=175

1no HL Iso erected,1no CB erected,jumpering in 1no CT erected,1no ISO one bay,90mtr Tray erected,6no CT & 6nos laying,2nos BMK Iso connectors fixing, foundation casting

89+69=158

31-Dec-11

6 nos ISO mechanism box fixing, 6 nos earth switch Iso mechanism box fixing, 30 mtr IPS tube erected, I nos BMK RCC, 2 nos BMK PCC , 2 nos grouting of equipment foundation

6 nos LA, 6 nos CT and 15 mtr PCC in 33 kv 3 nos ISO clamp cable trench, 20 mtr RCC connector fixing, 54mtr in 400kv cable trench IPS tube erected

CONTROL ROOM

STRINGING
1span 52mtr twin moos conductor in 400kv

EARTHMAT (In Mtr)


70 mtr main mat in 400kv

OTHER

AC wiring & light fitting u/p

2no PCC of Srt2

AC wiring & light fitting u/p

2no bolting & 1no rafting in BTG area

AC wiring & light fitting u/p

30mtr main mat,5mtr riser fitting=12no,

2nos bolting in BTG area,4no pcc of SRT 1 ,4no Raft of SRT2

4nos Aux foundtion Rcc of SRT2 &5nos Rafting complet in SRT1

Cable Trey fixing work u/p

3no Rafting of SRT1 & 6no PCC of SRT2.

Main earthmat=70mt r in 400kv

8nos RCC &6nos padestal of SRT2 Aux Foundation

lighting work u/p.

80 mtr main earth mat in 400kv

11 nos R C C & 7 nos column casting in SRT 1,4 nos column casting in SRT 2 aux. foundation

lighting work u/p.

light fitting work u/p.

7nos column casting in SRT 2 aux. foundation,Tower foundation (BTG area) exavation u/p

11nos column casting in SRT1,IPS tube welding u/p

20mtr trey fixing,battery stand fixing u/p

1 no PCC of tower foundtionin BTG area

100mtr shield Battery stand fixing wire stringing in u/p 400kv

120mtr shield wire stringing in 400kv

IPSTUBE welding u/p

Bus bar tightness of ACDB panel

62mtr shield wire stringing in 400kv

60mtr main mat laying,100mtr flat riser fixing in 33kv

IPSTUBE welding u/p,SRT TFR2 shifting u/p

Bus bar tightness of PMCC panel

50mtr flat riser fixing

IPS TUBE welding u/p,1no Raft of Tower(4t5 )in BTG area ,SRT TFR2 shifting u/p

Bus bar tightness of PMCC &DCDB panel

45mtr main earth mat laying in 33kv

IPS TUBE welding u/p

lighting work u/p & testing work u/p

IPS TUBE welding 50mtr main mat u/p,SRT 2 laying in 33kv Transfermer erected on foundation.

lighting work u/p & testing work u/p

IPS TUBE welding 45mtr main u/p.First lift column earth mat laying casting of tower in in 33kv Btg area,Earth leveling work u/p .

lighting work & testing work u/p,2nos exhaust Fan fixing in battery room,

LM no 3 erection on u/p

24mtr earthing LM no 3 erection on of equipment in u/p 33 kv

Testing & Tray work u/p

LM no 3 erection on u/p,SRT1 soak pit PCC completed

Battery stand ,Testing & Tray work u/p

50mtr equipment riser fixing

LM3 erection u/p,IPS Al tube welding u/p

Battery erection ,Testing & Tray work u/p

60mtr flat riser LM3 erection welding in main u/p,IPS Al tube cable tranch welding u/p,rod (33kv),100mtr binding of Tower nose angle upper lift(BTG area) fixing in 33kv & 4ookv.

Battery erection ,sanitary tile fixing work u/p,Testing & Tray work u/p in panel room.

3no Aux mat laying in 33kv,50mtr riser IPS Al tube welding u/p. fixing,45mtr nose angle fixing in cable tranch

Battery erection ,Testing & Tray work u/p in panel room.

30mtr riser fixing,3no Aux mat laying

IPS Al tube welding u/p..SRT1 soke pit wall casting

Battery erection ,Testing & Tray work u/p in panel room.

40mtr riser fixing,2no Aux mat laying in 33kv

IPS Al tube welding u/p.

400KV SWITCHYARD PROGR DATE


1-Jan-12 2-Jan-12

MAN POWER
45 17+60=77

PCC

33KV RCC

BOLTING

33KV SWITCHYARD

4 ,mtr IPS tube erected,3 nos machenism box ercted,

3-Jan-12

59+73=132

Main bus with feeder jumpering for 5bay,6no ISO mechanism box ,4no Earth switch erected.

4-Jan-12

110+59=169

1no CB casting

mainBus 2 to o/g feeder jumpering ,6no LA clamp connector fixing,2no ISO alignment with mechanism box,

5-Jan-12

143+59=202

12 nos BPI and 3 nos CT foudation grouting,jumpering from main bus to I/C fidder.

6-Jan-12

121+62=183

1nos BPI rcc,2nos CB,1nos pipe str,40 mtr cable trey erection complete, 3no ISO aligment complete,9nos equipment pipe str erected,Hl ISO -1no erection

7-Jan-12

153+65=218

8-Jan-12

132+62=194

1no CB casting

2no Al tube of 9mtr erected ,6no pipe structure erected,25mtr cable try laying

9-Jan-12

155+67=222

3no of 5mtr & 1no 8.5mtr Al tube erected ,3no line PT jumpering,5no BPI erected,50mtr cable tray laying,6no CT-JB glanding

10-Jan-12

141+61=210

2no ISO mechanism box fixing,12nos BPI erected,600mtr cable laying in between kiosk & bay 1.

11-Jan-12

143+69=212

6no BPI erected ,6nos structur erected,3no ISO aligment.450mtr

12-Jan-12

146+32=216

6nos CT structure erected,9no BPI str 2nos BMK aligment,3nos ISO faundation casting eligment,500mtr cable laying.testing of CT in Bay no 1. 2no ISO & 6no pipe structure eligment,9no BPI erected,1no BMK erected.500mtr cable laying .

13-Jan-12

109+70=179

14-Jan-12

102+70=172

9.5mtr of 3no Al pipe erected,12 no BPI insulator erected ,400mtr cable laying.25mtr cable tray laying,12no foundation grouting. 25 mtr cable tray laying, 6nos BPI erected, 9 nos pipe structure alignment, 8 nos foundation grouting, 100mtr cable laying.

15-Jan-12

74+70=144

16-Jan-12

106+55=161

3no ISO aligment,35mtr cable tray laying.

17-Jan-12

108+53=161

2no ISO alingment,2no ISO erected,360mtr cable laying,cable tray fixing u/p.

18-Jan-12

105+81=186

1no BMK panel erected,3no pipe structure aligment,cable glanding of jb&iso box of 5bay in 33kvu/p.

19-Jan-12

114+84=198

40no equipment grouting ,leveling working u/p

30no cable glanding in both JB & miso mechanism box,2no ISO erected,1no ISO alignement

20-Jan-12

86+94=180

40nos cable glanding,2no ISO aligment

21-Jan-12

119+80=199

3no ISO aligment.250mtr cable laying in bay 7,cable glanding in panel u/p.

22-Jan-12

111+81=192

16 nos cable glanding, 2 nos ISO alignment

23-Jan-12

116+82=198

18no cable glanding,2no ISO alignment.

24-Jan-12

129+81=210

1no ISO aligment,1 no ISO erected,32 no cable glanding,100 mtr tray laying in 33kv.

25-Jan-12

141+72=213

60mtr cable tray fixing,testing of bay no 6 u/p.cable glanding u/p.

26-Jan-12

27-Jan-12

80+71=151

cable glanding u/p in AC kiosk panel,testing of bkr,

28-Jan-12

94+70=164

Cable glanding u/p in AC kiosk 1 panel,testing CT in bay 7completed.

29-Jan-12

89+69=158

Cable glanding u/p in AC kiosk 1 panel, 25mtr PCC of fencing, 8nos foundation grouting.

30-Jan-12

77+69=146

Cable glanding u/p in AC kiosk 1 panel,testing in 33kv,1no ISO alignment.

31-Jan-12

84+68=152

Cable glanding u/p in AC kiosk 1 panel & continuty chek. Iso mechanism box suport fixing.

KV SWITCHYARD PROGRESS JAN-12 400KV CABLE TRENCH (In Mtr) CONTROL ROOM
cable laying u/p LM erection u/p , 3nos clamp connecter & 3 nos ISO ercted. LM 3 Tower erected ,1no ISO erected,6no CT & 3no ISO connector fixing,2 no of 18mtr jumpering in LA,CVT panel testing u/p , cable laying u/p

STRINGING

48volt charger panel testing u/p , cable laying u/p

1no LA & 2no CVT clamp connector fixing,1no LA jumpering,Gantry beam erection u/p

30mtr Rcc in 33kv,15mtr Raft in 400kv

48volt battery charging u/p , 220v Battery commissioning u/p,Panel testing & cable laying u/p

LA,CVT jumper 48volt battery charging complete of line #2,1 15mtr RCC in 33kv , 12 u/p , 220v Battery nos isolator mtr RCC in 400kv commissioning erected,1nos gantry u/p,Panel wiring chek. beam erected.

gantry beam box comlete

10mtr rccin 400 kv

Gantry beam 30mtr Raft in 220volt 150amp battery tightening 400kv,20mtr nose charging u/p , 220v ,Radiographi of Al pipe angle fixing,13mtr raft Battery electrolyte top jointing u/p.Al pipe & 20no equipment up u/p,DCDB Panel welding u/p. grouting in 33kv. wiring chek.

6no ISO mechanism box fixing ,cable tray 10mtr wall casting in support angle fixing in 33kv cable tranch.

1 span quad moos of 54mtr stringing in 400kv

ISO alingment u/p,

10mtr wall & 12mtr RCC in 33kv,25no equipment grouting,20mtr wall casting & 40mtr nose angle fixing in400kv.

PMCC relay scheam checking,220v battery charger panel tightness

108mtr Quad moos stringing in 400kv

20mtr wall casting & PMCC relay scheam Gantry Beam 10mtr rcc in checking & testing,220v assembling in Btg area 400kv,14mtr wall ,600 AH battery charger u/p casting & 3mtrb pcc in panel load testing 33kv

Gentry Beam 20mtr wall casting in assembling & tightness 33kv , 15mtr PCC & u/p. 20mtr RCC in 400kv

PMCC relay scheam checking & testing,220v ,150amp battery charger panel load testing

one side Gentry Beam erected in BTG 10mtr Pcc,11mtr wall area,30mtr cable tray 220volt,615AH Battery casting in 33kv,15mtr support fixing in main charging. Raft casting in 400kv. cable tranch,1no ISO aligment.

40 mtr Tray support fixing ,Gatry beam of btg area completed

25mtr raft in 400kv,7mtr raft in 33kv

220volt,615AH second Battery bank charging u/p,tesing of 33kv equipment u/p.

40mtr Tray support fixing u/p in main cable tranch.

20mtr wall casting & 220volt,615AH second 15mtr soakpit wall Battery bank charging casting in 400kv,14mtr ,tesing of 33kv wallcasting in 33kv. equipment u/p.

1 nos ISO alignment

12 mtr RCC of cable trench in 33 kv

1no ISO aligment, 6no (27mtr)Al pipe erected on main bus.6no pcc of aux founation in SRT2.

15mtr Pcc in 33kv,40mtr wall casting in 400kv.

4T 5p tower erection u/p in BTG area,nose angle fixing in main cable tranch.

10mtr wall casting ,40no precast slab Rcc,One side Aux Foundtion of SRT2 u/pin 400kv,20mtr wall casting in 33kv. 4nos Rcc of Aux foundtion of SRT2,10mtr Rcc in 400kv,15mtr wall casting in 33kv,9no grouting of tower in 33kv.

2pole CB erected,4t5p Tower erection completed in BTG area.

1no CB pole 5no padestal casting erected,120mtr cable of SRT2,12 mtr wall tray support fixing,1no caswting both side in ISO aligment. 400kv,

10mtr wall casting & 4nos padestal casting 1no ISO of SRT 2Aux foundtion aligment,120mtr cable in 400kv,12mtr tray support fixing. fencing work completed,Bay no 10 leveling u/p 15mtr wall casting in 2pole CB top ineruptor 400kv,40no precast erected,1no ISO slab in 33kv,20mtr aligment.50mtr cable fencing complet in tray support welding. 33kv. 1 pole CB top ineruptor erected, 1 10mtr fencing complet nos ISO alignment, 60 in 33kv. mtr cable tray support welding 3no CB top interuptor erected,1no ISO alignment,75mtr cable tray support welding. 25mtr break work of fenching in 33kv,15mtr wall casting in 400kv

2 span of 52 mtr twin conductor stringing

1 span twin moos of 68 mtr stringing in 400kv GT1 bay.

10 mtr wall casting in 33kv,15mtr wall 3no CB top interuptor casting in 400kv,srt2 erected, raft casting, 40no precast slab .

1 span 98mtr stringing in 400kv GT1 gantry Bay

3no CB top interuptor erected,1no ISO alignment. Sock pit raft of srt2.

5mtr raft in 33kv,10mtr wall in 400kv.

1 span 98mtr stringing in 400kv GT1 gantry Bay

3no CB top interuptor 10no pre cast slab with mechanism box casting & 20 mtr nose erected, angle casting in 400kv

spacers fixing between twin conductor in 400kv u/p.

3no CB top interuptor with mechanism box erected,2no cvt jb fixing in line dia.

20mtr wall casting in 400kv,20 mtr soke pit wall of srt2,10mtr wall casting in 33kv.

spacers fixing between twin conductor in 400kv dia-3.

12mtr both side cable trench wall casting in 33kv.

spacers fixing between twin conductor in 400kv dia-2.

2no CB top interuptor 20mtr wall casting in erected,1no CB 33kv, soke pit raft mechanism box casting of srt2 erected. LM no4 u/p,25nos pre cast erection u/p. slab casting .

spacers fixing between twin conductor in 400kv GT 1 bay.

7no mechanism box of 10mtr RCC soke pit CB erected,1no CB top wall in SRT2,10mtr interuptor erected,LM wall casting in 400kv 4 erection u/p.

jumpering of wave trap in line bay.

EARTHMAT (In Mtr)


30 mtr riser cuting 45 mtr riser

OTHER

80mtr flat riser fixing

second lift casting of tower in BTG area

45mtr Flat riser fixing in 33kv

100 mtr flat riser fixed in cable trey erection in 33 kv 33 kv gantry tower & cable trench , cable laying 2nos aux mat laying. u/p

50 mtr(ms rod) riser ,20mtr flat riser(GI), 4nos aux mat laying

tower 4t5p complete in BTG area

60mtr riser fixing in 33kv

35mtr main mat laying,4no aux mat welding,20mtr flat riser fixing in 33kv

60mtr riser fixing in 33kv

25mtr soak pit wall casting of SRT1

48mtr flat riser & 25mtr main mat laying in 33kv.

30mtr main mat laying in 33kv.15mtr GI flat laying in cable trach.

88mtr flat riser fixing in 33kv.

45 mtr flat riser fixing in 33kv

70mtr Flat riser fixing

Last tower erection u/p in BTG area

110mtr flat riser fixing in 33kv

Aux equipment of SRT 1erection work u/p

45mtr flat riser fixing in 33kv

Aux equipment of SRT 1 erection work u/p,Testing of equipment in bay no10(33kv) u/p.

123mtr flat (75x8) riser fixing in 33kv

Aux equipment of SRT 1 erection work u/p,Testing of equipment in bay no9(33kv) u/p.

42mtr of 75x8 flat riser fixing in 33kv

Aux equipment of SRT 1 erection work u/p,Testing of equipment in bay no9(33kv) u/p.

80mtr flat riser fixing in 33kv

Aux equipment of SRT 1 erection work u/p,Testing of equipment in bay no8(33kv) u/p. 2 nos aux foundation casting and 3 mtr PCCof SRT 2, Aux equipment of SRT 2 erection work u/p, 4 nos SRT 1 aux foundation casting

80mtr of( 75x10) flat riser fixing

Aux equipment of SRT 1 &2erection work u/p,

Bushing ct of SRT 1 testing &erection work u/p,Tesing of 33kv equipment u/p.

Bushing ct & neutral ctof SRT 1 testing completed.

Bushing of SRT 1 & 2, tan delta testing

Radiator support frame of SRT 2 erected,all testing of bushing & ct completed before erection.

110 mtr 40mm ms rod riser, 45mtr flat riser fixing in 33kv.

6nos SRT1 fans fixing, SRT 2 frame alignment, 4nos column casting in SRT2.

conservator tank ,2no HV bushing turret & 1no hvn bushing turret erected on SRT1.

3no LV bushing,1no LVN bushing & HVN bushing with turret erected on SRT1.

400KV SWITCHYARD PROGRESS FEB-201 DATE MAN POWER PCC 33KV RCC BOLTING 33KV SWITCHYARD

1-Feb-12

109+70=179

continuty check in AC kiosk 1

2-Feb-12

123+68=191

110*4 mtr ,35sq Al cable laying from ACDB to BMK1.12no glanding in AC kiosk panel.6no BPI erected,

3-Feb-12

88+77=165

9no Raft of AC kiosk 3,cable termination & glanding work u/p.

4-Feb-12

114+78=192

15mtr perforated tray fixing,cable glanding & termination work u/p.4no BPI erected.

5-Feb-12

101+78=179

3 nos column casting, 7 mtr grouting of wall, cable glanding & termination work u/p

6-Feb-12

130+73=203

72.5mtr 100mm tray fixing, 1 nos ISO erection,cable glanding & termination work u/p, 5 nos column casting of Ackiosk, 10 mtr PCC of fencing, 10 mtr fencing wall 3 nos PI erection, 6 nos pipe structure erection, 1 nos ISO erection, 1 nos column casting of AC Kiosk.

7-Feb-12

94+69=163

8-Feb-12

95+55=150

1 nos CB in bus coupler bay ,3 nos CT 3 STR alignement. 7 no. LM u/p

9-Feb-12

122+73=195

24 nos pipe str erected ,3 nos alignement,3nos BPI erected,

10-Feb-12 11-Feb-12 12-Feb-12 13-Feb-12 40 12 nos grauting of eqp structure 6no pipe structure alignment.cable terminaion in jb u/p

worked stoped due

14-Feb-12

29+40=69

15-Feb-12

61+50=111

2no pcc of BMK,3no LA erected,12no clamp connector fixing,termination work u/p

16-Feb-12

66+53=119

6no of 6.5IPS Al tube erected,cable termination u/p,4no equipment pipe structure alignment,1no ISO erected 3 nos IPS al tube fixed ,9 nos BPI connector fixed ,3 nos BPI str alignement ,

17-Feb-12

62+53=115

18-Feb-12

76+53=129

3no of 7mtr AL tube & 3no of 10mt Al tube 1no CB extention erected on I/C bay,3no foundtion casting BPI erected.cable temination u/p.

19-Feb-12

78+53=131

3no BMK rcc

1no 9mtr quad moos jumpering,LM5 erection u/p

20-Feb-12

60+53=113

1no CB extention foundtion casting,1no BMK bolting,1no BMK raft.

3nos PT erected,1no CB erected,3no BPI erected,cable termination u/p

21-Feb-12

79+64=143

3no ISO alignment,1no CB erected.

22-Feb-12

65+77=142

1no CB extention casting,1no BMK casting

5.5mtr of 6no Al pipe erected,6no clamp of HlPI erected,5no ISO mechanism box stand welding, LM 6 erection u/p. 5.5mtr of 6no Al pipe erected,6no BPI erected,5no ISO mechanism box stand welding, LM 6 erection u/p. 18mtr of 2no Altube erected,8mtr of 3mtr Al tube erected,24no cable glanding,LM6 erection u/p,4no ISO mechanism stand fixing. 36mtr IPS tube erected,9 nos earth switch erected & alignement,9mtr calvert RCC both side, 10 mtr fencing plaster.LM u/p. 18mtr IPS tube ercted, LM no.7 erection complete, .cable termination in AC KIOSK u/p. 9 mtr slab RCC of calvert , 9 mtr nos angle grouting. Reley instal in AC KIOSK.

23-Feb-12

89+62=151

1no BMK foundation casting

24-Feb-12

77+60=137

25-Feb-12

123+67=190

26-Feb-12

145+59=204

27-Feb-12

115+18=133

28-Feb-12

133+62=195

1 nos CB foundation RCC, leveling u/p, 2 nos ISO erection, 6nos machenism box erection, 4 nos earth switch erected, cable termination in AC kiosk u/p,2no CB erected,6mtr of 3no Al pipe erected on main bus2,1no ISO erected,1no Iso alignment.

29-Feb-12

137+62=199

0KV SWITCHYARD PROGRESS FEB-2012 400KV


3no CB top interuptor erected,jumpering work on main bus,LM 4 erection u/p,100mtr cable tray support welding.

CABLE TRENCH (In Mtr)

CONTROL ROOM

STRINGING

EARTHMAT (In Mtr)

10mtr rcc ,6no pcc of ac kiosk 3 in 33kv,10mtr wall casting in 400kv.

termination of power cable from 48mtr jumpering in ACDB TO 400 kv CHARGER

Flat riser bending work u/p

3no CB top interuptor erected,LM 4 erection 2no exhaust fan 30mtr wall casting in u/p,80 mtr cable tray maunted in panel 50mtr jumpering in 400kv,10mtr wall support welding in cable room,lighting & line 1 bay. casting in 400kv. tranch .2no AL tube sanitary work u/p. erected in line1 bay.

6no CB mechanism box erected,LM 4 erection 10mtr wall casting in u/p,25x3 mtr cable tray 400kv,20mtr sock pit support welding in cable wall casting of SRT 2 tranch,

one ACDB fixing for AC,Lighting work u/p.

8no of 8.5mtr jumpering in line dia.

30mtr flat riser fixing in 33kv.

1no ISO alignment, LM 4 10mtr wall casting in erection completed,LM5 400kv,20mtr wall erection u/p,6no ISO casting in 33kv,soke clamp connector pit wall of SRT 2 erected. completed.

8no of 7mtr jumpering

LM 5 erection u/p

7 mtr wall casting on both side in 33kv

30mtr flat riser fixing in 33kv.

75 mtr IPS tube erection, 12mtr wall casting in LM 5 u/p, 29 nos both side of cable precast slab casting trench in 400kv

40 mtr quad moose jumpering,

52 mtr main mat, 40 mtr euipment earthing

9 nos connector fixing in CB, LM 5 u/p, road work u/p,1 nos ISO alignment, 60 mtr cable tray support welding 18 nos CB connecter fixed, 96 mtr 32x3 cable support fixed,225 mtr cable laying from CT to JB, 7 nos staire case rcc of CB 30 mtr Pcc of road . 12 nos connecter fixed in 1 nos CB & 1nos CT, 60 mtr cable trey sopport fixed,240 mtr cablin from CT to JB, LM no. 6&7 erection u/p, 25 mtr pcc of road.

15 mtr wall RCC of cable

cable termination u/p, cable glanding u/p

28 mtr wall RCC of cable trench.

cable termination u/p, cable glanding u/p

30mtr flat riser fixing in 400 kv.

worked stoped due to labor problem


6 nos RCC of staire case padestal of CB 12no CT connector fixing,30mtr cable tray support welding.3nos rcc of staire case padestal casting.

3no PCC in BTG 2 area,AC foundation of AC kiosk,9no ct clamp connector fixing,

LM4 erection completed,12nos CBclamp connector erected,6nos CT clamp connector erected.6no 100mm tray fixing. 1 ISO alignement ,LM4 erected , 30 mtr trey erected, 9 nos CT connecter, CVT box cabling ,PCC of road 5 mtr,

5 mtr wall rcc of cable trench ,

2no quad moos of 9mtr jumpering,cable laying between cvt & jb.

7mtr wall casting in 400kv.

2no of 6mtr Al IPS tube 12mtr wall casting in erected,3no BPI both side of cable erected,cable trench in 400kv termination u/p.

12mtr wall casting in 1no ISO alignment, LM5 both side of cable erection u/p,1no 7mtr trench in quad moos jumpering,CT 400kv,12mtr nose cable glanding u/p. angle casting.

2no raft in BGT area,LM5 erected

15mtr nose angle casting

1no ISO alignment,3no CT cable glanding,

3no of 5.1mtr twin 2no AUX mat ofIso in jumpering(Bus1 line dia welding. cvt).

3no ct cable glanding,1no ISO alignment,10mtr pcc of fencing.

9mtr culvert wall casting both side & 9mtr pcc of culvert near control room,10mtr pcc in 400kv

jumpering work u/p.

2no AUX mat ofIso in line dia welding.

jumpering u/p,1no ISO alignment,tray fixing on 10mtr raft in 400kv. ct.

1nos ISO alignement,, 3nos cable tery fixed,cable glanding u/p ,9 nos CB stair case RCC&PCC. 1 nos ISO alignement ,6 nos 100 mm cable trey of CT erected AC erection in AC KIOSK no.2&3 u/p. 9 nos RCC of CB staire case. 9 nos PCC of CB staire case foundation. 27 nos pree-cast rcc.

3 nos jumpering

6 nos aux mat.

10mtr PCC of cable trench.

9 nos staire case RCC of CB, LM no.u/p, ISO u/p,6 nos trey 18 mtr of CT ercted .

10 mtr PCC.

1no culvert(9mtr) LM 7 erecteion u/p,6no upper slab perforated tray casting,7mtr raft in fixing,40mtr nose angle 33kv,12mtr pcc penting work u/p welding,pipe bending ,75mtr wbm work of job u/p. road in 33kv,30mtr nose angle casting.

3no aux mate welding in 400kv,25mtr main earthmat laying in 33kv.

OTHER

Equilising pipe conection & all turret erection of SRT1 completed

3no LV bushing turret,HVN & LVN turret & 2no HV bushing turret erected on SRT2.

1no HV bushing turret,all LV bushing,both LVN& HVN bushing,both side rediator & conservator tank frame erected on SRT2.

Equiliser pipe conection ,PRD bend pipe ,thermosyfon tank & butterfly valve fixing in SRT2.

6 nos fan mounting, DM shaft fixing in SRT 2.

2 nos column casting, 2 nos RCC of equipment foundation in BTG area, insulator erection, equaliser pipe fixing, tighting work in SRT 2

3 nos of SRT 1 and 1 nos of SRT2 HV bushing erection, 2 nos PCC in BTG area, 1 nos bolting of equipment foundation in BTG area

2 nos rcc of EQP foundation in BTG area

2 nos bo[ting of BPI foundation in BTG area.

1no culvert Pcc in 400kv,LM 4 erection u/p

10mtr pcc of road (srt site),LM4 erection u/p.

10mtr pcc of road (srt site),3no Raft of equipment foundation in BTG2 area.culvert rafting u/p in 400kv

8 nos grauting of srt 2 aux-foundation,

7no Aux foundtion of SRT casting,2no equipment foundtion bolting in BTG2 ,1no pcc of culvert,10mtr pcc of road srt bay.

10mtr Pcc of road,Oil filteration of SRT 1 u/p.

1no culvert casting,1no culvert wall casting in DIA3,2no Pcc & 1no boltingin BTG2 area,consevator tank of SRT2 erected.

6mtr casting of culvert near SRT2.12kl oil top up in SRT1.

oil felteration for SRT1 u/p.9mtr culvert PCC in between 33kv & 400kv,7mtr both side wall casting of culvert near SRT2.

marshaling box of SRT 1&2 erected,oil filteration u/p.

oil felteration of SRT1 u/p.One bolting in BTG2 area.9mtr raft of culvert on road.

penting of control room u/p

penting of control room u/p

Oil filteration of SRT1 u/p,25no BCU & 10no of ethernet switch fixing on relay panel.

400KV SWITCHYARD PROGRESS MAR-201 DATE MAN POWER CIVIL 33KV ELECTRICAL 400KV CIVIL

1/3/2012

135+62=197

Cable termination in Ac kiosk u/p,6mtr 3no IPS tube erected.

2/3/2012

86+59=145

1no ISO erected & alignment,2no 6mtr Al tube erected ,4no pipe stucture erected.1no AC assembled in AC kiosk.

3/3/2012

137+62=197

1no ISO erected & alignment,2no 6.6mtr 15mtr pcc of road Al tube erected ,cable termination in kiosk u/p.

4/3/2012 5/3/2012 6/3/2012 7/3/2012 8/3/2012 9/3/2012 10/3/2012

124+57=181

20mtr PCC of road

DC cable laying in AC KIOSK no 1.

SWITCHYARD PROGRESS MAR-2012 400KV ELECTRICAL


2no CB platform erected,3no of 3mtr Al tube fixing between BKR & ISO,6mtr of 3no perforated tray fixing ,LM7 erection u/p.

CABLE TRENCH (In Mtr)

CONTROL ROOM

STRINGING

EARTHMAT (In Mtr)

10mtr raft in 400kv,5mtr wall casting in 33kv,12mtr pcc in panting work u/p 33kv,1no culvert top slab casting near srt2

3no AUX mate laying in 400kv,30mtr main mat laying in 33kv.

9no of 3mtr100mm perforated tray welding for ct & cvt,LM7 erection u/p.

10mtr pcc in main cable tranch 400kv,5mtr pcc in panting work u/p 400kv,30mtr nose angle welding,

20mtr main mate laying in & 40mtr flat riser welding 33kv.

4no suspenion disk insulator erected,1no ISO alignment,6no perforated tray of ct fixing,4mtr ,3no Al tube erected . 3nos IPS tube LM u/p,

10mtr pcc in main cable tranch 400kv,10mtr raft in 400kv,30mtr nose angle welding in 33kv

panting work u/p

35mtr main mate laying & 30mtr riser welding in 33kv,1no aux mat of 400kv welding.

40mtr RCC of main cable trench, 5 nos excavation of BMK.

OTHER

Oil filteration of SRT1 u/p.

Oil filteration of SRT1 u/p.

Oil filteration & cabling of SRT1 u/p.

Oil filteration & cabling of SRT1 u/p.