33KV DATE MAN POWER PCC RCC BOLTING 33KV SWITCHYARD 400KV CABLE TRENCH (In Mtr) CONTROL ROOM STRINGING
29-Sep-11
(129+49) = 178
----
------
10
Door & window Fixing, Painting work in control building. Wall painting work, Tiles fixing.
-----
30-Sep-11 1-Oct-11
3 1
9 3
--6
-------
3 Nos CT erection work Aux Mat 1 no laying, Alignment work of CT & CVT.
10 15
-----
-----
2-Oct-11
(115+39) = 164
----
10
Corridor wall painting, Battery room tiles fixing, 4 nos door glass fixing. Battery room Tiles work, Door & Window fixing.
-----
3-Oct-11
(112+49) = 161
11
----
10
-----
4-Oct-11
(26+53) = 79
----
----
----
----
-----
Door & window Fixing, Painting work in control building. Door & window Fixing.
-----
5-Oct-11
(27+53) = 80
----
5 nos PI erected,
----------------60
-----------------
--------3 -----
--------3 3
----1 Aux mat 1 Tower beam erected, 1 no of Aux mat. 1 set of isolator erected.
------------10
10-Oct-11
(76+53)=129
----
Corridor wall Painting, Battery room tiles fixing Painting, Door fixing & Tile fixing. Door fixing, Tiles fixing, lighting, Painting. Tiles fixing, POP work in under progress. Tiles fixing, POP work in under progress. Polishing work, Tiles Fixing work under progress. Polishing work, Tiles Fixing work under progress. Tiles work & False Ceiling work under progres. Tiles work, Painting & False Ceiling work under progres.
----
11-Oct-11
(104+29+54)=187
----
----
12-Oct-11
(124+54)=178
1 no tower beam, 2 no's CT erected, 8 no's equipment pipe 1 pole of CB erected, AC structure errected. Kiosk misc work. 8 no's equipment pipe structure & 1 num tower beam erected.
15
----
13-Oct-11
(107+32+54)=193
1 pole of CB erected.
15 pcc
---124 Mtr in Twin conductor. 108 Mtr guard conductor stringing. 54 Mtr stringing in one phase
14-Oct-11
(110+54)=164
--
--
14 no's pipe structure 2 no's CT, CVT erected. erected. 16 no's pipe structure erected. 6 no's pipe structure erected. 17 no's equipment pipe structure erected. 2 no's CT erected. 13 nos pipe structure & 1 num ct erected. 1 num Aux mat, 4 no's CVT erected.
25 pcc
15-Oct-11
(155+50)=205
40
16-Oct-11
(175+50)=225
----
25
17-Oct-11
(194+51)=245
15
----
18-Oct-11
(193+53)=246
--
----
19-Oct-11 20-Oct-11
21-Oct-11
----
150 120
100
100
-----
-----
-----------------
200
120
160
160
140
80
----
250
250
400KV SWITCHYARD PROGRESS DATE MAN POWER PCC 33KV RCC BOLTING
6nos RCC AC KIOSK Spacer fixing work
33KV SWITCHYARD
1-Nov-11
65+52 =117
pipe str-12nos
3 3
6 4 3 pipe str-12nos
9-Nov-11
140+62=202
pipe str=12no
10-Nov-11
154+62=216
11-Nov-11
105+62= 167
12-Nov-11
101+62=162
13-Nov-11
102+64=166
LA =3nos
14-Nov-11
144+64=178
3 in BTG area
15-Nov-11
113+62=175
3 in BTG area
16-Nov-11
128+62=188
17-Nov-11
125+57 =182
pipe str=6nos
18-Nov-11
104+67=161
pipe str=3nos,pt=6no
19-Nov-11
100+54=154
20-Nov-11
88+50=138
21-Nov-11
96+49=145
22-Nov-11
111+49=160
23-Nov-11
96+43=139
24-Nov-11
109+44=153
25-Nov-11
84+44=128
1no PT JB fixing,6set suspention insulator erected 2set iso topcontact erected,1no CT JB fixing,panel shifting in kiosk3 1no CB foundation casting,1no CT,1set Isolator
26-Nov-11
114+47=161
27-Nov-11
106+46=152
28-Nov-11
114+45=159
29-Nov-11
119+43=162
30-Nov-11
105+45=150
CONTROL ROOM
STRINGING
FCBC CHARGER-3NOS,
Tower-1(BTG ) BPI-6
60mtr wall 10mtr rcc 10mtr rcc FCBC CHARGER-1NOS Main mat=130mtr 2 aux mat
2nos panel erected in 15mtr wall,12mtr AC KIOSK rcc,20mtr pcc 33mtr wall,8mtr rcc,10mtr pcc Iso=1set,3nos panel ercted in AC KIOSK T.beam1no(400kv),panel erection in kio 3 2 set insulator of iso ,panel alignment in ACKIOSK. 7nos piep str, 2set ISO. 15mtr wall,30mtr rcc,35mtr pcc 20mtr pcc,25mtr wall,(33kv-8mtr wall,10mtr rcc,) 22mtr wall,27mtr rcc in 400 kv,5mtr rcc in 33kv, 5.5mtr wall,10mtr rcc in 33 kv,5mtr rcc in 400 kv. 25mtr wall in 400 kv 17mtr wall in 33 kv,10mtr rcc,10mtr pcc 10mtr wall,10mtr rcc,17mtr pcc in 33 kv 5nos light fitted Main mat=80mtr Main mat=140mtr
5nos light fitted light,tiles fixing,& AC out door work is under progress.
Aux mat=2nos
stringing 40mt
Iso-1set
stringing 40mtr
17mtr rcc,10mtr pcc,7mtr wall in 33 kv,10mtr pcc,10mtr wall in 400 kv 13mtr wall both side casting,10mtr rcc,12mtr pcc in 33 kv,40mtr pcc in 400 kv
40mtr stringing ,
Main mat=150mtr
Bolting=3nos in BTGarea
(17mtr pcc,17mtr wall,15mtr raft) in 33kv, 40mtr pcc in 400kv 200mtr main mat laying ,Aux mat-4no(in 33kv) 26mtr main mat lalying & aux mat=8 nos(33kv),
24mtr raft pipe str =3no(LA),in in400kv,10mtr Painting & wiring work u/p BTG area, pcc=2no(btg in control room, wall &17mtr raft area) in33kv
stringing-22.8mtr in 33kv
Breaker=2 pole, 5nos 10mtr wall in bolting in BTG 33kv, 30mtr pcc in area,road work u/p 400kv Breaker=1pole,Iso=2s 32mtr wall (33kv) et,Earth removal work & 15mtr raft in u/p(from main cable 400kv. trech side) 15mtr rcc & 12mtr wall in 33kv,20mtr RCC &10mtr one sidewall castingin 400kv
Stringing=160mtr( 33kv)
100mtr
stringing=250mtr in 400kv
20mtr RCC
3no CT erection
String=30mtr(33kv 106mtr main ) mat in400kv 102mtr main mat in 400kv,25mtr in 33kv
17mtr pcc& 15mtr 2no Aux foundation wall casting in casting of SRT,1set Iso 33kv,15mtr rcc in erection 400kv 17mtrRCC &12.5mtr wall in 33kv,24mtr wall in 400kv 15mtr pcc&10mtr wallcasting in 400kv,25mtr pcc in 33kv
OTHER
400KV SWITCHYARD PROGRESS DEC-11 DATE MAN POWER PCC 33KV RCC BOLTING 33KV SWITCHYARD 400KV CABLE TRENCH (In Mtr)
1-Dec-11
112+48=160
2-Dec-11
98+55=153
1no pole CB erected,spacer fitting in 12nos pipe strs erected quad moose u/p,LM no2 erection u/p
3-Dec-11
123+54=177
1pole CB erected,20nos 12mtr Raft & 15mtr Wall spacer fitted in line casting in 33kv,50mtr dia,LM2 erection u/p Pcc in 400kv
4-Dec-11 5-Dec-11 10mtr Raft & 35mtr wall in 33kv,28mtr wall casting in 400kv
6-Dec-11
82+56=138
1no WT erected
7-Dec-11
92+57=149
1no WT erected,3no 47mtr Raft in 2no ISO eligment & 6no jumper insulator 400kv,12mtr wall & jumpering erected,LM2 erection 38mtr nose angle casting u/p of cable trench in 33kv
8-Dec-11
90+58=148
9-Dec-11
71+58=129
10-Dec-11
107+59=166
3 nos PT , 1 nos Iso 30mtr R.C.C in 400kv, 10 2 nos CB pole erected, erected, 2 nos Iso mtr PCC in 33kv, cable alignment & 40 mtr IPS 2 nos quad moose tray support work u/p. jumpering, LM 2 tube erection u/p 20 mtr PCC and 10 mtr RCC in 400kv, 3 mtr 2 nos Iso alignment, 2 3 nos CT erected, LM 2 PCC,5mtr one side wall nos jumpering erection u/p casting and 7mtr RCC, cable tray support work u/p in 33 kv
11-Dec-11
101+59=160
12-Dec-11
13-Dec-11
133+60=193
12 mtr RCC ,10 mtr PCC, cabletray supprot work u/p,50mtr PCC in 400kv
14-Dec-11
136+61=197
15-Dec-11
135+62=197
10
9 nos pipe strs erected,3no Ips tube erected,cable tray support welding u/p,
2nos CTJB fixing,LM2 erected,IPS tube welding u/p,9nos mechanism box fixing .
16-Dec-11
123+62=185
2set Isolater erected,1set iso 40mtr Pcc in Isolater Mech box stand eligment,6nos 400kv,10mtr wall casting fixing=5nos, suspension disc in 33kv insulater erection,2no CT JB fixing
17-Dec-11
127+64=191
16mtr PCC,16mtr RCC IPS tube welding u/p,2 &27mtr wall casting in 3nos IPS tube CT JB & 2nos CVT JB 33kv,27mtr PCC & 3omtr erected,6no BPI erected fixing wall casting,20nos precast slap casting
18-Dec-11
135+66=201
19-Dec-11
134+66=200
3no grouting ,6nos BPI erected,3no IPS tube erected,1set ISO eligment
35mtr wall casting in 33kv,10mtr rcc in 20nos BPI clamp fixing 400kv,20no precast slab in main BUS 1,6no ISO in 400kv. mechanism box fixing,
20-Dec-11
136+66=202
10
27mtr Al tube erected on main bus,5nos ISO 3nos IPS tube mechanism erected,1no CB box&3noE/S casting,cable tray mechanism box support fixing work u/p, fixing,1no BPI erected,4no bpi clam fixing
21-Dec-11
143+66=209
2set Iso contact fixing,2no LA clamp fixing,30mtr nose angle fixing in cable tranch
2no of 27mtr IPS tube erected on main bus,2no BPI erected ,2no ISO mechanism box fixing
22-Dec-11
135+65=200
30mtr pcc& 7.5mtr wall 3 span spacer casting in 33kv,10mtr fixing,3no jumpering in pcc & 30mtr raft in line dia & Isolater 400kv.13 precast slab in eligment u/p 400kv.
23-Dec-11
102+66=168
6.5mtr of 4no Al pipe tube erected on main bus,suspention jumper erected=6nos,7no BPI ereted 18mtr of 2no Al tube erected on main Bus,6.6mtr of 3no AL tube erected on o/g fidder ,5mtr of 1no Al tube erected on inter connecting.6no BPI erected,1no ISO eligment.
2no BPI erected,27mtr of 3noAI tube pipe 12.5mtr wall casting & erected ,2no quad 10mtr nose angle casting moos jumpering,6no in 33kv,15mtr Rcc in ISO mechanism box 400kv. fixing,
24-Dec-11
152+66=218
27mtr *2no AL tube erected on main bus2,3no pipe str 17mtr RCC in 33kv,35mtr erected,2no LA PCC in 400kv erected,8no Light fitting erecte on LM1
25-Dec-11
154+65=219
SRT1 soak pit PCC of one side, 3 nos pipe 15mtr RCC & 17mtr nose 44 mtr IPS tube Erected, structure erected, 1 angle work in cable 1 nos ISO alignment. nos LA erected, 40 mtr trench, IPS tube erected
26-Dec-11
176+17=193
27-Dec-11
129+60=189
7mtr Rcc & 30mtr wall 1no CB foundation 3nos LA erected,7nos casting in 33kv,30mtr casting,60mtr AL tube clamp connector of ct Pcc in 400kv,20mtr nose erected,6nos pipe str & 5no clamp connector angle casting in 33kv & erected of ISO fixing 40mtr nose angle fixing in 400kv.
28-Dec-11
117+63=180
12no equipment base 54 mtr AL tube erected grouting,3no PI pipe ,6no clamp connector structure & 3 nos ISO of CT& 6nos of ISO pipe str erected,6nos PI fixing,1no ISO ercted, erected.
25mtr Pcc ,20mtr wall casting &30mtr nose angle casting in 33kv.
29-Dec-11
137+67=204
1set CB pole 40mtr Pcc in 3no pipe structure erected,LM 3 erection 400kv,34mtr Pcc &15mtr erected,10mtr of 3no Al complete,6no ISO & wall casting in 33kv,5no tube erected,3no PI 6no CT link clamp foundation of Iso erected,6nos pipe str connector fixing ,27mtr mechanism box alignment of 2no Al tube erected stand.10mtr nose angle on main bus. casting in 33kv.
30-Dec-11
106+69=175
1no HL Iso erected,1no CB erected,jumpering in 1no CT erected,1no ISO one bay,90mtr Tray erected,6no CT & 6nos laying,2nos BMK Iso connectors fixing, foundation casting
89+69=158
31-Dec-11
6 nos ISO mechanism box fixing, 6 nos earth switch Iso mechanism box fixing, 30 mtr IPS tube erected, I nos BMK RCC, 2 nos BMK PCC , 2 nos grouting of equipment foundation
6 nos LA, 6 nos CT and 15 mtr PCC in 33 kv 3 nos ISO clamp cable trench, 20 mtr RCC connector fixing, 54mtr in 400kv cable trench IPS tube erected
CONTROL ROOM
STRINGING
1span 52mtr twin moos conductor in 400kv
OTHER
11 nos R C C & 7 nos column casting in SRT 1,4 nos column casting in SRT 2 aux. foundation
7nos column casting in SRT 2 aux. foundation,Tower foundation (BTG area) exavation u/p
IPS TUBE welding u/p,1no Raft of Tower(4t5 )in BTG area ,SRT TFR2 shifting u/p
IPS TUBE welding 50mtr main mat u/p,SRT 2 laying in 33kv Transfermer erected on foundation.
IPS TUBE welding 45mtr main u/p.First lift column earth mat laying casting of tower in in 33kv Btg area,Earth leveling work u/p .
lighting work & testing work u/p,2nos exhaust Fan fixing in battery room,
LM no 3 erection on u/p
60mtr flat riser LM3 erection welding in main u/p,IPS Al tube cable tranch welding u/p,rod (33kv),100mtr binding of Tower nose angle upper lift(BTG area) fixing in 33kv & 4ookv.
Battery erection ,sanitary tile fixing work u/p,Testing & Tray work u/p in panel room.
3no Aux mat laying in 33kv,50mtr riser IPS Al tube welding u/p. fixing,45mtr nose angle fixing in cable tranch
MAN POWER
45 17+60=77
PCC
33KV RCC
BOLTING
33KV SWITCHYARD
3-Jan-12
59+73=132
Main bus with feeder jumpering for 5bay,6no ISO mechanism box ,4no Earth switch erected.
4-Jan-12
110+59=169
1no CB casting
mainBus 2 to o/g feeder jumpering ,6no LA clamp connector fixing,2no ISO alignment with mechanism box,
5-Jan-12
143+59=202
12 nos BPI and 3 nos CT foudation grouting,jumpering from main bus to I/C fidder.
6-Jan-12
121+62=183
1nos BPI rcc,2nos CB,1nos pipe str,40 mtr cable trey erection complete, 3no ISO aligment complete,9nos equipment pipe str erected,Hl ISO -1no erection
7-Jan-12
153+65=218
8-Jan-12
132+62=194
1no CB casting
2no Al tube of 9mtr erected ,6no pipe structure erected,25mtr cable try laying
9-Jan-12
155+67=222
3no of 5mtr & 1no 8.5mtr Al tube erected ,3no line PT jumpering,5no BPI erected,50mtr cable tray laying,6no CT-JB glanding
10-Jan-12
141+61=210
2no ISO mechanism box fixing,12nos BPI erected,600mtr cable laying in between kiosk & bay 1.
11-Jan-12
143+69=212
12-Jan-12
146+32=216
6nos CT structure erected,9no BPI str 2nos BMK aligment,3nos ISO faundation casting eligment,500mtr cable laying.testing of CT in Bay no 1. 2no ISO & 6no pipe structure eligment,9no BPI erected,1no BMK erected.500mtr cable laying .
13-Jan-12
109+70=179
14-Jan-12
102+70=172
9.5mtr of 3no Al pipe erected,12 no BPI insulator erected ,400mtr cable laying.25mtr cable tray laying,12no foundation grouting. 25 mtr cable tray laying, 6nos BPI erected, 9 nos pipe structure alignment, 8 nos foundation grouting, 100mtr cable laying.
15-Jan-12
74+70=144
16-Jan-12
106+55=161
17-Jan-12
108+53=161
2no ISO alingment,2no ISO erected,360mtr cable laying,cable tray fixing u/p.
18-Jan-12
105+81=186
1no BMK panel erected,3no pipe structure aligment,cable glanding of jb&iso box of 5bay in 33kvu/p.
19-Jan-12
114+84=198
30no cable glanding in both JB & miso mechanism box,2no ISO erected,1no ISO alignement
20-Jan-12
86+94=180
21-Jan-12
119+80=199
3no ISO aligment.250mtr cable laying in bay 7,cable glanding in panel u/p.
22-Jan-12
111+81=192
23-Jan-12
116+82=198
24-Jan-12
129+81=210
1no ISO aligment,1 no ISO erected,32 no cable glanding,100 mtr tray laying in 33kv.
25-Jan-12
141+72=213
26-Jan-12
27-Jan-12
80+71=151
28-Jan-12
94+70=164
29-Jan-12
89+69=158
Cable glanding u/p in AC kiosk 1 panel, 25mtr PCC of fencing, 8nos foundation grouting.
30-Jan-12
77+69=146
31-Jan-12
84+68=152
Cable glanding u/p in AC kiosk 1 panel & continuty chek. Iso mechanism box suport fixing.
KV SWITCHYARD PROGRESS JAN-12 400KV CABLE TRENCH (In Mtr) CONTROL ROOM
cable laying u/p LM erection u/p , 3nos clamp connecter & 3 nos ISO ercted. LM 3 Tower erected ,1no ISO erected,6no CT & 3no ISO connector fixing,2 no of 18mtr jumpering in LA,CVT panel testing u/p , cable laying u/p
STRINGING
1no LA & 2no CVT clamp connector fixing,1no LA jumpering,Gantry beam erection u/p
48volt battery charging u/p , 220v Battery commissioning u/p,Panel testing & cable laying u/p
LA,CVT jumper 48volt battery charging complete of line #2,1 15mtr RCC in 33kv , 12 u/p , 220v Battery nos isolator mtr RCC in 400kv commissioning erected,1nos gantry u/p,Panel wiring chek. beam erected.
Gantry beam 30mtr Raft in 220volt 150amp battery tightening 400kv,20mtr nose charging u/p , 220v ,Radiographi of Al pipe angle fixing,13mtr raft Battery electrolyte top jointing u/p.Al pipe & 20no equipment up u/p,DCDB Panel welding u/p. grouting in 33kv. wiring chek.
6no ISO mechanism box fixing ,cable tray 10mtr wall casting in support angle fixing in 33kv cable tranch.
10mtr wall & 12mtr RCC in 33kv,25no equipment grouting,20mtr wall casting & 40mtr nose angle fixing in400kv.
20mtr wall casting & PMCC relay scheam Gantry Beam 10mtr rcc in checking & testing,220v assembling in Btg area 400kv,14mtr wall ,600 AH battery charger u/p casting & 3mtrb pcc in panel load testing 33kv
Gentry Beam 20mtr wall casting in assembling & tightness 33kv , 15mtr PCC & u/p. 20mtr RCC in 400kv
PMCC relay scheam checking & testing,220v ,150amp battery charger panel load testing
one side Gentry Beam erected in BTG 10mtr Pcc,11mtr wall area,30mtr cable tray 220volt,615AH Battery casting in 33kv,15mtr support fixing in main charging. Raft casting in 400kv. cable tranch,1no ISO aligment.
20mtr wall casting & 220volt,615AH second 15mtr soakpit wall Battery bank charging casting in 400kv,14mtr ,tesing of 33kv wallcasting in 33kv. equipment u/p.
1no ISO aligment, 6no (27mtr)Al pipe erected on main bus.6no pcc of aux founation in SRT2.
4T 5p tower erection u/p in BTG area,nose angle fixing in main cable tranch.
10mtr wall casting ,40no precast slab Rcc,One side Aux Foundtion of SRT2 u/pin 400kv,20mtr wall casting in 33kv. 4nos Rcc of Aux foundtion of SRT2,10mtr Rcc in 400kv,15mtr wall casting in 33kv,9no grouting of tower in 33kv.
1no CB pole 5no padestal casting erected,120mtr cable of SRT2,12 mtr wall tray support fixing,1no caswting both side in ISO aligment. 400kv,
10mtr wall casting & 4nos padestal casting 1no ISO of SRT 2Aux foundtion aligment,120mtr cable in 400kv,12mtr tray support fixing. fencing work completed,Bay no 10 leveling u/p 15mtr wall casting in 2pole CB top ineruptor 400kv,40no precast erected,1no ISO slab in 33kv,20mtr aligment.50mtr cable fencing complet in tray support welding. 33kv. 1 pole CB top ineruptor erected, 1 10mtr fencing complet nos ISO alignment, 60 in 33kv. mtr cable tray support welding 3no CB top interuptor erected,1no ISO alignment,75mtr cable tray support welding. 25mtr break work of fenching in 33kv,15mtr wall casting in 400kv
10 mtr wall casting in 33kv,15mtr wall 3no CB top interuptor casting in 400kv,srt2 erected, raft casting, 40no precast slab .
3no CB top interuptor erected,1no ISO alignment. Sock pit raft of srt2.
3no CB top interuptor 10no pre cast slab with mechanism box casting & 20 mtr nose erected, angle casting in 400kv
3no CB top interuptor with mechanism box erected,2no cvt jb fixing in line dia.
20mtr wall casting in 400kv,20 mtr soke pit wall of srt2,10mtr wall casting in 33kv.
2no CB top interuptor 20mtr wall casting in erected,1no CB 33kv, soke pit raft mechanism box casting of srt2 erected. LM no4 u/p,25nos pre cast erection u/p. slab casting .
7no mechanism box of 10mtr RCC soke pit CB erected,1no CB top wall in SRT2,10mtr interuptor erected,LM wall casting in 400kv 4 erection u/p.
OTHER
100 mtr flat riser fixed in cable trey erection in 33 kv 33 kv gantry tower & cable trench , cable laying 2nos aux mat laying. u/p
50 mtr(ms rod) riser ,20mtr flat riser(GI), 4nos aux mat laying
35mtr main mat laying,4no aux mat welding,20mtr flat riser fixing in 33kv
Aux equipment of SRT 1 erection work u/p,Testing of equipment in bay no10(33kv) u/p.
Aux equipment of SRT 1 erection work u/p,Testing of equipment in bay no9(33kv) u/p.
Aux equipment of SRT 1 erection work u/p,Testing of equipment in bay no9(33kv) u/p.
Aux equipment of SRT 1 erection work u/p,Testing of equipment in bay no8(33kv) u/p. 2 nos aux foundation casting and 3 mtr PCCof SRT 2, Aux equipment of SRT 2 erection work u/p, 4 nos SRT 1 aux foundation casting
Radiator support frame of SRT 2 erected,all testing of bushing & ct completed before erection.
110 mtr 40mm ms rod riser, 45mtr flat riser fixing in 33kv.
6nos SRT1 fans fixing, SRT 2 frame alignment, 4nos column casting in SRT2.
conservator tank ,2no HV bushing turret & 1no hvn bushing turret erected on SRT1.
3no LV bushing,1no LVN bushing & HVN bushing with turret erected on SRT1.
400KV SWITCHYARD PROGRESS FEB-201 DATE MAN POWER PCC 33KV RCC BOLTING 33KV SWITCHYARD
1-Feb-12
109+70=179
2-Feb-12
123+68=191
110*4 mtr ,35sq Al cable laying from ACDB to BMK1.12no glanding in AC kiosk panel.6no BPI erected,
3-Feb-12
88+77=165
4-Feb-12
114+78=192
15mtr perforated tray fixing,cable glanding & termination work u/p.4no BPI erected.
5-Feb-12
101+78=179
3 nos column casting, 7 mtr grouting of wall, cable glanding & termination work u/p
6-Feb-12
130+73=203
72.5mtr 100mm tray fixing, 1 nos ISO erection,cable glanding & termination work u/p, 5 nos column casting of Ackiosk, 10 mtr PCC of fencing, 10 mtr fencing wall 3 nos PI erection, 6 nos pipe structure erection, 1 nos ISO erection, 1 nos column casting of AC Kiosk.
7-Feb-12
94+69=163
8-Feb-12
95+55=150
9-Feb-12
122+73=195
10-Feb-12 11-Feb-12 12-Feb-12 13-Feb-12 40 12 nos grauting of eqp structure 6no pipe structure alignment.cable terminaion in jb u/p
14-Feb-12
29+40=69
15-Feb-12
61+50=111
16-Feb-12
66+53=119
6no of 6.5IPS Al tube erected,cable termination u/p,4no equipment pipe structure alignment,1no ISO erected 3 nos IPS al tube fixed ,9 nos BPI connector fixed ,3 nos BPI str alignement ,
17-Feb-12
62+53=115
18-Feb-12
76+53=129
3no of 7mtr AL tube & 3no of 10mt Al tube 1no CB extention erected on I/C bay,3no foundtion casting BPI erected.cable temination u/p.
19-Feb-12
78+53=131
20-Feb-12
60+53=113
21-Feb-12
79+64=143
22-Feb-12
65+77=142
5.5mtr of 6no Al pipe erected,6no clamp of HlPI erected,5no ISO mechanism box stand welding, LM 6 erection u/p. 5.5mtr of 6no Al pipe erected,6no BPI erected,5no ISO mechanism box stand welding, LM 6 erection u/p. 18mtr of 2no Altube erected,8mtr of 3mtr Al tube erected,24no cable glanding,LM6 erection u/p,4no ISO mechanism stand fixing. 36mtr IPS tube erected,9 nos earth switch erected & alignement,9mtr calvert RCC both side, 10 mtr fencing plaster.LM u/p. 18mtr IPS tube ercted, LM no.7 erection complete, .cable termination in AC KIOSK u/p. 9 mtr slab RCC of calvert , 9 mtr nos angle grouting. Reley instal in AC KIOSK.
23-Feb-12
89+62=151
24-Feb-12
77+60=137
25-Feb-12
123+67=190
26-Feb-12
145+59=204
27-Feb-12
115+18=133
28-Feb-12
133+62=195
1 nos CB foundation RCC, leveling u/p, 2 nos ISO erection, 6nos machenism box erection, 4 nos earth switch erected, cable termination in AC kiosk u/p,2no CB erected,6mtr of 3no Al pipe erected on main bus2,1no ISO erected,1no Iso alignment.
29-Feb-12
137+62=199
CONTROL ROOM
STRINGING
3no CB top interuptor erected,LM 4 erection 2no exhaust fan 30mtr wall casting in u/p,80 mtr cable tray maunted in panel 50mtr jumpering in 400kv,10mtr wall support welding in cable room,lighting & line 1 bay. casting in 400kv. tranch .2no AL tube sanitary work u/p. erected in line1 bay.
6no CB mechanism box erected,LM 4 erection 10mtr wall casting in u/p,25x3 mtr cable tray 400kv,20mtr sock pit support welding in cable wall casting of SRT 2 tranch,
1no ISO alignment, LM 4 10mtr wall casting in erection completed,LM5 400kv,20mtr wall erection u/p,6no ISO casting in 33kv,soke clamp connector pit wall of SRT 2 erected. completed.
LM 5 erection u/p
75 mtr IPS tube erection, 12mtr wall casting in LM 5 u/p, 29 nos both side of cable precast slab casting trench in 400kv
9 nos connector fixing in CB, LM 5 u/p, road work u/p,1 nos ISO alignment, 60 mtr cable tray support welding 18 nos CB connecter fixed, 96 mtr 32x3 cable support fixed,225 mtr cable laying from CT to JB, 7 nos staire case rcc of CB 30 mtr Pcc of road . 12 nos connecter fixed in 1 nos CB & 1nos CT, 60 mtr cable trey sopport fixed,240 mtr cablin from CT to JB, LM no. 6&7 erection u/p, 25 mtr pcc of road.
LM4 erection completed,12nos CBclamp connector erected,6nos CT clamp connector erected.6no 100mm tray fixing. 1 ISO alignement ,LM4 erected , 30 mtr trey erected, 9 nos CT connecter, CVT box cabling ,PCC of road 5 mtr,
2no quad moos of 9mtr jumpering,cable laying between cvt & jb.
2no of 6mtr Al IPS tube 12mtr wall casting in erected,3no BPI both side of cable erected,cable trench in 400kv termination u/p.
12mtr wall casting in 1no ISO alignment, LM5 both side of cable erection u/p,1no 7mtr trench in quad moos jumpering,CT 400kv,12mtr nose cable glanding u/p. angle casting.
3no of 5.1mtr twin 2no AUX mat ofIso in jumpering(Bus1 line dia welding. cvt).
9mtr culvert wall casting both side & 9mtr pcc of culvert near control room,10mtr pcc in 400kv
1nos ISO alignement,, 3nos cable tery fixed,cable glanding u/p ,9 nos CB stair case RCC&PCC. 1 nos ISO alignement ,6 nos 100 mm cable trey of CT erected AC erection in AC KIOSK no.2&3 u/p. 9 nos RCC of CB staire case. 9 nos PCC of CB staire case foundation. 27 nos pree-cast rcc.
3 nos jumpering
9 nos staire case RCC of CB, LM no.u/p, ISO u/p,6 nos trey 18 mtr of CT ercted .
10 mtr PCC.
1no culvert(9mtr) LM 7 erecteion u/p,6no upper slab perforated tray casting,7mtr raft in fixing,40mtr nose angle 33kv,12mtr pcc penting work u/p welding,pipe bending ,75mtr wbm work of job u/p. road in 33kv,30mtr nose angle casting.
OTHER
3no LV bushing turret,HVN & LVN turret & 2no HV bushing turret erected on SRT2.
1no HV bushing turret,all LV bushing,both LVN& HVN bushing,both side rediator & conservator tank frame erected on SRT2.
Equiliser pipe conection ,PRD bend pipe ,thermosyfon tank & butterfly valve fixing in SRT2.
2 nos column casting, 2 nos RCC of equipment foundation in BTG area, insulator erection, equaliser pipe fixing, tighting work in SRT 2
3 nos of SRT 1 and 1 nos of SRT2 HV bushing erection, 2 nos PCC in BTG area, 1 nos bolting of equipment foundation in BTG area
10mtr pcc of road (srt site),3no Raft of equipment foundation in BTG2 area.culvert rafting u/p in 400kv
7no Aux foundtion of SRT casting,2no equipment foundtion bolting in BTG2 ,1no pcc of culvert,10mtr pcc of road srt bay.
1no culvert casting,1no culvert wall casting in DIA3,2no Pcc & 1no boltingin BTG2 area,consevator tank of SRT2 erected.
oil felteration for SRT1 u/p.9mtr culvert PCC in between 33kv & 400kv,7mtr both side wall casting of culvert near SRT2.
oil felteration of SRT1 u/p.One bolting in BTG2 area.9mtr raft of culvert on road.
Oil filteration of SRT1 u/p,25no BCU & 10no of ethernet switch fixing on relay panel.
400KV SWITCHYARD PROGRESS MAR-201 DATE MAN POWER CIVIL 33KV ELECTRICAL 400KV CIVIL
1/3/2012
135+62=197
2/3/2012
86+59=145
1no ISO erected & alignment,2no 6mtr Al tube erected ,4no pipe stucture erected.1no AC assembled in AC kiosk.
3/3/2012
137+62=197
1no ISO erected & alignment,2no 6.6mtr 15mtr pcc of road Al tube erected ,cable termination in kiosk u/p.
124+57=181
CONTROL ROOM
STRINGING
10mtr raft in 400kv,5mtr wall casting in 33kv,12mtr pcc in panting work u/p 33kv,1no culvert top slab casting near srt2
9no of 3mtr100mm perforated tray welding for ct & cvt,LM7 erection u/p.
10mtr pcc in main cable tranch 400kv,5mtr pcc in panting work u/p 400kv,30mtr nose angle welding,
20mtr main mate laying in & 40mtr flat riser welding 33kv.
4no suspenion disk insulator erected,1no ISO alignment,6no perforated tray of ct fixing,4mtr ,3no Al tube erected . 3nos IPS tube LM u/p,
10mtr pcc in main cable tranch 400kv,10mtr raft in 400kv,30mtr nose angle welding in 33kv
35mtr main mate laying & 30mtr riser welding in 33kv,1no aux mat of 400kv welding.