Curriculum Vitae
Personal Data: Name :- Wazeef Fawzy Hussein El sakhawy.
Qualifications : - BCS, Civil Engineering /1997, Tanta University, Egypt Nationality :- Egyptian
Marital Status : - Married Contact No. Visa Status :- 00971 50 2624601 :- Residence (Emirates Link Maltauro).
Driving License :- Emirates License. Professional Experience: Feb. 2012 Till Present:- Emirates Link Maltauro L.L.C Project :- Emirates Identity Authority General Head Quarters . Client :- Emirates Identity Authority ( EIDA). Consultant : - PARSONS . Position :- Construction Manager . Responsibilities: - Start the project from Mobilization up to finishing the block works, plaster works and
facades waterproof for Alum. Works .
Job Duties
Checking MEP shop drawings with structural shop drawing. Making monthly and weekly programme for structural and finishing activities. Pushing work activities to get work ready and following inspections requests for all activities. Getting consultant approval for work according to program. Coordination between quality controller, quantity surveyor, safety officer, planning engineer, logistic engineer and chief surveyor to control quality, safety, cost and progress. 6- Coordination between MEP and civil works. 7- Coordination between Structural engineer, architectural engineer and project engineers. 8- Coordination with subcontractors. 12345-
Aug. 2011 Till Feb. 2012:- Emirates Link Maltauro L.L.C Project :- Brighton Collage . Client :- Bloom Properities. Consultant : - AEC ( Architecture, Engineering and Consultant) . Position :- Construction Manager . Responsibilities: - Internal and External finishing up to handing over .
Dec 2006 Till Dec. 2008 :- Pivot Engineering & General Contracting Company, UAE Project Client Consultant Position
:- Golf Gardens 1.( 391 Villas with community center, budget 790,000,000) :- SOROUH Real State :- OTAK international. :- Construction Manager.
Responsibilities:Finishing All Mobilization Works For All The Project Then Responsible For 100 Villas Starting From Piling Works To The Finishing Works Including Underground (Water Tanks, Pump Room) And Swimming Pools.
Project
Responsibilities: Completion of one project contains 5 villas starting from foundations activities to the final handing over in 45 days at Mubzara, Al Ain. Dealing with calculating all quantities, pricing for tenders follow up all under construction job in hand projects for D.M.W
Apr. 2001 Till Dec. 2002:- Amany Al Areesh General Contracting Company , Egypt. Project :- EBN Sena Village 2 (210 Villas 12 Block of flats), Alex, Egypt. Client :- Amany Al Areesh General Contracting Company. Consultant :- El Nagar Consultant Office. Position :- Site Engineer. Responsibilities:- Construction for 55 villas & 4 Blocks of flats consist of 4 floors. Nov. 1998 Till Mar. 2001 :- Arab Contracting Company , Egypt. Position Projects : :- Site Engineer.
Developing the drainage station, Tanta , Egypt. Construction Police Hospital (All Civil works), Mahallt Marhoum , Egypt.