Anda di halaman 1dari 26

SPP1 Site Clearance

Progress Calculation Report

Period 10 to 21st January


Prepared By
Signed

D Watters
I Stirzacker

Project Control Lead


Senior Cost Engineer

Date
/
/

Checked By
Signed

Date

J Mooney

Project Engineer

M Elliott

Engineering Manager

N Elliott

Technical Manager

P Waddicor

Principal Engineer

Approval and Authority to Issue


Signed

P Waddicor

Principal Engineer

Date

160521524.xlsx.ms_office

Sludge Packaging Plant 1 - Summary Level 1 Performance Data


BCWS Original
BCWS CCR 186
BCWP
ACWP

P1
157,414

P2
365,252

P3
660,298

P4
864,734

P5
1,027,203

P6
1,242,973
1,265,700

P7

P8

P9

P10

1,686,232

2,084,970

2,612,142

2,839,906

142,154
37,558

249,079
106,912

393,676
165,014

464,553
266,020

569,107
369,026

740,972
682,550

1,070,250
973,289

1,244,180
1,738,671

1,956,805
1,772,952

2,282,164
#VALUE!

EAC
BCWP To Go
SV
CV
SPI
CPI
Forecast SV
Forecast CV
Forecast SPI
Forecast CPI

-15,259
104,596
0.90
3.78

-116,173
142,167
0.68
2.33

-266,622
228,662
0.60
2.39

-400,181
198,532
0.54
1.75

-458,096
200,081
0.55
1.54

-524,728
58,422
0.59
1.09

-615,983
96,960
0.63
1.10

-840,790
-494,491
0.60
0.72

-655,337
183,853
0.75
1.10

P11

P12

3,144,398

3,550,225

#VALUE!
2,282,164

#VALUE!
2,733,102

#VALUE!
3,404,796

-557,742
#VALUE!
0.80
#VALUE!
-557,742
#VALUE!
0.80
#VALUE!

-411,296
#VALUE!
0.87
#VALUE!

-145,429
#VALUE!
0.96
#VALUE!

SUMMARY COST PROFILE


4,000,000
3,500,000
3,000,000
2,500,000
2,000,000
BCWS Original

1,500,000

BCWS CCR 186

1,000,000

BCWP
ACWP

500,000

EAC

0
P1

P2

P3

P4

P5

P6

P7

P8

P9

SCHEDULE VARIANCE

P11

P12

COST VARIANCE

0
P12

P11

P10

P9

P8

P7

P6

P5

P4

P3

P2

P1

300,000

-100,000

200,000

-200,000

Page 2 of 26

P12

P11

P12

P11

P8

P10

P7

P9

P6

P8

P5

P7

P4

0.80

P6

P3

Date Printed 7/27/2013 4:27 PM

0.75

1.10
0.72

P5

0.60

1.54

1.09 1.10

P4

0.63

1.75

P3

0.59

2.33 2.39

P2

0.55

3.78

P1

0.54

P12

0.60

4.00
3.75
3.50
3.25
3.00
2.75
2.50
2.25
2.00
1.75
1.50
1.25
1.00
0.75
0.50
0.25
P11

0.68
P2

P1

0.90

P10

CPI TREND

P9

SPI TREND

P10

-600,000

P9

-900,000

P8

-500,000

P7

-400,000

-800,000

P6

-300,000

-700,000

P5

-200,000

-600,000

P4

-500,000

P3

-100,000

P1

-400,000

P2

100,000

-300,000

4.00
3.75
3.50
3.25
3.00
2.75
2.50
2.25
2.00
1.75
1.50
1.25
1.00
0.75
0.50
0.25
-

P10

File Name 160521524.xlsx.ms_office and Tab Reference Level 1

160521524.xlsx.ms_office

35.11.12.35025.03000.35/06071 Sludge Packaging Plant 1 - Site Clearance (Project Assesment)


WPSS

Description

WPS-010
WPS-020
WPS-030
WPS-040
WPS-050
WPS-070
WPS-080

Project Control
Engineering & S&RM
Procurement Support
Site Infrastructure
Construction Mangement
B388 Refurbishment
B816 Demolition

75,026
74,576
44,370
33,388
308,815
113,203
72,000

Planned
81.1%
81.1%
81.1%
81.1%
81.1%
100.0%
100.0%

WPS-090

B262 Demolition

161,500

100.0%

WPS-100

B304 Demolition

1,965,285

WPS-110
WPS-120
WPS-900

B358 Refurbishment
Site Investigation
Project Management

265,076
96,203
340,784

3,550,226

80.0%

GRAND TOTAL SITE CLEARANCE YEAR 1

BAC

Values to Date
Earned
Variance
80.2%
-0.9%
80.2%
-0.9%
80.2%
-0.9%
80.2%
-0.9%
80.2%
-0.9%
100.0%
0.0%
100.0%
0.0%

Values to Date
BCWP

60,171

59,810

35,584

26,777

247,670

113,203

72,000

ACWP
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

BCWS
56,647
56,306
33,500
25,208
233,162
113,203
72,000

161,500

26,495

#VALUE!

161,500

1,477,731

1,207,944

#VALUE!

1,316,322

265,076
38,968
276,459

159,201
273,308

#VALUE!
#VALUE!
#VALUE!

265,076
21,920
257,298

2,839,906

2,282,164

#VALUE!

2,612,142

Spent
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

BCWS
60,865
60,499
35,994
27,085
250,525
113,203
72,000

16.4%

-83.6% #VALUE!

75.2%

61.5%

-13.7% #VALUE!

100.0%
40.5%
81.1%

60.1%
0.0%
80.2%

-39.9% #VALUE!
-40.5% #VALUE!
-0.9% #VALUE!

64.3%

-15.7%

#VALUE!

Previous Period
BCWP

55,970

55,634

33,100

24,907

230,376

113,203

72,000

BCWS
4,218
4,193
2,495
1,877
17,363
-

Period Movement
BCWP

4,201

4,176

2,485

1,870

17,294

ACWP
55,358
70,043
12,455
17,222
150,969
247,075
15,361

26,495

743

937,795

693,887

161,408

153,101
254,225

256,557
17,651
235,632

17,049
19,160

1,956,805

1,772,952

227,764

-
-
-
-
-
-
-
-
-
-

BCWS
43,087
42,829
25,481
19,174
177,351
113,203
54,900
25,543
743,876
245,076
195,710

ACWP
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Values to Date
ETC
EAC
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

-
-
-
-
-

Values to Date
SV
CV
694
#VALUE!
689
#VALUE!
410
#VALUE!
308
#VALUE!
2,855
#VALUE!
#VALUE!
0
#VALUE!

#VALUE!

#VALUE!

#VALUE!

135,005

#VALUE!

0.16

#VALUE!

270,149

#VALUE!

#VALUE!

#VALUE!

269,786

#VALUE!

0.82

#VALUE!

6,100
19,084

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

-
-
-

105,875
38,968
3,150

#VALUE!
#VALUE!
#VALUE!

0.60
0.99

#VALUE!
#VALUE!
#VALUE!

325,358

#VALUE!

#VALUE!

#VALUE!

557,742

#VALUE!

0.80

#VALUE!

ACWP
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Values to Date
ETC
EAC
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!

#VALUE!

Values to Date
SPI
CPI
0.99
#VALUE!
0.99
#VALUE!
0.99
#VALUE!
0.99
#VALUE!
0.99
#VALUE!
1.00
#VALUE!
1.00
#VALUE!

Comment

Complete Require to transfer now


Waste Desposal Delayed Portacabins Still in PBI Date
Possible Carryover if B.358 Not complete by mid Feb or Possible
other location for drum store not found
Slab to complete unknown Ground condition PBI For Walls
Complete in time
Electrical work has seriously delayed handover
Await PMP Now Require to go through a OSM
Carry Over?

35.11.12.35025.03000.35/06071 Sludge Packaging Plant 1- Site Clearance (Primavera Execution Database)


WPSS

Description

BAC

WPS-010
WPS-020
WPS-030
WPS-040
WPS-050
WPS-070
WPS-080
WPS-090
WPS-100
WPS-110
WPS-120
WPS-900

Project Control
Engineering & S&RM
Procurement Support
Site Infrastructure
Construction Mangement
B388 Refurbishment
B816 Demolition
B262 Demolition
B304 Demolition
B358 Refurbishment
Site Investigation
Project Management

75,026
74,576
44,370
33,388
308,815
113,203
72,000
161,500
1,965,285
265,076
96,203
340,784

Planned
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%

3,550,226

0.0%

GRAND TOTAL SITE CLEARANCE YEAR 1

Date Printed 7/27/2013 4:27 PM

Values to Date
Earned
Variance
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%

0.0%

0.0%

Spent
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Values to Date
BCWP

ACWP
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

BCWS
43,087
42,829
25,481
19,174
177,351
113,203
54,900
25,543
743,876
245,076
195,710

#VALUE!

#VALUE!

1,686,232

BCWS

Previous Period
BCWP

42,540

42,285

25,158

18,931

175,098

83,344

11,250

20,848

349,591

124,991

176,203

1,070,238

ACWP
55,358
70,043
12,455
17,222
150,969
247,075
15,361
743
693,887
256,557
17,651
235,632

1,772,952 -

Period Movement
BCWP
-
42,540
-
42,285
-
25,158
-
18,931
-
175,098
-
83,344
-
11,250
-
20,848
-
349,591
-
124,991

-
176,203

1,686,232 -

Page 3 of 26

1,070,238

#VALUE!

Values to Date
SV
CV
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!

Values to Date
SPI
CPI
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Comment

#VALUE!

File Name 160521524.xlsx.ms_office and Tab Reference Level 2

160521524.xlsx.ms_office
Activity

Activity
Desc

P3E Code

Expense / Role / Resource


Start

607100005
WPS-900
WPS-900
WPS-900
WPS-900
WPS-900
WPS-900
WPS-900
WPS-900
WPS-900
WPS-900
WPS-900
06071RM001
WPS-900
WPS-900
06071RM002
WPS-900
WPS-900
06071RM007
WPS-900
WPS-900
607100015
WPS-010
WPS-010
WPS-010
WPS-010
607100025
WPS-020
WPS-020
WPS-020
WPS-020
WPS-020
WPS-020
WPS-020
607100035
WPS-030
WPS-030
WPS-030
WPS-030
607100045
WPS-040
WPS-040
WPS-040
WPS-040
607100055
WPS-050
WPS-050
WPS-050
WPS-050
WPS-050
WPS-050
WPS-050
WPS-050
WPS-050
607100075
WPS-070
607100080
WPS-070
607100085
WPS-070
WPS-070
607100090
WPS-080
607100095
WPS-080
607100100
WPS-080
607100105
WPS-080
607100110
WPS-080
607100115
WPS-080
607100120
WPS-090
WPS-090
607100130
WPS-090
WPS-090
06071TB002
WPS-090
607100140
WPS-090
WPS-090
WPS-090
607100145
WPS-090
WPS-090
WPS-090
607100150
WPS-090
WPS-090
WPS-090
607100135
WPS-090
WPS-090
WPS-090
607100155
WPS-090
WPS-090
WPS-090
607100160
WPS-100
WPS-100
607100175
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
06071RM003
WPS-100

Project Management
1-Apr-05
6.31E+09
Prof Serv; Constn Manmt; Constn Manmt-Other1
1-Apr-05
6.58E+09
General Expenses; Office Expenses; Expenses-Other1
1-Apr-05
6.51E+09
General Expenses; Travel & Subsistence; Travel & Accommodation-Other1
1-Apr-05
6.53E+09
General Expenses; Training; Training Courses-Other1
1-Apr-05
6.31E+09
Info Techno; IT Infra-sture; Infra-sture-Other1
1-Apr-05
6.31E+09
Pro Ser; Dsgn Spt; Dsgn Ser, Gen Dsgn Ac-Other1
1-Apr-05
6001200
Senior Project Manager
1-Apr-05
5081460
Personal Assistant; ASW/CSW
1-Apr-05
2460360
Construction Manager; ASW/CSW
1-Apr-05
6000200
Head Project/Programme
1-Apr-05
5020400
Quality Team Leader
1-Apr-05
M 1&2 & 3: Stake Holder Management
1-Apr-05
6.31E+09
Pro Serv; Manmt Consultants; Consultants-Other1
1-Apr-05
6000360
Project Manager; ASW/CSW
1-Apr-05
M4 : PMP Support & Interfaces Management
1-Apr-05
6.31E+09
Pro Serv; Manmt Consultants; Consultants-Other1
1-Apr-05
6000360
Project Manager; ASW/CSW
1-Apr-05
M10: Liason and Interface with Regulatory Bodies
1-Apr-05
6.31E+09
Pro Serv; Manmt Consultants; Consultants-Other1
1-Apr-05
6000360
Project Manager; ASW/CSW
1-Apr-05
Project Controls
1-Apr-05
6.31E+09
Prof Serv; Constn Manmt; Constn Manmt-Other1
1-Apr-05
6011300
Project Controls Manager
1-Apr-05
6010460
Planning Engineer; ASW/CSW
1-Apr-05
6011460
Cost Engineer; ASW/CSW
1-Apr-05
Engineering & S&RM Support to Construction Team
1-Apr-05
6.31E+09
Pro Ser; Dsgn Spt; Dsgn Ser, Gen Dsgn Ac-Other1
1-Apr-05
2340400
Civil / Structural / Architectural Engineer
1-Apr-05
2310400
C,E &I Engineer
1-Apr-05
4000400
Safety/Environment Adviser
1-Apr-05
2300400
Mechanical Engineer; Design
1-Apr-05
5020360
Quality Manager; ASW/CSW
1-Apr-05
4000360
Safety/Environmental Manager; ASW/CSW
1-Apr-05
Procurement & Sub Contracts Support
1-Apr-05
6.31E+09
Prof Services; Finance; Accounting-Other1
1-Apr-05
5010300
Procurement Manager
1-Apr-05
5051300
Legal Officer
1-Apr-05
5010460
Procurement Assistant; ASW/CSW
1-Apr-05
Site Infrastructure Support
1-Apr-05
4000300
Safety/Environmental Manager
1-Apr-05
4002400
Health Physics Engineer
1-Apr-05
1200300
Ops Support Mgr
1-Apr-05
6000300
Project Manager
1-Apr-05
Construction Management
1-Apr-05
6.31E+09
Prof Services; Finance; Accounting-Other1
1-Apr-05
2460300
Construction Manager
1-Apr-05
4000400
Safety/Environment Adviser
1-Apr-05
2461480
Construction Team Leader; sub con
1-Apr-05
2330400
Construction Engineer
1-Apr-05
5022300
Quality Assurance Engineer
1-Apr-05
6000300
Project Manager
1-Apr-05
6000360
Project Manager; ASW/CSW
1-Apr-05
2330460
Construction Engineer; ASW/CSW
1-Apr-05
B388: Building Ownership Transfer
1-Apr-05
6.54E+09
Moving costs-Other1
1-Apr-05
B388: Rehabilitation of B388
29-Apr-05
6.54E+09
Moving costs-Other1
29-Apr-05
B388: Relocation of Occupants from B816/B841 to B388
28-Jun-05
6.54E+09
Moving costs-Other1
28-Jun-05
8950101
P50 Contingency-Other1
28-Jun-05
B816/B841: Approval of PMP
1-Apr-05
6.31E+09
Prof Serv; Constn Manmt; Constn Manmt-Other1
1-Apr-05
B816/B841: Building Transfer Agreement
29-Apr-05
6.54E+09
Moving costs-Other1
29-Apr-05
B816/B841: Pre Operations Survey (M6)
28-Jun-05
6.11E+09
Constn; Survey & Invests; Testing/Comisg-Other1
28-Jun-05
B816/B841: Decontamination & Demoilition of B841/841.1
26-Jul-05
6.11E+09
Decontamination; Demo; Marine Contracts-Other1
26-Jul-05
B816/B841: Decontamination & Demoilition of B816/816.1
7-Sep-05
6.11E+09
Decontamination; Demo; Marine Contracts-Other1
7-Sep-05
B816/B841: Decontamination & Demoilition of B816.2/816.3
19-Oct-05
6.11E+09
Decontamination; Demo; Marine Contracts-Other1
19-Oct-05
B262: Building Transfer Agreement
10-Jun-05
6.54E+09
Moving costs-Other1
10-Jun-05
6.58E+09
General Expenses; Office Expenses; Administration-Other1
10-Jun-05
B262: Pre Operations Survey (M6)
3-Oct-05
6.11E+09
Constn; Survey & Invests; Testing/Comisg-Other1
03-Oct-2005*
6.58E+09
General Expenses; Office Expenses; Administration-Other1
03-Oct-2005*
Team Building: B262 Start Up
3-Oct-05
6.53E+09
General Expenses; Training; Training Courses-Other1
3-Oct-05
B262: Spray Cladding with PVA Solution
17-Nov-05
6.11E+09
Construction; Steelwork; Cladding-Other1
17-Nov-05
6.58E+09
General Expenses; Office Expenses; Administration-Other1
17-Nov-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 17-Nov-05
B262: Remove Cladding
21-Nov-05
6.11E+09
Construction; Steelwork; Cladding-Other1
21-Nov-05
6.58E+09
General Expenses; Office Expenses; Administration-Other1
21-Nov-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 21-Nov-05
B262: Structural Steel Removal & Remove Scaffold
24-Nov-05
6.11E+09
Constn; Steelwork; Platforms / Stairs-Other1
24-Nov-05
6.58E+09
General Expenses; Office Expenses; Administration-Other1
24-Nov-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 24-Nov-05
B262: Scaffold Errection
31-Oct-05
6.58E+09
General Expenses; Office Expenses; Administration-Other1
31-Oct-05
6.31E+09
Scaffolding (Generally)
31-Oct-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 31-Oct-05
B262: Foundations Removal & Transfer of Services
5-Dec-05
6.11E+09
Foundations-Other1
5-Dec-05
6.58E+09
General Expenses; Office Expenses; Administration-Other1
5-Dec-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 5-Dec-05
B304: Approval B304 PMP (Cat B)
1-Apr-05
6.31E+09
Prof Serv; Constn Manmt; Constn Manmt-Other1
1-Apr-05
8950101
P50 Contingency-Other1
1-Apr-05
B304: Orphan Waste Transfer
1-Apr-05
6.11E+09
Decon; Decon & Dplt; Hazardous Deplant-Other1
1-Apr-05
8950101
P50 Contingency-Other1
1-Apr-05
4000300
Safety/Environmental Manager
1-Apr-05
3023400
Waste Management Engineer
1-Apr-05
6000300
Project Manager
1-Apr-05
1120500
Plant Operator (Reactors)
1-Apr-05
M5 : Alternate D&D B304 Methodology Preparation Excluding Crane Incl Mini HAZOP
1-Apr-05
6.31E+09
Pro Serv; Manmt Consultants; Consultants-Other1
1-Apr-05

Date Printed 7/27/2013 4:27 PM

Finish

28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Apr-05
28-Apr-05
27-Jun-05
27-Jun-05
25-Jul-05
25-Jul-05
25-Jul-05
28-Apr-05
28-Apr-05
27-Jun-05
27-Jun-05
25-Jul-05
25-Jul-05
6-Sep-05
6-Sep-05
18-Oct-05
18-Oct-05
29-Nov-05
29-Nov-05
4-Aug-05
4-Aug-05
4-Aug-05
28-Oct-05
29-Oct-05
30-Oct-05
7-Oct-05
7-Oct-05
18-Nov-05
18-Nov-05
18-Nov-05
18-Nov-05
23-Nov-05
23-Nov-05
23-Nov-05
23-Nov-05
2-Dec-05
2-Dec-05
2-Dec-05
2-Dec-05
16-Nov-05
16-Nov-05
16-Nov-05
16-Nov-05
19-Dec-05
19-Dec-05
19-Dec-05
19-Dec-05
27-May-05
27-May-05
27-May-05
30-Aug-05
30-Aug-05
30-Aug-05
30-Aug-05
30-Aug-05
30-Aug-05
30-Aug-05
25-Jul-05
25-Jul-05

Units

Cost Centre

750
1500
750
68
300

6044
6044
6044
6044
6044

500

6044

540

6044

540

6044

375
500
700

3038
6044
6044

750
750
325
325
100
325

6044
6044
3830
6044
6044
6044

200
200
750

6044
6044
6044

10
20
20
750

3984
3821
3984
3298

2025
600
625
75
150
150
1380
2920

5940
3540
5940
5940
3757
6044
6044
6044

750
500
250
1550

4262
4262
4262
4262

Baseline Cost

265,268.34
12,485.00
37,138.00
40,000.00
14,000.00
4,500.00
29,090.00
62,160.00
30,555.00
22,042.50
5,635.84
7,662.00
23,800.00
7,680.00
16,120.00
25,857.60
8,448.00
17,409.60
25,857.60
8,448.00
17,409.60
75,026.25
33,731.00
14,501.25
12,535.00
14,259.00
74,576.00
3,477.00
21,262.50
21,127.50
7,965.75
8,944.00
2,852.00
8,947.25
44,369.50
16,275.00
8,098.00
7,734.00
12,262.50
33,387.60
362.20
492.60
717.80
31,815.00
308,815.10
79,070.00
78,306.75
14,706.00
18,750.00
1,847.25
5,800.50
6,363.00
44,491.20
59,480.40
5,000.00
5,000.00
80,000.00
80,000.00
28,203.33
20,000.00
8,203.33
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
19,000.00
19,000.00
19,000.00
19,000.00
19,000.00
19,000.00
18,780.00
15,000.00
3,780.00
6,350.00
5,000.00
1,350.00
2,000.00
2,000.00
5,880.00
3,800.00
1,080.00
1,000.00
9,570.00
6,200.00
1,620.00
1,750.00
17,150.00
11,200.00
2,700.00
3,250.00
39,530.00
6,480.00
25,800.00
7,250.00
62,240.00
40,500.00
9,990.00
11,750.00
38,634.65
21,500.00
17,134.65
173,955.33
86,000.00
8,203.33
27,165.00
12,315.00
10,605.00
29,667.00
5,127.20
2,208.00

Actual Start

Forecast
Finish
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06

Complete

1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
25-Apr-05
25-Apr-05
22-Nov-05
22-Nov-05
22-Nov-05
3-Oct-05
3-Oct-05
10-Oct-05
10-Oct-05
13-Jun-05
13-Jun-05

Complete

13-Dec-06

23-Dec-05

Complete

13-Dec-06

13-Jan-06

Complete

13-Dec-06
10-Aug-05
10-Aug-05
10-Aug-05
1-Aug-05
1-Aug-05
1-Aug-05
1-Apr-05
1-Apr-05

Progress

80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
90.00%
90.00%
90.00%
100.00%
100.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%

Progress From

Approtioned Effort - Period 10


Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Approtioned Effort - Period 10
Complete
Complete
Complete
Complete
Complete
Complete

Complete
Complete
Await Final Documentation
Await Final Documentation
Complete

Actual Finish

20-May-05
20-May-05
21-Nov-05
21-Nov-05
28-Nov-05
28-Nov-05
28-Nov-05
10-Nov-05
10-Nov-05
31-Oct-05
31-Oct-05
17-Jun-05
17-Jun-05

20-Jan-06
30-Nov-05
30-Nov-05
6-Dec-05
6-Dec-05
1-Aug-05
1-Aug-05

Require B.258 To Be Commissioned ? For this Financial Year


Require B.258 To Be Commissioned ? For this Financial Year
Require B.258 To Be Commissioned ? For this Financial Year
As Above
As Above
As Above
As Above
As Above
As Above
As Above
As Above
As Above
As Above
As Above
As Above
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05

Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete
Page 4 of 26

13-Oct-05
13-Oct-05
13-Oct-05
29-Nov-05
29-Nov-05
29-Nov-05
29-Nov-05
29-Nov-05
29-Nov-05
29-Nov-05
22-Nov-05

BCWS

BCWP

215,197.02
10,128.28
30,127.89
32,449.69
11,357.26
3,650.55
23,599.25
50,426.87
24,787.42
17,881.86
4,572.04
6,215.91
19,307.94
6,230.46
13,077.48
20,976.88
6,853.45
14,123.43
20,976.88
6,853.45
14,123.43
60,865.00
27,364.12
11,764.07
10,169.09
11,567.72
60,499.44
2,820.74
17,249.19
17,139.70
6,461.98
7,255.84
2,313.72
7,258.27
35,994.42
13,203.13
6,569.45
6,274.12
9,947.72
27,084.98
293.72
399.55
582.17
25,809.54
250,524.81
64,145.10
63,525.78
11,930.12
15,210.97
1,498.43
4,705.78
5,161.92
36,093.36
48,253.35
5,000.00
5,000.00
80,000.00
80,000.00
28,203.33
20,000.00
8,203.33
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
19,000.01
19,000.01
19,000.02
19,000.02
19,000.02
19,000.02
18,780.00
15,000.00
3,780.00
6,350.00
5,000.00
1,350.00
2,000.00
2,000.00
5,880.00
3,800.00
1,080.00
1,000.00
9,570.00
6,200.00
1,620.00
1,750.00
17,150.00
11,200.00
2,700.00
3,250.00
39,530.01
6,480.00
25,800.01
7,250.00
62,240.00
40,500.00
9,990.00
11,750.00
38,634.65
21,500.00
17,134.65
173,955.20
86,000.04
8,203.25
27,164.97
12,315.02
10,605.01
29,666.91
5,127.19
2,208.00

212,745.21
10,012.97
29,784.68
32,080.00
11,228.00
3,609.00
23,330.18
49,852.32
24,505.11
17,678.09
4,519.94
6,144.92
19,087.60
6,159.36
12,928.24
20,737.80
6,775.30
13,962.50
20,737.80
6,775.30
13,962.50
60,171.05
27,052.26
11,630.00
10,053.07
11,435.72
59,809.95
2,788.55
17,052.53
16,944.26
6,388.53
7,173.09
2,287.30
7,175.69
35,584.34
13,052.55
6,494.60
6,202.67
9,834.53
26,776.86
290.48
395.07
575.68
25,515.63
247,669.71
63,414.14
62,802.01
11,794.21
15,037.50
1,481.49
4,652.00
5,103.13
35,681.94
47,703.28
5,000.00
5,000.00
80,000.00
80,000.00
28,203.33
20,000.00
8,203.33
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
5,000.00
19,000.00
19,000.00
19,000.00
19,000.00
19,000.00
19,000.00
18,780.00
15,000.00
3,780.00
5,715.00
4,500.00
1,215.00
2,000.00
2,000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
38,634.65
21,500.00
17,134.65
173,955.33
86,000.00
8,203.33
27,165.00
12,315.00
10,605.00
29,667.00
5,127.20
2,208.00

ACWP

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
0.00
0.00
0.00
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

To Go

EAC

BLIND CALCULATION
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

SV

-2,451.81
-115.31
-343.21
-369.69
-129.26
-41.55
-269.07
-574.55
-282.31
-203.78
-52.10
-70.99
-220.34
-71.10
-149.24
-239.08
-78.15
-160.93
-239.08
-78.15
-160.93
-693.95
-311.86
-134.07
-116.02
-132.00
-689.49
-32.19
-196.66
-195.44
-73.45
-82.75
-26.42
-82.58
-410.08
-150.58
-74.85
-71.45
-113.19
-308.12
-3.24
-4.48
-6.49
-293.91
-2,855.10
-730.96
-723.77
-135.91
-173.47
-16.94
-53.78
-58.79
-411.42
-550.07
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
-0.01
-0.01
-0.02
-0.02
-0.02
-0.02
0.00
0.00
0.00
-635.00
-500.00
-135.00
0.00
0.00
-5,880.00
-3,800.00
-1,080.00
-1,000.00
-9,570.00
-6,200.00
-1,620.00
-1,750.00
-17,150.00
-11,200.00
-2,700.00
-3,250.00
-39,530.01
-6,480.00
-25,800.01
-7,250.00
-62,240.00
-40,500.00
-9,990.00
-11,750.00
0.00
0.00
0.00
0.13
-0.04
0.08
0.03
-0.02
-0.01
0.09
0.01
0.00

CV

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

SPI

CPI

0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
0.99
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
0.90
0.90
0.90
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

File Name 160521524.xlsx.ms_office and Tab Reference Level 3

160521524.xlsx.ms_office
Activity

Activity
Desc

P3E Code

Expense / Role / Resource


Start

WPS-100
WPS-100
06071RM006
WPS-100
607100165
WPS-100
06071TB003
WPS-100
607100170
WPS-100
607100180
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
607100185
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
607100200
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
607100205
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
607100190
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
607100210
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
607100195
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
607100215
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
607100225
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
607100220
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
607100230
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
607100235
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
607100240
WPS-100
WPS-100
607100245
WPS-100
WPS-100
06071B2001
WPS-100
607100255
WPS-110
WPS-110
607100260
WPS-110
06071TB001
WPS-110
607100265
WPS-110
607100270
WPS-110
607100315
WPS-110
607100275
WPS-110
607100280
WPS-110
607100285
WPS-110
607100290
WPS-110
607100295
WPS-110
607100300

6000360
Project Manager; ASW/CSW
1-Apr-05
2330460
Construction Engineer; ASW/CSW
1-Apr-05
M8: B304 Orphan Waste Mitigation / Alternate Route for Disposal
1-Apr-05
6.11E+09
Decon; Decon & Dplt; Hazardous Deplant-Other1
1-Apr-05
B304: Building Ownership Transfer
31-May-05
6.54E+09
Moving costs-Other1
31-May-05
Team Building: B304 Start Up
28-Jun-05
6.53E+09
General Expenses; Training; Training Courses-Other1
28-Jun-05
B304: Pre Ops Survey (M6)
28-Jun-05
6.11E+09
Constn; Survey & Invests; Testing/Comisg-Other1
28-Jun-05
B304: Remove Bay Doors 2,3 & 4
31-Aug-05
6.11E+09
Decon; Decon & Deplant; Clean Deplant-Other1
31-Aug-05
8950101
P50 Contingency-Other1
31-Aug-05
6.31E+09
Crane Equipment (Generally)
31-Aug-05
6.31E+09
Scaffolding (Generally)
31-Aug-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 31-Aug-05
B304: Remove Concrete Panel West Elevation Bay 1
7-Sep-05
6.11E+09
Decon; Decon & Deplant; Clean Deplant-Other1
7-Sep-05
8950101
P50 Contingency-Other1
7-Sep-05
6.31E+09
Crane Equipment (Generally)
7-Sep-05
6.31E+09
Scaffolding (Generally)
7-Sep-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 7-Sep-05
B304: Remove Roof Slab Bay 3
7-Sep-05
6.11E+09
Decon; Decon & Deplant; Clean Deplant-Other1
7-Sep-05
8950101
P50 Contingency-Other1
7-Sep-05
6.31E+09
Crane Equipment (Generally)
7-Sep-05
6.31E+09
Scaffolding (Generally)
7-Sep-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 7-Sep-05
B304: Remove Roof Slab Bay 4
15-Sep-05
6.11E+09
Decon; Decon & Deplant; Clean Deplant-Other1
15-Sep-05
8950101
P50 Contingency-Other1
15-Sep-05
6.31E+09
Crane Equipment (Generally)
15-Sep-05
6.31E+09
Scaffolding (Generally)
15-Sep-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 15-Sep-05
B304: Remove Roof Slab Bay 2
21-Sep-05
6.11E+09
Decon; Decon & Deplant; Clean Deplant-Other1
21-Sep-05
8950101
P50 Contingency-Other1
21-Sep-05
6.31E+09
Crane Equipment (Generally)
21-Sep-05
6.31E+09
Scaffolding (Generally)
21-Sep-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 21-Sep-05
B304: Remove Internal Wall Bay 2-3
23-Sep-05
6.11E+09
Decon; Decon & Deplant; Clean Deplant-Other1
23-Sep-05
8950101
P50 Contingency-Other1
23-Sep-05
6.31E+09
Crane Equipment (Generally)
23-Sep-05
6.31E+09
Scaffolding (Generally)
23-Sep-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 23-Sep-05
B304: Remove Internal Wall Bay 1-2
29-Sep-05
6.11E+09
Decon; Decon & Deplant; Clean Deplant-Other1
29-Sep-05
8950101
P50 Contingency-Other1
29-Sep-05
6.31E+09
Crane Equipment (Generally)
29-Sep-05
6.31E+09
Scaffolding (Generally)
29-Sep-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 29-Sep-05
B304: Remove Internal Wall Bay 3-4
13-Oct-05
6.11E+09
Decon; Decon & Deplant; Clean Deplant-Other1
13-Oct-05
8950101
P50 Contingency-Other1
13-Oct-05
6.31E+09
Crane Equipment (Generally)
13-Oct-05
6.31E+09
Scaffolding (Generally)
13-Oct-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 13-Oct-05
B304: Remove External Wall South Elevation
19-Oct-05
6.11E+09
Decon; Decon & Deplant; Clean Deplant-Other1
19-Oct-05
8950101
P50 Contingency-Other1
19-Oct-05
6.31E+09
Crane Equipment (Generally)
19-Oct-05
6.31E+09
Scaffolding (Generally)
19-Oct-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 19-Oct-05
B304: Remove External Wall North Elevation
31-Oct-05
6.11E+09
Decon; Decon & Deplant; Clean Deplant-Other1
31-Oct-05
8950101
P50 Contingency-Other1
31-Oct-05
6.31E+09
Crane Equipment (Generally)
31-Oct-05
6.31E+09
Scaffolding (Generally)
31-Oct-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 31-Oct-05
B304: Remove External Wall East Elevation
5-Dec-05
6.11E+09
Decon; Decon & Deplant; Clean Deplant-Other1
5-Dec-05
8950101
P50 Contingency-Other1
5-Dec-05
6.31E+09
Crane Equipment (Generally)
5-Dec-05
6.31E+09
Scaffolding (Generally)
5-Dec-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 5-Dec-05
B304: Remove Plant and Scaffold / Clear Site
7-Feb-06
6.11E+09
Decon; Decon & Deplant; Clean Deplant-Other1
7-Feb-06
8950101
P50 Contingency-Other1
7-Feb-06
6.31E+09
Crane Equipment (Generally)
7-Feb-06
6.31E+09
Scaffolding (Generally)
7-Feb-06
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 7-Feb-06
B304: Removal B304 Foundations
1-Mar-06
6.11E+09
Foundations-Other1
1-Mar-06
8950101
P50 Contingency-Other1
1-Mar-06
B304: Removal Foundations Spoil
15-Mar-06
6.11E+09
Foundations-Other1
15-Mar-06
8950101
P50 Contingency-Other1
15-Mar-06
B304 Waste Crushing 05/06
6.11E+09
Decontamination; Demo; Treatment Plants-Other1
21-Sep-05
B358: Approval PMP
1-Apr-05
6.31E+09
Prof Serv; Constn Manmt; Constn Manmt-Other1
1-Apr-05
8950101
P50 Contingency-Other1
1-Apr-05
B358: Building Ownership Transfer Agreement
13-Apr-05
6.54E+09
Moving costs-Other1
13-Apr-05
Team Building: B358 Start Up
12-May-05
6.53E+09
General Expenses; Training; Training Courses-Other1
12-May-05
B358: Pre Ops Survey (M6)
12-May-05
6.11E+09
Constn; Surv & Invests; Surv / Invests-Other1
12-May-05
B358: Install Acess Scafold
10-Jun-05
6.31E+09
Scaffolding (Generally)
10-Jun-05
B358: Errect RUBB Shelter
10-Jun-05
6.31E+09
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment 10-Jun-05
B358: Building Fabric Repairs
24-Jun-05
6.21E+09
Repair contracts-Other1
24-Jun-05
B358: Re-Paint Structural Steel
26-Jul-05
6.11E+09
Constn; Civil; Sml Civ Spt Sub-Contract-Other1
26-Jul-05
B358: Install New Cladding
2-Aug-05
6.11E+09
Construction; Steelwork; Cladding-Other1
2-Aug-05
B358: Relay New Floor
16-Aug-05
6.11E+09
Constn; Civil; Sml Civ Spt Sub-Contract-Other1
16-Aug-05
B358: Seal South End of Building
19-Aug-05
6.11E+09
Constn; Civil; Sml Civ Spt Sub-Contract-Other1
19-Aug-05
B358: Install New Lighting
12-Sep-05

Date Printed 7/27/2013 4:27 PM

Finish

Units

Cost Centre

25-Jul-05
25-Jul-05
27-May-05
27-May-05
27-Jun-05
27-Jun-05
4-Jul-05
4-Jul-05
25-Jul-05
25-Jul-05
6-Sep-05
6-Sep-05
6-Sep-05
6-Sep-05
6-Sep-05
6-Sep-05
20-Sep-05
20-Sep-05
20-Sep-05
20-Sep-05
20-Sep-05
20-Sep-05
14-Sep-05
14-Sep-05
14-Sep-05
14-Sep-05
14-Sep-05
14-Sep-05
22-Sep-05
22-Sep-05
22-Sep-05
22-Sep-05
22-Sep-05
22-Sep-05
28-Sep-05
28-Sep-05
28-Sep-05
28-Sep-05
28-Sep-05
28-Sep-05
12-Oct-05
12-Oct-05
12-Oct-05
12-Oct-05
12-Oct-05
12-Oct-05
18-Oct-05
18-Oct-05
18-Oct-05
18-Oct-05
18-Oct-05
18-Oct-05
28-Oct-05
28-Oct-05
28-Oct-05
28-Oct-05
28-Oct-05
28-Oct-05
20-Dec-05
20-Dec-05
20-Dec-05
20-Dec-05
20-Dec-05
20-Dec-05
2-Dec-05
2-Dec-05
2-Dec-05
2-Dec-05
2-Dec-05
2-Dec-05
6-Feb-06
6-Feb-06
6-Feb-06
6-Feb-06
6-Feb-06
6-Feb-06
28-Feb-06
28-Feb-06
28-Feb-06
28-Feb-06
28-Feb-06
28-Feb-06
14-Mar-06
14-Mar-06
14-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06

40
80

6044
6044

31-Mar-06
12-Apr-05
12-Apr-05
12-Apr-05
11-May-05
11-May-05
18-May-05
18-May-05
9-Jun-05
9-Jun-05
23-Jun-05
23-Jun-05
11-Aug-05
11-Aug-05
25-Jul-05
25-Jul-05
1-Aug-05
1-Aug-05
15-Aug-05
15-Aug-05
18-Aug-05
18-Aug-05
9-Sep-05
9-Sep-05
16-Sep-05

Baseline Cost
1,289.60
1,629.60
100,000.00
100,000.00
66,250.00
66,250.00
2,000.00
2,000.00
5,000.00
5,000.00
20,556.25
9,800.00
3,076.25
1,920.00
1,860.00
3,900.00
12,196.25
4,000.00
3,076.25
1,280.00
1,240.00
2,600.00
17,756.25
7,000.00
3,076.25
1,920.00
1,860.00
3,900.00
17,756.25
7,000.00
3,076.25
1,920.00
1,860.00
3,900.00
17,756.25
7,000.00
3,076.25
1,920.00
1,860.00
3,900.00
33,236.25
14,800.00
3,076.25
3,840.00
3,720.00
7,800.00
33,236.25
14,800.00
3,076.25
3,840.00
3,720.00
7,800.00
33,236.25
14,800.00
3,076.25
3,840.00
3,720.00
7,800.00
101,776.25
47,500.00
3,076.25
12,800.00
12,400.00
26,000.00
63,396.25
29,600.00
3,076.25
7,680.00
7,440.00
15,600.00
158,136.25
75,700.00
3,076.25
19,840.00
19,220.00
40,300.00
26,126.25
10,250.00
3,076.25
3,200.00
3,100.00
6,500.00
28,076.25
25,000.00
3,076.25
11,076.25
8,000.00
3,076.25
1,000,000.00
1,000,000.00
8,076.25
5,000.00
3,076.25
5,000.00
5,000.00
2,000.00
2,000.00
10,000.00
10,000.00
12,100.00
12,100.00
53,400.00
53,400.00
25,000.00
25,000.00
6,100.00
6,100.00
12,000.00
12,000.00
3,600.00
3,600.00
18,200.00
18,200.00
3,500.00

Progress
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
30.38%
0.00%
50.00%
50.00%
50.00%
50.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
30.00%
30.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
0.00%
0.00%
100.00%
100.00%
35.00%

Progress From
Activity Complete
Activity Complete

Actual Start

Forecast
Finish

Actual Finish
22-Nov-05
22-Nov-05
1-Oct-05
1-Oct-05
30-Sep-05
30-Sep-05
21-Oct-05
21-Oct-05
18-Aug-05
18-Aug-05

Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete

1-Apr-05
1-Apr-05
1-Apr-05
1-Apr-05
30-Sep-05
30-Sep-05
13-Oct-05
13-Oct-05
1-Aug-05
1-Aug-05
18-Oct-05
18-Oct-05
18-Oct-05
18-Oct-05
18-Oct-05
18-Oct-05

Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete

12-Oct-05
12-Oct-05
12-Oct-05
12-Oct-05
12-Oct-05

28-Oct-05
28-Oct-05
28-Oct-05
28-Oct-05
28-Oct-05

Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete

1-Dec-05
1-Dec-05
1-Dec-05
1-Dec-05
1-Dec-05

16-Dec-05
16-Dec-05
16-Dec-05
16-Dec-05
16-Dec-05

Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete

19-Dec-05
19-Dec-05
19-Dec-05
19-Dec-05
19-Dec-05

17-Jan-06
17-Jan-06
17-Jan-06
17-Jan-06
17-Jan-06

Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete

22-Nov-05
22-Nov-05
22-Nov-05
22-Nov-05
22-Nov-05

30-Nov-05
30-Nov-05
30-Nov-05
30-Nov-05
30-Nov-05

Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete

1-Dec-05
1-Dec-05
1-Dec-05
1-Dec-05
1-Dec-05

16-Dec-05
16-Dec-05
16-Dec-05
16-Dec-05
16-Dec-05

Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete

22-Nov-05
22-Nov-05
22-Nov-05
22-Nov-05
22-Nov-05

30-Nov-05
30-Nov-05
30-Nov-05
30-Nov-05
30-Nov-05

Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete

19-Dec-05
19-Dec-05
19-Dec-05
19-Dec-05
19-Dec-05

17-Jan-06
17-Jan-06
17-Jan-06
17-Jan-06
17-Jan-06

Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete

9-Nov-05
9-Nov-05
9-Nov-05
9-Nov-05
9-Nov-05

30-Nov-05
30-Nov-05
30-Nov-05
30-Nov-05
30-Nov-05

Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete

19-Dec-05
19-Dec-05
19-Dec-05
19-Dec-05
19-Dec-05

17-Jan-06
17-Jan-06
17-Jan-06
17-Jan-06
17-Jan-06

Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete

9-Nov-05
9-Nov-05
9-Nov-05
9-Nov-05
9-Nov-05

17-Jan-06
17-Jan-06
17-Jan-06
17-Jan-06
17-Jan-06

Walkway Protection
Walkway Protection
Walkway Protection
Walkway Protection

16-Jan-06
16-Jan-06
16-Jan-06
16-Jan-06
16-Jan-06

Activity Complete
Activity Complete
Activity Complete
Activity Complete

31/11/05
31/11/05
31/11/05
31/11/05
31/11/05

27-Jan-06
27-Jan-06
27-Jan-06
27-Jan-06
27-Jan-06

Start 23 Jan 06
Start 23 Jan 06

3-Mar-06
3-Mar-06

Start 23 Jan 06
Start 23 Jan 06

10-Mar-06
10-Mar-06

Spent More Cost @ 35K Week

Activity Complete

5-Dec-05
12-Jul-05
12-Jul-05
12-Jul-05
5-Jul-05
5-Jul-05
25-Jul-05
25-Jul-05
27-Jun-05
27-Jun-05
25-Jul-05
25-Jul-05
25-Jul-05
25-Jul-05
11-Aug-05
11-Aug-05
12-Oct-05
12-Oct-05
11-Aug-05
11-Aug-05

Activity Complete

10-Oct-05
10-Oct-05

Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete
Activity Complete

Page 5 of 26

31-Mar-06
26-Jul-05
26-Jul-05
26-Jul-05
28-Jun-05
28-Jun-05
29-Jul-05
29-Jul-05
28-Jun-05
28-Jun-05
15-Aug-05
15-Aug-05
9-Sep-05
9-Sep-05
13-Feb-06
13-Feb-06
20-Dec-05
13-Dec-05

13-Dec-05

BCWS

BCWP

1,289.59
1,629.60
100,000.00
100,000.00
66,250.00
66,250.00
2,000.00
2,000.00
5,000.00
5,000.00
20,556.25
9,800.00
3,076.25
1,920.00
1,860.00
3,900.00
12,196.26
4,000.00
3,076.26
1,280.00
1,240.00
2,600.00
17,756.26
7,000.00
3,076.26
1,920.00
1,860.00
3,900.00
17,756.25
7,000.00
3,076.25
1,920.00
1,860.00
3,900.00
17,756.26
7,000.00
3,076.26
1,920.00
1,860.00
3,900.00
33,236.23
14,799.99
3,076.25
3,840.01
3,719.99
7,799.99
33,236.24
14,800.00
3,076.24
3,840.00
3,720.00
7,800.00
33,236.26
14,800.01
3,076.25
3,840.00
3,720.00
7,800.00
101,776.31
47,500.02
3,076.28
12,799.98
12,400.02
26,000.01
63,396.25
29,600.00
3,076.25
7,680.00
7,440.00
15,600.00
114,648.78
54,882.50
2,230.28
14,384.00
13,934.50
29,217.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
621,212.15
621,212.15
8,076.25
5,000.00
3,076.25
5,000.00
5,000.00
2,000.00
2,000.00
10,000.00
10,000.00
12,100.00
12,100.00
53,399.98
53,399.98
25,000.00
25,000.00
6,100.00
6,100.00
12,000.00
12,000.00
3,600.00
3,600.00
18,200.00
18,200.00
3,500.00

1,289.60
1,629.60
100,000.00
100,000.00
66,250.00
66,250.00
2,000.00
2,000.00
5,000.00
5,000.00
20,556.25
9,800.00
3,076.25
1,920.00
1,860.00
3,900.00
12,196.25
4,000.00
3,076.25
1,280.00
1,240.00
2,600.00
17,756.25
7,000.00
3,076.25
1,920.00
1,860.00
3,900.00
17,756.25
7,000.00
3,076.25
1,920.00
1,860.00
3,900.00
17,756.25
7,000.00
3,076.25
1,920.00
1,860.00
3,900.00
33,236.25
14,800.00
3,076.25
3,840.00
3,720.00
7,800.00
33,236.25
14,800.00
3,076.25
3,840.00
3,720.00
7,800.00
33,236.25
14,800.00
3,076.25
3,840.00
3,720.00
7,800.00
101,776.25
47,500.00
3,076.25
12,800.00
12,400.00
26,000.00
63,396.25
29,600.00
3,076.25
7,680.00
7,440.00
15,600.00
158,136.25
75,700.00
3,076.25
19,840.00
19,220.00
40,300.00
7,938.13
0.00
1,538.13
1,600.00
1,550.00
3,250.00
0.00
0.00
0.00
0.00
0.00
0.00
300,000.00
300,000.00
8,076.25
5,000.00
3,076.25
5,000.00
5,000.00
2,000.00
2,000.00
10,000.00
10,000.00
12,100.00
12,100.00
53,400.00
53,400.00
25,000.00
25,000.00
6,100.00
6,100.00
12,000.00
12,000.00
0.00
0.00
18,200.00
18,200.00
1,225.00

ACWP

To Go

EAC

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

SV

CV

SPI

CPI

0.01
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
-0.01
0.00
-0.01
0.00
0.00
0.00
-0.01
0.00
-0.01
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
-0.01
0.00
-0.01
0.00
0.00
0.00
0.02
0.01
0.00
-0.01
0.01
0.01
0.01
0.00
0.01
0.00
0.00
0.00
-0.01
-0.01
0.00
0.00
0.00
0.00
-0.06
-0.02
-0.03
0.02
-0.02
-0.01
0.00
0.00
0.00
0.00
0.00
0.00
43,487.47
20,817.50
845.97
5,456.00
5,285.50
11,082.50
7,938.13
0.00
1,538.13
1,600.00
1,550.00
3,250.00
0.00
0.00
0.00
0.00
0.00
0.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.38
1.38
1.38
1.38
1.38
1.38
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
-

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

-321,212.15
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.02
0.02
0.00
0.00
0.00
0.00
0.00
0.00
-3,600.00
-3,600.00
0.00
0.00
-2,275.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

0.48
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
0.35

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

File Name 160521524.xlsx.ms_office and Tab Reference Level 3

160521524.xlsx.ms_office

Activity

Activity
Desc

P3E Code

Expense / Role / Resource

WPS-110
6.11E+09
Lighting-Other1
607100305
B358: Install New Shutter Door
WPS-110
6.11E+09
Constn; Civil; Sml Civ Spt Sub-Contract-Other1
607100310
B358: Relocate B262 Product to Refurbished B358
WPS-110
6.11E+09
Wste Disp; Radioactive Materials; LLW-Other1
607100320
Site Investigation @ 10m Grid and 40 Boreholes 05/06
WPS-120
6.11E+09
Constn; Surv & Invests; Surv / Invests-Other1
WPS-120
8950101
P50 Contingency-Other1
06071RM004 M6 : Site Investigation Increased Density Borehole Grid > 10m Grid
WPS-120
6.11E+09
Constn; Surv & Invests; Surv / Invests-Other1
SITE CLEARANCE SCOPE OF WORK EXECUTION YEAR

Date Printed 7/27/2013 4:27 PM

Start

Finish

12-Sep-05
19-Sep-05
19-Sep-05
26-Sep-05
26-Sep-05
30-Nov-05
30-Nov-05
30-Nov-05
30-Nov-05
30-Nov-05

16-Sep-05
23-Sep-05
23-Sep-05
28-Oct-05
28-Oct-05
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06
28-Mar-06

Units

Cost Centre

Baseline Cost

3,500.00
6,100.00
6,100.00
100,000.00
100,000.00
78,203.33
70,000.00
8,203.33
18,000.00
18,000.00
3,550,225.58

Progress

Progress From

35.00% Electrical Cost Up To 120K


100.00%
100.00% Activity complete
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
64.28%

Actual Start

Forecast
Finish

Actual Finish

BCWS
3,500.00
6,100.00
6,100.00
100,000.00
100,000.00
31,677.31
28,354.43
3,322.88
7,291.13
7,291.13
2,839,905.97

Page 6 of 26

BCWP
1,225.00
6,100.00
6,100.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2,282,163.94

ACWP
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
0.00
#VALUE!

To Go

EAC

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

SV
-2,275.00
0.00
0.00
-100,000.00
-100,000.00
-31,677.31
-28,354.43
-3,322.88
-7,291.13
-7,291.13
-557,742.03

CV
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
0.00
0.00
#VALUE!

SPI

CPI
0.35
1.00
1.00
0.80

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
0.00
0.00
#VALUE!

File Name 160521524.xlsx.ms_office and Tab Reference Level 3

SPP1 Site Clearance Record of Data Stored in P3e


WPSS
WPS-900
WPS-010
WPS-020
WPS-030
WPS-040
WPS-050
WPS-070
WPS-070
WPS-070
WPS-080
WPS-080
WPS-080
WPS-080
WPS-080
WPS-080
WPS-090
WPS-090
WPS-090
WPS-090
WPS-090
WPS-090
WPS-090
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-110
WPS-110
WPS-110
WPS-110
WPS-110
WPS-110
WPS-110
WPS-110
WPS-110
WPS-110
WPS-110
WPS-110
WPS-110
WPS-120
WPS-100
WPS-900
WPS-900
WPS-100
WPS-120
WPS-100
WPS-900
WPS-110
WPS-090
WPS-100

WPSS

Activity
607100005
607100015
607100025
607100035
607100045
607100055
607100075
607100080
607100085
607100090
607100095
607100100
607100105
607100110
607100115
607100120
607100130
607100135
607100140
607100145
607100150
607100155
607100160
607100165
607100170
607100175
607100180
607100185
607100190
607100195
607100200
607100205
607100210
607100215
607100220
607100225
607100230
607100235
607100240
607100245
607100255
607100260
607100265
607100270
607100275
607100280
607100285
607100290
607100295
607100300
607100305
607100310
607100315
607100320
06071B2001
06071RM001
06071RM002
06071RM003
06071RM004
06071RM006
06071RM007
06071TB001
06071TB002
06071TB003

Activity Description
Project Management
Project Controls
Engineering & S&RM Support to Construction Team
Procurement & Sub Contracts Support
Site Infrastructure Support
Construction Management
B388: Building Ownership Transfer
B388: Rehabilitation of B388
B388: Relocation of Occupants from B816/B841 to B388
B816/B841: Approval of PMP
B816/B841: Building Transfer Agreement
B816/B841: Pre Operations Survey (M6)
B816/B841: Decontamination & Demoilition of B841/841.1
B816/B841: Decontamination & Demoilition of B816/816.1
B816/B841: Decontamination & Demoilition of B816.2/816.3
B262: Building Transfer Agreement
B262: Pre Operations Survey (M6)
B262: Scaffold Errection
B262: Spray Cladding with PVA Solution
B262: Remove Cladding
B262: Structural Steel Removal & Remove Scaffold
B262: Foundations Removal & Transfer of Services
B304: Approval B304 PMP (Cat B)
B304: Building Ownership Transfer
B304: Pre Ops Survey (M6)
B304: Orphan Waste Transfer
B304: Remove Bay Doors 2,3 & 4
B304: Remove Concrete Panel West Elevation Bay 1
B304: Remove Roof Slab Bay 2
B304: Remove Internal Wall Bay 1-2
B304: Remove Roof Slab Bay 3
B304: Remove Roof Slab Bay 4
B304: Remove Internal Wall Bay 2-3
B304: Remove Internal Wall Bay 3-4
B304: Remove External Wall North Elevation
B304: Remove External Wall South Elevation
B304: Remove External Wall East Elevation
B304: Remove Plant and Scaffold / Clear Site
B304: Removal B304 Foundations
B304: Removal Foundations Spoil
B358: Approval PMP
B358: Building Ownership Transfer Agreement
B358: Pre Ops Survey (M6)
B358: Install Acess Scafold
B358: Building Fabric Repairs
B358: Re-Paint Structural Steel
B358: Install New Cladding
B358: Relay New Floor
B358: Seal South End of Building
B358: Install New Lighting
B358: Install New Shutter Door
B358: Relocate B262 Product to Refurbished B358
B358: Errect RUBB Shelter
Site Investigation @ 10m Grid and 40 Boreholes 05/06
B304 Waste Crushing 05/06
M 1&2 & 3: Stake Holder Management
M4 : PMP Support & Interfaces Management
M5 : Alternate D&D B304 Methodology Preparation Excluding Crane Incl Mini HAZOP
M6 : Site Investigation Increased Density Borehole Grid > 10m Grid
M8: B304 Orphan Waste Mitigation / Alternate Route for Disposal
M10: Liason and Interface with Regulatory Bodies
Team Building: B358 Start Up
Team Building: B262 Start Up
Team Building: B304 Start Up

Activity

WPS-010
WPS-020
WPS-030
WPS-040
WPS-050
WPS-070
WPS-080
WPS-090
WPS-100
WPS-110
WPS-120
WPS-900
WPSS Sub Total

BAC

Activity Description
Project Control
Engineering
Procurement
Site Infrastructure
Construction Management
B388 Refurbishment
B816/B841 Demolition
B262 Demolotion
B304 Demolition
B358 Refurbishment
Site Investigation
Project Management

BOTTOM LINE CHECK FOR CORRECT SUB TOTALS

265,268.34
75,026.25
74,576.00
44,369.50
33,387.60
308,815.10
5,000.00
80,000.00
28,203.33
5,000.00
5,000.00
5,000.00
19,000.00
19,000.00
19,000.00
18,780.00
6,350.00
39,530.00
5,880.00
9,570.00
17,150.00
62,240.00
38,634.65
66,250.00
5,000.00
173,955.33
20,556.25
12,196.25
17,756.25
33,236.25
17,756.25
17,756.25
33,236.25
33,236.25
63,396.25
101,776.25
158,136.25
26,126.25
28,076.25
11,076.25
8,076.25
5,000.00
10,000.00
12,100.00
25,000.00
6,100.00
12,000.00
3,600.00
18,200.00
3,500.00
6,100.00
100,000.00
53,400.00
78,203.33
1,000,000.00
23,800.00
25,857.60
5,127.20
18,000.00
100,000.00
25,857.60
2,000.00
2,000.00
2,000.00
3,550,225.58

BCWS

BAC

75,026
74,576
44,370
33,388
308,815
113,203
72,000
161,500
1,965,285
265,076
96,203
340,784
3,550,225.58
TRUE

BCWP

BCWS

BCWP
-

TRUE

% Progress

% Progress
-

TRUE

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
-

SV

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
TRUE

SPI
-

SV

SPI
-

TRUE

TRUE

Site Clearance EAC Assesment


BAC
WPS-900

Core Team
Expenses
Sub Contract
Contingency
Sub Total

245,146
95,638
0
0
340,784

WPS-010

Core Team
Expenses
Sub Contract
Contingency
Sub Total

75,026
0
0
0
75,026

WPS-020

Core Team
Expenses
Sub Contract
Contingency
Sub Total

74,576
0
0
0
74,576

WPS-030

Core Team
Expenses
Sub Contract
Contingency
Sub Total

44,370
0
0
0
44,370

WPS-040

Core Team
Expenses
Sub Contract
Contingency
Sub Total

33,388
0
0
0
33,388

WPS-050

Core Team
Expenses
Sub Contract
Contingency
Sub Total

308,815
0
0
0
308,815

WPS-070

Core Team
Expenses

WPS-080

WPS-090

WPS-100

105,000
8,203
113,203

Core Team
Expenses
Sub Contract
Contingency
Sub Total

0
0
72,000
0
72,000

Total

To Go

279,344.44
73,464.05
352,808.49

279,344
73,464
0
0
352,808

34,199
-22,174
0
0
12,025

185,267
29,867
0
0
215,134

85,874.90
85,874.90

85,875
0
0
0
85,875

10,849
0
0
0
10,849

33,589
0
0
0
33,589

Trended on Actuals

93,211.29
93,211.29

93,211
0
0
0
93,211

18,635
0
0
0
18,635

39,221
0
0
0
39,221

11,194
0
0
0
11,194

Trended on Actuals

22,388.51
22,388.51

22,389
0
0
0
22,389

-21,981
0
0
0
-21,981

6,717
0
0
0
6,717

#VALUE!
0
0
0
#VALUE!

7,751
0
0
0
7,751

Trended on Actuals

15,502.89
15,502.89

15,503
0
0
0
15,503

-17,885
0
0
0
-17,885

6,640
0
0
0
6,640

247,670
0
0
0
247,670

#VALUE!
0
0
0
#VALUE!

94,203
0
0
0
94,203

Trended on Actuals

188,405.13
188,405.13

188,405
0
0
0
188,405

-120,410
0
0
0
-120,410

80,097
0
0
0
80,097

0
0

0
0

0
0

0
0

0
0

0
0

ACWP

To Go

196,607
76,702
0
0
273,308

#VALUE!
#VALUE!
0
0
#VALUE!

189,672
36,732
0
0
226,404

Trended on Actuals + 100k jim Lilly


Trended on Actuals

198,873
77,585
0
0
276,459

60,171
0
0
0
60,171

#VALUE!
0
0
0
#VALUE!

42,937
0
0
0
42,937

Trended on Actuals

60,865
0
0
0
60,865

60,499
0
0
0
60,499

59,810
0
0
0
59,810

#VALUE!
0
0
0
#VALUE!

46,606
0
0
0
46,606

35,994
0
0
0
35,994

35,584
0
0
0
35,584

#VALUE!
0
0
0
#VALUE!

27,085
0
0
0
27,085

26,777
0
0
0
26,777

250,525
0
0
0
250,525
0
0

105,000
8,203
113,203

105,000
8,203
113,203

#VALUE!
#VALUE!
#VALUE!

68,419
0
68,419

0
0
72,000
0
72,000

0
0
72,000
0
72,000

0
0
#VALUE!
0
#VALUE!

0
0
40,658
0
40,658

0
0

0
0

0
0

0
0

0
0

Sub Contract
Contingency
Sub Total

161,500
0
161,500

161,500
0
161,500

26,495
0
26,495

#VALUE!
0
#VALUE!

132,873
0
132,873

Core Team
Expenses

84,879
0

84,879
0

84,879
0

#VALUE!
0

2,419
0

1,812,000
68,405
1,965,285

1,334,521
58,331
1,477,731

1,062,350
60,715
1,207,944

#VALUE!
#VALUE!
#VALUE!

1,327,275
0
1,329,694

Core Team

Expenses

2,000

2,000

2,000

#VALUE!

Sub Contract
Contingency
Sub Total
WPS-120

Movement
from BAC

BCWP

Core Team
Expenses

Core Team
Expenses

260,000
3,076
265,076

0
0

Sub Contract
Contingency
Sub Total

88,000
8,203
96,203

Core Team
Expenses
Sub Contract
Contingency
Grand Total

866,199
97,638
2,498,500
87,888
3,550,226

PROJECT ASSESMENT MINIMUM Period 7


Minimum YE
EAC

BCWS

0
0

Sub Contract
Contingency
Sub Total

Sub Contract
Contingency
Sub Total
WPS-110

PROJECT ASSESMENT MINIMUM Period 6

CCRs

260,000
3,076
265,076

154,125
3,076
159,201

#VALUE!
#VALUE!
#VALUE!

290,481
0
290,481

0
0

0
0

0
0

0
0

35,646
3,323
38,968

0
0
0

#VALUE!
#VALUE!
#VALUE!

311,578
0
311,578

0
0
0
0
0

718,721
79,585
1,968,666
72,933
2,839,906

711,498
78,702
1,419,970
71,994
2,282,164

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

394,783
36,732
2,171,285
0
2,602,800

WPSS Ref
WPS-070
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-100
WPS-110
WPS-120

P3 Activity ID
607100085
607100160
607100160
607100175
607100180
607100185
607100190
607100195
607100200
607100205
607100210
607100215
607100220
607100225
607100230
607100235
607100240
607100245
607100255
607100320

Carry Over

Comment

Minimum EAC

PO Commitment = 212,466 + 6k
Data Coms PO to be placed

PO Commitment = 45,504

Current PO Commitment = 133,616

Trended on Actuals
Current PO Value = 538,798 + 1m
for Crushing Waste + 31K B304
Work Packages + 41.5K Free
Release Finger Print + 2K Bridge
Strength + 5K ISO Container
Maintenance
Assume no risk realised

218,466.00

218,466.00

218,466
0
218,466

113,466
-8,203
105,263

12,006
0
12,006

45,504.00
45,504.00

0
0
45,504
0
45,504

0
0
-26,496
0
-26,496

0
0
40,658
0
40,658

0
0

0
0

0
0

133,616.00

133,616.00

133,616
0
133,616

-27,884
0
-27,884

132,873
0
132,873

4,838.49
-

4,838
0

-80,041
0

1,728
0

1,434,136.49

927.60

Current PO Value = 198,295 + 12K


Data Comms + 20K Reallign Surface
Levels + 57K Elec Design & Mech
Addns + 45K Elec Installation+ 35K
FLT + 3K Trolley Mods

370,295.00

371,222.60

Risk Ref
SPP05 / R6
SPP16 / R5
SPP14 / R2
SPP05 / R8
SPP14 / R4
SPP14 / R4
SPP14 / R4
SPP14 / R4
SPP14 / R4
SPP14 / R4
SPP14 / R4
SPP14 / R4
SPP14 / R4
SPP14 / R4
SPP14 / R4
SPP14 / R4
SPP14 / R4
SPP14 / R4
SPP14 / R4
SPP05 / 05

P50 Allocation

8,203.33
14,058.40
3,076.25
8,203.33
3,076.25
3,076.25
3,076.25
3,076.25
3,076.25
3,076.25
3,076.25
3,076.25
3,076.25
3,076.25
3,076.25
3,076.25
3,076.25
3,076.25
3,076.25
8,203.33

-382,702
-68,405
-531,148

1,205,824
0
1,207,552

928

-1,072

370,295
0
371,223

110,295
-3,076
106,146

242,467
0
242,467

0
0

0
0

0
0

P50 Grand Total

87888.39

14058.4

49220

Trended on Actuals

94,131.32
94,131.32

94,131
0
0
0
94,131

19,555
0
0
0
19,555

920
0
0
0
920

#VALUE!
0
0
0
#VALUE!

Trended on Actuals

16,120.55
16,120.55

16,121
0
0
0
16,121

-28,249
0
0
0
-28,249

-6,268
0
0
0
-6,268

#VALUE!
0
0
0
#VALUE!

Trended on Actuals

15,936.76
15,936.76

15,937
0
0
0
15,937

-17,451
0
0
0
-17,451

434
0
0
0
434

#VALUE!
0
0
0
#VALUE!

Trended on Actuals

192,232.29
192,232.29

192,232
0
0
0
192,232

-116,583
0
0
0
-116,583

3,827
0
0
0
3,827

#VALUE!
0
0
0
#VALUE!

0
0

0
0

0
0

0
0

Current PO Value = 538,798 + 1m


for Crushing Waste + 31K B304
Work Packages + 41.5K Free
Release Finger Print + 2K Bridge
Strength + 5K ISO Container
Maintenance

218,466.00

218,466.00

218,466
0
218,466

113,466
-8,203
105,263

0
0
0

#VALUE!
#VALUE!
#VALUE!

45,504.00
45,504.00

0
0
45,504
0
45,504

0
0
-26,496
0
-26,496

0
0
0
0
0

0
0
#VALUE!
0
#VALUE!

0
0

0
0

0
0

0
0

133,616.00

133,616.00

133,616
0
133,616

-27,884
0
-27,884

0
0
0

#VALUE!
0
#VALUE!

4,147.28
-

4,147
0

-80,732
0

-691
0

#VALUE!
0

1,429,298.00

1,433,445.28

No further Team Building Planned

927.60

Current PO Value = 198,295 + 12K


Data Comms + 20K Reallign Surface
Levels + 57K Elec Design & Mech
Addns + 45K Elec Installation+ 35K
FLT + 3K Trolley Mods

370,295.00

371,222.60

Current PO Value = 69,213 (Nexia


Management) + 15K Excavation of
Pits + 180K Site Investigation Radar
+ 80K Analysis

SPP14
Construction
restrictions
impose
constraints on
the Project
resulting in
delays

8203.33

#VALUE!
0
0
0
#VALUE!

Assume no risk realised

SPP16

24609.99

-5,261
0
0
0
-5,261

189,000

Insufficient
support from
Stakeholders
result in cost
and time
increases

P50 Sub Total

5,587
0
0
0
5,587

Trended on Actuals

SPP05

3076.25
3076.25
3076.25
3076.25
3076.25
3076.25
3076.25
3076.25
3076.25
3076.25
3076.25
3076.25
3076.25
3076.25
3076.25

80,614
0
0
0
80,614

Site Clearance
work cannot be
completed to
programme,
resulting in late
delivery of SPP1

3076.25

80,613.72
80,613.72

Current PO Commitment = 133,616

0
0
189,000
0
189,000

14058.4

353,260
29,867
1,945,407
0
2,328,533

8203.33

Trended on Actuals

PO Commitment = 45,504

-176,634
-23,246
22,892
-87,888
-264,876

8203.33

#VALUE!
#VALUE!
0
0
#VALUE!

689,566
74,392
2,521,392
0
3,285,349

689,565.65

74,391.65
2,521,392.00

3,285,349.30

25,297
-1,784
0
0
23,513

PO Commitment = 212,466 + 6k
Data Coms PO to be placed

324,213.00

To Go

59,496
-23,958
0
0
35,538

311,578
0
311,578

EAC Movement
From P6

304,641
71,680
0
0
376,321

236,213
-8,203
228,010

Movement
from BAC

304,641.41
71,679.70
376,321.10

324,213.00

PROJECT ASSESMENT MINIMUM Period 8

Minimum YE EAC

189,000

Minimum EAC

Trended on Actuals
Trended on Actuals

324,213
0
324,213

Trended on Actuals
Trended on Actuals

1,429,298
0
1,434,136

Comment

1,429,298.00

No further Team Building Planned

Current PO Value = 69,213 (Nexia


Management) + 15K Excavation of
Pits + 180K Site Investigation Radar
+ 80K Analysis

Carry Over

Trended on Actuals
Trended on Actuals

324,213.00

324,213.00

707,823.32
72,607.30
2,521,392.00
3,301,822.62

1,240,298
0
1,244,445

-382,702
-68,405
-531,839

0
0
-691

#VALUE!
#VALUE!
#VALUE!

928

-1,072

#VALUE!

370,295
0
371,223

110,295
-3,076
106,146

0
0
0

#VALUE!
#VALUE!
#VALUE!

0
0

0
0

0
0

0
0

Carry Over

Minimum EAC

Minimum YE
EAC

Movement
from BAC

Trended on Actuals
Trended on Actuals

#VALUE!
#VALUE!
0
0
#VALUE!

#VALUE!
#VALUE!
0
0
#VALUE!

#VALUE!
#VALUE!
0
0
#VALUE!

EAC
Movement
From P7
#VALUE!
#VALUE!
0
0
#VALUE!

Trended on Actuals

#VALUE!
0
0
0
#VALUE!

#VALUE!
0
0
0
#VALUE!

#VALUE!
0
0
0
#VALUE!

#VALUE!
0
0
0
#VALUE!

Trended on Actuals

#VALUE!
0
0
0
#VALUE!

#VALUE!
0
0
0
#VALUE!

#VALUE!
0
0
0
#VALUE!

#VALUE!
0
0
0
#VALUE!

Trended on Actuals

#VALUE!
0
0
0
#VALUE!

#VALUE!
0
0
0
#VALUE!

#VALUE!
0
0
0
#VALUE!

#VALUE!
0
0
0
#VALUE!

Trended on Actuals

#VALUE!
0
0
0
#VALUE!

#VALUE!
0
0
0
#VALUE!

#VALUE!
0
0
0
#VALUE!

#VALUE!
0
0
0
#VALUE!

Trended on Actuals

#VALUE!
0
0
0
#VALUE!

#VALUE!
0
0
0
#VALUE!

#VALUE!
0
0
0
#VALUE!

#VALUE!
0
0
0
#VALUE!

0
0

0
0

0
0

0
0

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

0
0
#VALUE!
0
#VALUE!

0
0
#VALUE!
0
#VALUE!

0
0
#VALUE!
0
#VALUE!

0
0
#VALUE!
0
#VALUE!

PO Commitment = 212,466 +
6k Data Coms PO to be placed
0

PO Commitment = 45,504
0

Current PO Commitment =
133,616
0
Trended on Actuals

189,000

Current PO Value = 538,798


+ 1m for Crushing Waste +
31K B304 Work Packages +
41.5K Free Release Finger
Print + 2K Bridge Strength +
5K ISO Container Maintenance
Assume no risk realised

189,000

No further Team Building


Planned
Current PO Value = 198,295
+ 12K Data Comms + 20K
Reallign Surface Levels + 57K
Elec Design & Mech Addns +
45K Elec Installation+ 35K
FLT + 3K Trolley Mods
0

Current PO Value = 69,213


(Nexia Management) + 15K
Excavation of Pits + 180K Site
Investigation Radar + 80K
Analysis

324,213
0
324,213

236,213
-8,203
228,010

0
0
0

#VALUE!
#VALUE!
#VALUE!

707,823
72,607
2,332,392
0
3,112,823

-158,376
-25,031
22,892
-87,888
-248,403

18,258
-1,784
0
0
16,473

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

0
0
189,000
0
189,000

PROJECT

Comment

Trended on Actuals
Trended on Actuals

0
0

0
0

0
0

0
0

#VALUE!
0
#VALUE!

#VALUE!
0
#VALUE!

#VALUE!
0
#VALUE!

#VALUE!
0
#VALUE!

#VALUE!
0

#VALUE!
0

#VALUE!
0

#VALUE!
0

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

0
0

0
0

0
0

0
0

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

35/06071 SPP1 Site Clearance


Work Pack

Description

Compressed Version EAC Assesment


Elements

Budget

Period 6

Period 7

YE EAC

EAC

WPS-900

Project Management

Core Team
Expenses
Sub Contract
Contingency
Sub Total

245,145.54
95,638.00
340,783.54

279,344.44
73,464.05
352,808.49

WPS-010

Project Control

Core Team
Expenses
Sub Contract
Contingency
Sub Total

75,026.25
75,026.25

85,874.90
85,874.90

85,874.90
85,874.90

Core Team
Expenses
Sub Contract
Contingency
Sub Total

74,576.00
74,576.00

93,211.29
93,211.29

93,211.29
93,211.29

Core Team
Expenses
Sub Contract
Contingency
Sub Total

44,369.50
44,369.50

22,388.51
22,388.51

Core Team
Expenses
Sub Contract
Contingency
Sub Total

33,387.60
33,387.60

Core Team
Expenses
Sub Contract
Contingency
Sub Total

308,815.10
308,815.10

WPS-020

WPS-030

WPS-040

WPS-050

Engineering & S&RM

Procurement & Sub Contracts

Site Infrastructure Support

Construction management

Movement
from BAC

279,344.44
73,464.05 -

352,808.49

Period 8

YE EAC

Period
Movement
EAC
Movement in
from BAC
EAC
304,641.41
25,296.97
59,495.87
71,679.70 -
1,784.36 -
23,958.30

376,321.10
23,512.61
35,537.56

34,198.90
22,173.95
12,024.95

304,641.41
71,679.70
376,321.10

10,848.65
10,848.65

80,613.72
80,613.72

80,613.72 -

80,613.72 -

18,635.29
18,635.29

94,131.32
94,131.32

94,131.32
94,131.32

22,388.51 -

22,388.51 -

21,980.99
21,980.99

16,120.55
16,120.55

16,120.55 -

16,120.55 -

15,502.89
15,502.89

15,502.89 -

15,502.89 -

17,884.71
17,884.71

15,936.76
15,936.76

15,936.76
15,936.76

188,405.13
188,405.13

188,405.13 -

188,405.13 -

120,409.97
120,409.97

192,232.29
192,232.29

YE EAC
#VALUE!
#VALUE!

#VALUE!

EAC
#VALUE!
#VALUE!

#VALUE!

Period
Movement in
EAC
#VALUE!
#VALUE!

#VALUE!

Movement
from BAC
#VALUE!
#VALUE!

#VALUE!

5,261.18
5,261.18

5,587.47
5,587.47

#VALUE!
#VALUE!

#VALUE!
#VALUE!

#VALUE!
#VALUE!

#VALUE!
#VALUE!

920.03
920.03

19,555.32
19,555.32

#VALUE!
#VALUE!

#VALUE!
#VALUE!

#VALUE!
#VALUE!

#VALUE!
#VALUE!

6,267.96 -

6,267.96 -

28,248.95
28,248.95

#VALUE!
#VALUE!

#VALUE!
#VALUE!

#VALUE!
#VALUE!

#VALUE!
#VALUE!

433.87 -

433.87 -

17,450.84
17,450.84

#VALUE!
#VALUE!

#VALUE!
#VALUE!

#VALUE!
#VALUE!

#VALUE!
#VALUE!

192,232.29
192,232.29

3,827.15 -

3,827.15 -

116,582.81
116,582.81

#VALUE!
#VALUE!

#VALUE!
#VALUE!

#VALUE!
#VALUE!

#VALUE!
#VALUE!

WPS-070

B388 Refurbishment

Core Team
Expenses
Sub Contract
Contingency
Sub Total

105,000.00
8,203.33
113,203.33

218,466.00
218,466.00

218,466.00
-
218,466.00

113,466.00
8,203.33
105,262.67

218,466.00
218,466.00

218,466.00
218,466.00

113,466.00
8,203.33
105,262.67

WPS-080

Portakabins Demolition

Core Team
Expenses
Sub Contract
Contingency
Sub Total

72,000.00
72,000.00

45,504.00
45,504.00

45,504.00 -

45,504.00 -

26,496.00
26,496.00

45,504.00
45,504.00

45,504.00
45,504.00

26,496.00
26,496.00

WPS-090

B262 Demolition

Core Team
Expenses
Sub Contract
Contingency
Sub Total

161,500.00
161,500.00

133,616.00
133,616.00

133,616.00 -

133,616.00 -

27,884.00
27,884.00

133,616.00
133,616.00

133,616.00
133,616.00

27,884.00
27,884.00

WPS-100

B304 Demolition

Core Team
Expenses
Sub Contract
Contingency
Sub Total

84,879.20

1,812,000.00

68,405.48
1,965,284.68

4,838.49

1,429,298.00

1,434,136.49

4,838.49

1,429,298.00

1,434,136.49

691.21
691.21

-
-
-

80,731.92
382,702.00
68,405.48
531,839.40

-
-
-

80,040.71
382,702.00
68,405.48
531,148.19

4,147.28

1,240,298.00

1,244,445.28

4,147.28 -

1,429,298.00

1,433,445.28 -

#VALUE!
#VALUE!
#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!

#VALUE!
#VALUE!

#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!

WPS-110

B358 Refurbishment

Core Team
Expenses
Sub Contract
Contingency
Sub Total

2,000.00
260,000.00
3,076.25
265,076.25

927.60
370,295.00
371,222.60

927.60 -
370,295.00
-
371,222.60

1,072.40
110,295.00
3,076.25
106,146.35

927.60
370,295.00
371,222.60

927.60
370,295.00
371,222.60

1,072.40
110,295.00
3,076.25
106,146.35

#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!

WPS-120

Site Investigation

Core Team
Expenses
Sub Contract
Contingency
Sub Total

88,000.00
8,203.33
96,203.33

324,213.00
324,213.00

324,213.00
-
324,213.00

236,213.00
8,203.33
228,009.67

324,213.00
324,213.00

324,213.00
324,213.00

236,213.00
8,203.33
228,009.67

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

Total

Project Bottom Line

Core Team
Expenses
Sub Contract
Contingency
Grand Total

866,199.19

97,638.00
2,498,500.00

87,888.39
3,550,225.58

176,633.54
23,246.35
22,892.00
87,888.39
264,876.28

707,823.32

72,607.30
2,332,392.00

3,112,822.62

-
-

-
-

158,375.87
25,030.70
22,892.00
87,888.39
248,402.96

Printed at 4:27 PM on the 7/27/2013

689,565.65

74,391.65
2,521,392.00

3,285,349.30

689,565.65

74,391.65
2,521,392.00

3,285,349.30

-
-

-
-

707,823.32

72,607.30 -
2,521,392.00

3,301,822.62

18,257.67
1,784.36
16,473.32

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

160521524.xlsx.ms_office

160521524.xlsx.ms_office

35.11.12.35025.03000.35/06071 Sludge Packaging Plant 1 - Site Clearance


Forecast Spend Profile - EAC Minimum
Period 9 Report
PERIOD 9 EAC ASSESMENT ISSUED FOR APPROVAL
90,000

1
Site Investigation

80,000

Demolition

Refurbishment

70,000

Core Team
Cumulative Total

1
60,000
1
50,000

1
40,000
0
30,000
0
20,000

10,000

0
Period 1

Period 2

Period 3

Period 4

Period 5

Period 6

Period 7

Period 8

Period 9

Period 10

Period 11

Period 12

Carry Over

Current Period
WPSS

Description

Period 1

Period 2

Period 3

Period 4

Period 5

Period 6

Period 7

Period 8

Period 9

Period 10

Period 11

Period 12

WPS-010
WPS-020
WPS-030
WPS-040
WPS-050
WPS-070
WPS-080
WPS-090
WPS-100
WPS-110
WPS-120
WPS-900

Project Control
Engineering
Procurement
Site Infrastructure
Construction Management
B388 Refurbishment
B816 D&D
B262 D&D
B304 D&D
B358 Refurbishment
Site Investigation
Project Management

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Core Team
Refurbishment
Demolition
Site Investigation
Total Period
Cumulative Total

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Period 1

Period 2

Period 3

Period 4

Period 5

Period 6

Period 7

Period 8

Period 9

Period 10

Period 11

Period 12

Carry Over

80,000

0
0
80,000
0
80,000
#VALUE!

ACWP

ETC

YE EAC

EAC

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

ACWP

ETC

YE EAC

EAC

Previous Period
WPSS

Description

WPS-010
WPS-020
WPS-030
WPS-040
WPS-050
WPS-070
WPS-080
WPS-090
WPS-100
WPS-110
WPS-120
WPS-900

Project Control
Engineering
Procurement
Site Infrastructure
Construction Management
B388 Refurbishment
B816 D&D
B262 D&D
B304 D&D
B358 Refurbishment
Site Investigation
Project Management
Core Team
Refurbishment
Demolition
Site Investigation
Total Period
Cumulative Total

1,623
7,085
0
1,110
0
2,227
0
0
427
0
0
6,824

10,562
8,035
4,530
1,582
34,992
11,106
0
0
100
928
0
10,685

3,906
5,261
1,899
1,328
22,135
10,111
1,000
0
417
231
11,000
20,878

4,856
6,938
0
2,067
15,734
9,511
0
0
15,814
15,865
1,276
17,013

10,757
2,748
2,248
1,110
12,749
14,923
0
743
11,319
23,428
359
22,624

5,380
16,551
0
1,600
18,857
101,320
0
0
94,470
45,811
0
28,998

460
11,273
0
1,355
12,143
56,413
0
0
105,408
51,482
0
50,046

7,339
5,090
2,559
3,292
13,849
38,321
0
0
136,563
31,646
0
32,324

10,477
7,063
1,218
3,778
20,509
3,141
14,361
0
329,368
87,166
5,016
46,240

6,589
10,734
844
1,664
10,473
0
42,970
0
289,257
109,777
23,618
25,468

8,785
10,449
1,125
2,219
14,120
0
0
0
299,797
36,311
13,849
27,353

12,640
14,990
1,688
3,328
21,257
0
0
134,451
323,250
32,641
19,839
55,224

16,641
2,227
427
0
19,295
19,295

70,386
12,034
100
0
82,521
101,816

55,407
10,343
1,417
11,000
78,167
179,983

46,608
25,377
15,814
1,276
89,074
269,057

52,235
38,352
12,062
359
103,007
372,064

71,386
147,131
94,470
0
312,987
685,050

75,277
107,895
105,408
0
288,580
973,630

64,454
69,967
136,563
0
270,984
1,244,614

89,285
90,307
343,729
5,016
528,338
1,772,952

55,771
109,777
332,227
23,618
521,393
2,294,345

64,050
36,311
299,797
13,849
414,008
2,708,353

109,127
32,641
457,701
19,839
619,309
3,327,662

Carry Over

189,000

0
0
189,000
0
189,000
3,516,662

44,881.35
62,979.91
11,236.78
13,443.66
130,459.16
243,934.25
1,000.48
742.69
364,518.39
169,391.12
12,634.72
189,391.96

38,491.26
43,235.40
4,874.84
10,988.91
66,359.28
3,140.69
57,330.41
134,451.00
1,430,672.93
265,895.75
62,322.00
154,284.96

83,372.61
106,215.32
16,111.62
24,432.58
196,818.44
247,074.94
58,330.89
135,193.69
1,606,191.32
435,286.87
74,956.72
343,676.92

83,372.61
106,215.32
16,111.62
24,432.58
196,818.44
247,074.94
58,330.89
135,193.69
1,795,191.32
435,286.87
74,956.72
343,676.92

452,393
413,325
366,262
12,635
1,244,614
1,244,614

318,235
269,036
1,622,454
62,322
2,272,047
2,272,047

770,627
682,362
1,799,716
74,957
3,327,662
3,327,662

770,627
682,362
1,988,716
74,957
3,516,662
3,516,662

Period Movment
WPSS

Description

Period 1

Period 2

Period 3

Period 4

Period 5

Period 6

Period 7

Period 8

Period 9

Period 10

Period 11

Period 12

ACWP

ETC

YE EAC

EAC

WPS-010
WPS-020
WPS-030
WPS-040
WPS-050
WPS-070
WPS-080
WPS-090
WPS-100
WPS-110
WPS-120
WPS-900

Project Control
Engineering
Procurement
Site Infrastructure
Construction Management
B388 Refurbishment
B816 D&D
B262 D&D
B304 D&D
B358 Refurbishment
Site Investigation
Project Management

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

0
0
0
0
0
0
0
80,000
-189,000
0
0
0

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Core Team
Refurbishment
Demolition
Site Investigation
Total Period
Cumulative Total

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

0
0
-109,000
0
-109,000
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

\\vboxsrv\conversion_tmp\scratch_1\160521524.xlsx.ms_office

Carry Over

SPP1 - Phil Waddicor


Sludge Packaging Plant 1 - Site Clearance
2550
35/06071
2,550
1,000

Original
Processing
waste and
management
costs

N/A
N/A
CCR: Approved Baseline Update Addition

Carry Over
Totals
Opportunities

3,550

Opportunities Totals
Overall Project
Totals
AFC (P12)

0
3,550
3,285

SPP1 - Site Clearance


3577 EAC Business Objects

N/A
0

-265

N/A
CCR00186_01_BCP Completed, FCN Approved
and implemented

Current trend to total forecast based on efficienies


observed to date. Potential overspends amount to
145,746 excluding Schedule Carry Over Listed
below. Potential Underspends ammount to
599,533.
Increased forecast capacity and efficientcy of
Crushing Machine at B16

-265

0
-265
#VALUE!

#REF!

High - Current level of commitment


made and forecast to be made to
complete both Refurbishment and
demolition contracts including P50
Contingency. Low - As above
excludiong P50 Contingency. Carry
Over - Current forecast carry over for
B304 Waste Crushing Costs based
on Early Start slippage from 5th Sept
to 17th October. This is being
assesed in line with underpinning
detailed Demolition strategy and
crusher capacity.

Performance to date Stuff

160521524.xlsx.ms_office

35.11.12.35025.03000.35/06071 Sludge Packaging Plant 1 - Site Clearance

Reporting Period

Work Pack Specification Sheet 010 Project Control


NTWP 2 Estimate
607100015

Qty
Project Controls
Prof Serv; Constn Manmt; Constn Manmt-Other1 BALANCE
#VALUE!
LINE
Project Controls Manager
#VALUE!
Planning Engineer; ASW/CSW
#VALUE!
Cost Engineer; ASW/CSW
#VALUE!
Activity Sub Total
#VALUE!
Period 1
#VALUE!
Period 2
#VALUE!
Period 3
#VALUE!
Period 4
#VALUE!
Period 5
#VALUE!
Period 6
#VALUE!
Period 7
#VALUE!
Period 8
#VALUE!
Period 9
#VALUE!
Period 10
#VALUE!
Period 11
#VALUE!
Period 12
#VALUE!
Step Assesment Calculation
#VALUE!

P10

Prepared By
PO Rate

Actual
Quantity

UOM

TQ Rate

Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

UOM

TQ Rate

PO Rate

Actual
Quantity

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Effort

14,501.25
12,535.00
14,259.00
41,295.25
2,601.60
3,138.44
3,923.05
3,262.32
3,303.62
3,923.05
3,262.32
3,303.62
4,088.23
2,312.53
3,262.32
4,914.13
41,295.25

CSW Balance
Line

33,731.00

33,731.00
2,125.05
2,563.56
3,204.45
2,664.75
2,698.48
3,204.45
2,664.75
2,698.48
3,339.37
1,888.94
2,664.75
4,013.99
33,731.00

Other Costs

Grand Total

33,731.00
14,501.25
12,535.00
14,259.00
75,026.25
4,726.65
5,702.00
7,127.49
5,927.07
6,002.10
7,127.49
5,927.07
6,002.10
7,427.60
4,201.47
5,927.07
8,928.12
75,026.25

Physical
Progress

Weighted
Progress

80.20%
80.20%
80.20%
80.20%
80.20%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
0.00%
0.00%
80.20%

36.06%
15.50%
13.40%
15.24%
80.20%
6.30%
7.60%
9.50%
7.90%
8.00%
9.50%
7.90%
8.00%
9.90%
5.60%
0.00%
0.00%
80.20%

Weighting

Physical
Progress

Weighted
Progress

100.00%

80.20%

80.20%

Weighting
44.96%
19.33%
16.71%
19.01%
100.00%
6.30%
7.60%
9.50%
7.90%
8.00%
9.50%
7.90%
8.00%
9.90%
5.60%
7.90%
11.90%

BCWP

27,052.26
11,630.00
10,053.07
11,435.72
60,171.05
4,726.65
5,702.00
7,127.49
5,927.07
6,002.10
7,127.49
5,927.07
6,002.10
7,427.60
4,201.47
60,171.05

aw128
ACWP

Comments

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Grand Total WPSS 010

P3e Activity

P3e Cost Element and Description

Qty

Effort

CSW Balance
Line

Other Costs

Grand Total

BCWP

ACWP

Comments

NTWP2
Estimate
607100015

Notes

Project Controls

Reporting Period General Comment


P1
P2
P3
P4
Actual spend running to plan
P5
P6
P7
P8
P9
P10
P11
P12

Date Printed 7/27/2013 4:27 PM

#VALUE!

Hrs

#VALUE!

#VALUE!

#VALUE!

41,295.25

33,731.00

75,026.25

#VALUE!

Hrs

#VALUE!

#VALUE!

#VALUE!

41,295.25

33,731.00

75,026.25

Opportunities

Threats

100.00%

#VALUE!

60,171.05

#VALUE!

60,171.05

#VALUE!

Issues

Improve systems and reduce future costs

Page 14 of 26

File Name 160521524.xlsx.ms_office and Tab Reference WPSS 010

160521524.xlsx.ms_office

35.11.12.35025.03000.35/06071 Sludge Packaging Plant 1 - Site Clearance

Reporting Period

Work Pack Specification Sheet 020 Engineering


NTWP 2 Estimate
607100025

Qty
Engineering & S&RM Support to Construction Team
Pro Ser; Dsgn Spt; Dsgn Ser, Gen Dsgn Ac-Other1 BALANCE LINE
Civil / Structural / Architectural Engineer
750.0
C,E &I Engineer
750.0
Safety/Environment Adviser
325.0
Mechanical Engineer; Design
325.0
Quality Manager; ASW/CSW
100.0
Safety/Environmental Manager; ASW/CSW
325.0
Activity Sub Total
1,825.0
Period 1
115.0
Period 2
138.7
Period 3
173.4
Period 4
144.2
Period 5
146.0
Period 6
173.4
Period 7
144.2
Period 8
146.0
Period 9
180.7
Period 10
102.2
Period 11
144.2
Period 12
217.2
Step Assesment Calculation
1,825.0

Prepared By

UOM

Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs

P10

TQ Rate

28.35
28.17
24.51
27.52
28.52
27.53
38.96
38.96
38.96
38.96
38.96
38.96
38.96
38.96
38.96
38.96
38.96
38.96
38.96
38.96

PO Rate

40.86
40.86
40.86
40.86
40.86
40.86
40.86
40.86
40.86
40.86
40.86
40.86
40.86
40.86

Actual
Quantity
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Effort

21,262.50
21,127.50
7,965.75
8,944.00
2,852.00
8,947.25
71,099.00
4,479.24
5,403.52
6,754.41
5,616.82
5,687.92
6,754.41
5,616.82
5,687.92
7,038.80
3,981.54
5,616.82
8,460.78
71,099.00

CSW Balance
Line

3,477.00

3,477.00
219.05
264.25
330.32
274.68
278.16
330.32
274.68
278.16
344.22
194.71
274.68
413.76
3,477.00

Other Costs

Grand Total

3,477.00
21,262.50
21,127.50
7,965.75
8,944.00
2,852.00
8,947.25
74,576.00
4,698.29
5,667.78
7,084.72
5,891.50
5,966.08
7,084.72
5,891.50
5,966.08
7,383.02
4,176.26
5,891.50
8,874.54
74,576.00

Physical
Progress

Weighted
Progress

80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
0.00%
0.00%
80.20%

3.74%
22.87%
22.72%
8.57%
9.62%
3.07%
9.62%
80.20%
6.30%
7.60%
9.50%
7.90%
8.00%
9.50%
7.90%
8.00%
9.90%
5.60%
0.00%
0.00%
80.20%

Weighting

Physical
Progress

Weighted
Progress

100.00%

80.20%

80.20%

Weighting
4.66%
28.51%
28.33%
10.68%
11.99%
3.82%
12.00%
100.00%
6.30%
7.60%
9.50%
7.90%
8.00%
9.50%
7.90%
8.00%
9.90%
5.60%
7.90%
11.90%

BCWP

2,788.55
17,052.53
16,944.26
6,388.53
7,173.09
2,287.30
7,175.69
59,809.95
4,698.29
5,667.78
7,084.72
5,891.50
5,966.08
7,084.72
5,891.50
5,966.08
7,383.02
4,176.26
59,809.95

aw128
ACWP

Comments

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Grand Total WPSS 010

P3e Activity

P3e Cost Element and Description

Qty

UOM

TQ Rate

PO Rate

Actual
Quantity

Effort

CSW Balance
Line

Other Costs

Grand Total

BCWP

ACWP

Comments

NTWP2
Estimate
607100025

Notes

Engineering & S&RM Support to Construction Team

Reporting Period General Comment


P1
P2
P3
P4
P5
P6
P7
P8
P9
P10
P11
P12

Date Printed 7/27/2013 4:27 PM

1,825.0

Hrs

38.96

40.86

#VALUE!

71,099.00

3,477.00

74,576.00

1,825.0

Hrs

38.96

40.86

#VALUE!

71,099.00

3,477.00

74,576.00

Opportunities

Threats

Page 15 of 26

100.00%

80.20%

59,809.95

#VALUE!

59,809.95

#VALUE!

Issues

File Name 160521524.xlsx.ms_office and Tab Reference WPSS 020

160521524.xlsx.ms_office

35.11.12.35025.03000.35/06071 Sludge Packaging Plant 1 - Site Clearance

Reporting Period

Work Pack Specification Sheet 030 Procurement


NTWP 2 Estimate
607100035

P3e Activity

Qty
Procurement & Sub Contracts Support
Prof Services; Finance; Accounting-Other1
Procurement Manager
Legal Officer
Procurement Assistant; ASW/CSW
Activity Sub Total
Period 1
Period 2
Period 3
Period 4
Period 5
Period 6
Period 7
Period 8
Period 9
Period 10
Period 11
Period 12
Step Assesment Calculation

P3e Cost Element and Description

200
200
750
1,150
72
87
109
91
92
109
91
92
114
64
91
137
1,150

Qty

UOM

Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs

Prepared By
TQ Rate

UOM

P10

40.49
38.67
16.35
24.43
24.43
24.43
24.43
24.43
24.43
24.43
24.43
24.43
24.43
24.43
24.43
24.43
24.43

PO Rate

38.58
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

38.58

TQ Rate

PO Rate

Actual
Quantity
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Effort

Actual
Quantity

8,098.00
7,734.00
12,262.50
28,094.50
1,769.95
2,135.18
2,668.98
2,219.47
2,247.56
2,668.98
2,219.47
2,247.56
2,781.36
1,573.29
2,219.47
3,343.25
28,094.50

CSW Balance
Line

16,275.00

16,275.00
1,025.33
1,236.90
1,546.13
1,285.73
1,302.00
1,546.13
1,285.73
1,302.00
1,611.23
911.40
1,285.73
1,936.73
16,275.00

Effort

CSW Balance
Line

Other Costs

Other Costs

Grand Total

16,275.00
8,098.00
7,734.00
12,262.50
44,369.50
2,795.28
3,372.08
4,215.10
3,505.19
3,549.56
4,215.10
3,505.19
3,549.56
4,392.58
2,484.69
3,505.19
5,279.97
44,369.50

Grand Total

Physical
Progress

Weighted
Progress

80.20%
80.20%
80.20%
80.20%
80.20%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
0.00%
0.00%
80.20%

29.42%
14.64%
13.98%
22.17%
80.20%
6.30%
7.60%
9.50%
7.90%
8.00%
9.50%
7.90%
8.00%
9.90%
5.60%
0.00%
0.00%
80.20%

Weighting

Physical
Progress

Weighted
Progress

100.00%

80.20%

80.200%

Weighting
36.68%
18.25%
17.43%
27.64%
100.00%
6.30%
7.60%
9.50%
7.90%
8.00%
9.50%
7.90%
8.00%
9.90%
5.60%
7.90%
11.90%

BCWP

13,052.55
6,494.60
6,202.67
9,834.53
35,584.34
2,795.28
3,372.08
4,215.10
3,505.19
3,549.56
4,215.10
3,505.19
3,549.56
4,392.58
2,484.69
35,584.34

BCWP

aw128
ACWP

Comments

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

ACWP

Comments

NTWP2
Estimate
607100035

Notes

Procurement & Sub Contracts Support

Reporting Period General Comment


P1
P2
P3
P4
Leagal and commercial will not book to job
P5
P6
P7
P8
P9
P10
P11
P12

Date Printed 7/27/2013 4:27 PM

1,150

Hrs

24.43

38.58

#VALUE!

28,094.50

16,275.00

44,369.50

1,150

Hrs

24.43

38.58

#VALUE!

28,094.50

16,275.00

44,369.50

Opportunities

None

Page 16 of 26

100.00%

80.20%

80.200%

35,584.34

#VALUE!

35,584.34

#VALUE!

Threats

Issues

None

Raise trend to remove budget - 15,832

File Name 160521524.xlsx.ms_office and Tab Reference WPSS 030

160521524.xlsx.ms_office

35.11.12.35025.03000.35/06071 Sludge Packaging Plant 1 - Site Clearance

Reporting Period

Work Pack Specification Sheet 040 Site Infrastructure Support


NTWP 2 Estimate
607100045

P3e Activity

Qty
Site Infrastructure Support
Safety/Environmental Manager
Health Physics Engineer
Ops Support Mgr
Project Manager
Activity Sub Total
Period 1
Period 2
Period 3
Period 4
Period 5
Period 6
Period 7
Period 8
Period 9
Period 10
Period 11
Period 12
Step Assesment Calculation

P3e Cost Element and Description

10
20
20
750
800
50
61
76
63
64
76
63
64
79
45
63
95
800

Qty

UOM
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs

TQ Rate

UOM

36.22
24.63
35.89
42.42
41.73
41.73
41.73
41.73
41.73
41.73
41.73
41.73
41.73
41.73
41.73
41.73
41.73
41.73

PO Rate

TQ Rate

36.22
24.63
35.89
42.42
41.73
41.73
41.73
41.73
41.73
41.73
41.73
41.73
41.73
41.73
41.73
41.73
41.73
41.73

PO Rate

P10

Prepared By
Actual
Quantity
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Effort

Actual
Quantity

362.20
492.60
717.80
31,815.00
33,387.60
2,103.42
2,537.46
3,171.82
2,637.62
2,671.01
3,171.82
2,637.62
2,671.01
3,305.37
1,869.71
2,637.62
3,973.12
33,387.60

CSW Balance
Line

Effort

CSW Balance
Line

Other Costs

Other Costs

Grand Total

362.20
492.60
717.80
31,815.00
33,387.60
2,103.42
2,537.46
3,171.82
2,637.62
2,671.01
3,171.82
2,637.62
2,671.01
3,305.37
1,869.71
2,637.62
3,973.12
33,387.60

Grand Total

Physical
Progress

Weighted
Progress

80.20%
80.20%
80.20%
80.20%
80.20%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
156.57%
0.00%
0.00%
0.00%
80.20%

0.87%
1.18%
1.72%
76.42%
80.20%
6.30%
7.60%
9.50%
7.90%
8.00%
9.50%
7.90%
8.00%
15.50%
0.00%
0.00%
0.00%
80.20%

Weighting

Physical
Progress

Weighted
Progress

Weighting
1.08%
1.48%
2.15%
95.29%
100.00%
6.30%
7.60%
9.50%
7.90%
8.00%
9.50%
7.90%
8.00%
9.90%
5.60%
7.90%
11.90%

BCWP

290.48
395.07
575.68
25,515.63
26,776.86
2,103.42
2,537.46
3,171.82
2,637.62
2,671.01
3,171.82
2,637.62
2,671.01
5,175.08
26,776.86

BCWP

aw128
ACWP
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

ACWP

Comments
Cost Saving
Cost Saving
Cost Saving
Apportioned Effort DW 14/10

Comments

NTWP2
Estimate
607100045

Notes

Reporting Period General Comment


P1
P2
P3
P4
P5
P6
P7
P8
P9
P10
P11
P12

Date Printed 7/27/2013 4:27 PM

Site Infrastructure Support

800

Hrs

41.73

41.73

#VALUE!

33,387.60

33,387.60

100.00%

80.20%

80.20%

26,776.86

#VALUE!

800

Hrs

41.73

41.73

#VALUE!

33,387.60

33,387.60

100.00%

80.20%

80.20%

26,776.86

#VALUE!

Opportunities

Threats

Page 17 of 26

Issues

File Name 160521524.xlsx.ms_office and Tab Reference WPSS 040

160521524.xlsx.ms_office

35.11.12.35025.03000.35/06071 Sludge Packaging Plant 1 - Site Clearance

Reporting Period

Work Pack Specification Sheet 050 Construction Management


NTWP 2 Estimate
607100055

P3e Activity

Qty
Construction Management
Prof Services; Finance; Accounting-Other1 BALANCE LINE
Construction Manager
Safety/Environment Adviser
Construction Team Leader; sub con
Construction Engineer
Quality Assurance Engineer
Project Manager
Project Manager; ASW/CSW
Construction Engineer; ASW/CSW
Activity Sub Total
Period 1
Period 2
Period 3
Period 4
Period 5
Period 6
Period 7
Period 8
Period 9
Period 10
Period 11
Period 12
Step Assesment Calculation

P3e Cost Element and Description

2,025
600
625
75
150
150
1,380
2,920
7,925
499
11
14
12
12
14
12
12
15
8
12
18
640

Qty

UOM

Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs
Hrs

TQ Rate

UOM

38.67
24.51
30.00
24.63
38.67
42.42
32.24
20.37
38.97
38.97
2,058.77
2,058.77
2,058.77
2,058.77
2,058.77
2,058.77
2,058.77
2,058.77
2,058.77
2,058.77
2,058.77
482.66

PO Rate

TQ Rate

38.97
38.97
2,058.77
2,058.77
2,058.77
2,058.77
2,058.77
2,058.77
2,058.77
2,058.77
2,058.77
2,058.77
2,058.77
482.66

PO Rate

P10

Prepared By
Actual
Quantity

Effort

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

79,070.00
78,306.75
14,706.00
18,750.00

1,847.25

5,800.50

6,363.00
44,491.20
59,480.40
308,815.10
19,455.35
23,469.95
29,337.43
24,396.39
24,705.21
29,337.43
24,396.39
24,705.21
30,572.69
17,293.65
24,396.39
36,749.00
308,815.10

Actual
Quantity

Effort

CSW Balance
Line

CSW Balance
Line

Other Costs

Other Costs

aw128

Physical
Progress

Weighted
Progress

BCWP

ACWP

80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
156.57%
0.00%
0.00%
0.00%
80.20%

20.53%
20.34%
3.82%
4.87%
0.48%
1.51%
1.65%
11.55%
15.45%
80.20%
6.30%
7.60%
9.50%
7.90%
8.00%
9.50%
7.90%
8.00%
15.50%
0.00%
0.00%
0.00%
80.20%

63,414.14
62,802.01
11,794.21
15,037.50

1,481.49

4,652.00

5,103.13
35,681.94
47,703.28
247,669.71
19,455.35
23,469.95
29,337.43
24,396.39
24,705.21
29,337.43
24,396.39
24,705.21
47,866.34

247,669.71

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Weighting

Physical
Progress

Weighted
Progress

BCWP

ACWP

Grand Total

Weighting

79,070.00
78,306.75
14,706.00
18,750.00

1,847.25

5,800.50

6,363.00
44,491.20
59,480.40
308,815.10
19,455.35
23,469.95
29,337.43
24,396.39
24,705.21
29,337.43
24,396.39
24,705.21
30,572.69
17,293.65
24,396.39
36,749.00
308,815.10

25.60%
25.36%
4.76%
6.07%
0.60%
1.88%
2.06%
14.41%
19.26%
100.00%
6.30%
7.60%
9.50%
7.90%
8.00%
9.50%
7.90%
8.00%
9.90%
5.60%
7.90%
11.90%

Grand Total

Comments

Comments

NTWP2
Estimate
607100055

Notes

Construction Management

Reporting Period General Comment


P1
P2
P3
P4
Construction budgets not yet being used - refurb under way
P5
P6
P7
P8
P9
P10
P11
P12

Date Printed 7/27/2013 4:27 PM

7,925

Hrs

38.97

38.97

#VALUE!

308,815.10

308,815.10

100.00%

80.20%

80.20%

247,669.71

#VALUE!

7,925

Hrs

38.97

38.97

#VALUE!

308,815.10

308,815.10

100.00%

80.20%

80.20%

247,669.71

#VALUE!

Opportunities

None

Page 18 of 26

Threats

Issues

May be needed

Raise Trend to remove Budget (47,466)Bennet Wace to Advise

File Name 160521524.xlsx.ms_office and Tab Reference WPSS 050

160521524.xlsx.ms_office

35.11.12.35025.03000.35/06071 Sludge Packaging Plant 1 - Site Clearance

Reporting Period

Work Pack Specification Sheet 070 B388 Refurbishment


AMEC Quotation 153A - B388 Refurbishment

Qty

Quanitity
Tracking

UOM

1
2

Unknown balance to make grand total from sheet not supllied


Unknown Line Item

3
4

Lighting & Small Power - Electricians


Lighting & Small Power - Materials

86

hrs

Yes
N/a

5
6
7

Heating & Ventilation - Ricurculation and fresh air chiller units


Remove roof extract fans and re-connect ceiling vents - Effort
Electic wall mounted convector heater units

8
54
6

off
hrs
off

Relocate office funiture - effort

172

9
10
11

Clean roof area - scaffold errect & Strip effort


Scaffold Hire
Clean Roof - Effort

108
40
86

P3e Activity

Prepared By
Actual
Quantity

N/a
N/a

Prelims Pro
Rata

Estimate

Bucknal Austin
Pro Rata

Grand Total

Weighting

Physical
Progress

Weighted
Progress

BCWP

660.83
28,000.00

191.64
8,120.00

363.64
363.64

1,216.11
36,483.64

1.5%
45.5%

100.000%
100.000%

1.5%
45.5%

1,216.11
36,483.64

86
0

2,269.24
500.00

658.08
145.00

363.64
363.64

3,290.96
1,008.64

4.1%
1.3%

100.000%
100.000%

4.1%
1.3%

3,290.96
1,008.64

Yes
Yes
Yes

8
54
6

8,000.00
1,046.68
1,200.00

2,320.00
303.54
348.00

363.64
363.64
363.64

10,683.64
1,713.85
1,911.64

13.3%
2.1%
2.4%

100.000%
100.000%
100.000%

13.3%
2.1%
2.4%

10,683.64
1,713.85
1,911.64

hrs

Yes

172

2,788.46

808.65

363.64

3,960.75

4.9%

100.000%

4.9%

3,960.75

hrs
Days
Hrs

Yes
N/a
Yes

108
40
86

12,756.96
500.00
1,394.23

3,699.52
145.00
404.33

363.64
363.64
363.64

16,820.11
1,008.64
2,162.19

21.0%
1.3%
2.7%

100.000%
100.000%
100.000%

21.0%
1.3%
2.7%

16,820.11
1,008.64
2,162.19

59,116.40
17,143.76
76,260.16
4,000.00
80,260.16

17,143.76

4,000.00

80,260.16

100.0%

100.000%

80,260.16

Sub Total
+ Prelims @ 29% of base cost
Grand Total
Further Estimate for Bucknall Austin Effort
Overall Total

P3e Cost Element and Description

Design

Lighting &
Small Power

Heating &
Ventilation

Relocate Office
Funiture

Clean Roof

37,699.74
46.97%

4,299.59
5.36%

14,309.13
17.83%

3,960.75
4.93%

19,990.94
24.91%

Activity %
Complete

BCWP

aw128
ACWP

DW Assumed figure
Scaffolding Errected
Scaffolding Erected for 30 Days

ACWP

5,000.00

n/a

n/a

n/a

n/a

n/a

100.000%

5,000.00

#VALUE!

607100080 B388: Rehabilitation of B388


Moving costs-Other1

80,000.00

47.0%

5.4%

17.8%

4.9%

24.9%

100.000%

80,000.00

#VALUE!

607100085 B388: Relocation of Occupants from B816/B841 to B388


Moving costs-Other1
P50 Contingency-Other1

20,000.00
8,203.33

n/a
n/a

n/a
n/a

n/a
n/a

n/a
n/a

n/a
n/a

100.000%
100.000%

20,000.00
8,203.33

#VALUE!
#VALUE!

Comments

3rd Party Design Review Complete


Building Transferred
= Items 1 through to 11

Provision advised by G Griffiths


P50 Contingency

#VALUE!
#VALUE!
113,203.33

Reporting Period General Comment


P1
P2
P3
P4
Progress report completed. Slippage against NTWP2 and Revised Programme.
P5
P6
P7
P8
P9
P10
P11
P12

Comments
Design works
Design Works

607100075 B388: Building Ownership Transfer


Moving costs-Other1

607110000 Internal Resource


607110000 Moving costs-Other1

Notes

P10

100.000%

Opportunities

Accelerate programme with AMEC

113,203.33

#VALUE!

Threats

Issues

Insufficient funds for total scope

Uncerrtainty / poor clarity of total estimated cost

Period Narrative

Date Printed 7/27/2013 4:27 PM

Page 19 of 26

File Name 160521524.xlsx.ms_office and Tab Reference WPSS 070

160521524.xlsx.ms_office

35.11.12.35025.03000.35/06071 Sludge Packaging Plant 1 - Site Clearance

Reporting Period

P10

Prepared By

aw128

Work Pack Specification Sheet 080 Portacabins Decontamination & Demolition


AMEC Quotation 174 - Demolish 7 No Portacabins
1
2
3
Sub Total 11

7
8
Sub Total 2

PROVISION - Scaffolding Access by Hertel


Scaffold Hire- 11wks @ 400/wk
Scaffold Hire Escallation @ 7.5%
Sub Total
Group 1
Group 2
Group 3

Qty

UOM

Quanitity
Tracking

Actual
Quantity

PROV
11
PROV

N/a
wks
N/a

Installation
Hire
N/a

1
11
1

Internal Soft Strip - 4 Ops @ 3d per Cabin x 7 Cabins


Group 1
Group 2
Group 3

756

External Demollition - 4 Ops @ 5.5d per cabin x 7 cabin


Group 1
Group 2
Group 3

1386

Demolish Metal Stairs - 4 Ops for 4 days


Group 1
Group 2
Group 3

144

Fencing - 1.8m Chain Link Fence


Fencing - Straining Post 1 strutt

7
2

Hrs

Cabins

Hrs

Cabins

Hrs

Removal

m
off

Installation
Installation

Group 1
Group 2
Group 3
Sub Total
+ Prelims @ 29% of base cost
Grand Total
Further Estimate for Bucknall Austin Effort
Overall Total

7
2

Prelims Pro
Rata

Estimate

Bucknal Austin
Pro Rata

Grand Total

Weighting

Physical
Progress

Weighted
Progress

BCWP

12,870.00
4,400.00
1,295.25
18,565.25
6,188.42
6,188.42
6,188.42

3,732.30
1,276.00
375.62
5,383.92
1,794.64
1,794.64
1,794.64

450.00
450.00
450.00
1,350.00
450.00
450.00
450.00

17,052.30
6,126.00
2,120.87
25,299.17
8,433.06
8,433.06
8,433.06

33.4%
33.3%
33.3%
33.3%

100%
100%
100%
100%

33.4%
33.4%
33.4%

8,433.06
8,433.06
8,433.06

12,256.27
4,085.42
4,085.42
4,085.42

3,554.32
1,184.77
1,184.77
1,184.77

450.00
150.00
150.00
150.00

16,260.59
5,420.20
5,420.20
5,420.20

21.5%
33.3%
33.3%
33.3%

100%
100%
100%
100%

21.5%
21.5%
21.5%

5,420.20
5,420.20
5,420.20

22,469.83
7,489.94
7,489.94
7,489.94

6,516.25
2,172.08
2,172.08
2,172.08

450.00
150.00
150.00
150.00

29,436.08
9,812.03
9,812.03
9,812.03

38.9%
33.3%
33.3%
33.3%

100%
100%
100%
100%

38.9%
38.9%
38.9%

9,812.03
9,812.03
9,812.03

2,334.53
778.18
778.18
778.18

677.01
225.67
225.67
225.67

450.00
150.00
150.00
150.00

3,461.54
1,153.85
1,153.85
1,153.85

4.6%
33.3%
33.3%
33.3%

100%
100%
100%
100%

4.6%
4.6%
4.6%

1,153.85
1,153.85
1,153.85

138.67
107.14
245.81
81.94
81.94
81.94

40.21
31.07
71.28
23.76
23.76
23.76

450.00
450.00
900.00
300.00
300.00
300.00

628.88
588.21
1,217.09
405.70
405.70
405.70

1.6%
33.3%
33.3%
33.3%

100%
100%
100%
100%

1.6%
1.6%
1.6%

405.70
405.70
405.70

55,871.69
16,202.79
72,074.48
3,900.00
75,974.48

16,202.79

3,600.00

75,674.48

Scaffolding

Internal Strip

External Strip

Metal Stairs

Fencing

25,299.17
33.43%

16,260.59
21.49%

29,436.08
38.90%

3,461.54
4.57%

1,217.09
1.61%

Activity %
Complete

BCWP

ACWP

Comments

ACWP

Comments

607100090 B816/B841: Approval of PMP


Professional Services; Construction Management; Construction Management-Other1

5,000.00

100.00%

5,000.00

#VALUE!

PMP Drafted pending Shepplys inpuit - assumed no change

607100095 B816/B841: Building Transfer Agreement


Moving costs-Other1

5,000.00

100.00%

5,000.00

#VALUE!

B841 STC completed, B816 STc underway

607100100 B816/B841: Pre Operations Survey (M6)


Constn; Survey & Invests; Testing/Comisg-Other1

5,000.00

100.00%

5,000.00

#VALUE!

Complete

607100105 B816/B841: Decontamination & Demoilition of B841/841.1


Decontamination; Demo; Marine Contracts-Other1

19,000.00

33.4%

21.5%

38.9%

4.6%

1.6%

100.0%

19,000.00

#VALUE!

Planned start 25/11/05

607100110 B816/B841: Decontamination & Demoilition of B816/816.1


Decontamination; Demo; Marine Contracts-Other1

19,000.00

33.4%

21.5%

38.9%

4.6%

1.6%

100.0%

19,000.00

#VALUE!

607100115 B816/B841: Decontamination & Demoilition of B816.2/816.3


Decontamination; Demo; Marine Contracts-Other1

19,000.00

33.4%

21.5%

38.9%

4.6%

1.6%

100.0%

19,000.00

#VALUE!

72,000.00

100.0%

72,000.00

#VALUE!

Notes

Reporting Period General Comment


P1
P2
P3
P4
P5
P6
P7
P8
P9
P10
P11
P12
Period Narrative

Date Printed 7/27/2013 4:27 PM

Opportunities

Threats

Page 20 of 26

Issues

File Name 160521524.xlsx.ms_office and Tab Reference WPSS 080

160521524.xlsx.ms_office

35.11.12.35025.03000.35/06071 Sludge Packaging Plant 1 - Site Clearance

Reporting Period

Work Pack Specification Sheet 090 B262 Demolition


PCR Quatation

Qty UOM

Prepared By

Quanitity
Tracking

Actual Qty

Prelims Pro
Rata

Estimate

Bucknal Austin
Pro Rata

1
2
3
4
5

Decommissioning / Demolition of B262


Prepare Safety Documentation / PMP Documentation
Design Access & Produce Drawing for Approval
Carry Radiological Surveys
Prepare Detailed Method Statements

N/a
N/a
N/a
N/a

4,915.20
4,915.20
5,000.00
4,915.20

6
7
8
9
10
11
12

Installation of Access
Mark out scaffold area
Transfer scaffold to work area
Set out scaffold to full external area
Install first lift of scaffold to external area of B262
Install second lift of scaffold to external area of B262
Install third lift of scaffold to external area of B262

X
X
X

m^2
m^2
m^2

N/a
N/a
N/a
Yes
Yes
Yes

0
0
0

1,206.91
965.55
10,877.94
4,337.11
4,337.11
4,144.57

1,666.67
1,666.67
1,666.67
1,666.67
1,666.67
1,666.67

13
14
15
16
17

Removal of Cement Clad Sheets


Spray cladding with PVA solution Internal/External
Remove cladding from west end elevation of B262
Remove cladding from centre of B262
Remove Cladding from east end elevation of B262

7.5
X
X
X

m^3
m^2
m^2
m^2

Yes
Yes
Yes
Yes

0
0
0
0

3,858.48
3,265.99
1,537.84
1,324.38

1,666.67
1,666.67
1,666.67
1,666.67

18
19
20
21
22
23

Removal of Steelwork / Base


Remove purling bars / transfer to wheel abrator
X
Te
Remove structural steelwork & transfer to wheel abrator / remove accessXscaffold
Te
Remove concrete base & transfer to B16 for free release sentancing 1800 m^3
Transfer services if required
X
off
Process Waste
X
Te

Yes
Yes
Yes
Yes
Yes

0
0
0
0
0

2,972.66
8,057.85
19,863.30
748.72
20,233.20

107,477.21

Total Labour Costs


Plant & Equipment
Materials
Grand Total

19,745.60
12.38%

607100130

607100135

607100140

607100145

607100150

607100155

06071TB002

Grand Total

Weighting

Physical
Progress

Weighted
Progress

BCWP

4,915.20
4,915.20
5,000.00
4,915.20

33.3%
33.3%
100.0%
33.3%

100.0%
100.0%
90.0%
100.0%

33.3%
33.3%
90.0%
33.3%

1,800.00
1,800.00
1,800.00
1,800.00
1,800.00
1,800.00

4,673.58
4,432.22
14,344.61
7,803.78
7,803.78
7,611.24

10.0%
9.5%
30.7%
16.7%
16.7%
16.3%

0.0%
0.0%
0.0%
0.0%
0.0%
0.0%

0.0%
0.0%
0.0%
0.0%
0.0%
0.0%

1,800.00
1,800.00
1,800.00
1,800.00

7,325.15
6,732.66
5,004.51
4,791.05

100.0%
40.7%
30.3%
29.0%

0.0%
0.0%
0.0%
0.0%

0.0%
0.0%
0.0%
0.0%

1,666.67
1,666.67
1,666.67
1,666.67
1,666.67

1,800.00
1,800.00
1,800.00
1,800.00
1,800.00

6,439.33
11,524.52
23,329.97
4,215.39
23,699.87

35.8%
64.2%
45.5%
8.2%
46.2%

0.0%
0.0%
0.0%
0.0%
0.0%

0.0%
0.0%
0.0%
0.0%
0.0%

25,000.00

27,000.00

159,477.21

700.0%

aw128
ACWP

4,915.20
4,915.20
4,500.00
4,915.20

Comments

Assumed byu D Watters


Assumed byu D Watters
Assumed byu D Watters
Assumed byu D Watters

159,477.21

PCR Non Qty

607100120

P10

PCR Qty
Tracked
139,731.61
87.62%

BNG Core
Team

P50
Contingency

Activity %
Complete

BCWP

ACWP

Comments

B262: Building Transfer Agreement


Moving costs-Other1
General Expenses; Office Expenses; Administration-Other1

15,000.00
3,780.00

100.0%
100.0%

100.0%
100.0%

15,000.00
3,780.00

#VALUE!
#VALUE!

= 1+ 2 + 3

B262: Pre Operations Survey (M6)


Constn; Survey & Invests; Testing/Comisg-Other1
General Expenses; Office Expenses; Administration-Other1

5,000.00
1,350.00

90.0%
90.0%

90.0%
90.0%

4,500.00
1,215.00

#VALUE!
#VALUE!

=4

B262: Scaffold Errection


General Expenses; Office Expenses; Administration-Other1
Scaffolding (Generally)
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

6,480.00
25,800.00
7,250.00

0.0%
0.0%
0.0%

0.0%
0.0%
0.0%

#VALUE!
#VALUE!
#VALUE!

B262: Spray Cladding with PVA Solution


Construction; Steelwork; Cladding-Other1
General Expenses; Office Expenses; Administration-Other1
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

3,800.00
1,080.00
1,000.00

0.0%
0.0%
0.0%

0.0%
0.0%
0.0%

#VALUE!
#VALUE!
#VALUE!

= 11

B262: Remove Cladding


Construction; Steelwork; Cladding-Other1
General Expenses; Office Expenses; Administration-Other1
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

6,200.00
1,620.00
1,750.00

0.0%
0.0%
0.0%

0.0%
0.0%
0.0%

#VALUE!
#VALUE!
#VALUE!

=12 + 13 + 14

B262: Structural Steel Removal & Remove Scaffold


Constn; Steelwork; Platforms / Stairs-Other1
General Expenses; Office Expenses; Administration-Other1
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

11,200.00
2,700.00
3,250.00

0.0%
0.0%
0.0%

0.0%
0.0%
0.0%

#VALUE!
#VALUE!
#VALUE!

=15 + 16

B262: Foundations Removal & Transfer of Services


Foundations-Other1
General Expenses; Office Expenses; Administration-Other1
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

40,500.00
9,990.00
11,750.00

0.0%
0.0%
0.0%

0.0%
0.0%
0.0%

#VALUE!
#VALUE!
#VALUE!

=17 + 18 + 19

100.0%

2,000.00

#VALUE!
#VALUE!

16.4%

26,495.00

#VALUE!

Team Building: B262 Start Up


General Expenses; Training; Training Courses-Other1

2,000.00

100%

161,500.00

Date Printed 7/27/2013 4:27 PM

Page 21 of 26

= 5+6+7+8+9+10

Provision

File Name 160521524.xlsx.ms_office and Tab Reference WPSS 090

160521524.xlsx.ms_office

35.11.12.35025.03000.35/06071 Sludge Packaging Plant 1 - Site Clearance

Reporting Period

Work Pack Specification Sheet 100 B304 Demolition


PCR Quatation

Qty

UOM Quanitity Tracking

2
3
4

Prepare Safety Documentation / PMP


Design Access scaffold & Produce Drawings
Organise Waste Routes Free release low level

Transfer Orphan Waste from B304 to B206 Cell 2 114

Items

Yes

6
7

Install access scaffold


Prepare crane proposal

m^2
-

Yes

N/a
N/a
N/a

N/a

P10

Prepared By
Plant &
Equipment

Actual Qty

Estimate

Grand Total

Weighting

11,673.60
5,000.00
5,000.00

11,673.60
5,000.00
5,000.00

53.9%
23.1%
23.1%

############

Scaffolding

Physical
Progress
100.0%
100.0%
100.0%

Weighted
Progress
53.9%
23.1%
23.1%

11,673.60
5,000.00
5,000.00

BCWP

ACWP

36,381.20

36,381.20

100.0%

100.0%

36,381.20

61,722.45
5,000.00

61,722.45
5,000.00

92.5%
7.5%

100.0%
100.0%

92.5%
7.5%

61,722.45
5,000.00

aw128
Comments

carry out radiological surveys

off

Yes

5,000.00

5,000.00

100.0%

100.0%

100.0%

5,000.00

10

Remove doors from bays 2,3 & 4

off

Yes

9,780.73

5,878.79

1,878.79

17,538.31

100.0%

100.0%

100.0%

9,780.73

11
12
14

Set up wire saw in bay1


Mark out grid reference for proposed saw cuts
Remove front concrete panel on west elevation bay 11

m^3

Yes

2,110.90
1,055.46
4,221.80

5,878.79
5,878.79
5,878.79

1,878.79
1,878.79
1,878.79

9,868.48
8,813.04
11,979.38

32.2%
28.7%
39.1%

100.0%
100.0%
100.0%

32.2%
28.7%
39.1%

2,110.90
1,055.46
4,221.80

15
16
17

Install wire saw on roof slab in bay 2


Mark out grid reference for proposed saw cuts
Remove roof slab in bay 2

m^3

Yes

1,055.46
1,055.46
4,221.80

5,878.79
5,878.79
5,878.79

1,878.79
1,878.79
1,878.79

8,813.04
8,813.04
11,979.38

29.8%
29.8%
40.5%

100.0%
100.0%
100.0%

29.8%
29.8%
40.5%

1,055.46
1,055.46
4,221.80

18
19
20

Set up wire saw on internal wall in bay 1


Mark out grid reference for proposed saw cuts
Remove internal wall bay 1-2

m^3

Yes

1,055.46
1,055.46
12,665.40

5,878.79
5,878.79
5,878.79

1,878.79
1,878.79
1,878.79

8,813.04
8,813.04
20,422.98

23.2%
23.2%
53.7%

100.0%
100.0%
100.0%

23.2%
23.2%
53.7%

1,055.46
1,055.46
12,665.40

21
22
23

Install wire saw on roof slab in bay 3


Mark out grid reference for proposed saw cuts
Remove roof slab in bay 3

m^3

Yes

1,046.62
1,046.62
4,186.46

5,878.79
5,878.79
5,878.79

1,878.79
1,878.79
1,878.79

8,804.20
8,804.20
11,944.04

29.8%
29.8%
40.4%

100.0%
100.0%
100.0%

29.8%
29.8%
40.4%

1,046.62
1,046.62
4,186.46

24
25
26

Install wire saw on roof slab in bay 4


Mark out grid reference for proposed saw cuts
Remove roof slab in bay 4

m^3

Yes

1,046.62
1,046.62
4,186.46

5,878.79
5,878.79
5,878.79

1,878.79
1,878.79
1,878.79

8,804.20
8,804.20
11,944.04

29.8%
29.8%
40.4%

100.0%
100.0%
100.0%

29.8%
29.8%
40.4%

1,046.62
1,046.62
4,186.46

27
28
29

Set up wire saw on internal wall in bay 2


Mark out grid reference for proposed saw cuts
Remove internal wall bay 2-3

m^3

Yes

1,046.62
1,046.62
12,665.40

5,878.79
5,878.79
5,878.79

1,878.79
1,878.79
1,878.79

8,804.20
8,804.20
20,422.98

23.1%
23.1%
53.7%

100.0%
100.0%
100.0%

23.1%
23.1%
53.7%

1,046.62
1,046.62
12,665.40

30
31
32

Set up wire saw in bay 3


Mark out grid reference for proposed saw cuts
Remove internal wall bay 3-4

m^3

Yes

1,055.46
1,055.46
12,665.40

5,878.79
5,878.79
5,878.79

1,878.79
1,878.79
1,878.79

8,813.04
8,813.04
20,422.98

23.2%
23.2%
53.7%

100.0%
100.0%
100.0%

23.2%
23.2%
53.7%

1,055.46
1,055.46
12,665.40

33
34
35

Set up wire saw on external wall north elevation


Mark out grid reference for proposed saw cuts
Remove external wall north elevation

m^3

Yes

6,332.70
2,110.90
21,109.00

5,878.79
5,878.79
5,878.79

1,878.79
1,878.79
1,878.79

14,090.28
9,868.48
28,866.58

26.7%
18.7%
54.6%

100.0%
100.0%
100.0%

26.7%
18.7%
54.6%

6,332.70
2,110.90
21,109.00

36
37
38

Set up wire saw on external wall south elevation


Mark out grid reference for proposed saw cuts
Remove external; wall south elevation

m^3

Yes

10,554.50
5,277.26
31,663.50

5,878.79
5,878.79
5,878.79

1,878.79
1,878.79
1,878.79

18,312.08
13,034.84
39,421.08

25.9%
18.4%
55.7%

100.0%
100.0%
100.0%

25.9%
18.4%
55.7%

10,554.50
5,277.26
31,663.50

Top section wall revomed

39
40
41

Set up wire saw on external wall east elevation


Mark out grid reference for proposed saw cuts
Remove external; wall east elevation

m^3

Yes

6,332.70
6,332.70
63,061.95

5,878.79
5,878.79
5,878.79

1,878.79
1,878.79
1,878.79

14,090.28
14,090.28
70,819.53

14.2%
14.2%
71.5%

100.0%
100.0%
100.0%

14.2%
14.2%
71.5%

6,332.70
6,332.70
63,061.95

Top Section wall removed

42

Breakout concrete to align floor area in bay 1 with 1

m^3

Yes

31,530.98

5,878.79

1,878.79

39,288.56

100.0%

0.0%

0.0%

43

Remove plant, scaffold & Clear site

10,510.33

5,878.79

1,878.79

18,267.91

100.0%

0.0%

0.0%

N/a

660,966.06

PCR Non Qty

607100160

607100175

06071RM006

607100165

BNG Core
Team

P50
Contingency

Activity %
Complete

BCWP

ACWP

100.00%
100.00%

21,500.00
17,134.65

#VALUE!
#VALUE!

100.00%
100.00%
100.00%
100.00%
100.00%
100.00%

86,000.00
8,203.33
27,165.00
12,315.00
10,605.00
29,667.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

M5 : Alternate D&D B304 Methodology Preparation Excluding Crane Incl Mini HAZOP
Pro Serv; Manmt Consultants; Consultants-Other1 BALANCE LINE
2,208.00
Project Manager; ASW/CSW
1,289.60
Construction Engineer; ASW/CSW
1,629.60

100.00%
100.00%
100.00%

2,208.00
1,289.60
1,629.60

#VALUE!
#VALUE!
#VALUE!

Direct Measure
Direct Measure
Direct Measure

M8: B304 Orphan Waste Mitigation / Alternate Route for Disposal


Decon; Decon & Dplt; Hazardous Deplant-Other1

100,000.00

100.00%

100,000.00

#VALUE!

Direct Measure

B304: Approval B304 PMP (Cat B)


Prof Serv; Constn Manmt; Constn Manmt-Other1
P50 Contingency-Other1

21,500.00
17,134.65

100.00%
100.00%

Comments

= 2+3+4

B304: Orphan Waste Transfer


Decon; Decon & Dplt; Hazardous Deplant-Other1
P50 Contingency-Other1
Safety/Environmental Manager
Waste Management Engineer
Project Manager
Plant Operator (Reactors)

06071RM003

PCR Qty
Tracked

B304: Building Ownership Transfer


Moving costs-Other1

86,000.00
8,203.33
27,165.00
12,315.00
10,605.00
29,667.00

100.00%
100.00%
100.00%
100.00%
100.00%
100.00%

=5 with 50K added by Core


Team by PCR estimate

66,250.00

100.00%

66,250.00

#VALUE!

=6+7

Team Building: B304 Start Up


General Expenses; Training; Training Courses-Other1

2,000.00

100.00%

2,000.00

#VALUE!

CORE TEAM ESTIMATE

607100170

B304: Pre Ops Survey (M6)


Constn; Survey & Invests; Testing/Comisg-Other1

5,000.00

100.00%

5,000.00

#VALUE!

=8

607100180

B304: Remove Bay Doors 2,3 & 4


Decon; Decon & Deplant; Clean Deplant-Other1
P50 Contingency-Other1
Crane Equipment (Generally)
Scaffolding (Generally)
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

9,800.00
3,076.25
1,920.00
1,860.00
3,900.00

100.00%

9,800.00
3,076.25
1,920.00
1,860.00
3,900.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

=10

B304: Remove Concrete Panel West Elevation Bay 1


Decon; Decon & Deplant; Clean Deplant-Other1
P50 Contingency-Other1
Crane Equipment (Generally)
Scaffolding (Generally)
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

4,000.00
3,076.25
1,280.00
1,240.00
2,600.00

4,000.00
3,076.25
1,280.00
1,240.00
2,600.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

=14

B304: Remove Roof Slab Bay 3


Decon; Decon & Deplant; Clean Deplant-Other1
P50 Contingency-Other1
Crane Equipment (Generally)
Scaffolding (Generally)
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

7,000.00
3,076.25
1,920.00
1,860.00
3,900.00

7,000.00
3,076.25
1,920.00
1,860.00
3,900.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

=21+22+23

B304: Remove Roof Slab Bay 4


Decon; Decon & Deplant; Clean Deplant-Other1
P50 Contingency-Other1
Crane Equipment (Generally)
Scaffolding (Generally)
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

7,000.00
3,076.25
1,920.00
1,860.00
3,900.00

7,000.00
3,076.25
1,920.00
1,860.00
3,900.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

=24+25+26

B304: Remove Roof Slab Bay 2


Decon; Decon & Deplant; Clean Deplant-Other1
P50 Contingency-Other1
Crane Equipment (Generally)
Scaffolding (Generally)
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

7,000.00
3,076.25
1,920.00
1,860.00
3,900.00

7,000.00
3,076.25
1,920.00
1,860.00
3,900.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

=15+16+17

B304: Remove Internal Wall Bay 2-3


Decon; Decon & Deplant; Clean Deplant-Other1
P50 Contingency-Other1
Crane Equipment (Generally)
Scaffolding (Generally)
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

14,800.00
3,076.25
3,840.00
3,720.00
7,800.00

14,800.00
3,076.25
3,840.00
3,720.00
7,800.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

=27+28+29

B304: Remove Internal Wall Bay 1-2


Decon; Decon & Deplant; Clean Deplant-Other1
P50 Contingency-Other1
Crane Equipment (Generally)
Scaffolding (Generally)
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

14,800.00
3,076.25
3,840.00
3,720.00
7,800.00

14,800.00
3,076.25
3,840.00
3,720.00
7,800.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

=18+19+20

B304: Remove Internal Wall Bay 3-4


Decon; Decon & Deplant; Clean Deplant-Other1
P50 Contingency-Other1
Crane Equipment (Generally)
Scaffolding (Generally)
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

14,800.00
3,076.25
3,840.00
3,720.00
7,800.00

14,800.00
3,076.25
3,840.00
3,720.00
7,800.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

=30+31+32

B304: Remove External Wall South Elevation


Decon; Decon & Deplant; Clean Deplant-Other1
P50 Contingency-Other1
Crane Equipment (Generally)
Scaffolding (Generally)
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

47,500.00
3,076.25
12,800.00
12,400.00
26,000.00

47,500.00
3,076.25
12,800.00
12,400.00
26,000.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

B304: Remove External Wall North Elevation


Decon; Decon & Deplant; Clean Deplant-Other1
P50 Contingency-Other1
Crane Equipment (Generally)
Scaffolding (Generally)
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

29,600.00
3,076.25
7,680.00
7,440.00
15,600.00

29,600.00
3,076.25
7,680.00
7,440.00
15,600.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

=33+34+35

B304: Remove External Wall East Elevation


Decon; Decon & Deplant; Clean Deplant-Other1
P50 Contingency-Other1
Crane Equipment (Generally)
Scaffolding (Generally)
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

75,700.00
3,076.25
19,840.00
19,220.00
40,300.00

75,700.00
3,076.25
19,840.00
19,220.00
40,300.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

=39+40+41

B304: Remove Plant and Scaffold / Clear Site


Decon; Decon & Deplant; Clean Deplant-Other1
P50 Contingency-Other1
Crane Equipment (Generally)
Scaffolding (Generally)
Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

10,250.00
3,076.25
3,200.00
3,100.00
6,500.00

0.00
1,538.13
1,600.00
1,550.00
3,250.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

=43

B304: Removal B304 Foundations


Foundations-Other1
P50 Contingency-Other1

25,000.00
3,076.25

0.00%

0.00
0.00

#VALUE!
#VALUE!

=42

0.00%

B304: Removal Foundations Spoil


Foundations-Other1
P50 Contingency-Other1

8,000.00
3,076.25

0.00%

0.00
0.00

#VALUE!
#VALUE!

=42

0.00%

1,000,000.00

1,000,000.00

30.00%

300,000.00

#VALUE!

06071TB003

607100185

607100200

607100205

607100190

607100210

607100195

607100215

607100225

607100220

607100230

607100235

607100240

607100245

06071B2001

B304 Waste Crushing 05/06


Decontamination; Demo; Treatment Plants-Other1

100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%
100.00%

0.00%
50.00%
50.00%
50.00%
50.00%

965,284.68

Date Printed 7/27/2013 4:27 PM

125.1%

Page 22 of 26

1,207,944.06

=36+37+38

#VALUE!

File Name 160521524.xlsx.ms_office and Tab Reference WPSS 100

160521524.xlsx.ms_office

ORPHAN WASTE REMOVAL

Orphan Waste Qtys

Qty

UOM

Low Level Lead


Oil Waste
Silica Gel
Uranium
277 Evaporator Roof Plugs
277 Heat Exchangers
277 Charge Tube Coffins

25
25
25
30
4
4
1

Sub Total

off
off
off
off
off
off
off

Moved

% Progress
25
25
25
30
4
4
1

114

114

21.9%
21.9%
21.9%
26.3%
3.5%
3.5%
0.9%

21.93%
21.93%
21.93%
26.32%
3.51%
3.51%
0.88%

Site
Waste
Managem
ent Team
21.9%
21.9%
21.9%
26.3%
3.5%
3.5%
0.9%

% Complete

100.00%

100.0%

%
Weighting

100%
100%
100%
100%
100%
100%
100%

Weighted
Actual
Progress

PCR

44.4%
44.4%
11.1%
100.0%

Summary
Site Waste Team
PCR Richardson
P50 Contingency

79,752.00
86,000.00
8,203.33

100.0%
100.0%
75.0%

79,752.00
86,000.00
6,152.50

Total

173,955.33

98.8%

171,904.50

ilw lead boxes 3of 7 gonenow all; gone

Date Printed 7/27/2013 4:27 PM

Page 23 of 26

File Name 160521524.xlsx.ms_office and Tab Reference WPSS 100 OWR

160521524.xlsx.ms_office

35.11.12.35025.03000.35/06071 Sludge Packaging Plant 1 - Site Clearance

Reporting Period

Work Pack Specification Sheet 110 B358 Refurbishment


PCR Quatation

P10

Prepared By

Qty

UOM

Quanitity
Tracking

Actual Qty

Prelims Pro
Rata

Labour

Plant &
Equipment Pro
Rata

Grand Total

Weighting

Physical
Progress

Weighted
Progress

BCWP

aw128
ACWP

Comments

Prepare Safety Documentation / PMP

N/a

4,915.20

4,915.20

100.0%

100.0%

100.0%

Ref CGS Act ID 248

Design Access Scaffold & Produce Drawings for Approval

N/a

4,915.20

4,915.20

100.0%

100.0%

100.0%

to be advised

4
5

Carry out radiological survey on B358


Carry out Radiological surveys on proposed site for new Rubb Building

N/a
N/a

5,000.00
5,000.00

5,000.00
5,000.00

50.0%
50.0%

100.0%
100.0%

50.0%
50.0%

Ref NFR_LPSERP-035_PROJ_00086
Ref NFR_LPSERP-035_PROJ_00086

Install Access Scaffold

m^2

Yes

12,114.80

2,210.53

3,000.00

17,325.33

100.0%

100.0%

100.0%

8
9
10
11
12

Removal of Existing Scaffold


Remove old Roller Shutter Door
Clean Structural Steelwork
Repair Existing Floor
Apply Resin Coating to floor area

1
1
1
1
1

m^2
off
m^2
m^2
m^2

Yes
Yes
Yes
Yes
Yes

1
1
1
1
0

6,057.40
2,422.96
6,057.40
6,596.40
7,210.80

2,210.53
2,210.53
2,210.53
2,210.53
2,210.53

3,000.00
3,000.00
3,000.00
3,000.00
3,000.00

11,267.93
7,633.49
11,267.93
11,806.93
12,421.33

12.5%
8.5%
12.5%
13.1%
13.8%

100.0%
100.0%
100.0%
100.0%
0.0%

12.5%
8.5%
12.5%
13.1%
0.0%

13

Re-paint structural steel work

m^2

Yes

6,057.40

2,210.53

3,000.00

11,267.93

100.0%

100.0%

100.0%

14

Install new Cladding

m^2

Yes

12,114.80

2,210.53

3,000.00

17,325.33

100.0%

100.0%

100.0%

15

Relay new Floor

m^2

Yes

3,634.44

2,210.53

3,000.00

8,844.97

100.0%

0.0%

0.0%

16

Seal south end of building 50% brick and 50% cladding

m^2

Yes

18,172.20

2,210.53

3,000.00

23,382.73

100.0%

100.0%

100.0%

17

Install new lighting system

off

Yes

0.35

3,531.40

2,210.53

3,000.00

8,741.93

100.0%

35.0%

35.0%

18

Install new shutter door

off

Yes

6,057.40

2,210.53

3,000.00

11,267.93

100.0%

100.0%

100.0%

20
21
22
23
24
25
26

Set out & mark area for proposed ring beam


Carry out pre-work for ring beam
Cast in situ ring beam
Install structural steelwork
Install fabric cover
Install vent
Inspection & Handover

1
1
1
1
1
1
1

JC
JC
m^3
m^3
m^2
off
Doc

Yes
Yes
Yes
Yes
Yes
Yes
Yes

1
1
1
1
1
1
0

3,705.48
4,311.72
18,527.40
18,527.40
6,175.80
1,886.76
245.76

2,210.53
2,210.53
2,210.53
2,210.53
2,210.53
2,210.53
2,210.53

3,000.00
3,000.00
3,000.00
3,000.00
3,000.00
3,000.00
3,000.00

8,916.01
9,522.25
23,737.93
23,737.93
11,386.33
7,097.29
5,456.29

9.9%
10.6%
26.4%
26.4%
12.7%
7.9%
6.1%

100.0%
100.0%
100.0%
100.0%
100.0%
100.0%
0.0%

9.9%
10.6%
26.4%
26.4%
12.7%
7.9%
0.0%

PCR Non Qty

607100255

PCR Qty
Tracked

BNG Core
Team

cladding rails

start 20th due to hot spots

P50
Contingency

Activity %
Complete

100.0%

100.0%
100.0%

5,000.00
3,076.25

#VALUE!
#VALUE!

=2
BNuG P50 Contingency

100.0%

5,000.00

#VALUE!

=3

100.0%

2,000.00

#VALUE!

BNuG Estimate

100.0%

10,000.00

#VALUE!

=4+5

BCWP

ACWP

Comments

B358: Approval PMP


Prof Serv; Constn Manmt; Constn Manmt-Other1
P50 Contingency-Other1

5,000.00
3,076.25

100.0%

607100260

B358: Building Ownership Transfer Agreement


Moving costs-Other1

5,000.00

100.0%

06071TB001

Team Building: B358 Start Up


General Expenses; Training; Training Courses-Other1

2,000.00

607100265

B358: Pre Ops Survey (M6)


Constn; Surv & Invests; Surv / Invests-Other1

10,000.00

607100270

B358: Install Acess Scafold


Scaffolding (Generally)

12,100.00

100.0%

100.0%

12,100.00

#VALUE!

=7

607100315

B358: Errect RUBB Shelter


Hire; Mobile Plant & Equipment Hire; Major Construction Equipment

53,400.00

93.9%

100.0%

53,400.00

#VALUE!

= 20+21+22+23+24+25+26

607100275

B358: Building Fabric Repairs


Repair contracts-Other1

25,000.00

85.0%

100.0%

25,000.00

#VALUE!

= 8 + 9 + 10 + 11 + 12

607100280

B358: Re-Paint Structural Steel


Constn; Civil; Sml Civ Spt Sub-Contract-Other1

6,100.00

100.0%

100.0%

6,100.00

#VALUE!

= 13

607100285

B358: Install New Cladding


Construction; Steelwork; Cladding-Other1

12,000.00

100.0%

100.0%

12,000.00

#VALUE!

= 14

B358: Relay New Floor


Constn; Civil; Sml Civ Spt Sub-Contract-Other1

3,600.00

0.0%

0.0%

#VALUE!

= 15

B358: Seal South End of Building


Constn; Civil; Sml Civ Spt Sub-Contract-Other1

18,200.00

100.0%

100.0%

18,200.00

#VALUE!

= 16

B358: Install New Lighting


Lighting-Other1

3,500.00

35.0%

35.0%

1,225.00

#VALUE!

= 17

B358: Install New Shutter Door


Constn; Civil; Sml Civ Spt Sub-Contract-Other1

6,100.00

100.0%

100.0%

6,100.00

#VALUE!

=18

B358: Relocate B262 Product to Refurbished B358


Wste Disp; Radioactive Materials; LLW-Other1

##########

0.0%

#VALUE!

= Prelim & Plant

60.1%

159,201.25

607100290

607100295

607100300

607100305

607100310

100.0%

100.0%

0.0%

265076.25

Date Printed 7/27/2013 4:27 PM

Page 24 of 26

#VALUE!

File Name 160521524.xlsx.ms_office and Tab Reference WPSS 110

160521524.xlsx.ms_office

35.11.12.35025.03000.35/06071 Sludge Packaging Plant 1 - Site Clearance

Reporting Period

Work Pack Specification Sheet 120 Site Investigation


Ref number

Description

0607100320

Site Investigation @ 10m Grid and 40 Boreholes 05/06

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40

Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA
Location TBA - current limit is 26 planned locations
Location TBA - current limit is 26 planned locations
Location TBA - current limit is 26 planned locations
Location TBA - current limit is 26 planned locations
Location TBA - current limit is 26 planned locations
Location TBA - current limit is 26 planned locations
Location TBA - current limit is 26 planned locations
Location TBA - current limit is 26 planned locations
Location TBA - current limit is 26 planned locations
Location TBA - current limit is 26 planned locations
Location TBA - current limit is 26 planned locations
Location TBA - current limit is 26 planned locations
Location TBA - current limit is 26 planned locations
Location TBA - current limit is 26 planned locations
Location TBA - current limit is 26 planned locations
P50 Contingency
Activity Sub Total

Qty UOM

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off

40

Quanitity
Tracking

Prepared By
Actual Qty

Labour

off

06071RM004
1
2
3
4
5
6
7
8
9
10

M6 : Site Investigation Increased Density Borehole Grid > 10m Grid


Location TBA - No plans yet to undertake
1 off
Location TBA - No plans yet to undertake
1 off
Location TBA - No plans yet to undertake
1 off
Location TBA - No plans yet to undertake
1 off
Location TBA - No plans yet to undertake
1 off
Location TBA - No plans yet to undertake
1 off
Location TBA - No plans yet to undertake
1 off
Location TBA - No plans yet to undertake
1 off
Location TBA - No plans yet to undertake
1 off
Location TBA - No plans yet to undertake
1 off
Activity Sub Total
10 off

Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes

P3e Activity

P3e Cost Element and Description

607100320

Site Investigation @ 10m Grid and 40 Boreholes 05/06


Constn; Surv & Invests; Surv / Invests-Other1
P50 Contingency-Other1

40

off

Yes

Actual
Quantity
-

Labour

Plant &
Equipment

Prelims

Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes

Qty UOM Qty Tracking

P10

Weighting

Physical
Progress

Weighted
Progress

BCWP

ACWP

1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
8,203.33
78,203.33

1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
1,750.00
8,203.33
78,203.33

2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
2.24%
10.49%
100.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

1,800.00
1,800.00
1,800.00
1,800.00
1,800.00
1,800.00
1,800.00
1,800.00
1,800.00
1,800.00
18,000.00

1,800.00
1,800.00
1,800.00
1,800.00
1,800.00
1,800.00
1,800.00
1,800.00
1,800.00
1,800.00
18,000.00

10.00%
10.00%
10.00%
10.00%
10.00%
10.00%
10.00%
10.00%
10.00%
10.00%
100.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

Weighting

Physical
Progress

Weighted
Progress

81.29%

0.00%

0.00%

Plant &
Equipment

Prelims

Grand Total

78,203.33

Grand Total

78,203.33

Comments

Nexia Desktop Study


Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Currently Planned
Not planned
Not planned
Not planned
Not planned
Not planned
Not planned
Not planned
Not planned
Not planned
Not planned
Not planned
Not planned
Not planned
Not planned
11K ACWP non progressible

ACWP

Comments

#VALUE!
#VALUE!

06071RM004

M6 : Site Investigation Increased Density Borehole Grid > 10m Grid


10
Constn; Surv & Invests; Surv / Invests-Other1

off

Yes

18,000.00

18,000.00

18.71%

0.00%

0.00%

WPSS 120

Site Investigation

off

Yes

96,203.33

96,203.33

100.00%

0.00%

0.00%

Date Printed 7/27/2013 4:27 PM

#VALUE!

BCWP

aw128

50

Page 25 of 26

#VALUE!

#VALUE!

File Name 160521524.xlsx.ms_office and Tab Reference WPSS 120

160521524.xlsx.ms_office

35.11.12.35025.03000.35/06071 Sludge Packaging Plant 1 - Site Clearance

Reporting Period

Work Pack Specification Sheet 900 Project Management


NTWP 2 Estimate
607100005

06071RM001

06071RM002

06071RM007

P3e Activity

Qty

UOM

Project Management
Prof Serv; Constn Manmt; Constn Manmt-Other1 BALANCE LINE
General Expenses; Office Expenses; Expenses-Other1
General Expenses; Travel & Subsistence; Travel & Accommodation-Other1
100.0
Trips
General Expenses; Training; Training Courses-Other1
70.0 Courses
Info Techno; IT Infra-sture; Infra-sture-Other1
Pro Ser; Dsgn Spt; Dsgn Ser, Gen Dsgn Ac-Other1
Senior Project Manager
750.0
Hrs
Personal Assistant; ASW/CSW
1,500.0
Hrs
Construction Manager; ASW/CSW
750.0
Hrs
Head Project/Programme
68.0
Hrs
Quality Team Leader
300.0
Hrs
Activity Sub Total
3,368.0
Hrs

400.00
200.00

82.88
20.37
29.39
82.88
25.54
38.02

M 1&2 & 3: Stake Holder Management


Pro Serv; Manmt Consultants; Consultants-Other1 BALANCE LINE
Project Manager; ASW/CSW
500.0
Activity Sub Total
500.0

Hrs
Hrs

32.24
32.24

M4 : PMP Support & Interfaces Management


Pro Serv; Manmt Consultants; Consultants-Other1 BALANCE LINE
Project Manager; ASW/CSW
540.0
Activity Sub Total
540.0

Hrs
Hrs

32.24

M10: Liason and Interface with Regulatory Bodies


Pro Serv; Manmt Consultants; Consultants-Other1 BALANCE LINE
Project Manager; ASW/CSW
540.0
Activity Sub Total
540.0

Hrs
Hrs

P3e Cost Element and Description

Qty

Prepared By

TQ Rate

UOM

P10

PO Rate

Actual
Quantity
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

41.73

#VALUE!
#VALUE!

47.60

#VALUE!
#VALUE!

#VALUE!
#VALUE!

32.24

TQ Rate

PO Rate

Effort

CSW Balance
Line

Other Costs

12,485.00

16,120.00
16,120.00

17,409.60
17,409.60

17,409.60
17,409.60

Actual
Quantity

Effort

12,485.00

7,680.00

7,680.00

8,448.00

8,448.00

8,448.00

8,448.00

Weighting

Physical
Progress

Weighted
Progress

BCWP

ACWP

124,728.00

12,485.00
37,138.00
40,000.00
14,000.00
4,500.00
29,090.00
62,160.00
30,555.00
22,042.50
5,635.84
7,662.00
265,268.34

4.71%
14.00%
15.08%
5.28%
1.70%
10.97%
23.43%
11.52%
8.31%
2.12%
2.89%
100.00%

80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%
80.20%

3.77%
11.23%
12.09%
4.23%
1.36%
8.79%
18.79%
9.24%
6.66%
1.70%
2.32%
80.20%

10,012.97
29,784.68
32,080.00
11,228.00
3,609.00
23,330.18
49,852.32
24,505.11
17,678.09
4,519.94
6,144.92
212,745.21

7,680.00
16,120.00
23,800.00

32.27%
67.73%
100.00%

80.20%
80.20%
80.20%

25.88%
54.32%
80.20%

6,159.36
12,928.24
19,087.60

#VALUE!
#VALUE!
#VALUE!

8,448.00
17,409.60
25,857.60

32.67%
67.33%
100.00%

80.20%
80.20%
80.20%

26.20%
54.00%
80.20%

6,775.30
13,962.50
20,737.80

#VALUE!
#VALUE!
#VALUE!

8,448.00
17,409.60
25,857.60

32.67%
67.33%
100.00%

80.20%
80.20%
80.20%

26.20%
54.00%
80.20%

6,775.30
13,962.50
20,737.80

#VALUE!
#VALUE!
#VALUE!

Weighting

Physical
Progress

Weighted
Progress

62,160.00
30,555.00
22,042.50

5,635.84

7,662.00
128,055.34

Grand Total

aw128

CSW Balance
Line

37,138.00
40,000.00
14,000.00
4,500.00
29,090.00

Other Costs

Grand Total

BCWP

Comments

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

ACWP

Comments

NTWP2
Estimate
607100005

Project Management

3,368.0

Hrs

38.02

41.73

128,055.34

12,485.00

06071RM001

M 1&2 & 3: Stake Holder Management

500.0

Hrs

32.24

47.60

16,120.00

06071RM002

M4 : PMP Support & Interfaces Management

540.0

Hrs

32.24

47.88

17,409.60

06071RM007

M10: Liason and Interface with Regulatory Bodies

540.0

Hrs

32.24

47.88

4,948.0

Hrs

36.18

43.67

Work Pack Spec Sheet 900 Grand Total

Notes

Reporting Period General Comment


P1
P2
P3
P4
P5
P6
P7
P8
P9
P10
P11
P12

Date Printed 7/27/2013 4:27 PM

124,728.00

265,268.34

77.84%

80.20%

62.43%

212,745.21

#VALUE!

7,680.00

23,800.00

6.98%

80.20%

5.60%

19,087.60

#VALUE!

8,448.00

25,857.60

7.59%

80.20%

6.09%

20,737.80

#VALUE!

17,409.60

8,448.00

25,857.60

7.59%

80.20%

6.09%

20,737.80

#VALUE!

178,994.54

37,061.00

340,783.54

273,308.40

#VALUE!

124,728.00

Opportunities

Threats

Page 26 of 26

100.00%

80.20%

80.20%

Issues

File Name 160521524.xlsx.ms_office and Tab Reference WPSS 900

Anda mungkin juga menyukai