The 000-106 practice exam is written and formatted by Certified Senior IT Professionals working in today's prospering companies and data centers all over the world! The 000-106 Practice Test covers all the exam topics and objectives and will prepare you for success quickly and efficiently. The 000-106 exam is very challenging, but with our 000-106 questions and answers practice exam, you can feel confident in obtaining your success on the 000-106 exam on your FIRST TRY! IBM 000-106 Exam Features - Detailed questions and answers for 000-106 exam - Try a demo before buying any IBM exam - 000-106 questions and answers, updated regularly - Verified 000-106 answers by Experts and bear almost 100% accuracy - 000-106 tested and verified before publishing - 000-106 exam questions with exhibits - 000-106 same questions as real exam with multiple choice options Acquiring IBM certifications are becoming a huge task in the field of I.T. More over these exams like 000-106 exam are now continuously updating and accepting this challenge is itself a task. This 000-106 test is an important part of IBM certifications. We have the resources to prepare you for this. The 000-106 exam is essential and core part of IBM certifications and once you clear the exam you will be able to solve the real life problems yourself.Want to take advantage of the Real 000-106 Test and save time and money while developing your skills to pass your IBM 000-106 Exam? Let us help you climb that ladder of success and pass your 000-106 now!

000-106

QUESTION: 1 A system is being planned with three production partitions, one each for an IBM i, AIX standard edition, and Power Linux applications. One fibre-channel attached TS3100 tape library will be shared between the partitions for backup.Which solution provides tape library sharing with minimum operator intervention?

A. Configure VIO Server Express Edition to control the tape library through one fibre channel card.Assign the library to the production partitions when needed. B. Configure the IBM i partition to own the tape library.Use IBM i virtualization to host a virtual tape library connection to the AIX and Linux partition.Assign the library to the production partitions when needed. C. Configure a fibre channel card for each partition, and a configure fibre switch.Connect the partitions and tape library to the switch.Zone the switch so all partitions can enable the tape when needed and disable the tape when finished. D. Configure AIX to control the tape library through one fibre channel adapter.Use AIX virtualization to host a virtual tape library connection to the IBM i and Linux partitions.Assign the library to the production partitions when needed. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=1
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 2 Which of the following items in a single enclosure Power 770 improves Reliability, Availability, and Serviceability?

A. Redundant system clocks B. Redundant service processors C. eDRAM chips have redundant L3 cache D. Main memory DIMMs contain a redundant DRAM chip Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=2
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 3 The Power 720 is offered with how many cores?

A. 1, 2, or 4 B. 2, 4, or 6 C. 2, 4, or 8 D. 4, 6, or 8 Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=3
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 4 A customer would like to have the ability to permanently activate processor and memory resources as their workload increases. Which of the following supports the customer requirement?

A. Reserve Capacity on Demand B. Utility Capacity on Demand C. Capacity Upgrade on Demand D. Uncapped Capacity on Demand Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=4
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 5 A customer is planning to buy a two enclosure Power 770, and will implement 4 LPARs with the following requirements:Each LPAR must have a private, dedicated connection to the network.The adapter for this network connection must be hot-swappable.The customer wants to minimize the number of I/O slots used.Which of the following fulfills the customer requirements?

A. Two dual-port PCIe adapters B. A four-port PCIe Ethernet adapter C. Four separate PCIe Ethernet adapters D. Two embedded Integrated Virtual Ethernet adapters (IVE) Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=5
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 6 Which of the following is included in IBM Systems Director Express Edition?

A. Energy management B. Virtual image deployment C. Virtual resource management D. Networking device management Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=6
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 7 A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs.How can they manage the new machines for the least cost?

A. Purchase a second HMC and use this to manage the new servers. B. Connect all of the new servers to the existing private HMC network. C. Configure a second private network on their existing HMC for the new servers. D. Connect 9 of the new servers to the existing HMC and use Integrated Virtualization Manager on the 10th. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=7
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 8 What is an advantage of using an HMC rather than IVM for system management?

A. Support for a single VIO Server environment B. Adapters can be dedicated or virtual for each LPAR environment C. Interfaces with Systems Director to manage the Power Systems servers D. Supports multiple Power Systems servers from a single point of control Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=8
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 9 A customer is planning on having a single Virtual I/O Server (VIOS) configuration in a Power 750. They have selected a 4-port 1Gb Integrated Virtual Ethernet (IVE). There will be no other network cards installed in the system. One IVE logical port will be used in the VIO Server and will be used as the physical port in a Shared Ethernet Adapter (SEA).What is the maximum number of IVE logical ports available to use in other LPARs?

A. 1 B. 7 C. 15 D. 31 Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=9
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 10 A customer has a Power 780 with 16 cores installed and activated. If the system is running in TurboCore mode, how many cores are available to use?

A. 8 B. 16 C. 24 D. 32

Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=10
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 11 When performing an expert level pre-install Technical & Delivery Assessment (TDA), which team member has the responsibility for assigning, tracking and updating the completion of action items during the TDA process?

A. The Delivery Leader B. The Opportunity Owner C. The Solution Designer D. The Subject Matter Expert Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=11
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 12 Which data synchronization options between two geographical locations are supported by PowerHA SystemMirror?

A. Parallel and Serial B. Serial and Asynchronous C. Parallel and Synchronous D. Synchronous and Asynchronous Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=12
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 13 A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure.Which solution addresses the customer requirements?

A. Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAs B. Move the existing physical network and storage adapters to the new system and virtualize the I/O using a single VIO Server. C. Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC connectors and dual HBAs. D. Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC connectors and the other with dual HBAs. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=13
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 14 What describes the difference between NPIV and vSCSI in the way fibre-channel attached disk and tape are presented when VIO Server is used?

A. NPIV presents Virtual HBA addresses and vendor specific information for disk and tape devices.vSCSI presents generic disk and tape device interfaces. B. NPIV presents generic disk and tape device interfaces on virtual HBA addresses.vSCSI presents HBA addresses as SCSI with vendor specific information for disk and tape devices. C. NPIV presents HBA addresses and vendor specific device information directly to the client partition.vSCSI presents vendor specific disk information and generic tape device interfaces through VIO server. D. NPIV presents virtual HBA addresses with generic device information for SCSI based disk and tape devices.vSCSI presents vendor specific information for disk and tape device devices attached via SCSI hardware interfaces. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=14
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 15 A new customer wants to install a Power 750 in a warehouse location that has no local staff to support it. They are concerned about hardware support and would like to have the system notify IBM service if there is an issue.Which actions will address the customer concern?

A. Enable automatic problem reporting from smit B. Use IVM to enable console mirroring to IBM Remote Support. C. Use the HMC to enable reporting through Electronic Service Agent. D. Enable Automatic Problem Reporting in ASMI using he embedded modem on the FSP. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=15
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 16 A customer is consolidating seven IBM i partitions onto a POWER7 system, using VIO Server to virtualize resources.Which of the following PowerVM editions is appropriate for this customer?

A. IBM i Edition B. Express Edition C. Standard Edition D. Enterprise Edition Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=16
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 17 Which of the following has an integrated database?

A. AIX B. IBM i C. Linux D. VIO Server Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=17


-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 18 A stock exchange needs extremely low latency in their disk subsystem. Which disk storage technology is most likely to fulfill their need?

A. SSD B. SSA C. SAS D. SAN Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=18


-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 19 A customer has a POWER6 520 system with 6 partitions. They plan to upgrade their system and need to determine the current hardware configuration of the partitions before making any upgrade decisions.What is needed to read the exported system plan and design the new system?

A. e-Config B. System Planning Tool (SPT) C. IBM Workload Estimator (WLE) D. IBM Performance Monitor (PM) Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=19
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 20 Which of the following includes Active Memory Sharing (AMS)?

A. PowerHA Enterprise Edition B. PowerVM Enterprise Edition C. VMControl Enterprise Edition D. Systems Director Enterprise Edition

Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=20
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 21 A customer is upgrading from a 16-core POWER6 570 with two enclosures to a 16-core Power 770 with only one enclosure. There are 22 PCI-X adapters and 19 PCIe adapters spread across the current CECs and I/O drawers.How many and what kind of drawers are needed to connect these adapters?

A. 2 PCI-X drawers and 2 PCIe drawers B. 3 PCI-X drawers and 4 PCIe drawers C. 4 PCI-X drawers and 3 PCIe drawers D. 4 PCI-X drawers and 2 PCIe drawers Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=21
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 22 A customer is considering procuring HP servers with Virtual Server Environment (VSE) to consolidate servers and dynamically move resources between partitions.How can the technical sales representative position PowerVM as the solution to virtualize this server environment?

A. PowerVM supports shared servers compared to VS E. B. PowerVM supports shared processors and memory compared to VS E. C. PowerVM supports shared processors, memory and I/O compared to VS E. D. PowerVM supports DLPAR without a reboot and supports dedicated I/O compared to VSE. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=22
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 23 A customer would like to create a shared processor partition with 16 virtual processors. What is the minimum number of processing units required in the partition profile?

A. 0.80 B. 0.16 C. 1.60 D. 0.10 Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=23


-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 24 A customer has a 32-core Power 770 with 4 AIX partitions and 2 IBM i partitions. They want to improve network availability and allow for concurrent maintenance. What will support the customer requirement at least cost?

A. Build the logical partition infrastructure based on 6 or more VLANs. B. Build the logical partition infrastructure based on two or more IVEs. C. Build the logical partition infrastructure based on Partition Mobility. D. Build the logical partition infrastructure based on redundant VIO Servers. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=24
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 25 When a customer attempts to manage virtual machines, virtual images and system pools with the VMControl Express Edition, all operations fail except for managing virtual machines. What is recommended to resolve this situation?

A. Upgrade to VMControl Standard Edition B. Upgrade to VMControl Enterprise Edition C. Upgrade to latest version of VMControl Express Edition D. Download the latest fixes for VMControl Express Edition Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=25
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 26 A customer is evaluating PowerVM capabilities for dynamically allocating resources without rebooting LPARs. Which features of PowerVM support the customer requirement?

A. CoD and PCI hot-plug B. DLPAR and Active Memory Sharing C. Hot node add and hot node repair D. Dynamic processor failure and processor instruction retry Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=26
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 27 A customer is unsure how POWER7 processors can outperform POWER6 processors when the clock speeds are slower. What contributes to the improved performance?

A. Added Turbo memory switching B. Removed internal OLTP limits C. Moved L3 cache onto the chip

D. Increased DDR2 memory speeds Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=27


-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 28 A BladeCenter S chassis with 2 storage modules requires how many power supplies?

A. 1 B. 2 C. 4 D. 6 Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=28
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 29 Which of the following configuration is valid for expansion drawers on a Power 750 with 2 processor boards installed?

A. 3 PCI-e I/O drawers and 1 PCI-X I/O drawer B. 4 PCI-e I/O drawers and 4 RIO-2 I/O drawers C. 2 PCI-e I/O drawers and 4 PCI-x I/O drawers D. 4 PCI-e I/O drawers and 2 PCI-X I/O drawers Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=29
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 30 A system administrator has been instructed to attach storage in their client LPARs, in a Power 770, with fibre channel adapters using N_port ID virtualization (NPIV).Which of the following partitions has the minimum requirements to utilize virtual fibre channel?

A. LPAR-A with 1Gb FC HBA and SAN connection B. LPAR-B with 2Gb FC HBA and SAN connection C. LPAR-C with 4Gb FC HBA and SAN connection D. LPAR-D with 8Gb FC HBA and SAN connection Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=30
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 31 A customer wants to monitor energy consumption for all of their IBM systems. What part of the IBM Systems Director family supports this function?

A. Active Energy Manager B. PowerVM Energy Manager C. Power and Energy Manager D. Thermal and Energy Manager Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=31
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 32 What is a design consideration when using existing PCIe I/O drawers in a maximum bandwidth/throughput configuration on a new Power 750 system?

A. The new system requires 1 installed processor card for the GX++ bus adapter B. The new system requires a minimum of 2 installed processor cards for the GX++ bus adapter C. The new system requires a minimum of 3 installed processor cards and the HPC InfiniBand cluster adapter D. The new system requires 1 installed processor card for the GX++ bus adapter and the HPC InfiniBand cluster adapter Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=32
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 33 What is a key ability of IBM Systems Director Enterprise Edition as compared to Standard Edition?

A. Manage multiple operating systems on a server B. Manage energy consumption and network traffic to increase efficiency C. Manage LPARs, operating systems and servers to reduce administration D. Manage workloads across multiple servers to optimize resource utilization Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=33
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 34 When considering migrating a POWER6 server with PCI-X and PCIe adapters to a Power 720, which statement is true?

A. PCIe adapters are supported only in I/O drawers B. PCI-X adapters are supported in both the CEC and in I/O drawers C. PCI-X adapters are supported in the CEC; PCIe adapters are supported in 12X I/O drawers D. PCIe adapters are supported in the CEC; PCI-X adapters are supported in 12X I/O drawers Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=34

-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 35 On a POWER7 processor based server what is the minimum number of cores used by the Hypervisor to run four threads?

A. 1 B. 2 C. 4 D. 8 Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=35
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 36 A system is being designed with many LPARs which will be clients of dual VIO Servers. The VIO Servers must be redundant so that, in the event of scheduled maintenance, the clients do not need to be shut down.Which of these strategies could be used to ensure that the client LPARs continue to be able to use the network in the event of a VIO Server being shut down?

A. Implement PowerHA SystemMirror on both VIO servers. B. Configure Etherchannel between the client LPARs and the two VIO servers C. Configure Network Interface Backup between the two VIO servers and use each VIO server to access the network. D. Implement Shared Ethernet Adapter failover and have all client partitions access the network through the shared adapters. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=36
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 37 A customer has a Power 770 running an SAP ERP workload on AIX 7. It has a single partition with 12 cores and 48GB of memory and the CPU is underutilized at 46% with 1000 users. Memory utilization is at 80%. The number of users will increase to 1700, increasing memory utilization by 37%.Which of the following supports this requirement?

A. Active Memory Server B. Active Memory Sharing C. Active Memory Pooling D. Active Memory Expansion Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=37
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 38 A Technical and Delivery Assessment (TDA) is a structured technical inspection of a

completed solution design. After the inspection is complete, what deliverable can the customer expect?

A. Verification of the expected performance of the new solution. B. A document used by IBM manufacturing to build and ship the system solution. C. An IBM Quality Assurance Certificate which is supplied to the customer with the system. D. A list of actions that are recommended to reduce risk and create a successful implementation. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=38
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 39 A customer has 4 application and 2 database servers that will be installed in partitions on a Power 750. They are concerned that the database software vendor will charge based on every processor core in the server.Which action will reduce the potential vendor software costs?

A. Create capped partitions for the database servers. B. Create workload partitions for the database servers. C. Create a separate shared processor pool for the database servers. D. Create virtual processors equal to the entitlement for database servers. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=39
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 40 A customer wants to implement the following Blades in BladeCenter H:Two POWER Blades running IBM i partitions.Two POWER Blades running AIX and LinuxFour x86 Blades running WindowsWhich of the following design consideration statements is correct?

A. The Blades must use the same CIOv and CFFh expansion adapter types. B. Two physical BladeCenter H chassis will be required. One for the POWER Blades, the other for the x86 Blades. C. The x86 Blades and POWER Blades may use different expansion adapters provided the POWER Blades are in bays 1-7 and the x86 Blades are in slots 8-14. D. The x86 Blades and POWER Blades may use different expansion adapters, provided the corresponding I/O modules to Blade midplane connections are configured in the Advanced Management Module (AMM). Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=40
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 41 A customer has shut down an LPAR after using DLPAR to add or remove processor and memory resources. When the partition is reactivated, the desired changes are missing.What

action, or sequence of actions, will immediately and permanently solve this problem?

A. Add or remove the resources in the profile, click apply , then save . B. Add or remove the resources using DLPAR and change the partition profile. C. Add or remove the resources using DLPAR, then shutdown and reactivate the LPAR. D. Add or remove the resources in the system profile and reboot the managed system. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=41
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 42 Where is specific information regarding height, width, depth, and weight of a Power Systems server located?

A. Hardware InfoCenter B. System Planning Tool C. Offering Information website D. Technical Delivery and Assessment Guide Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=42
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 43 Which system provides the highest performance per core, and the least cost for applications licensed per core?

A. A Power 795 with MaxCore mode B. A Power 780 with MaxCore mode C. A Power 755 with TurboCore mode D. A Power 780 with TurboCore mode Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=43
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 44 An end user is deploying Blade servers to replace obsolete rack mounted servers. In addition to AIX Web server and database workloads, they also have Windows workloads. Which Blade is designed for Windows workloads?

A. HS22 B. JS43 C. QS21 D. PS701

Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=44
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 45 Which of the following solutions provides maximum core density per rack?

A. Power 730 B. PS700 Blades C. PS702 Blades D. PS703 Blades Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=45
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 46 The Power 720 is offered with how many cores?

A. 1, 2, or 4 B. 2, 4, or 6 C. 2, 4, or 8 D. 4, 6, or 8 Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=46
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 47 A customer has a 4-core POWER6 570 with 4 partitions and a 2-port 1Gbps Integrated Virtual Ethernet (IVE) Adapter. They are having problems with throughput on the Ethernet adapter and want to improve performance. Which of the following solutions will help the customer with this issue for the least cost and with the least interruption?

A. Order a 2-port 1Gbps Ethernet LAN adapter. B. Order a 2-port 10Gbps Ethernet LAN adapter. C. Upgrade the IVE adapter to a 4-port 1Gbps IVE adapter. D. Upgrade the IVE adapter to a 2-port 10Gbps IVE adapter. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=47
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 48 A customer has a Power 750 with the following: One processor card with 8 cores enabled, and 64GB RAM installed One GX+ adapter with one I/O drawer attached One 4-port 1Gbps IVE adapter PowerVM Standard Edition They need to add a GX++ adapter and cable it to an I/O drawer. Which of the following must also be ordered?

A. A second IVE adapter B. A second processor card C. PowerVM Enterprise Edition D. An additional cable-management arm Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=48
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 49 A customer requires two 12X loops on their new POWER7 system. What is the smallest system that will support two loops?

A. Power 710 B. Power 720 C. Power 730 D. Power 740 Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=49
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 50 Which operating system can directly host managed storage for IBM i, AIX, Linux, VMware and Windows on a Power Systems server?

A. AIX B. IBM i C. Linux D. VIO Server Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=50


-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 51 A customer has an LPAR with 4 dedicated cores on a POWER7 server with SMT4 enabled. How many logical processors are presented to an application running on this LPAR?

A. 4 B. 8 C. 16 D. 32 Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=51
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 52 A POWER7 processor has L1, L2 and L3 caches. Which of the three caches uses embedded

DRAM (eDRAM) technology?

A. L3 only B. L1 and L2 C. L2 and L3 D. L1, L2 and L3 Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=52


-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 53 Which of the following provide for higher system availability on a single CEC Power 770 or Power 780?

A. Redundant system clock B. Redundant service processor C. POWER7 cores include redundant L3 caches D. Main memory DIMMs contain an extra DRAM chip for improved redundancy Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=53
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 54 Which of the following uses compression/decompression to increase the memory available for client workloads?

A. PowerVM B. VMControl C. Active Memory Sharing D. Active Memory Expansion Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=54
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 55 A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3). Which of these statements is true and would minimize the cost?

A. All the machines can be connected to the existing HMC, as long as it is updated to code level 7.7.1 or later. B. The Power 770 requires an HMC (7042-CR5 or later), so they must buy one. All of the systems can be managed by this new HM

C. C. They should buy a new HMC for the Power 770 system, and leave the POWER5 and POWER6 based systems connected to the existing one. D. The Power 770 requires an HMC, so they should connect the Power 770 to the HMC and convert the POWER5 and POWER6 based servers to IVM. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=55
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 56 A system is being designed with many LPARs which will be clients of dual VIO Servers. The VIO Servers must be redundant so that, in the event of scheduled maintenance, the clients do not need to be shut down. Which of these strategies could be used to ensure that the client LPARs continue to be able to use the network in the event of a VIO Server being shut down?

A. Implement PowerHA SystemMirror on both VIO servers. B. Configure Etherchannel between the client LPARs and the two VIO servers C. Configure Network Interface Backup between the two VIO servers and use each VIO server to access the network. D. Implement Shared Ethernet Adapter failover and have all client partitions access the network through the shared adapters. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=56
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 57 A customer is implementing a POWER Blade solution which requires the VIO Server to be mirrored on internal disk drives. Which Blade supports the requirement?

A. JS21 B. JS23 C. PS700 D. PS701 Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=57


-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 58 An customer with limited storage management skills needs a disk subsystem with up to 70TB capacity and enterprise class performance. Which disk storage system should be recommended?

A. DS6800 B. DS8100 C. DS8300 D. XIV Storage System

Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=58
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 59 A customer requires their application to have high availability within a data center, and also the ability to recover at a data center located 600km away in the event of an outage. Which system software solution component supports the customer requirement?

A. PowerHA SystemMirror Basic Edition B. PowerHA SystemMirror Express Edition C. PowerHA SystemMirror Standard Edition D. PowerHA SystemMirror Enterprise Edition Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=59
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 60 An HMC managed Power 720 with two partitions is being planned. One partition is production, the other is a test/development partition. Customer management requires the following: Redundant LAN hardware for the production partition Dual LAN interfaces Automatic failover between the redundant physical LAN ports. Which of the following meets the customer requirement?

A. Order two PCIe dual-port LAN adapters. Use port 1 on each adapter for the production partition. Configure the test partition to use port 2 of each adapter. B. Order two dual-port Integrated Virtual Ethernet Adapters (IVEs). Configure the production partition to use port 0 on each IV E. Configure the test partition to use port 1 on each IV E. C. Include a PCIe dual-port LAN adapter in the production partition. Configure the production partition to use a port on the PCIe adapter and another on the Integrated Virtual Ethernet Adapter (IVE). Configure the test partition to use the IV E. D. Include a PCIe dual-port LAN adapter in the production partition. Configure the production partition to use one port on the PCIe adapter and another on the Integrated Virtual Ethernet Adapter (IVE). Configure the test partition to use the other PCIe adapter port. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=60
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 61 Using the following information: - Performance data from an existing system that a new system will replace - Performance estimates that anticipate future workloads - Micropartitioning and logical partitioning implementations Which of the following allows a technical sales representative to create a system design which can be imported into an HMC?

A. IBM eConfig B. IBM Performance Monitor C. IBM Workload Estimator (WLE) D. IBM System Planning Tool (SPT) Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=61
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 62 What is the primary purpose of the Technical and Delivery Assessment (TDA)?

A. Identify, assess, and mitigate technical risks. B. Verify pricing and gather components for special bid submission. C. Verify the proposed solution will fit within the customer s budget. D. Review competitive offerings, system performance and delivery schedules. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=62
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 63 What is the correct stage in the sales process for a Pre-Sales Technical & Delivery Assessment (TDA)?

A. Before the first solution design meeting with the customer B. After the solution design proposal is submitted to manufacturing for review C. Once the customer has supplied the solution design specifications to the sales team D. After the solution design is completed and before the proposal is submitted to the customer Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=63
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 64 A customer is deploying a new database on a PS701 Blade in a BladeCenter H, and requires redundant network and SAN adapters. Which configuration supports the customer requirement?

A. Configure 2 CFFh combination fibre channel / gigabit Ethernet adapters B. Configure 1 CFFh 2-port fibre channel adapter and 1 CIOv 2-port gigabit Ethernet adapter C. Configure 1 CIOv 2-port fibre channel adapter and 1 CFFh combination fibre channel / gigabit Ethernet adapter D. Configure 1 CIOv 2-port gigabit Ethernet adapter and 1 CFFh combination fibre channel / gigabit Ethernet adapter

Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=64
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 65 A company plans to deploy a two-enclosure, 23-core Power 780 system with AIX, IBM i and Linux in the following configuration: 3 AIX partitions with dedicated network and disk adapters 1 native IBM i partition acting as a host 1 hosted IBM i partition 2 hosted Linux partitions Which configuration will provide boot disk capability to all partitions?

A. Use dual-split backplane in both enclosures for the three AIX partitions and the IBM i partition. B. Put each partition on a dedicated controller using the triple-split backplane option in both enclosures. C. Use the triple-split backplane option in one enclosure for the AIX partitions, and the default dual-split backplane for the IBM i partition in the second enclosure. D. Use the triple-split backplane option in one enclosure for the AIX partitions, and the non-split backplane mode in the second enclosure for the IBM i hosting partition. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=65
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 66 A customer is evaluating PowerVM and VMware to run a data warehouse application. Which feature of PowerVM should be highlighted as a differentiator?

A. PowerVM offers partition mobility. B. PowerVM can virtualize network and SAN resources. C. PowerVM supports multiple operating systems running concurrently. D. PowerVM allows an LPAR to use activated cores and memory without limitation. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=66
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 67 A customer plans to consolidate two 8-core POWER6 systems with a total of 8 PCI-X adapters, 6 PCIe adapters, and a PCI-X I/O drawer into a 16-core Power 750. Which action allows the most efficient use of existing equipment?

A. Populate the Power 750 first then add a GX+ adapter to support PCI-X and PCIe I/O drawer loops. B. Populate the Power 750 first then add 2 GX+ adapters to support PCI-X and PCIe I/O drawer loops. C. Populate the Power 750 first then add a GX++ adapter to support PCI-X and PCIe I/O drawer loops. D. Populate the Power 750 first then add GX+ and GX++ adapters to support PCI-X and PCIe I/O drawer loops.

Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=67
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 68 A customer wants to migrate their existing compute-intensive POWER6 570 to a Power 770. Which of their existing I/O adapters can be migrated to Power 770 enclosures?

A. PCIe adapters B. PCI-X adapters C. PCI-X and PCIe adapters D. PCI, PCI-X and PCIe adapters Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=68
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 69 A customer would like to configure an uncapped LPAR so that it can use 2 to 8 cores depending on the workload characteristics. With SMT4 enabled, what is the least amount of processing resources which can be configured for the LPAR?

A. 8 desired processing units and 8 desired virtual processors B. 2 desired processing units and 8 desired virtual processors C. 8 desired processing units and 32 desired virtual processors D. 2 desired processing units and 32 desired virtual processors Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=69
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 70 A customer has an HMC-managed Power Systems server with 6 partitions. Four production partitions are subject to varying workloads throughout the day, and two are used for development and testing. The production applications have different licensing limitations on the number of physical cores that may be used. The development partitions can use no more than 1 core. The customer would like to dynamically optimize processor utilization within the licensing limits, with minimal operator intervention. Which of the following meets the customer requirement?

A. Define the production partitions maximum CPU to the licensing limitations. Define the development/test partition maximums to one core. Configure each partition to be capped. B. Define the production partitions maximum CPU to the licensing limitations. Define the development/test partition maximums to one core. Configure each partition to be uncapped. C. Define the production partitions maximum CPU to the licensing limitations. Define the development/test partitions to use no more than one core. Configure the HMC

scheduler to dynamically assign processors among the pools over a day. D. Create a shared processor pool for each production partition, with the maximum processor limit set to the licensing limit for the application in the pool. Assign the development and testing partitions to a processor pool with a maximum of 1 core. Configure each partition to use uncapped processing. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=70
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 71 A retail customer has an 8-core Power 740 server with 2 partitions. Production has 4 dedicated cores and the test partition has 2 dedicated cores. Both partitions run during the day without problems. At night, batch processing is exceeding the run window. Which solution addresses this problem without requiring additional hardware?

A. Adding VMControl will automate processor resource allocation during peak workloads B. Enable Dynamic Symmetric Multithreading in the HMC to balance workloads across processors. C. Add processing resources during the times they are required using Utility Capacity on Demand. D. Changing the partitions to Uncapped can make use of additional processor cycles during peak workloads. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=71
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 72 A customer plans to consolidate multiple business unit applications on a single Power Systems server. The maximum number of cores which can be used by each business unit must be limited by creating shared processor pools. What is the minimum PowerVM Edition which provides this feature?

A. Basic B. Express C. Standard D. Enterprise Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=72


-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 73 Which of the following includes Active Memory Sharing (AMS)?

A. PowerHA Enterprise Edition B. PowerVM Enterprise Edition

C. VMControl Enterprise Edition D. Systems Director Enterprise Edition Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=73


-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 74 How can resource allocations for an active partition on a Power 750 be changed immediately and permanently?

A. Use Capacity on Demand to add the resources. B. Use DLPAR to add the resources and select the permanent option. C. Use DLPAR to add the resources, and change the partition profile. D. Use an Operating System command to permanently request the resources. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=74
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 75 A customer is installing an HMC-managed Power 720 with two partitions, one for Production the other for Testing. They plan to use the Testing partition only occasionally and want to minimize hardware. Which of the following meets these requirements?

A. Create a system profile for each partition. Assign all needed resources as required . B. Define all system resources as desired on the Testing partition. Activate only as needed. C. Create two shared processor pools. Assign the minimal I/O resources required for each partition to the shared pools. D. Create both partitions with minimal required resources, and optional resources as desired . Activate each partition as necessary. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=75
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 76 while using virtualization to share SAN adapters on a server, how does Node Port ID Virtualization (NPIV) differ from Virtual SCSI (vSCSI) related to the use of multipathing software?

A. NPIV and vSCSI both require multipathing in VIO Server only. B. NPIV requires multipathing software on client LPARs, vSCSI requires multipathing software on VIO Server C. NPIV requires multipathing software on VIO Server, vSCSI requires multipathing software on client LPARs D. NPIV requires multipathing and MPIO software on VIO Server LPARs, vSCSI requires multipathing software on VIO Server and MPIO on client LPARs

Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=76
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 77 Which of the following is included in IBM Systems Director Express Edition?

A. Energy management B. Virtual image deployment C. Virtual resource management D. Networking device management Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=77
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 78 A data center includes a Power 750 server running AIX and Linux, and PS700 Blades running AIX. What can the customer use to update AIX and Linux, create and deploy LPARs, and set energy caps for both servers from a single console?

A. PowerVM Standard Edition B. VMControl Standard Edition C. Hardware Management Console D. IBM Systems Director Standard Edition Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=78
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 79 What are key benefits of IBM Systems Director Standard Edition?

A. Backup data Manage problems, Monitor network system B. Report problems, Manage servers and virtual environment, Monitor the network C. Monitor system health and network, Install and manage AIX and IBM I, Manage energy consumption D. Monitor system health and network, Manage servers and virtual environment, Collect performance data Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=79
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 80 Which of the following is a compelling reason to deploy IBM Systems Director Active Energy Manager (AEM) in a data center with high energy utilization?

A. Removes the requirement for Intelligent PDUs

B. Monitor and balance disk speeds according to utilization needs C. Is a required element for EnergyStar certification of the server/data center D. Monitor and report power and thermal trending to optimize energy consumption Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=80
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 81 A Power 720 customer using IVM wants to implement dual VIO servers, but is unable to create the second server. What is the most likely reason for this?

A. An HMC is required for dual VIO servers. B. Dual VIO servers require a split backplane. C. A dual VIO enablement code must be entered from the ASMI interface. D. The second VIO server must be created using the IVM command line interface. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=81
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 82 Which of the following functions can be performed using the Integrated Virtualization Manager?

A. Concurrent firmware updates B. Management of virtual storage C. Hot add/remove of I/O drawers D. Management of Capacity on Demand Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=82
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 83 A medical services customer has multiple partitioned Power 720 and 740 systems managed by an HMC. The development manager has requested access to the system console of the development partitions to enable PTF and system save management. What is the most appropriate response to this request?

A. Inform the manager that due to regulatory requirements their request must be denied. B. Create a user id for the manager and assign them the resource role of All Resources . C. Move all the development work to one of the Power 720s and acquire a second HMC to manage that system alone. Create a user id for the manager on the new HM C. D. Create a resource role named Development on the HMC that includes the development partitions. Create a user id for the manager and assign them the resource role of Development

Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=83
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 84 What is the maximum number of expansion drawers supported by a Power 740?

A. Up to six 12X I/O drawers in any combination of PCIe or PCI-X. B. Up to two 12X PCIe I/O drawers or up to four 12X PCI-X I/O drawers. C. Up to eight 12X PCIe I/O drawers or up to four 12X PCI-X I/O drawers. D. Up to four 12X PCIe I/O drawers or up to eight 12X PCI-X I/O drawers. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=84
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 85 A customer would like to use a Power Systems server with 16 cores active and 256GB memory. They also want to non-disruptively activate 16 additional cores and 256GB of additional memory when the workload increases. Which system supports this requirement?

A. Power 750 B. Power 770 C. Power 755 D. PS702 Blade Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=85
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 86 What is the maximum number of hardware threads possible on an 8-core Power 720?

A. 8 B. 16 C. 32 D. 64 Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=86
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 87 What must be configured in the VIO Server to support N_port ID virtualization (NPIV)?

A. RAID adapter B. Ethernet adapter C. IVE Logical port D. Fibre channel HBA

Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=87
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 88 An IBM i customer would like to run multiple workloads on a new POWER7 system. One of the software packages that needs to run is Systems Director Standard Edition. The customer also needs to use DB2, Domino, and WebSphere in a single operating system instance. What will meet the customer needs with the minimum number of partitions?

A. One partition running IBM i. B. One AIX and one IBM i partition. C. A single physical partition running IBM i, and a hosted AIX partition running AIX 5.2. D. Two VIO Server instances, one to support IBM i running DB2, WebSphere, and Domino, and the other to run Systems Director. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=88
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 89 What makes a POWER7 processor-based system a balanced system design?

A. Out-of-order instruction processing balances utilization across the POWER7 cores, maximizing system throughput. B. POWER7 processor-based systems adjust the clock frequency to provide additional performance for slowly running applications. C. POWER7 processor-based systems give higher priority to I/O-intensive applications to balance system performance across all concurrently running applications. D. POWER7 processor-based systems are designed to ensure sufficient bandwidth amongst the processors, memory, I/O, and other chips to maintain high processor utilization. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=89
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 90 How does the POWER7 processor architecture differ from a POWER6 processor?

A. On-chip L3 cache B. On-chip L2 cache C. On-chip L2 and L3 cache D. On-chip L1 and L2 cache Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=90
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 91

A customer has a Power 770 with PowerVM Enterprise Edition. What must they purchase to implement Active Memory Sharing (AMS) and Active Memory Expansion (AME)?

A. Separate enablement keys need to be purchased for AME and AMS. B. Both AMS and AME are included with PowerVM Enterprise Edition without the need to purchase enablement keys. C. AMS is included with PowerVM Enterprise Edition and a separate enablement key must be purchased to enable AM E. D. AME is included with PowerVM Enterprise Edition and a separate enablement key must be purchased to enable AMS. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=91
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 92 A customer with multiple AIX partitions on a Power 750 has made application changes that have increased the memory required by that partition. The processors are only 18% utilized but the installed memory is fully committed. The customer has little available budget, but requires a cost effective solution while they resolve the application issue. What would be the most cost effective option?

A. Active Memory Sharing B. Active Memory Expansion C. Trial Capacity on Demand D. Capacity Upgrade on Demand Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=92
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 93 A customer is planning a pair of Power 770 systems with multiple identical partitions. There are redundant HMCs and Flexible Service Processors (FSPs). What is IBM s recommended network configuration for this situation?

A. Configure each HMC and all FSP ports to use a static address on each of the local LANs. Provide one virtual LAN. B. Configure the HMC private network to access the FSP1 ports on a dedicated LAN segment and the FSP2 ports to the public network. C. Configure the HMC and the first FSP ports to a local dedicated LAN segment. Configure the second FSP ports and the public HMC port to the customer network. D. Configure the first port on the FSPs to one HMC and the second port on the FSPs to the second HMC on private LAN segments. Configure another network segment for regular traffic. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=93

-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 94 A customer has been using PowerVM Express Edition with a single VIO Server. They would like to implement dual VIO Servers to improve the availability and multiple shared processor pools for flexibility. What is necessary to implement these features?

A. Install latest VIO Server fixes B. Upgrade to AIX Enterprise Edition C. Upgrade PowerVM to Standard Edition D. Upgrade Express Edition to the latest level Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=94
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 95 A 12-core Power 740 has 2 LPARs. One LPAR has its disk in the CEC and the other has an HBA attachment to external disk. DVD-RAM access is required for both partitions. What is the lowestcost option to achieve this requirement?

A. Configure a second DVD-RAM in the CEC to be used by both partitions. B. Configure a second SAS adapter to separate the disk and DVD-RAM devices. C. Configure an external SAS Media Enclosure with a DVD-RAM for the second LPAR. D. Configure the internal SAS RAID Enablement Daughter Card to provide integrated DVD-RAM sharing. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=95
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 96 A fully populated BladeCenter S chassis with 2 storage modules requires how many power supplies?

A. 2 B. 3 C. 4 D. 6 Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=96
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 97 A customer has a local data center with production and backup servers sharing a DS6800. They need to switch between backup and production systems for maintenance and cannot afford to have any disruption in service. Which product is the correct solution for this customer?

A. PowerHA Realtime B. PowerHA FlashCopy C. PowerHA SystemMirror D. PowerHA MetroMirror Local Edition Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=97
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 98 A Power 720 is being planned with 2 VIO server partitions and 3 client partitions. Each VIO server partition will provide a Shared Ethernet Adapter (SEA). A database which will require 2 dedicated network connections will run in one of the client partitions. Which solution will minimize the number of adapters required?

A. One dual-port HEA/IVE for the VIO servers and a quad-port PCI Ethernet adapter for the database LPAR B. Two dual-port HEA/IVEs, one for the VIO servers, the other virtualized with two logical ports for the database LPAR C. One quad-port HEA/IVE with two ports being used for the VIO Servers and logical ports being used for the database LPAR D. One quad-port HEA/IVE with two ports being used for the VIO Servers, two ports used by the database LPAR and an additional PCI Ethernet adapter Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=98
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 99 What System Planning Tool function will provide a graphical image of the chassis and the partition information?

A. Report and print B. Export to a spreadsheet C. Report and export images D. Export to CFR file and import to e-Config Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=99
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 100 Who determines if a Technical and Delivery Assessment (TDA) is required and how in-depth it should be?

A. The customer initiates the process and determines the depth of the solution review. B. The opportunity owner follows the Solution Assurance Trigger Criteria to determine

need and depth. C. The TDA council uses the Designated Products List to determine if a review is needed and its depth. D. The IBM manufacturing requires confirmation that a pre-install TDA was completed before assembly and shipping. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=100
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 101 What are the three levels of review utilized in Technical and Delivery Assessments?

A. Self review, peer review, expert review B. Design review, customer review, order review C. Sales review, IBM review, manufacturing review D. Self review, business partner review, IBM review Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=101
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 102 Which Power Systems model has a separate SAS controller for the media bay, permitting it to be independently switchable?

A. Power 720 B. Power 730 C. Power 740 D. Power 770 Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=102
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 103 A customer with limited rack space wants to purchase a 4-core POWER7 server with a total of four 8Gb Fibre Channel adapters and four 2-port Ethernet adapters. Which server is the least expensive solution that meets the customer s requirements?

A. Power 710 B. Power 720 C. Power 740 D. Power 750 Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=103
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 104 A customer is considering consolidating several stand alone x86 systems. The following two

options are being considered: 1) A larger x86 processor than is currently installed using VMWare OR 2) A POWER7 processor-based system using PowerVM. They have reliable benchmark data for the proposed systems in a single workload environment comparing the proposed x86 and Power Systems. How should the processing demand of the target system be calculated?

A. Combine the raw performance ratings of the individual workloads. B. Combine the raw performance ratings of the individual workloads, and add overhead for VMWare on the x86 platform. C. Combine the raw performance ratings of the individual workloads, and add overhead for PowerVM on the Power Systems platform. D. Combine the raw performance ratings of the individual workloads, and add overhead for both VMWare and PowerVM on their respective platforms. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=104
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 105 How can a customer use existing traditional 3.5 inch SAS disks in a new 6-core Power 720 at minimum cost?

A. Disks can be placed into a FC #5802 PCI-e 12X I/O drawer. B. Disks can be placed into a FC #5796 PCI-x DDR 12X I/O drawer. C. Disks can be placed into a FC #5886 EXP 12S expansion drawer. D. Disks can be re-mounted in FC #6887 2.5 inch carriers and placed in the CEC. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=105
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 106 Which statement concerning Multiple Shared Processor Pools (MSPPs) in Power Systems is correct?

A. PowerVM Enterprise Edition is required. B. MSPPs have an associated Uncapped Weight. C. Capped and Uncapped LPARs can exist in MSPPs. D. Either AIX 6.1 or IBM i 6.1 (or later) is required. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=106
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 107 A customer has a Power Systems server running two AIX partitions hosting an eCommerce application that is heavily used during the daylight hours, and three IBM i partitions running the company s ERP and fulfillment systems. Each partition services separate geographical regions. All partitions are memory constrained for several hours each day, though not at the

same time. How can the customer address this problem?

A. Implement Active Memory Sharing (AMS) B. Configure Active Memory Expansion (AME) for each partition. C. Create a shared memory pool with the HMC, and add the partitions to it. D. Use the Systems Director Management Console (SDMC) to balance memory on demand. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=107
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 108 Which Power Systems virtualization technology allows an end user to relocate an application while maintaining its availability to users?

A. PowerVM Live Partition Mobility B. PowerVM Workload Partition Mobility C. PowerVM Mobile Logical Partitioning D. PowerVM Dynamic Logical Partitioning Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=108
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 109 Which function requires the customer to purchase PowerVM Standard Edition instead of PowerVM Express?

A. The ability to run x86 Linux applications B. The ability to run two LPARS on a Power 750 C. The ability to use VIO Server on a Power 750 D. The ability to use VIO Server on a Power 770 Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=109
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 110 What is the minimum required to support Active Memory Sharing (AMS)?

A. PowerVM Standard Edition B. PowerVM Enterprise Edition C. Systems Director Standard Edition D. Systems Director Enterprise Edition Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=110
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 111 A customer changed processor and memory resources to an LPAR dynamically using DLPAR, but the changes are not retained after the partition is shut down and reactivated. What will resolve this situation?

A. Recycle power to the managed system. B. Make the changes in the system profile. C. Make the changes in the partition profile. D. Use ASMI to apply the changes to the hypervisor. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=111
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 112 What is common to both NPIV and vSCSI?

A. They provide remote SAN management. B. They enable access to World Wide Names (WWNs). C. They provide virtualized access to tape devices. D. They enable Fibre Channel over Ethernet (FCoE) connectivity. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=112
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 113 What is used as the management interface to create dual VIO Servers on a PS704 Blade?

A. IVM B. HMC C. ASMI D. SDMC Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=113


-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 114 A customer has just purchased several Power 740 systems for their data center. They plan to monitor and manage energy consumption using Active Energy Manager. What additional element is necessary to implement the customer s plan?

A. PowerVM Enterprise Edition B. IBM System Director licenses C. Active Energy Variable Power Supplies D. Intelligent PDUs installed in the rack

Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=114
-------------------------------------------------------------------------------------------------------------------------------------

QUESTION: 115 What is a feature of Integrated Virtualization Manager (IVM)?

A. It enables using shared processor pools without an HM C. B. It provides tools to ease problem determination and service support. C. It allows the management of multiple systems from a single point in the network. D. The service processor can be locally accessed through a serial connection using system ports when the system is powered down. Answer: http://www.twpass.com/twpass.com/exam.aspx?ecode=000-106&qno=115
-------------------------------------------------------------------------------------------------------------------------------------

TwPass Certification Exam Features;


TwPass offers over 2500 Certification exams for professionals. More than 98,800 Satisfied Customers Worldwide. Average 99.8% Success Rate. Over 120 Global Certification Vendors Covered. Services of Professional & Certified Experts available via support. Free 90 days updates to match real exam scenarios. Instant Download Access! No Setup required. Price as low as $19, which is 80% more cost effective than others. Verified answers researched by industry experts. Study Material updated on regular basis. Questions / Answers are downloadable in PDF format. Mobile Device Supported (Android, iPhone, iPod, iPad) No authorization code required to open exam. Portable anywhere. Guaranteed Success. Fast, helpful support 24x7.

View list of All Exams (AE);


http://www.twpass.com/twpass.com/vendors.aspx

Download Any Certication Exam DEMO.


http://www.twpass.com/twpass.com/vendors.aspx

To purchase Full version of exam click below; http://www.TwPass.com/

Anda mungkin juga menyukai