mine (Peru)
Massachusetts Institute of Technology Engineering System Analysis for Design Richard de Neufville Michael Benouaich Slide 1 of 16
Note
This presentation is based on the case developed by Peter Tufano and Alberto Moel from the Harvard Business School. It contains simplifications. The figures appearing here differ from those presented by Tufano and Moel. They reflect the assumptions of the authors of this presentation about the treatment of uncertainty and the cash flows projection.
Massachusetts Institute of Technology Engineering System Analysis for Design Richard de Neufville Michael Benouaich Slide 3 of 23
Close mine
in Flexibility
Designers can create flexibility in system Ex: create port during exploration period, to provide flexibility to expedite development to 2 years (from 3) and thus advance revenue stream by 1 year and increase NPV
Massachusetts Institute of Technology Engineering System Analysis for Design Richard de Neufville Michael Benouaich Slide 8 of 23
Sources of Uncertainty
Revenues Mines life Future prices of zinc and copper Quantity of ore Costs Operation expenses Capital Expenditures
Massachusetts Institute of Technology Engineering System Analysis for Design
10
Sources of Uncertainty
Price and quantity uncertainty prevails only during the first two years Price risk is assumed to be eliminated in year 2 by entering forward contracts to sell the output of the mine (this is assumption M&T made a bit of a stretch) All other sources of uncertainty are modeled in the Monte Carlo simulation after year 2 Simulation result: Realization of expected NPV
Massachusetts Institute of Technology Engineering System Analysis for Design Richard de Neufville Michael Benouaich Slide 11 of 23
11
12
Value of on Option = EV(all positive NPV) EV(project without option to abandon) Value of in Option = further improvements in NPV due to flexibility provided
Massachusetts Institute of Technology Engineering System Analysis for Design Richard de Neufville Michael Benouaich Slide 13 of 23
13
10,000 Trials
.046
Frequency Chart
.034
342.7
.023
228.5
114.2
.000 ($1,092.85)
M
$4,238.52
0 $6,015.64
$2,461.40
14
10,000 Trials
.046
Frequency Chart
.034
342.7
.023
228.5
.011 Mean = $556.85 Mean = $819 $684.28 $2,461.40 $4,238.52 Certainty is 75.61% from $0.00 to $6,015.64
114.2
.000 ($1,092.85)
0 $6,015.64
15
16
17
Engineering Flexibility
Add flexibility, add value? Starting engineering study earlier and faster would allow you to shorten construction to two years and ramp up production faster
18
10,000 Trials
.046
Frequency Chart
.034
342.7
.023
228.5
114.2
.000 ($1,160.61)
0 $6,115.11
19
20
10,000 Trials
.046
.034
344.2
.023
229.5
.011 Mean = $566.91 Mean = $836 $770.71 $2,489.21 $4,207.72 Certainty is 76.09% from $0.00 to $5,926.22
114.7
.000 ($947.79)
0 $5,926.22
21
22
References
Tufano, P., Moel, A., (1997) Bidding for Antamina, Harvard Business School Case number 9-297-054, Rev. Sept. 15. Tufano, P., Moel, A., (2000) Bidding for the Antamina Mine Valuation and Incentives in a Real Option Context, in Project Flexibility, Agency, and Competition, edited by Brennan, M. and Trigeorgis, L., Oxford University Press Hertz, D. (1979) Risk Analysis in Capital Investment, Harvard Business Review September-October, pp. 169-180
Massachusetts Institute of Technology Engineering System Analysis for Design Richard de Neufville Michael Benouaich Slide 23 of 23
23