MANGALORE ELECTRICITY SUPPLY COMPANY LIMITED


Progress on various subsidiary Programme
R.E Works serviced from 2005-06 to 2009-10
Sl. No 1 2 3 4 5 6 7 2005-06 Division Target Mangalore Puttur Udupi Shimoga Sagar Chickmagalur Kadur 7 43 44 36 42 40 212 Progress 1 51 46 27 65 28 218 Target 36 108 108 94 105 73 71 595 Progress 7 119 136 97 109 55 2 525 Target 6 30 28 29 25 24 23 165 Progress 6 36 175 42 61 38 0 358 Target 10 28 20 21 23 16 16 134 Progress 8 60 61 15 34 46 0 224 Target 7 18 13 18 18 11 11 96 Progress 3 144 117 24 19 30 0 337 2006-07 2007-08 2008-09 2009-10

Company Total

MANGALORE ELECTRICITY SUPPLY COMPANY LIMITED


Progress on various subsidiary Programme
BJ/KJ serviced from 2005-06 to 2009-10
Sl. No 1 2 3 4 5 6 7 Division Mangalore Puttur Udupi Shimoga Sagar Chickmagalur Kadur 2005-06 Target 5750 6270 6330 9078 8970 9650 46048 Progress 43 1785 546 807 0 132 3313 2006-07 Target 4300 6000 6000 6850 6850 5000 5000 40000 Progress 180 2192 1458 4425 2771 605 1093 12724 2007-08 Target 1275 1475 2050 2050 2050 2050 2050 13000 Progress 241 1758 644 1984 2926 1913 718 10184 2008-09 Target 620 980 885 955 890 885 885 6100 Progress 254 2038 465 860 1752 675 336 6380 2009-10 Target 495 872 760 845 770 760 755 5257 Progress 118 1625 180 1183 928 441 238 4713

Company Total

MANGALORE ELECTRICITY SUPPLY COMPANY LIMITED


Progress on various subsidiary Programme
Ganga Kalyana Schemes serviced from 2005-06 to 2009-10
Sl. No. 1 2 3 4 5 6 7 Division Mangalore Puttur Udupi Shimoga Sagar Chickmagalur Kadur 2005-06 Target Progress 7 34 25 99 107 128 400 2006-07 Target Progress 4 35 20 137 84 46 35 361 2007-08 Target Progress 12 84 56 149 296 36 135 768 2008-09 Target Progress 48 239 141 262 515 127 222 1554 2009-10 Target Progress 31 224 113 143 190 118 234 1053

Company Total

RAJIV GANDHI GRAMEEN VIDHYUTHIKARAN YOJANA (R.G.G.V.Y)


RGGVY Scheme is launched by Govt. of India in April 2005 for providing access to Electricity to all House holds in villages/habitations with population more than 100 in 5 years. The Scheme is implemented through Rural Electrification Corporation (REC). 90% Capital Subsidy will be provided for over all Cost of project under the scheme. The rest is borne by MESCOM. Under the scheme, projects could be financed with capital subsidy for provision of: i. Rural Electricity Distribution Backbone (REDB) Provision of 33/11 KV (or 66/11KV) sub-stations of adequate capacity and lines in blocks where these do not exist. ii. Creation of village Electrification Infrastructure (VEI) Electrification of un-electrified villages. Electrification of un-electrified habitations. iii. Provision of distribution transformers of appropriate capacity in electrified villages/habitation(s). Electrification of un- electrified Below Poverty Line (BPL) households would be financed with 100% capital subsidy as per norms of Kutir Jyoti Programme in all rural habitations. BPL Beneficiaries will be provided free Kutir Jyothi connection and the Cost of Rs. 2200=00 per connection towards overall wiring, will be provided under the scheme. The tender invited for RGGVY works in Shimoga and Chickmagalur districts in MESCOM vide Bid Enquiry No: MESCOM/SEE (P)/EEE (APR) /TE-93/ 25-09-2008.

The details are as below: Sl. No. 1 2 3 4 5 Details No. of Habitations covered No. of Rural House Holds including BPL Houses BPL House Holds Project Cost (in Rs.Crores) Amount put to tender (in Rs.Crores) Shimoga District 121 42533 24415 47.68 43.82 Chickmagalur District 126 37147 16041 48.30 44.24

Projects for Shimoga and Chikmagalore Districts are sanctioned by REC on 19.02.2009 for Rs. 42.73 crores and 42.30 crores respectively. The details of Loan sanctioned and Loan released are as follows:
Financial Assistance Sanctioned For The Project (Rs. Lakhs) Capital Subsidy for the Project (Excl. grant for BPL househol ds) 3 Amount released (Rs. Lakh) Total Expendit ure Incurred (Rs. Lakh)

Sl. No.

Name of District

Grant for BPL Househo lds

Loan Amount

Total financial assistance for the project 6 7

Loan

Subsidy

TOTAL

10

1 2

Shimoga Chickmagalur Total

3309.01 3454.22 6763.23

537.13 352.90 890.03

427.35 423.01 850.36

4273.49 4230.13 8503.62

256.41 253.81 510.22

2174.87 2188.56 4363.43

2431.28 2442.37 4873.65

1278.71 1419.53 2698.24

Rural House Holds (including BPL) covered in the scheme is Shimoga Dist. 42533 and Chikmagalore Dist. 37147 nos. Out of these RHHs Kutir Jyothi connection of 24415 nos. in Shimoga Dist. and 16041 nos. in Chikmagalore Dist. will be provided free of cost.

Also all the 1440 Villages in Shimoga District and 1033 in Chikmagalore District which are already Electrified are covered under intensive Electrification if infrastructure exists, except those villages and Habitations with population less than 100. RGGVY works in both the Districts are awarded to M/s L&T Ltd., Bangalore on 20.2.2009. Quality Control Mechanism Methodology Of Quality Control In RGGVY Scheme, a new three tier Quality Control Mechanism (QCM) has been developed. First Tier: The project implementing agency (PIA) shall be responsible for first tier quality control. PIA shall prepare a detailed Quality Assurance Program, which should ensure quality cheeks as below: TURNKEY CONTRACTOR 100% material as per MQP 100% villages as per FQP 33/11KV sub-stations for quality of works in the field. 100% new sub-stations 100% Augmentation of sub-stations. 100% verification of BPL connections PROJECT IMPLEMENTING AGENCY 100% material as per MQP 100% villages as per FQP 33/11KV sub-stations for quality of works in the field. 100% new sub-stations 100% Augmentation of sub-stations. 100% verification of BPL connections THIRD PARTY INSPECTION AGENCY (To be engaged by project implementing agency) 10% material inspection at pre-shipment stage at vendors works on random sampling basis as per MQP

50% villages on random sampling basis 100% verification of BPL connections in 10% of villages to be inspected and in remaining villages atleast 5 BPL connections shall be verified. 33/11KV sub-stations for quality of works in the field on random sampling basis. 100% new sub-stations 50% Augmentation of sub-stations. Second Tier: Rural Electrification Corporation (REC) shall be responsible for second tier Quality Control Mechanism. Shall ensure quality checks as below: At least one inspection of major material like poles, transformers, conductors etc. at pre-shipment stage at vendors works on random sampling basis as per MQP for all manufacturers in every contract. 10% villages on random sampling basis as per FQP. 33/11 KV sub-stations for Quality of Works in the field covering. 25% new sub-stations. 5% Augmentation of sub-stations. 100% verification of BPL connections in 25% of villages to be inspected. VIP references/complaints referred by REC relating to Quality of Works. Third Tier: MOP shall be responsible for third tier Quality Control Mechanism. Shall ensure quality checks as below: 1% villages on random sampling basis as per FQP. 33/11KV sub-stations for quality of works in the field covering. At least one new sub-stations. At least one augmentation of sub-stations.

100% verification of BPL connections in all village to be inspected. Review of test records for major material like transformers, poles & conductors etc. on random sampling basis. Any other study of RGGVY assigned by MOP. Progress as on 31-03-2010.
Shimoga District No. of Villages identified for intensive electrification No. of Villages in which survey works completed (Cumulative) W.U.P (No. of Villages) Chikmagalur District No. of Villages in which survey work is completed (Cumulative) No. of Villages identified for intensive electrification W.U.P (No. of Villages) BPL Serviced 41 75 0 299 0 113 42 570

Sl. No

Name of Taluks

W. C

BPL Serviced

Name of Taluks

W.C.

1 2 3 4 5 6 7

Shimoga Bhadravathi Thirthahalli Sagar Soraba Shikaripura Hosanagar Total

170 129 224 204 248 144 170 1289

170 129 224 204 248 144 170 1289

33 46 49 83 72 103 34 420

1 81 0 0 14 27 0 123

37 789 0 0 268 887 0 1981

Chickmagalur Mudigere Sringeri N.R.Pura Koppa Kadur Tarikere Total

200 129 46 57 73 245 191 941

200 129 46 57 73 245 191 941

17 41 1 21 16 36 22 154

1 5 0 7 0 6 4 23