EAPM

BP.080 TO BE PROCESS
RailTel Corporation of India Limited Purchasing

Author: Creation Date: Last Updated: Document Ref: Version:

Ajay Kummar Singh 12-Jan-2013 22-March-2013 RCIL-BP080-PO 1.0

Disclaimer:
This document is a confidential document between Wipro Ltd. and RailTel Corporation Of India Limited. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or by any means, whether electronic, mechanical, photocopying, recording or otherwise, without the written permission of Wipro / RCIL. This document includes confidential information related to Wipro and RCIL and shall not be distributed to any persons other than those mentioned in the distribution list herein. All product names referenced herein are trademarks of their respective companies

BP.080 - Purchasing Process

Document Control

Change Record
4

Date 12-Jan-2013 22-Mar-2013

Author Ajay Singh Ajay Singh

Version 0.1 1.0

Change Reference Base Document Final Version

Reviewers
Name Prithwish Chatterjee Swarup Ghosal Chaudhary Position Wipro Project Manager Wipro Program Manager

Approver
Name Sh. Kamal Kant Kaushaik Sh. Kumar Bachchan Sh. A K Sablania Sh. Ashutosh Vasant Sh. Puran Singh Sh. Suresh Kumar Position Manager - Projects Sr. Manager - DNM GGM DNM GM - Projects GGM - Infrastructure GGM NTP Signature

Distribution
Copy No. 1 2 3 4 5 Name RailTel Project Parivartan Steering Committee RailTel Project Parivartan Core Working Group RailTel Project Parivartan Regional CWG Wipro Onsite Team Wipro Technical Team Location Gurgaon Gurgaon New Delhi/Mumbai/Secunderabad/Kolkata Gurgaon Gurgaon

Note to Holders: If you receive an electronic copy of this document and print it out, please write your name on the equivalent of the cover page, for document control purposes. If you receive a hard copy of this document, please write your name on the front cover, for document control purposes.

Company Confidential - For internal use only

BP.080 - Purchasing Process

Contents

Document Control ..................................................................................................................... ii Introduction ............................................................................................................................... 1 About this Document.......................................................................................................... 1 How this document is organized ........................................................................................ 2 Generic Assumptions .......................................................................................................... 3 Overall Project & Procurement Flow ......................................................................................... 4 PO 01 - On Line Purchase Indent Process .................................................................................. 6 PO 02 - Purchase Indent Process ............................................................................................... 9 PO 03 - Indent Preparation & Approval ................................................................................... 11 PO 04 - Overall Procurement Tender Process (Supply Item) ................................................... 13 PO 05 - Overall Project Tender Process (Works/Service/Item) ............................................... 17 PO 06 - Open/Global Tender Process Single Packet ............................................................. 21 PO 07 - Open/Global Tender Process Two Packet ................................................................ 24 PO 08 - Limited Tender Process ............................................................................................... 27 PO 09 - Single Tender Process ................................................................................................. 30 PO 10 - Dispensation of Tender Process for Material .............................................................. 33 PO 11 - Dispensation of Tender Process for Works Contract & Execution .............................. 35 PO 12 - Procurement Process for Material (Supply Item) ....................................................... 38 PO 13 - Procurement Process for Works Contract (Supply, Installation & Commissioning) ... 41 PO 14 - Procurement Process for Execution ............................................................................ 44 PO 15 - Procurement Process for AMC (Equipments, Sections, Miscellaneous) ..................... 47 PO 16 - Procurement Process for Inspection (Material, Works Contract & Execution) .......... 49 PO 17 - Imprest/Advance Procurement Process ..................................................................... 52 PO 18 - Bank Guarantee Process ............................................................................................. 54 PO 19 - Site Readiness Process-For Material and Service ........................................................ 56 PO 20 - Inspection Process....................................................................................................... 59 PO 21 - Standard Purchase Order Process ............................................................................... 62 PO 22- Rate Contract for Material (Supply Item) ..................................................................... 65 PO 23 - Rate Contract Releases of Material (Sub PO) .............................................................. 68 PO 24 - Rate Contract for Service & Works Contract ............................................................... 71 PO 25 - Rate Contract Releases of Service & Works Contract (Sub PO) .................................. 75 PO 26 - Advance Purchase Order ............................................................................................. 78 PO 27 - Advance Purchase Order Release (Sub PO) ................................................................ 80

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 28 - Global Purchase Agreement........................................................................................ 83 PO 29 - Maintain Purchase Order Process (Variation/Enhancement in Quantities) ............... 86 PO 30 - RFI- Request for Information (Tender Process) ........................................................... 89 PO 31 - Request for Quotation and Quotations (Tender Process)........................................... 92 PO 32 - Supplier Registration (iSupplier Module) .................................................................... 96 PO 33 PO/LOA Acknowledgement (iSupplier Module) ......................................................... 98 PO 34 - ASN Creation and Online Submission (iSupplier Module) ......................................... 101 PO 35 - Contracting Process (Procurement Contract) ........................................................... 104 PO 36 - Contracting Amendment Process (Procurement Contract) ...................................... 107 PO 37 - Approved Supplier List (ASL) ..................................................................................... 110 PO 38 Spot Purchase Process.............................................................................................. 113 PO 39 Inspection Waiver Process ....................................................................................... 116 PO 40 Delivery Period/Date of Completion - Extension ..................................................... 119 Open and Closed Issues for this Deliverable .......................................................................... 121 Open Issues..................................................................................................................... 121 Closed Issues ................................................................................................................... 121

Company Confidential - For internal use only

BP.080 - Purchasing Process

Introduction
About this Document
RAILTEL has appointed Wipro Limited to implement Oracle E-Business Suite. The implementation spans Financials and Supply Chain Management processes. This document describes the Procurement Process for RAILTEL. The project is divided into Five Stages viz. Plan, Analyse, Design, Develop and Go-Live. The Analyse Stage covers identifying the gaps in the As-Is processes and re-designing them in order to adopt leading processes as also to harness the capability of the chosen technology. This document contains the RAILTEL Procurement process flow that would be configured onto the Oracle E-Business Suite.

Company Confidential - For internal use only

BP.080 - Purchasing Process

How this document is organized


This document forms deliverable of the operation analysis phase of the ERP implementation project for RailTel. The purpose of this document is to compile a comprehensive list of requirements against which to map Application features. The scenarios listed in the subsequent sections are reusable templates and are created once for each business process. Each of the following sections consists of the following sub sections: Assumptions Any assumptions that are specific to the process being detailed are recorded in this sub section. Process Scenario The Event initiates the corresponding process. Process Solution: 1. 2. Description 1. 2. Process Title & Description: The bold letters gives the process title followed by the detailed description of the process in normal font. Key Requirements from the above process Complete process flow Process Id #: process. Unique number for the sub-processes within the main

Requirement Fulfillment using ERP Approach 1. Solution Type & Description: Used to designate type of solution. The types mentioned here are Screen, Manual and System. The Screen refers to the type where the data is to be entered in the screen or can be viewed in the screen. Manual type is the manual way of doing the process whether the user would be performing the process in the system or otherwise. The System type of solution is referred to when the system performs the step through automation or sub-automation. The following keys can be used for the process in the system. i. S Standard ii. W - Workaround iii. C Extension/Customization 2. Navigation Path: The path to navigate to the relevant functionality in Applications. The following acronyms have been used for navigation type: i. (T) Tab ii. (B) Button iii. (CB) Check Box iv. (F) Field

3.

Impact analysis Process Improvements Quality & Customer Service

Company Confidential - For internal use only

BP.080 - Purchasing Process

Leading Practices Note: The texts in grey shade are optional activities.

Generic Assumptions
Any additional information captured in ERP through external systems will be highly dependent on the external systems. Wipro will not be responsible for the functioning or the implementation of the external systems. Customizations identified in the requirement definition document will be developed subject to the scope defined in the approved project charter.

Company Confidential - For internal use only

BP.080 - Purchasing Process

Overall Project & Procurement Flow

Company Confidential - For internal use only

BP.080 - Purchasing Process

Railtel End to End Project Flow and Integration with other Modules
General Ledger

ERP

Manual

Payables
Note: The Business plan is conceptualized by the Railtel Directors Business Plan prepared by Railtel Team / Consultants Projects are created as per the Business plan decided.

Fixed Assets

Receivables

Business

START

Business Plan

General Ledger Budget Definition as per the Business Plan Transaction posted form other Modules

Finance

Invoicing related to Project in Payables

Asset Posting in Fixed Assets

Invoice to the Customer in Recievables

Sources of the Projects Railways Pink Book Railtel Law Book Others Marketing

Project Creation & Approval

Workplan Creation, Versioning and Progress Management

Project Budget Creation, Revision & Approval

Project Status Inquiry

Project Asset Creation & Transfer to FA

Projects

Note : The Approval related to the projects is further elaborated in the next flow. The Project Planning team will do the estimation and enter the budget in the system. The details estimate will be done and Indent / Requisitions will be raised with reference to the project. Detail processes related to the project are further elaborated in the document.

Project Closure

Procurement

Purchase Indent/ Creation & Approval

Tender Creation & Floating

Commercial & Technical Analysis

Purchase Orders/APO/ Rate Contracts

Inspection & Recieving

Transfer to Inventory/ Project Vice Versa

Marketing & Sales

Demand Note Creation & Customer Acceptance

Sales Order Booking

Contract Creation

Billing END

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 01 - On Line Purchase Indent Process

Company Confidential - For internal use only

BP.080 - Purchasing Process

On Line Purchase Indent Process

ERP

Manual

Email

Start

Log in to I Procurement Enter indent online using web forms and catalogs O&M activities

Projects (Railway/ RailTel/LMC etc)

Find Items

Add Items , Quantity Add and Items delivery & Quantity location detail

All Departments

Proceed to Check Out Others (General Admin etc.)

Edit Shopping Cart No Proceed to Check Out

Workflow based purchase indent approval Yes Procurement Process PO12

Submit Indent

Check Out

Review/Modify Indent

Supplier notified and deliver the goods

Record receipt in to the web

End

Finance

Finance Vetting

RAILTEL Process: On Line Purchase Indent Process

Business Function: RAILTEL Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 01

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 01

Description: This step explains the On Line Purchase Indent Process.

Event

Description: This process is triggered to raise the online purchase indent. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID #

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y Y Y Y

Procurement Procurement Procurement Procurement Procurement Procurement Procurement

POM_PO_PI_1 POM_PO_PI_1 POM_PO_PI_1 POM_PO_PI_1 POM_PO_PI_1 POM_PO_PI_1 POM_PO_PI_1

PO 01.01 PO 01.02 PO 01.03 PO 01.04 PO 01.05 PO 01.06 PO 01.07

On line Indent will be created using web forms and catalogs. Find Items online and add quantity and delivery details. Edit, modify and review indent online. Online Indent will be submitted. Purchase Indent will be approved as per defined approval hierarchy. After approval of Online Indent, Procurement process is initiated. Supplier notified and delivers the goods as required. Receipt detail will be recorded.

System System System System System System System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 02 - Purchase Indent Process


Purchase Indent Process
ERP Manual Email

Start User to enter the Indent Header details Enter the Line details Item code, Qty, Need by date, Etc Select the Organization, Location and Supplier(Optional) Capture the Charge Account, If any consumables items(without Item Code)

O&M activities

All Departments

Projects (Railway/ RailTel/LMC etc)

Others (General Admin etc.)

Save the Document and submit for Approval

Purchase Indent Approved

Yes

Automatic notification to Requestor

End

No Approved Purchase Indent becomes the input for Purchase Order to be created by the Purchasing department Procurement Process PO12

Finance

Finance Vetting

Company Confidential - For internal use only

BP.080 - Purchasing Process

RAILTEL Process: Purchase Indent Process Control Number: PO 02

Business Function: RAILTEL Project Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 02

Description: This step explains the Purchase Indent Process.

Event

Description: This process is triggered to raise the purchase indent. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID #

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y Y

Procurement Procurement

POM_PO_PI_1 POM_PO_PI_1

PO 02.01 PO 02.02

User will create the Indent by mentioning the PR headers details like the PR type , Description Create Purchase Indent with information like item or description, quantity and (Approx) purchase price. When item not available the user should choose purchasing category and write a description. Indent preparers should select the inventory organization name, location and Supplier details (options). Select the Charge Account Number in case of Expense or Consumables items. Generate a Purchase Indent with automatic document number. Submit the purchase Indent for approval through the delegation of authority. Requester will not be able to approve Indent. Indent approval will be a workflow based process based on approval limits. Approved Purchase Indent is the input for Purchase Order Creation.

System System

Procurement

POM_PO_PI_1

PO 02.03

System

Procurement Procurement Procurement Procurement

POM_PO_PI_1 POM_PO_PI_1 POM_PO_PI_1 POM_PO_PI_1

PO 02.04 PO 02.05 PO 02.06 PO 02.07

System System System System

Y Y Y Y

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 03 - Indent Preparation & Approval


Indent Preparation & Approval
ERP Manual

Territory Level
Start

Regional Level

Corporate Level

Project & Procurement

Indent/ Estimates raised at territory level

Submit for approval & Finance Concurrence

RO collates all Indent/ Estimates of territory level and prepares consolidated proposal Or Indent/Estimate raised at regional level

Submit for approval & Finance Concurrence

CO collates all Indent/ Estimates of regional level and prepares consolidated proposal Or Indent/Estimate raised at corporate level

Submit for approval & Finance Concurrence

More Info

No

Yes

Yes

More Info

More Info

Finance

More Info Tender Process at Territory Level If applicable PO04-PO05 Tender Process at Regional Level PO04-PO05

More Info

Company Confidential - For internal use only

oN

No
Approval as per SOP Yes Approval from TM as per SOP Finance concurrence as per SOP Yes Approval from RGM as per SOP Corporate finance concurrence as per SOP Yes More Info Approval from MD/Director as per SOP Tender Process at Corporate Level PO04-PO05 End

BP.080 - Purchasing Process

RAILTEL Process: Indent Preparation & Approval Control Number: PO 03

Business Function: RAILTEL Project Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 03

Description: This step explains the Indent preparation and approval.

Event

Description: This process is triggered whenever an Indent is prepared and approved. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID #

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y Y Y Y Y Y Y

Procurement Procurement Procurement Procurement Procurement Procurement Procurement Procurement Procurement Procurement

POM_RP_EP_2 POM_RP_EP_2 POM_RP_EP_2 POM_RP_EP_2 POM_RP_EP_2 POM_RP_EP_2 POM_RP_EP_2 POM_RP_EP_2 POM_RP_EP_2 POM_RP_EP_2

PO 03.01 PO 03.02 PO 03.03 PO 03.04 PO 03.05 PO 03.06 PO 03.07 PO 03.08 PO 03.09 PO 03.10

Indent/Estimates are raised at territory level Indent is submitted for approval Approval is done as per SOP Final approval is done from TM as per SOP RO collates all indent/estimates of territory level and prepares consolidated proposal then it is put up for approval Approval from finance for concurrence is done as per SOP Final approval is done from RGM as per SOP CO collates all indent/estimates of regional level and prepares consolidated proposal then it is put up for approval Approval from finance for concurrence is done as per SOP Final approval is done from CMD/Director as per SOP

System System System System System System System System System System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 04 - Overall Procurement Tender Process (Supply Item)

Company Confidential - For internal use only

BP.080 - Purchasing Process

Overall Procurement Tender Process


Start Project Budgeting Process PRJ05 Tender processing officer is nominated

ERP

Manual

Email B

Business Plan

Global Tender

NIT Published in News Paper (Online)

Approved Supplier List or Fresh approved supplier list via approval PO37

Tender Document Floated Railways OFC Section Works Purchase Indent/ Estimates raised at Territory Level.(Project budget will be revised if indent estimate increases more than project budget) RO collates all requisitions from territories & Prepares consolidated proposal Open Tender NIT and Tender Document uploaded on website PR Process Limited Tender CO collates all requisitions from regions & Prepares consolidated proposal Special Limited Tender Tender cost Estimation prepared and Put up to Finance for Finance Vetting & approval as per SOP along with PAC issued by Region/ Corporate and approved by Director

Prebid meeting and change/modification Tender document accordingly

Receive response from bidder

Tender document is opened by nominated TOC

Comparative sheet and Briefing note are prepared by executive

TC nomination as per SOP

Vetted comparative sheet and Briefing note put up to TC

Other Railways Project

Procurement

Purchase Indent/ Estimates raised at regional Level Other Customer Project

Discharge

Purchase Indent raised at corporate level O&M Activities

TC prepares final observation Single Tender

Comparative sheet & final minutes sent to TAA for approval

Purchase Order Issued to successful bidder. Tender estimate will be revised if PO estimate increases more than tender estimate.

Acceptance from Supplier

Successful bidder deposit various documents like PBG, Security Deposit

EMD Return to unsuccessful bidder & EMD returns to successful bidder or adjusted with Invoice

A Govt. Projects

Quotation Non-Acceptance

Negotiation may done with supplier Acceptance

Supplier Registration Process PO32

End

Counter offer/LOI

Finance

EMD handed over to finance

Comparative sheet & Briefing note vetted by finance

Tender cost Estimation prepared and Put up to Finance for Finance Vetting

RAILTEL Process: Overall Procurement Tender Process

Business Function: RAILTEL Tender

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 04

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 04

Description: This step explains the Overall Procurement Tender process for material.

Event

Description: This process is triggered Whenever a Tender is created for material. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID #

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y

Requirement Generation

POM_TP_ RG_1

PO 04.1

Indent/Estimates

POM_RP_ EP_2

PO 04.2

Tender Document

POM_TP_ TD_2

PO 04.3

Requirement for floating the tender is triggered from the various sources. Business Plan (Long Term & Short Term) Railway Project OFC section works Other Railway Projects Other Customer projects O&M activities Customer Lead Government Project Purchase Indent/Estimates raised at territory and regional level RO & CO collates all the indent and prepares consolidated proposal Estimates and Tender document prepared and put up to finance for finance vetting. Tender Processing officer is nominated. Tender are of various types, open tender, limited tender, special limited tender, Global tender, single tender and quotation. Respective tender document is created. As per SOP and schedule of work, Tender process is followed and floated; Simultaneously It is published in news paper and on RailTel website also. As required tender is floated to selected supplier from approved supplier list. Prebid meeting is done and tender document is changed accordingly Response is received from various vendors.

Manual

System

System

Tender Document Execution

POM_TP_ TE_3

PO 04.4

System

Company Confidential - For internal use only

BP.080 - Purchasing Process

AS IS Process

AS IS ID #

Process ID #

Description Mode Tender document is opened by nominated TOC Comparative sheet and Briefing note are prepared by executive EMD is hand over to finance and Comparative sheet and briefing note are vetted by finance. TC nomination is done. Vetted comparative sheet put up to TC and TC prepares the final observation. Comparative sheet and final minutes sent to competent authority approval. Negotiation is done if required and Discharge can also be happen Counter offer process is done for final price. Purchase Order is issued to successful bidder and acknowledgment is received. Successful bidder deposit various document like PBG, Security deposit. Simultaneously EMD is returned to unsuccessful bidder.

Requirement Fulfillment using ERP Approach (Y/N)

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 05 - Overall Project Tender Process (Works/Service/Item)

Company Confidential - For internal use only

BP.080 - Purchasing Process

Overall Project Tender Process


Start Project Budgeting Process PRJ05 Tender processing officer is nominated

ERP

Manual

Email

Business Plan

Global Tender

NIT Published in News Paper (Online)

Approved Supplier List or Fresh approved supplier list via approval PO37

Tender Document Floated Railways OFC Section Works Purchase Indent/ Estimates raised at Territory Level.(Project budget will be revised if indent estimate increases more than project budget) RO collates all requisitions from territories & Prepares consolidated proposal Open Tender NIT and Tender Document uploaded on website PR Process Limited Tender CO collates all requisitions from regions & Prepares consolidated proposal Special Limited Tender Tender cost Estimation prepared and Put up to Finance for Finance Vetting & approval as per SOP along with PAC issued by Region/ Corporate and approved by Director

Prebid meeting and change/modification Tender document accordingly

Receive response from bidder

Tender document is opened by nominated TOC

Comparative sheet and Briefing note are prepared by executive

TC nomination as per SOP

Vetted comparative sheet and Briefing note put up to TC

Other Railways Project Purchase Indent/ Estimates raised at regional Level Other Customer Project

Discharge

Project

Purchase Indent raised at corporate level O&M Activities

TC prepares final observation Single Tender

Comparative sheet & final minutes sent to TAA for approval

LOA Issued to successful bidder. Tender estimate will be revised if LOA estimate increases more than tender estimate.

Acceptance from Supplier

Successful bidder deposit various documents like PBG, Security Deposit

EMD Return to unsuccessful bidder & EMD returns to successful bidder or adjusted with Invoice

A Quotation Govt. Projects Non-Acceptance

Negotiation may done with supplier Acceptance

Supplier Registration Process PO32

End

Counter offer/LOI

Finance

EMD handed over to finance

Comparative sheet & Briefing note vetted by finance

Tender cost Estimation prepared and Put up to Finance for Finance Vetting

RAILTEL Process: Overall Project Tender Process

Business Function: RAILTEL Tender

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 05

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 05

Description: This step explains the Overall Project Tender process for Service and Work Contract.

Event

Description: This process is triggered Whenever a Tender is created for service and works contract. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID #

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y

Requirement Generation

POM_TP_ RG_1

PO 05.1

Indent/Estimates

POM_RP_ EP_2

PO 05.2

Tender Document

POM_TP_ TD_2 POM_TP_ TE_3

PO 05.3

Tender Document Execution

PO 05.4

Requirement for floating the tender is triggered from the various sources. Business Plan (Long Term & Short Term) Railway Project OFC section works Other Railway Projects Other Customer projects O&M activities Customer Lead Government Project Purchase Indent/Estimates raised at territory and regional level RO & CO collates all the indent and prepares consolidated proposal Estimates and Tender document prepared and put up to finance for finance vetting. Tender Processing officer is nominated. Tender are of various types, open tender, limited tender, special limited tender, Global tender, single tender and quotation. Respective tender document is created. As per SOP and schedule of work, Tender process is followed and floated; Simultaneously It is published in news paper and on RailTel website also. As required tender is floated to selected supplier from approved supplier list. Prebid meeting is done and tender document is changed accordingly Response is received from various vendors. Tender document is opened by nominated TOC Comparative sheet and Briefing note are prepared by executive

Manual

System

System

System

Company Confidential - For internal use only

BP.080 - Purchasing Process

AS IS Process

AS IS ID #

Process ID #

Description Mode EMD is hand over to finance and Comparative sheet and briefing note are vetted by finance. TC nomination is done. Vetted comparative sheet put up to TC and TC prepares the final observation. Comparative sheet and final minutes sent to competent authority approval. Negotiation is done if required and Discharge can also be happen Counter offer process is done for final price. LOA is issued to successful bidder and acknowledgment is received. Successful bidder deposit various document like PBG, Security deposit. Simultaneously EMD is returned to unsuccessful bidder.

Requirement Fulfillment using ERP Approach (Y/N)

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 06 - Open/Global Tender Process Single Packet


Open/Global Tender Process Single Packet
ERP Manual Email B

Start

Project Budgeting Process PRJ05 Tender processing officer is nominated RO collates all requisitions from territories & Prepares consolidated proposal

NIT Published in News Paper (Online)

Open/Global Tender document floated

Purchase Indent/ Estimates raised at Territory Level.(Project budget will be revised if indent estimate increases more than project budget)

Receive response from bidder

Tender document is opened by nominated TOC

Comparative sheet and Briefing note are prepared by executive

TC nomination as per SOP

Vetted comparative sheet and Briefing note put up to TC

NIT and Tender Document uploaded on website PR Process

Project & Procurement

Purchase Indent/ Estimates raised at regional Level

CO collates all requisitions from regions & Prepares consolidated proposal

Discharge

Purchase Indent raised at corporate level

Tender cost Estimation prepared and Put up to Finance for Finance Vetting & approval as per SOP

TC prepares final observation

Comparative sheet & final minutes sent to TAA for approval

Purchase Order/LOA Issued to successful bidder. Tender estimate will be revised if LOA/PO estimate increases more than tender estimate.

Acceptance from Supplier

Successful bidder deposit various documents like PBG, Security Deposit

EMD Return to unsuccessful bidder & EMD returns to successful bidder or adjusted with Invoice

A Negotiation may done with supplier Non-Acceptance Acceptance Supplier Registration Process PO32

Counter offer/LOI

End

Finance

EMD handed over to finance

Comparative sheet & Briefing note vetted by finance

Tender cost Estimation prepared and Put up to Finance for Finance Vetting

Company Confidential - For internal use only

BP.080 - Purchasing Process

RAILTEL Process: Open/Global Tender Process Single Packet Control Number: PO 06

Business Function: RAILTEL Tender Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 06

Description: This step explains the Open/Global Tender process for Single Packet.

Event

Description: This process is triggered Whenever an Open Tender is created. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID #

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N)

Indent/Estimates

POM_RP_ EP_2

PO 06.1

Tender Document Tender Document Execution

POM_TP_ TD_2 POM_TP_ TE_3

PO 06.2 PO 06.3

Purchase Indent/Estimates raised at territory and regional level RO & CO collates all the indent and prepares consolidated proposal Estimates and Tender document prepared and put up to finance for finance vetting. Tender Processing officer is nominated for Open/Global Tender Single Packet. As per SOP and schedule of work, Tender process is followed and floated; Simultaneously It is published in news paper and on RailTel website also. Response is received from various vendors. Tender document is opened by nominated TOC Comparative sheet and Briefing note are prepared by executive EMD is hand over to finance and Comparative sheet and briefing note are vetted by finance. TC nomination is done. Vetted comparative sheet put up to TC and TC prepares the final observation. Comparative sheet and final minutes sent to competent authority approval. Negotiation is done if required and Discharge can also be happen Counter offer process is done for final price. PO/LOA is issued to successful bidder and acknowledgment is received. Successful bidder deposit various document like PBG, Security deposit.

System System

Y Y

Company Confidential - For internal use only

BP.080 - Purchasing Process

AS IS Process

AS IS ID #

Process ID #

Description Mode Simultaneously EMD is returned to unsuccessful bidder.

Requirement Fulfillment using ERP Approach (Y/N)

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 07 - Open/Global Tender Process Two Packet


Open/Global Tender Process Two Packet
NIT Published in News Paper (Online) ERP Manual Email B

Start

Project Budgeting Process PRJ05 Tender processing officer is nominated RO collates all requisitions from territories & Prepares consolidated proposal

Prebid queries Publish on Website

Open/Global Tender document floated

Purchase Indent/ Estimates raised at Territory Level.(Project budget will be revised if indent estimate increases more than project budget)

Prebid Meeting & Change/Modify Tender document

Receive response from bidder

Tender document(Technical) is opened by nominated TOC

Price bid kept in seal packet with executive along with seal of RCIL and sign. of TOC and all bidders

Briefing note are prepared by executive

TC nomination as per SOP

Vetted Briefing note put up to TC

NIT and Tender Document uploaded on website PR Process

EMD and Unopened Price bid returns to unsuccessful bidders

Notification to all successful bidder of Price bid

B C

Project & Procurement

Purchase Indent/ Estimates raised at regional Level

CO collates all requisitions from regions & Prepares consolidated proposal

TC prepares final observation

Final minutes sent to TAA for approval

Price TC opened by nominated TOC

Comparative sheet are prepared by executive

Vetted comparative sheet put up to TC

Purchase Indent raised at corporate level

Tender cost Estimation prepared and Put up to Finance for Finance Vetting and approval as per SOP

Discharge

TC prepares final observation

Comparative sheet & final minutes sent to TAA for approval

Purchase Order/LOA Issued to successful bidder. Tender estimate will be revised if LOA/PO estimate increases more than tender estimate.

Acceptance from Supplier

Successful bidder deposit various documents like PBG, Security Deposit

EMD Return to unsuccessful bidder & EMD returns to successful bidder or adjusted with Invoice

Non-Acceptance

Negotiation may done with supplier

Acceptance

Supplier Registration Process PO32

Counter Offer/LOI End

Finance

EMD handed over to finance

Comparative sheet & Briefing note vetted by finance

Tender cost Estimation prepared and Put up to Finance for Finance Vetting

Company Confidential - For internal use only

BP.080 - Purchasing Process

RAILTEL Process: Open/Global Tender Process Two Packet Control Number: PO 07

Business Function: RAILTEL Tender Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 07

Description: This step explains the Open/Global Tender process for Two Packet.

Event

Description: This process is triggered Whenever an Open Tender is created. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID #

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) N

Indent/Estimates

POM_RP_ EP_2

PO 07.1

Tender Document Tender Document Execution

POM_TP_ TD_2 POM_TP_ TE_3

PO 07.2 PO 07.4

Purchase Indent/Estimates raised at territory and regional level RO & CO collates all the indent and prepares consolidated proposal Estimates and Tender document prepared and put up to finance for finance vetting. Tender Processing officer is nominated for Open/Global Tender Two Packet. As per SOP and schedule of work, Tender process is followed and floated; Simultaneously It is published in news paper and on RailTel website also. Prebid meeting is done and tender document is changed /modified accordingly. Prebid queries are published on website also. Response is received from various vendors. Tender document (Technical) is opened by nominated TOC Price bid kept in seal packet with executive along with seal of RCIL and sign. of TOC and all bidders Briefing note is prepared by executive. EMD is hand over to finance and briefing note is vetted by finance. TC nomination is done. Vetted Briefing note put up to TC and TC prepares the technical observation. Technical minutes sent to competent authority for approval. EMD and unopened price bid returned to unsuccessful bidder

Manual

System System

Y Y

Company Confidential - For internal use only

BP.080 - Purchasing Process

AS IS Process

AS IS ID #

Process ID #

Description Mode Price TC opened by nominated TOC Notification is sent to all successful bidders of price bid for opening. Comparative sheet and Briefing note are prepared by executive Comparative sheet and briefing note are vetted by finance. Vetted comparative sheet put up to TC and TC prepares the final observation. Comparative sheet and final minutes sent to competent authority approval. Negotiation is done if required and Discharge can also be happen Counter offer process is done for final price. PO/LOA is issued to successful bidder and acknowledgment is received. Successful bidder deposit various document like PBG, Security deposit. Simultaneously EMD is returned to unsuccessful bidders.

Requirement Fulfillment using ERP Approach (Y/N)

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 08 - Limited Tender Process


Limited Tender
ERP Manual Email B Project Budgeting Process PRJ05 Tender processing officer is nominated RO collates all requisitions from territories & Prepares consolidated proposal Approved Supplier List PO37 Fresh approved supplier list via approval

Start

Limited Tender floated to selected vendor

Purchase Indent/ Estimates raised at Territory Level.(Project budget will be revised if indent estimate increases more than project budget)

Prebid Meeting & Change/Modify Tender document

Receive response from bidder

Tender document is opened by nominated TOC

Comparative sheet and Briefing note are prepared by executive

TC nomination as per SOP

Vetted comparative sheet and Briefing note put up to TC

NIT and Tender Document uploaded on website PR Process

Project & Procurement

Purchase Indent/ Estimates raised at regional Level

CO collates all requisitions from regions & Prepares consolidated proposal

Discharge

Purchase Indent raised at corporate level

Tender cost Estimation prepared and Put up to Finance for Finance Vetting & approval as per SOP

TC prepares final observation

Comparative sheet & final minutes sent to TAA for approval

Purchase Order/ LOA Issued to successful bidder. Tender estimate will be revised if LOA/ PO estimate increases more than tender estimate.

Acceptance from Supplier

Successful bidder deposit various documents like PBG, Security Deposit

EMD Return to unsuccessful bidder & EMD returns to successful bidder or adjusted with Invoice

Negotiation may done with supplier Non-Acceptance Acceptance

Supplier Registration Process PO32

Counter offer/LOI

End

Finance

EMD handed over to finance

Comparative sheet & Briefing note vetted by finance

Tender cost Estimation prepared and Put up to Finance for Finance Vetting

Company Confidential - For internal use only

BP.080 - Purchasing Process

RAILTEL Process: Limited Tender Process Control Number: PO 08

Business Function: RAILTEL Tender Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 08

Description: This step explains the Limited Tender process.

Event

Description: This process is triggered Whenever a Limited Tender is created. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID #

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y

Indent/Estimates

POM_RP_ EP_2

PO 08.1

Tender Document

POM_TP_ TD_2 POM_TP_ TE_3

PO 08.2

Purchase Indent/Estimates raised at territory and regional level RO & CO collates all the indent and prepares consolidated proposal Estimates and Tender document prepared and put up to finance for finance vetting. Tender Processing officer is nominated and Limited tender is floated to selected vendors. As per SOP and schedule of work, Tender process is followed and floated; Simultaneously It is published on RailTel website also. As required tender is floated to selected supplier from approved supplier list or fresh approved supplier list can be created before floating the tender document. Prebid meeting may be done and tender document is changed accordingly if required. Response is received from various vendors. Tender document is opened by nominated TOC Comparative sheet and Briefing note are prepared by executive EMD is hand over to finance and Comparative sheet and briefing note are vetted by finance. TC nomination is done. Vetted comparative sheet put up to TC and TC prepares the final observation.

System

System

Tender Document Execution

PO 08.3

System

Company Confidential - For internal use only

BP.080 - Purchasing Process

AS IS Process

AS IS ID #

Process ID #

Description Mode Comparative sheet and final minutes sent to competent authority approval. Negotiation is done if required and Discharge can also be happen Counter offer process is done for final price. LOA is issued to successful bidder and acknowledgment is received. Successful bidder deposit various document like PBG, Security deposit. Simultaneously EMD is returned to unsuccessful bidder.

Requirement Fulfillment using ERP Approach (Y/N)

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 09 - Single Tender Process


Single Tender
ERP Manual Email B Project Budgeting Process PRJ05 Tender processing officer is nominated RO collates all requisitions from territories & Prepares consolidated proposal C Approved Supplier List PO37 Fresh approved supplier list via approval

Start

Single Tender floated to single vendor

Purchase Indent/ Estimates raised at Territory Level.(Project budget will be revised if indent estimate increases more than project budget)

Receive response from bidder

Tender document is opened by nominated TOC

Comparative sheet and Briefing note are prepared by executive

TC nomination as per SOP

Vetted comparative sheet and Briefing note put up to TC

Project & Procurement

Purchase Indent/ Estimates raised at regional Level

CO collates all requisitions from regions & Prepares consolidated proposal

Discharge

Purchase Indent raised at corporate level

Tender cost Estimation prepared and Put up to Finance for Finance Vetting & approval as per SOP. Along with PAC issued by region/ Corporate (with vetting) and approval by director/ Corporate

TC prepares final observation

Comparative sheet & final minutes sent to TAA for approval

Purchase Order/LOA Issued to successful bidder. Tender estimate will be revised if LOA/PO estimate increases more than tender estimate.

Acceptance from Supplier

Successful bidder deposit various documents like PBG, Security Deposit

EMD returns or adjusted with Invoice

Non Acceptance

Negotiation may done with supplier Acceptance

Supplier Registration Process PO32

Counter offer/LOI

End

Finance

EMD handed over to finance

Comparative sheet & Briefing note vetted by finance

Tender cost Estimation prepared and Put up to Finance for Finance Vetting

Company Confidential - For internal use only

BP.080 - Purchasing Process

RAILTEL Process: Single Tender Process Control Number: PO 09

Business Function: RAILTEL Tender Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 09

Description: This step explains the Single Tender process.

Event

Description: This process is triggered Whenever Single Tender is created. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID #

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y

Indent/Estimates

POM_RP_ EP_2

PO 09.1

Tender Document Tender Document Execution

POM_TP_ TD_2 POM_TP_ TE_3

PO 09.2 PO 09.3

Purchase Indent/Estimates raised at territory and regional level RO & CO collates all the indent and prepares consolidated proposal Estimates and Tender document prepared and put up to finance for finance vetting, along and with PAC issued by region (with vetting) and approval by director/corporate. Tender Processing officer is nominated and Singe tender is floated to vendor. As per SOP and schedule of work, Tender process is followed and floated. As required tender is floated to selected supplier from approved supplier list or fresh approved supplier list can be created before floating the tender document. Tender document is opened by nominated TOC Comparative sheet and Briefing note are prepared by executive EMD is hand over to finance and Comparative sheet and briefing note are vetted by finance. TC nomination is done. Vetted comparative sheet put up to TC and TC prepares the final observation. Comparative sheet and final minutes sent to competent authority approval. Negotiation is done if required and Discharge can also be happen Counter offer process is done for final price. LOA is issued to successful bidder and acknowledgment is received.

System

System System

Y Y

Company Confidential - For internal use only

BP.080 - Purchasing Process

AS IS Process

AS IS ID #

Process ID #

Description Mode Successful bidder deposit various document like PBG, Security deposit. Simultaneously EMD is returned to unsuccessful bidder.

Requirement Fulfillment using ERP Approach (Y/N)

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 10 - Dispensation of Tender Process for Material


Dispensation of Tender for Material
ERP Manual Email

Project & Procurement

Start

Executive processes the dispensation of Tender

RFQ will be created for quotation

RFQ Process PO31

Quotation are called from various vendors (Minimum 3) PO31

Comparative statement is prepared by the executive and sent to finance for vetting

Comparative sheet sent to competent authority approval

Purchase Indent Process PO01-PO02 Purchase Order is issued to successful bidder

Successful bidder deposit various documents like PBG, Security Deposit (Optional)

Procurement Process PO12

End

Finance

Finance Vetting

Territory/Region/ Corporate

Executive sends the proposal Purchase Requisition/Indent to Manager (HQ/RO/CO) PO01-PO02

Company Confidential - For internal use only

BP.080 - Purchasing Process

RAILTEL Process: Dispensation of Tender Process for Material Control Number: PO 10

Business Function: RAILTEL Tender Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 10

Description: This step explains the Dispensation of Tender process for Material.

Event

Description: This process is triggered Whenever Dispensation of Tender Process is done. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID #

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y

Dispensation of Tender/Quotation Process Dispensation of Tender/Quotation Process Dispensation of Tender/Quotation Process Dispensation of Tender/Quotation Process Dispensation of Tender/Quotation Process Dispensation of Tender/Quotation Process

POM_TP _DT_4 POM_TP _DT_4 POM_TP _DT_4 POM_TP _DT_4 POM_TP _DT_4 POM_TP _DT_4

PO 10.1

Dispensation of tender is requested on urgent basis for extension of maintenance activity or last mile. Executive processes the dispensation of tender process. RFQ document is created and sent to approve suppliers or Fresh Suppliers. Quotations are called from various suppliers. Comparative statement is prepared and sends to finance for vetting then it is sent to competent authority for approval. Purchase Order is issued to successful bidder

System

PO 10.2

System

PO 10.3

System

PO 10.4

System

PO 10.5

Successful bidder deposits various documents like PBG, Security deposit.

System

PO 10.6

Procurement process is initiated for further activity.

System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 11 - Dispensation of Tender Process for Works Contract & Execution

Company Confidential - For internal use only

BP.080 - Purchasing Process

Dispensation of Tender for Works Contract & Execution

ERP

Manual

Email

Start

Executive processes the dispensation of Tender

RFQ will be created for quotation

RFQ Process PO31

Procurement

Quotation are called from various vendors (Minimum 3) PO31

Comparative statement is prepared by the executive and sent to finance for vetting

Comparative sheet sent to competent authority approval

Purchase Indent Process PO01-PO02 LOA is issued to successful bidder

Successful bidder deposit various documents like PBG, Security Deposit (Optional)

Procurement Process PO13

End

Finance

Finance Vetting

Territory/Region/ Corporate

Executive sends the proposal Purchase Requisition/Indent to Manager (HQ/RO/CO) PO01-PO02

RAILTEL Process: Dispensation of Tender Process for

Business Function: RAILTEL Tender

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Service & Works Contract Control Number: PO 11

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 11

Description: This step explains the Dispensation of Tender process for Service & Works Contract.

Event

Description: This process is triggered Whenever Dispensation of Tender Process is done. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID #

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y

Dispensation of Tender/Quotation Process Dispensation of Tender/Quotation Process Dispensation of Tender/Quotation Process Dispensation of Tender/Quotation Process Dispensation of Tender/Quotation Process Dispensation of Tender/Quotation Process

POM_TP _DT_4 POM_TP _DT_4 POM_TP _DT_4 POM_TP _DT_4 POM_TP _DT_4 POM_TP _DT_4

PO 11.1

Dispensation of tender is requested on urgent basis for extension of maintenance activity or last mile. Executive processes the dispensation of tender process. RFQ document is created and sent to approve suppliers or Fresh Suppliers Quotations are called from various suppliers. Comparative statement is prepared and sent to finance for vetting then it is sent to competent authority for approval. LOA is issued to successful bidder

System

PO 11.2

System

PO 11.3

System

PO 11.4

System

PO 11.5

Successful bidder deposits various documents like PBG, Security deposit.

System

PO 11.6

Procurement process is initiated for further activity.

System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 12 - Procurement Process for Material (Supply Item)


Procurement Process for Supply Item
Purchase Order Document Created ERP Manual Email

Standard Purchase Order

Purchase Order Issued to Successful bidder

Acceptance & BG submission from Supplier PO18

Supplier offer RailTel for carrying inspection

Inspection from nominated agency either from ASL or by RailTel officials


RailTel

Confirmation of Change of consignee if any

PO will be amended to change the consignee detail with executive approval

Inspection report is entered in to the system

Item delivered at store

Start

Advance Purchase Order Standing Bank Guarantee Submission from Supplier Rate Contract

Sub PO are released against APO

Inspection

Outside

Approved Supplier List or New Supplier PO37

Nomination of inspection authorized agency

RailTel Uses the item to the site or RailTel deliver the item to the site

Procurement

Sub PO are released against RC

Payment to Outside Inspection authority

Warranty as per PO conditions

Region wise Distribution

End

Receiving Process INV02

End

Finance

APO/RC/SPO/Sub APO/Sub RC Sent for Finance Vetting

Invoice Bills & Payments AP02-AP04

Company Confidential - For internal use only

BP.080 - Purchasing Process

RAILTEL Process: Procurement Process for Material Control Number: PO 12

Business Function: RAILTEL-Project Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 12

Description: This step explains the procurement process of Material.

Event

Description: This process is triggered Whenever a purchase order is raised for material procurement. Source: RAILTEL Project Team/AS-IS Document

AS IS Process Purchase Order Creation Purchase Order

AS IS ID #

Process ID # Description Mode


System

Requirement Fulfillment using ERP Approach (Y/N) Y

POM_PO_PC_3

PO 12.1

Purchase Order is created as per the requirement in the tender with the successful bidder. Purchase Order can be of multiple types like Standard PO, APO and RC. Purchase Order is issued to successful bidder after finance vetting. Standing BG is submitted from supplier against APO and RC. BG is submitted and accepted from supplier against Standard PO and Sub-Pos against APO & RC. Supplier offer RailTel for carrying Inspection. Inspection can be from nominated agency either from ASL or by RailTel officials. If Inspection is from outside, nomination of inspection authorized agency is done from ASL and Payment to inspection authority is made. Inspection report is entered in to the system. PO will be amended to change the consignee detail with the executive approval.

POM_PP_PO_4

PO12.2

System

Inspection

POM_PO_IP_4

PO 12.3

System

None

None

PO 12.4

System

Receiving/D elivery Inspection/F

POM_PO_RD_5 POM_RP_TS_4/P

PO 12.5 PO 12.6

Item is delivered at store RailTel uses the item to the site or RailTel deliver the item to the site. Warranty will be applicable after delivery of Item as per PO condition.

System System

Y Y

Company Confidential - For internal use only

BP.080 - Purchasing Process

AS IS Process AT

AS IS ID #

Process ID # Description Mode

Requirement Fulfillment using ERP Approach (Y/N)

OM_PP_FT_5

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 13 - Procurement Process for Works Contract (Supply, Installation & Commissioning)


Procurement Process for Works Contract
LOA Document Created Acceptance & BG Submission from Supplier PO18 ERP Manual Email

Start

LOA Issued to Successful bidder

Contract agreement is prepared with successful bidder

Contractor offer RailTel for carrying inspection

Inspection from nominated agency either from ASL or by RailTel officials


RailTel

Confirmation of change in consignee if any

LOA will be amended to change the consignee detail with executive approval

Service/Item delivered & recorded

Vendor does I&C after site readiness

Region wise Distribution Inspection


Outside

Approved Supplier List PO37

Nomination of inspection authorized agency

Item delivered at site

Project

Payment to Inspection authority

End

SI Conducts AT in coordination with RailTel Executive

PAC released after AT

Part PAC can also be released as per LOA T&C

FAC as per LOA T&C

Warranty as per LOA T&C

End

Finance

LOA Sent for Finance Vetting

Contract agreement is sent for legal vetting

Invoice Bills & Payments AP02-AP04

Company Confidential - For internal use only

BP.080 - Purchasing Process

RAILTEL Process: Procurement Process for Service & Works Contract Control Number: PO 13

Business Function: RAILTEL-Project Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 13

Description: This step explains the procurement process for service & Works Contract.

Event

Description: This process is triggered Whenever a LOA is created for service and Works Contract. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID #

Process ID # Description Mode


System

Requirement Fulfillment using ERP Approach (Y/N) Y Y

LOA Creation LOA Creation None None Inspection

POM_PO_P C_3 POM_PP_P O_4 None POM_RP_TP _5 POM_PO_IP _4

PO 13.1 PO 13.2 PO 13.3 PO 13.4 PO 13.5

LOA document is created and region wise distribution can also be happen. LOA is issued to successful bidder after finance vetting. LOA is accepted and Bank Guarantee is submitted from supplier. Contract agreement is prepared with successful bidder and it is sent for legal vetting. Contractor offer RailTel for carrying Inspection Inspection can be from nominated agency either from ASL or RailTel officials. Fresh nomination of agency can also be done. If inspection is from outside, nomination of inspection authorized agency is done from ASL and Payment to inspection authority is made. Consignee detail can be changed by amending the consignee detail in LOA. LOA will go for executive approval. Service/Item is delivered to site/Store. Vendor does I&C at site after site readiness.

System

System System

Y Y

None Receiving/Delivery

None POM_PO_R D_5

PO 13.6 PO 13.7

System System

Y Y

Inspection/FAT

POM_PP_FT

PO 13.8

SI conducts AT in coordination with RailTel executive

Company Confidential - For internal use only

BP.080 - Purchasing Process

AS IS Process

AS IS ID #

Process ID # Description Mode

Requirement Fulfillment using ERP Approach (Y/N)

_5/POM_RP _TS_4

PAC is released after AT, Part PAC can also be released as per LOA terms & condition FAC will be issued after PAC release as per LOA terms & condition Warranty will be applicable after delivery as per LOA terms & condition

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 14 - Procurement Process for Execution

Company Confidential - For internal use only

BP.080 - Purchasing Process

Procurement Process for Execution


LOA Document Created Acceptance & BG, SD Submission from Supplier PO18

ERP

Manual

Email

Start

LOA Issued to Successful bidder

Contract agreement is prepared with successful bidder

Work Confirmation of Service delivered

SI Conducts AT in co-ordination with RailTel Executive

Region wise Distribution

Indent for Material requirement at sites PO01-PO02

Stock Transfer from Store to Project Site INV04

PAC released after AT

Project

Material required at site for other activity

On-hand quantity will get updated

Part PAC can also be released as per LOA condition

FAC as per LOA condition End

End

RAILTEL Process: Procurement Process for Execution

Finance

LOA Sent for Finance Vetting

Contract agreement is sent for legal vetting Optional for Execution works at RO

Invoice Bills & Payments AP02-AP04

Business Function: RAILTEL-Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 14

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 14 Event

Description: This step explains the procurement process for Execution. Description: This process is triggered Whenever LOA is raised for execution activity. Source: RAILTEL Project Team/AS-IS Document

AS IS Process LOA Creation LOA Creation None None Receiving/D elivery None

AS IS ID #

Process ID # Description Mode


System

Requirement Fulfillment using ERP Approach (Y/N) Y Y

POM_PO_ PC_3 POM_PP_ PO_4 None POM_RP_ TP_5 POM_PO_ RD_5 None

PO 13.1 PO 13.2 PO 13.3 PO 13.4 PO 13.5 PO 13.6

LOA document is created and region wise distribution can also be happen. LOA is issued to successful bidder after finance vetting. LOA is accepted and Bank Guarantee, Security Deposit is submitted from supplier. Contract agreement is prepared with successful bidder and it is sent for legal vetting. Work Confirmation of Service is entered for service receiving. In case of Material requirement like Duct, Cable at site an Indent will be raised to issue the material from store to site. Stock is transferred from store to site. SI conducts AT in coordination with RailTel executive PAC is released after AT, Part PAC can also be released as per LOA terms & condition FAC will be issued after PAC release as per LOA terms & condition

System

System System System

Y Y Y

Inspection/F AT

POM_PP_ FT_5/PO M_RP_TS _4

PO 13.7

System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 15 - Procurement Process for AMC (Equipments, Sections, Miscellaneous)


Procurement Process for AMC Work (Equipment, Section)
LOA Document Created LOA Issued to Successful bidder for AMC Work Acceptance & BG Submission from Supplier PO18 ERP Manual Email

Start

Contract agreement is prepared with successful bidder

Service delivered & recorded

Work Confirmation of Service

Work Order MNT04

Region wise Distribution

End

Project

Finance

LOA Sent for Finance Vetting

Contract agreement is sent for legal vetting

Invoice Bills & Payments AP02-AP04

Company Confidential - For internal use only

BP.080 - Purchasing Process

RAILTEL Process: Procurement Process for AMC Control Number: PO 15

Business Function: RAILTEL-Project Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 15

Description: This step explains the procurement process for AMC work.

Event

Description: This process is triggered Whenever LOA is raised for AMC work against Work Order and Purchase Indent. Source: RAILTEL Project Team/AS-IS Document

AS IS Process LOA Creation LOA Creation None None Receiving/D elivery

AS IS ID #

Process ID # Description Mode


System

Requirement Fulfillment using ERP Approach (Y/N) Y Y

POM_PO_ PC_3 POM_PP_ PO_4 None POM_RP_ TP_5 POM_PO_ RD_5

PO 13.1 PO 13.2 PO 13.3 PO 13.4 PO 13.5

LOA document is created and region wise distribution can also be happen for AMC work. LOA is issued to successful bidder after finance vetting. LOA is accepted and Bank Guarantee is submitted from supplier. Contract agreement is prepared with successful bidder and it is sent for legal vetting. Work Confirmation of Service is entered for service receiving.

System

System System

Y Y

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 16 - Procurement Process for Inspection (Material, Works Contract & Execution)

Company Confidential - For internal use only

BP.080 - Purchasing Process

Procurement Process for Inspection Charges

ERP

Manual

Email

Start

Service PO is created for Inspection Charges with Supplier Ship to and Bill to details

Procurement Procurement

Service details, amount, need by date and promised date is entered

Shipment detail is entered

Give Distribution detail location wise and delivery schedule for item delivery

Distribution detail is entered for service delivery/Inspection work/Inspection charges

No Work Confirmation of Service INV03 Service Delivered/ Inspection completed

Inspection report is submitted to Project Executive

Automatic notification to buyer

Yes

PO approved

Approve PO

End

Invoice Bill & Payments to supplier for Inspection Work AP02-AP04

PO sent for finance vetting

RAILTEL Process: Procurement Process for Inspection

Finance

Business Function: RAILTEL-Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 16

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 16

Description: This step explains the procurement process for Inspection Charges.

Event

Description: This process is triggered Whenever Payment for Inspection Charges is done. Source: RAILTEL Project Team/AS-IS Document

AS IS Process None None None None None None None

AS IS ID #

Process ID # Description Mode


System System System System System System Manual

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y Y Y N

None None None None None None None

PO 16.1 PO 16.2 PO 16.3 PO 16.4 PO 16.5 PO 16.6 PO 16.7

Service Purchase Order is created for Inspection charges with supplier details. Service amount/quantity, service fulfillment date is entered. Shipment detail is entered Distribution detail location wise is entered for service delivery information Service Purchase Order is submitted for approval for finance vetting Automatic notification will be sent to buyer for confirmation of LOA approval. Inspection report is submitted to project executive.

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 17 - Imprest/Advance Procurement Process


Imprest/Advance Procurement Process
Unorered receipt of Item/ Service detail is created ERP Manual Email

Procurement Operation & Maintenance

Start

Receipt of line detail is recorded

Item/Service, Quantity, UOM and receiving location for receipt line is specified

Generate new receipt or add unordered receipt lines to an existing receipt

Receipt header information is entered and transaction is submitted

Receiving of Item/Service is done in the system

Final delivery of Item/Service

End

Projects & Procurement

Purchase Order is created to match the receipt lines

Search Unordered receipts to match

Select receipt lines to match

Select Purchase Order document number & Line details to match

Submit Unordered receipt line for matching

Finance

Service Purchase Order sent for finance vetting

Invoice Bill & Payments to supplier AP02-AP04

Company Confidential - For internal use only

BP.080 - Purchasing Process

RAILTEL Process: Imprest/Advance Procurement Process Control Number: PO 17

Business Function: RAILTEL-Project Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 17

Description: This step explains the Imprest/Advance Procurement Process.

Event

Description: This process is triggered Whenever unordered receipt is made without valid Purchase Order. Source: RAILTEL Project Team/AS-IS Document

AS IS Process None None None None None None None None None

AS IS ID #

Process ID # Description Mode


System System System System System System System System System

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y Y Y Y Y Y

None None None None None None None None None

PO 17.1 PO 17.2 PO 17.3 PO 17.4 PO 17.5 PO 17.6 PO 17.7 PO 17.8 PO 17.9

Unordered receipt of Item/Service detail is created Item/Service, Quantity, UOM and receiving location for receipt line is specified Generate new receipt or add unordered receipt lines to an existing receipt Receipt header information is entered and transaction is submitted Purchase Order is created to match the receipt lines Unordered receipt and receipt lines is searched to match with PO document number Unordered receipt line is submitted for matching Receiving of Item/Service is done in the system Final delivery is created of Item/Service.

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 18 - Bank Guarantee Process


Bank Guarantee Process
ERP Manual Email

Purchase Order Extension of Bank Guarantee date & Performance Bank Guarantee will sent to bank Yes for confirmation. System alert will go to finance for bank guarantee date extension

Start

Letter of Award

Procurement Project & Procurement

Performance Bank Guarantee will sent to bank for confirmation

After confirmation, sent for legal vetting

After legal vetting submitted to finance for safe custody

Delivery/ DOC period extends

Sub PO against Rate Contract No Sub PO against Advance Purchase Order

Supplier Bank Guarantee will be released after PO/LOA fulfillment/Encashment in case of default/termination

After Bank Confirmation it is submitted to finance for safe custody

Advance Purchase Order

End Standing BG will be sent to bank for confirmation

Rate Contract

Legal

PBG sent for legal vetting

Company Confidential - For internal use only

BP.080 - Purchasing Process

RAILTEL Process: Bank Guarantee Submission Process Control Number: PO 18

Business Function: RAILTEL-Project Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 18

Description: This step explains the Bank Guarantee Process.

Event

Description: This process is triggered to track the Bank Guarantee and Extension activity. Source: RAILTEL Project Team/AS-IS Document

AS IS Process None None None None None None None None None

AS IS ID #

Process ID # Description Mode


System System System System System System System System System

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y Y Y Y Y Y

None None None None None None None None None

PO 18.1 PO 18.2 PO 18.3 PO 18.4 PO 18.5 PO 18.6 PO 18.7 PO 18.8 PO 18.9

Performance Bank Guarantee is required for PO, LOA, Sub RC and Sub APO. Standing Bank Guarantee is required for APO and RC PBG and Standing BG is sent to bank for confirmation After confirmation PBG is sent for legal vetting After legal vetting, PBG is submitted to finance for safe custody If delivery period of service Purchase Order or LOA get extends then extension of bank guarantee date & PBG will be sent to bank for confirmation After Bank confirmation, it is submitted to finance for safe custody Supplier bank guarantee will be released after PO/LOA fulfillment If delivery does not get extend, Supplier BG will be released after PO/LOA fulfillment.

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 19 - Site Readiness Process-For Material and Service

Company Confidential - For internal use only

BP.080 - Purchasing Process

Site Readiness Process

ERP

Manual

No (Authority will put suitable remarks)

Procurement

PO/LOA issued for Material/Works PO12-PO13

Notification will be sent to concern stores for Space check

Space Available for Material

Yes

Executive will check & show drop down menu for readiness of activity

Activities can be like for I&C activity: Fiber through & Terminated from BS to BS Power Supply-AC Power Supply-DC, Battery, Chargers Rack Installation Space Earthing etc.

Concern authority will put suitable remarks for readiness/non readiness

Project & Procurement

End Start Procurement process for Material/Works Execution

LOA for work execution PO14

Pre-requisite Activity defined

Yes

Executive will check & show drop down menu for readiness of activity

Activities can be like: Proposed route Plan Approval from Railways/other authority along with offset boundary lines ROW permission Duct Availability OFC Availability etc..

Concern authority will put suitable remarks for readiness/non readiness

No (Authority will put suitable remarks)

End

RAILTEL Process: Installation & Commissioning and

Business Function: RAILTEL-Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Site Readiness Process Control Number: PO 19

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 19

Description: This step explains the Installation & Commissioning/Site readiness activity.

Event

Description: This process is triggered to fulfill pre-requisite activity before doing the Installation and Commissioning. Source: RAILTEL Project Team/AS-IS Document

AS IS Process None None None None None

AS IS ID #

Process ID # Description Mode


System System System System System

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y Y

None None None None None

PO 19.1 PO 19.2 PO 19.3 PO 19.4 PO 19.5

None None None None

None None None None

PO 19.6 PO 19.7 PO 19.8 PO 19.9

None

None

PO 19.10

PO/LOA is issued for Material/Work/Execution process Notification will be sent to concern stores for space check Concern store checks the space availability of material Executive will check and enter detail for readiness of activity for works Various activities are required to check before I&C activities like: Fiber through & Terminated from BS to BS Power Supply AC Power Supply DC, Battery, Chargers Rack Installation etc.. Concern authority will put suitable remarks for readiness/non-readiness Pre-requisite activity will be defined for execution activity Executive will check and enter detail for readiness of activity for execution Various activities are required to check before execution: Proposed Route Plan Approval from railways authority along with offset boundary lines Duct availability OFC availability etc..boundary lines Duct availability OFC availability etc.. Concern authority will put suitable remarks for readiness/non-readiness

System System System System

Y Y Y Y

System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 20 - Inspection Process

Company Confidential - For internal use only

BP.080 - Purchasing Process

Inspection Process

ERP

Manual

Inspection by RailTel official

Procurement

Inspection report is submitted to Project Executives

Inspection report is entered in to the system

End

RailTel

Project & Procurement

Start

Supplier/ Contractor offer RailTel for carrying Inspection

Inspection

Outside Agency

Nomination of Inspection authorized agency either by ASL or by RailTel officials

Outside agency submits the Inspection report to Project Executives

Inspection report is entered in to the system

End

In case of FAT/AT outside India agreement in between RailTel and Supplier is mandate, without agreement (Formal) no official of RailTel can go outside of India

RAILTEL Process: Inspection Process

Business Function: RAILTEL-Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 20

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 20

Description: This step explains the Inspection Process.

Event

Description: This process is triggered whenever Inspection is required. Source: RAILTEL Project Team/AS-IS Document

AS IS Process None None None None None None None None

AS IS ID #

Process ID # Description Mode


System System System System System System System System

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y Y Y Y Y

None None None None None None None None

PO 20.1 PO 20.2 PO 20.3 PO 20.4 PO 20.5 PO 20.5 PO 20.5 PO 20.5

Supplier/Contractor offer RailTel for carrying Inspection Inspection can be done by RailTel team or Outside agency In case of RailTel team, Inspection is done by RailTel officials Inspection report is submitted to Project executives Inspection report is entered in to the system In case of Outside agency, nomination of Inspection authorized agency is done either by ASL, or by RailTel officials Outside agency submits the inspection report to project executive Inspection report is entered in to the system

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 21 - Standard Purchase Order Process

Company Confidential - For internal use only

BP.080 - Purchasing Process

Standard Purchase Order

ERP

Manual

Email

Start

Identify the standard items that are not frequently used for creating the standard purchase order

Create standard purchase order with Supplier, Ship to and Bill to details

Give Item details, quantity, need by date and promised date

Enter shipment details for item shipment

Give Distribution detail location wise and delivery schedule for item delivery

Project & Purchasing

Purchase Indent PO01-PO02 End

No

Automatic notification to buyer

Yes

Purchase Order approved

Approve Purchase Order

Receiving Process INV02

Finance

Finance Vetting

RAILTEL Process: Standard Purchase Order

Business Function: RAILTEL Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 21

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 21

Description: This step explains the Standard Purchase Order Process

Event

Description: This process is triggered to raise the standard purchase order. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None None None None None None None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y Y Y Y

None None None None None None None

PO 21.01 PO 21.02 PO 21.03 PO 21.04 PO 21.05 PO 21.06 PO 21.07

Identify the standard items that are not frequently used for creating the standard purchase order. Create standard purchase order with details like Supplier information, Ship to and Bill to shipment and delivery. Give item details, quantity, need by date and promise date. Enter shipment information for item shipment. Give distribution detail location wise for item delivery at various location Charge account related information will be automatically generated Approve the purchase order and purchase order approval will be a workflow based process based on approval limits. Automatic notification will be sent to the buyer after document approval.

System System System System System System System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 22- Rate Contract for Material (Supply Item)


Rate Contract for Material
ERP Manual Email

Start

Identify the items that are frequently needed from the same supplier for creating the RC

Agree the amount with the supplier. This amount should get deducted whenever the RC is released

Give the item details for which the RC is needed

Minimum Release, Quantity agreed, Note to supplier

Purchase Indent Process PO01-PO02

No

Procurement

PO Agreement Approved ? Yes

Save the Document, the document No generates automatically and Submit for Approval

Enter terms and conditions

End

Automatic notification to Buyer

Sub PO/ RC Release PO23

Finance

Finance Vetting

Company Confidential - For internal use only

BP.080 - Purchasing Process

RAILTEL Process: Rate Contract Process for Material Control Number: PO 22

Business Function: RAILTEL Project Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 22

Description: This step explains the Rate Contract Process for Material

Event

Description: This process is triggered to create the rate contract. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y

None

PO 22.01

If a department frequently needs supplies or services from the same supplier, Procurement may establish a blanket purchase order. Blanket purchase orders are established for varying periods, and allow the department to order directly from the supplier. The blanket purchase order contains ordering and billing instructions, a price agreement, and a description of the goods or services that can be ordered. Header Level Information. - Select Blanket Agreement from LOV. - Select Supplier Name and Site. - Select Ship To and Bill To Locations - Enter Total Agreed Amount of Agreement (Optional). Buyer will select the Appropriate line type as below : - Goods : Inventory Item or Expensed Item In case of goods quantity field will not be activated only unit price can be entered where as in case of service both quantity and unit price cant be entered. Terms and condition can be entered like Payment terms, Shipment details and Control dates. Generate Blanket Purchase Agreement with automatic document number. Blanket Agreements are sent for approval according to pre-defined approval

System

None

None

PO 22.02

System

None None None

None None None

PO 22.03 PO 22.04 PO 22.05

System System System

Y Y Y

Company Confidential - For internal use only

BP.080 - Purchasing Process

AS IS Process

AS IS ID #

Process ID #

Description Mode hierarchies that are set up within Oracle Purchasing. Once the Blanket Agreement is approved Blanket releases can be prepared against Blanket Agreement. Automatic notification will sent to Buyer after approved the document.

Requirement Fulfillment using ERP Approach (Y/N)

None

None

PO 22.06

System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 23 - Rate Contract Releases of Material (Sub PO)

Company Confidential - For internal use only

BP.080 - Purchasing Process

Rate Contract Release of Material (Sub PO)

ERP

Manual

Email

Start

Create a RC release if any item is required from the supplier for which RC is already created

Query the Approved PR from Auto create Pool

Enter the Blanket release number in the release Header

Enter the details like the qty that needs to be released, Promised date and Shipment details

Procurement

NO Rate Contract PO22 End Automatic notification to Buyer PO Agreement Approved ? Save the Document, the document No generates automatically and Submit for Approval

Yes

Receiving Process INV02-INV03

Finance

Finance Vetting

RAILTEL Process: Rate Contract Release of Material

Business Function: RAILTEL Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 23

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 23

Description: This step explains the Rate Contract Release of Material.

Event

Description: This process is triggered Whenever release is done against the Rate Contract of Materail. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y

None

PO 23.01

None

None

PO 23.02

Blanket release creation is equivalent to creating a standard Purchase Order. A release can be created from the PR directly against the BPA. Select the Approved PR number from Auto Create pool and select the Create type as Automatic or Manual Select Blanket Agreement number from List. Select the Line number. Enter quantity, Promised date , Etc On Blanket Release shipment information can needs to be entered. Blanket Release is sent for approval according to pre-defined approval hierarchies that are set up within Oracle Purchasing. Automatic notification will sent to Buyer after approved the document.

System

System

None None None

None None None

PO 23.03 PO 23.04 PO 23.05

System System System

Y Y Y

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 24 - Rate Contract for Service & Works Contract

Company Confidential - For internal use only

BP.080 - Purchasing Process

Rate Contract for Work Execution

ERP

Manual

Email

Start

Identify the Work Execution/ Service for which Rate Contract is created

Agree the amount with the supplier. This amount should get deducted whenever the RC is released

Give the Service details for which the RC is needed

Minimum Release, amount agreed, Note to supplier

Purchase Indent Process PO01-PO02

No

PO Agreement Approved ? Yes

Project

Save the Document, the document No generates automatically and Submit for Approval

Enter terms and conditions

End

Automatic notification to Buyer

Sub RC Release PO25

Finance

Finance Vetting

RAILTEL Process: Rate Contract Process for Service &

Business Function: RAILTEL Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Works Contract Control Number: PO 24

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 24

Description: This step explains the Rate Contract Process for Service & Works Contract.

Event

Description: This process is triggered to create the rate contract for service and Works Contract. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y

None

PO 24.01

If a department frequently needs supplies or services from the same supplier, Procurement may establish a blanket purchase order. Blanket purchase orders are established for varying periods, and allow the department to order directly from the supplier. The blanket purchase order contains ordering and billing instructions, a price agreement, and a description of the goods or services that can be ordered. Header Level Information. - Select Blanket Agreement from LOV. - Select Supplier Name and Site. - Select Ship To and Bill To Locations - Enter Total Agreed Amount of Agreement (Optional). Buyer will select the Appropriate line type as below : - Goods : Inventory Item or Expensed Item In case of goods quantity field will not be activated only unit price can be entered where as in case of service both quantity and unit price cant be entered. Terms and condition can be entered like Payment terms, Shipment details and Control dates. Generate Blanket Purchase Agreement with automatic document number. Blanket Agreements are sent for approval according to pre-defined approval

System

None

None

PO 24.02

System

None None None

None None None

PO 24.03 PO 24.04 PO 24.05

System System System

Y Y Y

Company Confidential - For internal use only

BP.080 - Purchasing Process

AS IS Process

AS IS ID #

Process ID #

Description Mode hierarchies that are set up within Oracle Purchasing. Once the Blanket Agreement is approved Blanket releases can be prepared against Blanket Agreement. Automatic notification will sent to Buyer after approved the document.

Requirement Fulfillment using ERP Approach (Y/N)

None

None

PO 24.06

System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 25 - Rate Contract Releases of Service & Works Contract (Sub PO)

Company Confidential - For internal use only

BP.080 - Purchasing Process

Rate Contract Release for Work Execution

ERP

Manual

Email

Start

Create a RC release if service is required from the supplier for which RC is already created

Query the Approved PR from Auto create Pool

Enter the RC release number in the release Header

Enter the details like the amount/Quantity that needs to be released, Promised date and Shipment details

Project

Rate Contract for Works Contract PO24

NO End Automatic notification to Buyer PO Agreement Approved ?

Yes

Save the Document, the document No generates automatically and Submit for Approval

Receiving Process INV03

Finance

Finance Vetting

RAILTEL Process: Rate Contract Release of Service &

Business Function: RAILTEL Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Works Contract Control Number: PO 25

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 25

Description: This step explains the Rate Contract Release of Service & Works Contract.

Event

Description: This process is triggered Whenever release is done against the Rate Contract. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y

None

PO 25.01

None

None

PO 25.02

Blanket release creation is equivalent to creating a standard Purchase Order. A release can be created from the PR directly against the BPA. Select the Approved PR number from Auto Create pool and select the Create type as Automatic or Manual Select Blanket Agreement number from List. Select the Line number. Enter quantity, Promised date , Etc On Blanket Release shipment information can needs to be entered. Blanket Release is sent for approval according to pre-defined approval hierarchies that are set up within Oracle Purchasing. Automatic notification will sent to Buyer after approved the document.

System

System

None None None

None None None

PO 25.03 PO 25.04 PO 25.05

System System System

Y Y Y

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 26 - Advance Purchase Order


Advance Purchase Order
ERP Manual Email

Start

Identify the items that are required for long term from the same supplier for creating the advance purchase order

Agree the amount and price with the supplier. This amount and quantity get deducted whenever advance purchase is released

Give the item/service details for which the advance purchase is needed

Minimum release , quantity agreed note to supplier can be entered

Project & Purchasing

End

Automatic notification to buyer

Sub PO/Advance Purchase Order PO27

Finance

ON Yes Advance Purchase Order approved Save the document, the document number generates automatically and submit for approval Enter terms & conditions and tentative delivery schedules Finance Vetting

Purchase Indent Process PO01-PO02

Company Confidential - For internal use only

BP.080 - Purchasing Process

RAILTEL Process: Advance Purchase Order Control Number: PO 26

Business Function: RAILTEL Project Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 26

Description: This step explains the Advance Purchase Order.

Event

Description: This process is triggered Whenever Advance Purchase Order is created. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None None None None None None None None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y Y Y Y Y

None None None None None None None None

PO 26.01 PO 26.02 PO 26.03 PO 26.04 PO 26.05 PO 26.06 PO 26.07 PO 26.08

Identify the items that are required for long term from the same supplier for creating the planned purchase order Agree the amount and price with the supplier. This amount and quantity get deducted whenever release is done against the purchase order. Give item/service details for which the planned purchase order is needed Minimum release, quantity agreed, note to supplier can be entered Enter terms & conditions and tentative delivery schedules is fixed Save the document and document number generates automatically Planned Purchase order is sent for approval according to pre-defined approval hierarchies that are set up within Oracle Purchasing. Automatic notification is sent to buyer after approval of document

System System System System System System System System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 27 - Advance Purchase Order Release (Sub PO)

Company Confidential - For internal use only

BP.080 - Purchasing Process

Advance Purchase Order Release

ERP

Manual

Email

Start

Project & Purchasing

Create a schedule release, if any item is required from the supplier for which the advance purchase order is already created

Query the approved PR from auto create pool

Enter schedule release number in release header

Enter details like quantity needs to be released, promise date and shipment details

End

Automatic notification to buyer

Receiving Process INV02-INV03

Finance

RAILTEL Process: Advance Purchase Order Release

Business Function: RAILTEL Project

ON Yes Schedule release approved Save the document, the document number generates automatically and submit for approval Finance Vetting

Advance Purchase Order PO26

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 27

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 27

Description: This step explains the release process of Advance Purchase Order.

Event

Description: This process is triggered Whenever release is done. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None None None None None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y Y

None None None None None

PO 27.01 PO 27.02 PO 27.03 PO 27.04 PO 27.05

Create a schedule release for which the planned purchase order is already created. Query the approved PR from Autocreate pool Enter schedule release number in release header and quantity detail that needs to be released Save the document number and document number generates automatically Automatic notification will sent to Buyer after approved the document.

System System System System System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 28 - Global Purchase Agreement

Company Confidential - For internal use only

BP.080 - Purchasing Process

Global Purchase Agreement

ERP

Manual

Email

Start

Set up Supplier & Supplier Sites for operating units

Site name should be same in all OU for global agreements

Create Blanket agreement & check global box in header

Enable multiple operating units for global blanket agreement

Approve global blanket agreement

Project & Purchasing

End

Automatic notification to buyer

Yes

Approve standard purchase order

Create standard purchase order in operating unit by taking the reference of global purchase agreement

Receiving Process INV02-INV03

No

Finance

Finance Vetting

RAILTEL Process: Global Purchase Agreement

Business Function: RAILTEL Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 28

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 28

Description: This step explains the Global Purchase Agreement Process.

Event

Description: This process is triggered to raise the global purchase agreement. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None None None None None None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y Y Y

None None None None None None

PO 28.01 PO 28.02 PO 28.03 PO 28.04 PO 28.05 PO 28.06

Setup and Supplier and supplier site for all operating units, Supplier site name should be same in all operating units for global agreements. Create blanket agreement and check global box in header for global agreements Enable multiple operating units for global blanket agreement and approve the GPA. Now, create the standard purchase order in another operating unit by taking the reference of global agreement Check global agreement in owning organization, it is updated with order quantity from another operating unit. Automatic notification will be sent to the buyer after document approval

System System System System System System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 29 - Maintain Purchase Order Process (Variation/Enhancement in Quantities)

Company Confidential - For internal use only

BP.080 - Purchasing Process

Maintain Purchase Order Process

ERP

Manual

Email

Start

Open the Purchase order

Type Of changes Modity

Control Actions Select the Control options like cancel, close, hold, Etc

System applies Specific controls on PO

Project & Purchasing

Procurement Process PO12-PO13

Modify the portion of the PO like Variation in PO Quantity, Tolerances, Dates, Etc.

No Approved PO ?

PO Approval Process

End

Yes

System generates the revision number and requires Re-Approval

Finance

Finance Vetting

RAILTEL Process: Maintain Purchase Order Process

Business Function: RAILTEL Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 29

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 29

Description: This step explains the maintenance of Purchase Documents.

Event

Description: This process is triggered Whenever purchasing document is maintained. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None None None None None None None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y Y Y Y

None None None None None None None

PO 29.01 PO 29.02 PO 29.03 PO 29.04 PO 29.05 PO 29.06 PO 29.07

Open the Purchase orders for modify the details Make the Changes like quantity, Terms and conditions, Etc and save the document. System generates the Revision number for the Purchase order and status will be changed automatically as Requires Re-Approval for Approved PO POs are sent for approval according to pre-defined approval hierarchies that are set up within Oracle Purchasing. In case of any cancellation of PO, Hold, etc Cancellation of PR Save the Document, so system applies specific controls on the Document

System System System System System System System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 30 - RFI- Request for Information (Tender Process)

Company Confidential - For internal use only

BP.080 - Purchasing Process

RFI Process
Procurement Process PO12-PO13
Yes Purchase Indent PO01-PO02 Does Rate Contract Exists?

ERP

Manual

End

Start

No

Search for new Suppliers from database, market research, referrals, Web search

Is Supplier Registered?

Yes

Define the Rating parameter for RFI

Prepare the RFI template

No

Procurement

Supplier Registration PO32

End

Float the final RFI to all the suppliers mentioning the submission timelines

Yes

Supplier Selected?

Supplier visit & audit done

Yes

Supplier facility visit & audit required?

No

Short list suppliers for RFQ/RFP, Reverse Auction, Negotiation

End

No Comparative rating of the suppliers based on RFI responses

End

Supplier rejected

Answer to Queries

Supplier

Update and Submit the RFI as per the timelines

Supplier Queries

RFI received along with the predefined timelines

RAILTEL Process: RFI (Request for Information)

Business Function: RAILTEL Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 30

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 30

Description: This step explains the process of creating the RFI.

Event

Description: This process is triggered as and when organization wants information from suppliers Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None None None None None None None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y Y Y Y

None None None None None None None

PO 30.01 PO 30.02 PO 30.03 PO 30.04 PO 30.05 PO 30.06 PO 30.07

After the PR is created, a RFI is created by the sourcing to get information from the suppliers Create a template for send RFI to the supplier Enter Business Terms and conditions for RFI Enter Item Defaults for the RFI Select Response Controls for the RFI like opening the RFI immediately, suppliers can see other suppliers notes etc Review and Submit the RFI RFI is received by the suppliers. Suppliers need to update and submit the RFI. Short listing of the suppliers is done for RFQ/ RFP/Reverse Auction/ Negotiation after audit

System System System System System System System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 31 - Request for Quotation and Quotations (Tender Process)

Company Confidential - For internal use only

BP.080 - Purchasing Process

RFQ/RFP Process

ERP

Manual

Approve the RFQ?

Legal

No

Receive and review the legal terms and condition of RFQ

Yes

Start

RFI Process PO30

Off line or RFQ method to be followed

RFQ

Prepare the RFQ comprising legal and commercial terms and condition

Forward the legal terms and conditions to legal department for review

Float the Final RFQ to the shortlisted supplier mentioning submission timelines

Offline Quote analysis and Negotiation PO31

Procurement

Offline

End oN Any Correction? Review and Validate Response Yes Response Received Auto alerts to supplier/Remind the supplier , follow up with supplier Yes Answer the queries Submit the updated RFQ as per timelines Supplier Queries Receive the RFQ along with predefined submission timelines

Follow offline/ Online Negotiation

Comparative analysis and shortlist the supplier for negotiation

No

Online

Reverse Auction Process

End

Supplier

Supplier informed about the error incurred

Company Confidential - For internal use only

BP.080 - Purchasing Process

Quote Analysis and Negotiation

ERP

Manual

RFI Process PO30 End Start Call the shortlisted supplier for negotiations RFQ Process PO31 Contract Creation Process Yes Ask Final quotes & cost breakup sheet from supplier Receive & Compile cost breakups Call supplier for final negotiation & discussion

Procurement

Is Supplier selected? No Rejection reason mentioned

End

Supplier

Submit the final cost breakups

Company Confidential - For internal use only

BP.080 - Purchasing Process

RAILTEL Process: Request for Quotation and Quotations Control Number: PO 31

Business Function: RAILTEL Project Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 31

Description: This step explains the process of creating the RFQ and Quotations.

Event

Description: This process is triggered as and when organization wants to float the request for quotations and get Quotations from suppliers Source: RAILTEL Project Team/AS-IS Document AS IS ID # None Process ID # Description Mode PO 31.01 RFI/ RFQ can be created in two ways: one through sourcing and one manual (email). In the system, buyer can directly enter the RFQ Header information or it can be created from Indent using Auto create functionality. Buyer should be able to input the required information like terms and conditions, payment terms, Supplier note (If any), Shipment details Assign the Supplier list to communicate to vendors about the new item details. RFQ numbering will be automatic. Change the RFQ status as ACTIVE and send the communications to suppliers Quotation can be converted from RFQ information Based on the Best bid, Enter the Price details, Terms and conditions in Quotation Approve a single/Entire quotation line from the list System Requirement Fulfillment using ERP Approach (Y/N) Y

AS IS Process

None

None

None

PO 31.02

System

None None None None None None

None None None None None None

PO 31.03 PO 31.04 PO 31.05 PO 31.06 PO 31.06 PO 31.07

System System System System System System

Y Y Y Y Y Y

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 32 - Supplier Registration (iSupplier Module)


Supplier Registration Process
ERP Manual

Start

Supplier

Go to Web based Portal

Open the Supplier Registration Template

Fill & Submit details in Template

Intimate Supplier for disqualification

End

No Reverse Auction Process Issue login id & Password for future transaction Online Template received for evaluation

Yes

Is supplier acceptable

Procurement

End

RFQ Process PO31

If Required buyer will forward the profile to user for inputs

User

Inputs on Supplier based on the profile

Company Confidential - For internal use only

BP.080 - Purchasing Process

RAILTEL Process: Supplier Registration Module Control Number: PO 32

Business Function: RAILTEL Project Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 32

Description: This step explains the Supplier Registration Process.

Event

Description: This process is triggered to define the supplier in the system. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None None None None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y

None None None None

PO 32.01 PO 32.02 PO 32.03 PO 32.04

Supplier Registration can be done manually or through isupplier portal. For manual process, suppliers need to be registered manually in the application. To register through isupplier portal, go to the web based portal and open the registration template Fill in the details of the supplier to be registered Issue the login details to the Supplier if acceptable by the Purchasing department else notify the supplier

System System System System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 33 PO/LOA Acknowledgement (iSupplier Module)

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO/LOA Acknowledgement Process

ERP

Manual

User

PR Returned to User

PR Amended against change requested by Supplier

PR Approval as per DOA

Yes
A

Is PR Required to be Amended

No

PO Amended

Receipt of Amended PR

Procurement

Start

Procurement Process PO12-PO13


A

Approved PO received online, fax, email, etc.

Supplier

PO Accepted or Change Requested or Rejected

Change Requested

Request received online, Fax, Email etc.

Acceptance Received

End

Accepted

Acceptance Communicated

Rejected

PO Cancellation Process/Maintain Purchase Order PO29

End

RAILTEL Process: PO Acknowledgement

Business Function: RAILTEL Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 33

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 33

Description: This step explains the PO Acknowledgement Process.

Event

Description: This process is triggered Whenever PO is acknowledged. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None None None None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y

None None None None

PO 33.01 PO 33.02 PO 33.03 PO 33.04

Approved PO with Acceptance required flag set as Yes goes to supplier for acceptance Supplier gets a notification for acceptance for a PO Supplier can accept the PO/ reject the PO or request changes If acceptance is not provided by the supplier, PO needs to be cancelled. If acceptance is given by the supplier, the PO is ready for further processing. If change is requested by the supplier, the PR/ PO needs to be amended accordingly

System System System System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 34 - ASN Creation and Online Submission (iSupplier Module)

Company Confidential - For internal use only

BP.080 - Purchasing Process

ASN Creation & Online Submission

ERP

Manual

End

Material Receipt/ Receiving Process INV02-INV03 Yes

Procurement

Start

PO Acknowledgement Process PO33

Review Pending PO status of the Supplier

Check ASN as per PO terms

Payment Process AP04

No

Intimate Supplier for Correction in ASN

Start

Login Web bases Online Portal

Track the Pending PO status

Create/Amend Advance Shipment Notice (ASN) against the PO

Submit ASN

Payment Tracking

Supplier

End

Open Online Invoice form

Create Invoice against the PO

Submit Invoice

RAILTEL Process: ASN Creation and Online Submission

Business Function: RAILTEL Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 34

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 34

Description: This step explains the advance shipment notification number and online submission process.

Event

Description: This process is triggered Whenever ASN is communicated to the buyer. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None None None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y

None None None

PO 34.01 PO 34.02 PO 34.03

Supplier can track the PO pending status through isupplier portal Supplier can create / amend ASN Supplier can open the online invoice form to create and submit invoice

System System System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 35 - Contracting Process (Procurement Contract)

Company Confidential - For internal use only

BP.080 - Purchasing Process

Contracting Process

ERP

Manual

Legal Department

Start

Create Section & Clauses

Standard Terms & Condition Library

Standard Contract Templates

Approve Standard Contract Template

End

Approved

No Inputs to Standard Contract Template Standard Terms & Condition Submit online for legal approval Negotiate the terms with the suppliers Quote Analysis & Negotiation PO31 Create draft contract from standard contract template End

Monitor Contract deliverables

Procurement

Start

Supplier Selection Process RFI/RFQ PO30

Contract

Purchasing Process PO12-PO13 Yes Receive alerts on important due dates Update Contract in Contract Repository

Submit online/ manually to supplier for approval

End

Supplier

Give Inputs online/manually on the terms to be discussed No Receive draft contract online or manually for review Contract Terms acceptable Give acceptance on line , Sign-off the contract

Yes

RAILTEL Process: Contracting Process

Business Function: RAILTEL Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 35

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 35

Description: This step explains the Procurement contracts.

Event

Description: This process is triggered Whenever contract is done with the supplier. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y

None

PO 35.01

None

None

PO 35.02

None

None

PO 35.03

None

None

PO 35.04

None None None

None None None

PO 35.05 PO 35.06 PO 35.07

Oracle Procurement Contracts enables to define a standard set of templates to easily default contract terms for contracts authored by your organization. Create templates that include both clauses and deliverables. Sections are headings under contract clauses are organized. The headings provide structure and organization to a printed contract document. Define sections that can be used in authoring templates and contracts. A standard clause is the text that describes the legal or business language used to author a contract. Clauses are drafted based on both business and statutory requirements. Setting up Contract types - When users create Repository contracts in Oracle Contracts, they must select and assign one of the user-defined contract types, such as Non-Disclosure Agreement and Partnership Agreement, to the contract. Similarly setup risks and contract roles also in the contracts set up Create drafts from standard contract templates and get it approved. Give inputs on the terms to be discussed to the supplier Once getting the signoff from the supplier, contracts can be updated in the contracts library

System

System

System

System

System System System

Y Y Y

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 36 - Contracting Amendment Process (Procurement Contract)

Company Confidential - For internal use only

BP.080 - Purchasing Process

Contract Amendment Process

ERP

Manual

Legal Department

Approved

No

Procurement

Negotiate the terms with the supplier

End

Start

Need to revise an existing contract

Change the terms & condition in the existing contract

Create revised draft contract

Submit on line for legal approval

Submit online/ manually to supplier for approval

Update contract in contract repository with revision record

Supplier

Start

Request for revision in existing contract Give Inputs online/ manually on the terms to be discussed

Receive draft contract on line or manually for review

No

Contract terms acceptable

Yes

Give acceptance online, Sign-off the contract

RAILTEL Process: Contracting Amendment Process

Business Function: RAILTEL Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 36

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 36

Description: This step explains the Contract Amendment Process.

Event

Description: This process is triggered to amend the procurement contract. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None None None None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y

None None None None

PO 36.01 PO 36.02 PO 36.03 PO 36.04

Query the template that needs to be revised. Change the terms and conditions in the approved template. Submit the revised contract for approval Give inputs on the terms to be discussed to the supplier Once getting the signoff from the supplier, contracts can be updated in the contracts library

System System System System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 37 - Approved Supplier List (ASL)

Company Confidential - For internal use only

BP.080 - Purchasing Process

Approved Supplier List

ERP

Manual

Single/Limited Tender PO08-PO09

Start

Dispensation of Tender PO10-PO11

Identify the item for which ASL needs to be created

Quotation from supplier exists for the item

No

Float the RFQ and get Quotations for the item from the suppliers

Project & Purchasing

Supplier Creation Process

RFQ Process PO31

Yes

Select the Supplier Name and Site that can be associated with the item based on the quotation

Assign the Status to the supplier and Item

Assign the Source document name , Number and Save

End

Each Department will maintain its own ASL, but the main custodian with all the details will be with finance of CO and Region in case of Execution

RAILTEL Process: Approved Supplier List

Business Function: RAILTEL Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 37

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 37

Description: This step explains the Approved Supplier List Process.

Event

Description: This process is triggered Whenever supplier is approved for procurement of specific item. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y

None

PO 37.01

None None None

None None None

PO 37.02 PO 37.03 PO 37.04

Approved Supplier Lists in Oracle is the term used to describe a list of items and commodities that have approved sources from a list of suppliers. Enter the Item code which wants to associate with Approved Supplier list Enter the Supplier name and Site details based on the quotation Create the Link between supplier and Item and update the status Approved Update the Blanket Agreement number to default the price details in Delivery releases and save the document

System

System System System

Y Y Y

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 38 Spot Purchase Process

Company Confidential - For internal use only

BP.080 - Purchasing Process

Spot Purchase Process

ERP

Manual A

Email

Start

Check On hand availability of Item before raising the Indnet

Item Available

No

Indent raised by executive of concerned department

Indent approved by concerned DGM/ AGM/GM/Directors

Yes

Authority will be defined as a Supplier in the System

Annual celling limit will be defined as Prepayment amount in the Payables

Yes No Item will be utilized from Stores, If it is above minimum threshold limit only No Committee nominated by authority, Minimum 2 members are required for committee, one will be from finance

Procurement

PO approved

Purchase Order raised to current authority limit PO12

Yes

Total Item cost falls under current authority limit

Survey report will be submitted to authority by committee

Nominated Committee will do the survey in to the market

Committee will confirm available prepayment amount in the system

Yes No Item is received as per Item type asset/Expense Purchase Order raised to higher authority as per their annual celling limit PO12

A Invoice will be adjusted against the Prepayment for Purchased Item AP02

Payment & Amount will be deducted from total Prepayment AP04

Finance

End

Supplier

Prepayment

Finance Vetting

RAILTEL Process: Spot Purchase Process

Business Function: RAILTEL Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 38

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 38

Description: This step explains the Spot Purchase Process.

Event

Description: This process is triggered Whenever Spot purchase is done by committee. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None None None None None None None None None None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y Y Y Y Y Y Y

None None None None None None None None None None

PO 38.01 PO 38.02 PO 38.03 PO 38.04 PO 38.05 PO 38.06 PO 38.07 PO 38.08 PO 38.09 PO 38.10

As per on-hand availability of Item, Indent will be raised. Authority will be defined as a Supplier in the system Annual ceiling of authority will be defined as a prepayment in the payables Minimum two committee member is nominated by authority, one will be from finance. Committee will confirm available prepayment in the payables before doing the survey in the market. Survey report will be submitted to authority by committee members PO will be raised to authority of total invoice bill Item is received as per item type asset/expense PO Invoice will be adjusted against the prepayment Payment will deduct from total prepayment.

System System System System System System System System System System

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 39 Inspection Waiver Process

Company Confidential - For internal use only

BP.080 - Purchasing Process

Inspection Waiver Process

ERP

Manual

Start

TAA decide Inspection waiver of some equipment in case of Urgency

Inspection authority RailTel/Outside Agency

Supplier is advised to ask for waiver certificate from RailTel authority

Department issue waiver certificate to region as well as supplier

Case Put up to TAA for approver

Material is received without Inspection certificate

Procurement

System will generate waiver certificate document

End

Finance

Invoice Bill and Payments AP02 AP04

RAILTEL Process: Inspection Waiver Process

Business Function: RAILTEL Project

Date: 12-01-2013

Company Confidential - For internal use only

BP.080 - Purchasing Process

Control Number: PO 39

Mapping Team: Wipro

Process Owner: RAILTEL Project Team

Process Number: PO 39

Description: This step explains the Inspection Waiver Process.

Event

Description: This process is triggered whenever waiver is given for Inspection. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None None None None None None None None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) N N N N N N N N

None None None None None None None None

PO 39.01 PO 39.02 PO 39.03 PO 39.04 PO 39.05 PO 39.06 PO 39.07 PO 39.08

TAA decides inspection waiver of some equipment in case of urgency Inspection authority can be RailTel or Outside agency. Supplier is advised to ask for waiver certificate from RailTel authority Case Put up to TAA for waiver Department issues waiver certificate to region as well as supplier Material is received without certificate System will generate waiver certificate document Invoice, Bill and Payment is done accordingly.

Manual Manual Manual Manual Manual Manual Manual Manual

Company Confidential - For internal use only

BP.080 - Purchasing Process

PO 40 Delivery Period/Date of Completion - Extension


Delivery Period/Date of Completion - Extension
ERP Manual

Material Delivery Period Extension

Reason for Extension

PO will be amended, System will check actual position from iSupplier No

PO approved

Yes

Delivery Period will be extended

LD will be applicable or Not decided at the time of PO amendment

Bank Guarantee date extension

Material

End

Receiving of Material on new delivery date

System alert will go to finance for bank guarantee date extension

Procurement

Start

Delivery date extension of DP/DOC

Material/ Service Extension

Service Date of Commissioning Extension LOA will be amended, System will check actual position from iSupplier LD will be applicable or Not decided at the time of LOA amendment Bank Guarantee date extension

Reason for Extension

LOA approved

Yes

DOC will be extended

End

Work confirmation of Service on new delivery date

System alert will go to finance for bank guarantee date extension

Finance

Invoice Bill & Payments AP02 AP04

Company Confidential - For internal use only

BP.080 - Purchasing Process

RAILTEL Process: Delivery Period/Date of Completion - Extension Control Number: PO 40

Business Function: RAILTEL Project Mapping Team: Wipro

Date: 12-01-2013 Process Owner: RAILTEL Project Team

Process Number: PO 40

Description: This step explains the Delivery Period/Date of Completion - Extension

Event

Description: This process is triggered whenever Delivery Period/Date of Completion is extended. Source: RAILTEL Project Team/AS-IS Document

AS IS Process

AS IS ID # None None None None None None None None None None None None None None None

Process ID #

Description Mode

Requirement Fulfillment using ERP Approach (Y/N) Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y

None None None None None None None None None None None None None None None

PO 40.01 PO 40.02 PO 40.03 PO 40.04 PO 40.05 PO 40.06 PO 40.07 PO 40.08 PO 40.09 PO 40.10 PO 40.11 PO 40.12 PO 40.13 PO 40.14 PO 40.15

Delivery Period of material is extended and reason for extension is entered PO will be amended and it goes for approval, System will check actual position from iSupplier Delivery Period will be extended LD will be applicable or not decided at the time of PO amendment Bank Guarantee date will also be extended System alert will go to finance for bank guarantee date extension Receiving of material is done on new delivery date DOC of services is extended and reason for extension is entered LOA will be amended and it goes for approval, System will check actual position from iSupplier DOC period will be extended LD will be applicable or not decided at the time of LOA amendment Bank Guarantee date will also be extended System alert will go to finance for bank guarantee date extension Receiving of service is done on new delivery date Invoice, Bill and Payment is done accordingly.

System System System System System System System System System System System System System System System

Company Confidential - For internal use only

BP.080 - Purchasing Process

Open and Closed Issues for this Deliverable


Open Issues

ID

Issue

Resolution

Responsibility

Target Date

Impact Date

Closed Issues
ID Issue Resolution Responsibility Target Date Impact Date

POM_PP_BP_1 POM_PP_ES_2 POM_PP_TP_3 POM_PP_PO_4 POM_PP_FT_5 POM_RP_RG_1 POM_RP_EP_2 POM_RP_MU_3 POM_RP_TD_4 POM_RP_TP_5 POM_RP_SH_5 POM_TP_VI_6 POM_RP_RC_7 POM_RP_TP_3 POM_RP_TS_4 POM_PO_PI_1 POM_PO_TD_2 POM_PO_PC_3 POM_PO_IP_4 POM_PO_RD_5 POM_TP_RG_1 POM_TP_TD_2 POM_TP_TE_3 POM_TP_DT_4 POM_TP_VI_5

Project Module Project Module Purchasing Module Purchasing Module Purchasing & O&M Project Module Project Module Project Module Purchasing Module Purchasing Module Project Module Finance Module Finance Module Purchasing Module O&M Module Purchasing Module Purchasing Module Purchasing Module Purchasing Module Purchasing Module Project Module Purchasing Module Purchasing Module Purchasing Module Finance Module

Company Confidential - For internal use only