Anda di halaman 1dari 4

T4300 Load Sharer

• Automatic load sharing with voltage


based speed control
• Adaptable to most speed controllers
• 2-wire communication with other
T4300 Load Sharers
• Unload facility
• Reverse power and unloaded trip
• Visual indication of voltage and
­generator C/B state
• Cost effective and highly reliable
compact design
• 50 hours burn-in before final test
• Operating temperature range:
-20°C to +70°C
• Flame retardant enclosure
• DIN rail or screw mounting

Application
The T4300 Load Sharer provides drift within the speed controller. A soft An unload function is also provided.
­automatic load sharing for parallel load / unload function is also provided When activated, the T4300 will reduce
running generators. The load sharing is in the T4400. the load on the generator and maintain
proportional, meaning that the it on a low value. A built-in relay can
­generators will be loaded equally automatically trip the circuit breaker
­compared to their individual capacity. Function when the unload procedure is
The input to the T4300 is the voltage ­completed.
The T4300 works in connection with and current, from which the active load
most electronic speed controllers. and frequency are determined. The T4300 has a built-in reverse power
protection with selectable limits and
The load on each generator is compared The T4300 calculates I x cos f, represen­ time delays.
with the load on the other generators ting the active load. The load on each
and corrected until balance is obtained. generator is compared with the load on Fig. 1 shows how to connect to most
the other generators and calculated into a Woodward and Heinzmann speed
Load sharing is necessary after control signal that is connected to the ­controllers. For connection to other
­synchronization in order to re-establish electronic speed controller for regulating makes please refer to the section
load balance and to obtain long term the load with optimal speed and stability. ­“Interfacing” on the following page.
stability of the load.

When applied with the B9300 Power


Reference Unit, one or several genera­
tors can be operated in parallel with the
grid (utility).

Together with the T4000 Auto Synchro­­-


­ i­zer, the T4300 provides a good
n
­solution for generator control in many
land-based applications.
The T4900 VAr-Load Sharer can also be
used as a supplement. The combination
of the T4300 and the T4900 will provide
complete load sharing of both active
load and reactive load.

An interesting alternative to the T4300


is the T4400 Load Sharer. In addition to
the features of the T4300 the T4400 Load
Sharer includes a built-in frequency
control and an integration function.
These two features provide a very high
overall stability and compensate for any Fig. 1. Application diagram for T4300 and speed controller with -5V to +5V DC input.
Supply voltage / current Input from synchronizer a variable resistor in the output 16 (+).
The supply voltage from L1 and L2 is Between terminals 9 (FREQ. IN) and 12 This control gives 0W in the output at
connected to terminals 1 and 3 or 2 and the SELCO T4000 Auto Synchronizer or setting 1 and this setting is for
3, depending on the system voltage. most other synchronizer makes can be governors with low impedance input.
connected. The synchronizer will then The resistance increases with higher
The measuring current from L3 is give the synchronizing output through setting. The setting must be the same on
­connected to terminals 5 and 6 with 5 the T4300. This signal is not affected by all load sharers.
referring to the generator (see the the output adjustments on the T4300.
­application diagram on page 1). The DROOP is only used in droop control
current measurement must be taken External power measurement mode. If droop control is preferred to
from the same phase on all generators. On terminal 10 (WATT IN) a negative isochronous load sharing, disconnect
The current is measured in the phase voltage (0 to -1V DC from a watt conver­ the parallel lines (12 and 13) and open
that is not supplying the unit. It is ter) can be connected to substitute the the bridge between 28 and 29 (NO
­important to ensure that the phase internal load measuring circuit. In this DROOP). Droop setting of 1 is
­sequence is correct. case no input on terminals 5 and 6 is equivalent to zero droop, and the droop
needed. Most standard measuring is increasing with higher setting.
This relation between the connections of ­signals can be adapted with external
voltage and current must be correct in resistors. DRIVE or output setting is intended for
order to achieve a correct load measure­ 0-10V : series resistor 510kW adjusting the size of the output signal to
ment. It can be checked on terminal 11 0-5mA : parallel resistor 200W the governor. Output increases with
(TEST OUT), where an input of nominal higher setting. Too much output can
current (1A or 5A) and power factor 1.0 Communication between load sharers result in instability, and if this is the
gives +6V for correct connection. For communication between the load situation, turn anti clockwise until
sharers all terminals 12 (COM.) are inter- ­stability is restored.
Common reference connected, as well as all terminals 13 (+).
Terminal 12 (COM.) is the common
reference for terminals 9 to 13. External speed control Interfacing
External speed control is available from A detailed note on interfacing the T4000
Unload facility a variable voltage input of ±4V on Auto Synchronizer and the T4400 Load
The unload facility will unload the ­terminal 14 (SPEED IN) compared to Sharer to a wide number of different
generator. In order to activate unload, terminal 15 (REF.). electronic speed controllers is available
terminals 7 and 8 (C/B) should be from SELCO. The schematic diagrams
­disconnected. When activated, the load Output to the speed controller in this note are also valid for the T4300
on the generator will be reduced and Output to the electronic speed Load Sharer in place of the T4400. The
maintained at a low level. controller is taken from terminals 15 only difference is the terminal numbers
(REF.) and 16 (+) with terminal 15 as (INV. OUTPUT is terminal 14 on the
Connecting terminals 7 and 8 will again reference. If an inverse signal is needed, T4400 rather than terminal 26 on
activate the T4300 for load sharing. use terminals 15 (REF.) and 26 (INV. T4300).This note can also be downloaded
OUTPUT) rather than changing wires to from our web-site www.selco.com.
Unload trip terminals 15 and 16.
When the load passes below 5% load, a
trip signal is provided for a duration of Droop Trouble Shooting
0.5 sec. as a normally open (NO) contact Terminals 28 and 29 (NO DROOP) If load balance is not obtainable
on terminals 23-24 and a normally should normally be bridged. When If load balance is not obtainable and the
closed (NC) contact on 24-25. This trip bridged, the T4300 is working in the power goes to maximum or reverse
signal can be used to trip the circuit normal manner, providing isochronous power, one of the signals is inverted
breaker. load sharing. With no connection the due to wrong polarity or interchanged
droop control is active. wires. If this is the case, the following
Reverse power trip should be checked:
The reverse power trip operates at 10%
with a delay of 10 sec., but it can be Adjustments 1. The polarity of the power measuring
reduced to 5% by bridging terminals 17 LOAD GAIN can be used for fine signals on terminal 11 (TEST OUT)
and 18 and to 5 sec. delay by bridging ­adjustments of the load balance. LOAD must be positive with the generator
terminals 18 and 19. A resistor of 510kW GAIN should also be used to obtain on load. If the polarity is negative,
between terminals 17 and 18 gives 7.5%, load balance with generators of change the voltage connections 1 and
a resistor of 2.7MW between 18 and 19 different size and with different types of 3 or 2 and 3 or the current connections
gives 7.5 sec. delay. current transducers (CTs). For 5 and 6.
­generators of same size and with same 2. Output from 15 (REF.) and 16 (+)
The reverse power trip is also provided type of CT, the setting 1 should be used must be connected to the speed
as a normally open (NO) contact on on all load sharers. Load increases with ­controller input. Terminal 16 is going
terminals 23-24 and a normally closed higher setting. positive for increased load. If a
(NC) contact on terminals 24-25. ­negative voltage for increased load is
­However, the reverse power trip signal ADAPTION or stability control is used needed, then terminal 26 (INV.
is continuous, whereas the unload trip to adapt the load sharer to the input ­OUTPUT) should be used rather than
signal only has a duration of 0.5 sec. resistance of the governor by means of terminal 16 (+).
3. The parallel lines connected to
­terminals 12 (COM.) and 13 (+) BUS
­between load sharers must not be
interchanged.
GRID
If the load balance is incorrect
If there is a balance point, but the load
balance is incorrect, the following
should be checked:
7 8
1. Load gain shall be set to 1 for same
LOAD SHARER
size of generators and same type of T4300
XX

current transducers (CTs).


2. The frequency of the generators
before paralleling should be the
same.
3. The output adjustment must have
the same setting on all load sharers.
4. If the deviation from other generators
is approximately two times, it is
likely that the current on 5 and 6 is
measured in one of the phases
supply­ing the T4400. The current
must be measured in the phase that 7 8

is not supplying the unit (see the LOAD SHARER


T4300
diagram on figure 1).

Check the voltage on terminal 11


(TEST OUT) to be +6V DC for
ominal current input (IN= 1A or
IN= 5A) and power factor = 1.0. A
current measurement in a wrong
phase will give +3V DC.
Fig. 2. Application Diagram. B9300 with T4300.

L1
L2
L3

SYNCHRONIZE SYNCHRONIZE BUS

9 10 13 12 15 9 10 13 12 15
1 1
CLOSE

2 SYNCHRONIZER T4000 2 SYNCHRONIZER T4000


CLOSE

3 3
5 6 7 21 22-27 5 6 7 21 22-27
UNLOAD - AND REV.POWER

UNLOAD - AND REV.POWER

UNLOAD UNLOAD

1 7 8 28 29 12 9 1 7 8 28 29 12 9
TRIP

TRIP

2 2
3 LOAD SHARER T4300 3 LOAD SHARER T4300
6 6
5 23 24 25 15 16 26 12 13 5 23 24 25 15 16 26 12 13

13 TO NEXT
12 T4300
L1 L2 L3 L1 L2 L3

0 +_ 0 +_

GEN 1 GOV. GEN 2 GOV.

D/G 1 D/G 2
Fig. 3. Application Diagram. Synchronization and load sharing with the T4000, T4300 and speed controller with -5V to +5V DC input.
Specifications
T4300 Load Sharer
Max voltage 660V
150
Voltage range 70 - 110%
Consumption Voltage 4VA at U N
Current 0.4VA at I N
Fixing holes Continuous current 2 x IN
50

2 x ø 4.5 mm
Frequency range 35 - 70Hz
Output voltage Max. ±6V
10

7.5 135 Contact rating AC: 400V, 2A, 250VA


DC: 110V, 2A, 100W
115
Operating temperature -20°C to +70°C
EMC CE according to EN50081-1, EN50082-1, EN50081-2,
EN50082-2
Dimensions in mm Burn-in 50 hours before final test
70

Enclosure material Polycarbonate, flame retardant


Weight 0.7kg
Dimensions 70 x 150 x 115mm (H x W x D)
Fig. 4. Dimensions.
Installation 35 DIN rail or two 4mm (3/16”) screws

Example: The specifications are subject to change without notice.


If the current in terminals 5 and 6 is
2.0A, the nominal current IN is 5A, and
the power factor is 0.8, then the voltage
for correct connection is:
Type Description
6 x 2_ x 0.8 = +1.9V Type Terminals
5 1-3 2-3 IN
T4300.0010 450V 400V 5A
T4300.0020 110V 100V 1A
SELCO Worldwide T4300.0030 450V 400V 1A
Other supply voltages, nominal currents and combinations are available on request.

Main office:
SELCO A/S
Betonvej 10
DK-4000 Roskilde
Denmark
Phone: + 45 7026 1122
Fax: + 45 7026 2522
e-mail: selco.dk@selco.com
www.selco.com
T4395-62E

Anda mungkin juga menyukai