Modern Delay Analysis Techniques


Scott Adams BEng LLB PgD LLM CEng MICE FCIArb MAPM MAE Scott Adams Consultants Ltd. 505 Winfield Commercial Bldg. 6-8 Prat Avenue, TST, HK Tel: 2312 1708, Fax: 2723 1738 Web: www.scadacon.com.hk

Modern Delay Analysis Techniques


1. Static methods

www.scadacon.com.hk

Only one network used: Delays added into it, or subtracted from it progress not accounted for

2. Dynamic methods
Several networks used, updated either in real time or retrospectively progress accounted for

[AACE International Recommended Practice No.29R-03 Forensic Schedule Analysis: 5-level taxonomy, giving 8 broad methodologies described over 105 closely-typed pages]

www.scadacon.com.hk

Contents
The Mirant case Windows analysis an example Other RDA techniques Advantages and disadvantages The City Inn Case Problems of programming

www.scadacon.com.hk

Mirant v Ove Arup [2007]


Summary observations of HHJ Toulmin at 564:

Windows analysis, reviewing the course of a Project month by month, provides an excellent form of analysis to inform those controlling the Project what action they need to take to prevent delay to the Project. Without such analysis those controlling the Project may think they know what activities are on the critical path but it may well appear after a critical path analysis that they were mistaken.

www.scadacon.com.hk

Windows Analysis
The expert must not only be familiar with the chronology, he must tell the story in his report. Some would say that the software exercise counts for nothing unless backed up by the narrative.
John Marrin QC: Expert Evidence on Delay and Disruption The Tribunals Perspective

www.scadacon.com.hk

Windows Analysis
Example project: Civil Engineering Works But - exactly the same programming principles apply in building works projects

www.scadacon.com.hk

Windows Analysis
Example project: Bridge and Approach Road; Start date 01-Jan-07; Date for Completion 30-Jun-07; (6 month project) Main Contractor a bridge specialist; but not a road-works specialist so this will be sub-contracted out

www.scadacon.com.hk

Bridge forms critical path (6 months to construct)

Approach Road has 66d of float

66d

THE INITIAL PROGRAMME (Carefully planned and resourced)

www.scadacon.com.hk

Events in First Window (Jan/Feb)


Day 1: Excavation starts; S/C bids compiled; Day 10: VO1 issued, increasing the depth of abutment foundations 20d extra excavation required; Day 25: Road Subcontract awarded (NB. 5d late); Day 58 (End of window): (i) Abutments excavation almost completed; (ii) Road paving cannot be sourced (materials shortage)

www.scadacon.com.hk

Increased depth: 20d additional excavation


VO1 1st window

Subcontract award after 25d (5d late)

Paving not commenced due to material shortage


20d delay due to VO1 SITUATION AS AT END OF FEB 07 (Close of First Window)

www.scadacon.com.hk

Events in 2nd Window (Mar/Apr)


Day 60: Excavation of abutments completed; Day 75: Pavement laying commenced Day 90: Concreting of abutments completes slowly, taking 30d in total (so a 14d delay); Day 100: VO2 major instruction for a further km of road, in difficult ground (on piles) planned at 21d to source piling s/c, 30d to drive 30 piles, 20d to test, 30d to construct new road & drains, and 15d for street furniture Day 120 (End of window): No further delays, but due to massive VO2, the approach roads are now on the critical path

www.scadacon.com.hk

Slow Concreting of Abutments (14d delay)

2nd window

21d

VO2 New 0.5km of road; in poor ground (on piles) 48d delay; (20d VO1, 14d slow abutments; 14d VO2)

SITUATION AS AT END OF APR 07 (Close of Second Window)

www.scadacon.com.hk

www.scadacon.com.hk

Events in 3rd Window (May/Jun)


Day 121: Falsework erectors go on strike for the whole month of May Day 135: Contractor says that he will mitigate the delay by doubling up resources on the commissioning stage; Day 160: VO3 10 more piles instructed in the new piled approach section, these will take an extra 10 days to complete Day 181 (End of window): No further delays, but due to the month-long strike, the bridge has become once again more critical than the approach road

www.scadacon.com.hk

One month lost due to falsework s/c strike

3rd window

21d

VO3 VO3: Additional piles instructed at new road

Mitigation: commissioning now only 8d

66d delay; (20d VO1, 14d slow abutments; 14d VO2; 25d strike; -7d mitigation) SITUATION AS AT END OF JUN 07 (Close of Third Window)

www.scadacon.com.hk

Events in 4th Window (Jul/Aug)


Day 182 - Day 243: Further problems with Falsework erectors not all were pleased with strike settlement terms, and productivity suffers. Day 243 (End of window): No further delays; approach road completed bar for commissioning; but the elevated bridge concrete deck only managed completion at the very end of this period. The bridge thus remained more critical than the approach road throughout.

www.scadacon.com.hk More than one further month lost due to poor falsework s/c productivity

4th window

21d

98d delay; (20d VO1, 14d slow abutments; 14d VO2; 25d strike; -7d mitigation; 32d poor falsework productivity)
SITUATION AS AT END OF AUG 07 (Close of Fourth Window)

www.scadacon.com.hk

Events in 5th Window (Sep/Oct)


Day 270: VO4, some new road markings and revised drainage causes an extra 10d of work. Day 289 (End of project): The project completes on 16 October 2007, some 108 days late. Critical VOs:- VO1=20d, VO2=14d; VO4=10d: Total = 44d

www.scadacon.com.hk

5th window
21d

New Road marking scheme


-108

VO4

SITUATION AS AT END OF OCT 07 (Close of Fifth Window)

108d

www.scadacon.com.hk
2007 Jan 110 100 90 80 70 60 50 40 30 20 10 0 -10 -20 -30 -40 -50 -60 -70 Jan Feb Mar Apr May 2007 Time v Delay Chart Jun Jul Aug Sep Oct
S/C issued late Lack of paving materials Slow abutments progress
1st window [20d delay] 2nd window [48d delay] 3rd window [66d delay]

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep VO4

Oct

10d
Falseworker Strike action

110 90 80 70 60 50 40 30 20 10 0 -10

100
4th window [98d Bridge complete delay]

108d late

Poor falsework productivity

14d

VO3

Approach Road construction completed

VO1

20d

VO2

Mitigation by increasing commissioning teams

KEY: BRIDGE APPROACH ROAD

-20 -30 -40 -50 -60 -70

www.scadacon.com.hk

As-Built Subtracted Analysis


Take the as-built programme, and subtract the delays which the contractor has suffered (which are not to his own default). This gives rise to a theoretical date, the date on which the contractor would have finished but for the delays The difference between the ABBF date, and the actual completion date represents the potential entitlement to EOT

www.scadacon.com.hk

VO1

21d

VO2 VO3

-108

VO4

AS-BUILT BUT-FOR / AS-BUILT SUBTRACTED ANALYSIS

www.scadacon.com.hk

30d
-78

AS-BUILT BUT-FOR / AS-BUILT SUBTRACTED ANALYSIS

www.scadacon.com.hk

As-Built Subtracted Analysis


The longest path is favoured Only the VOs on the longest path feature in the subtraction, irrespective of the contemporary criticality of other VOs Thus, VO1 (20d) and VO4 (10d) are those which, when subtracted, cause the ABBF date to be collapsed back in time. Thus the potential EOT entitlement here is 30d (cf. 44d in the windows analysis)

www.scadacon.com.hk

As-Planned Impacted Analysis


The initial programme (warts and all) is taken, and into it are impacted all of the delays which the contractor has suffered The impacts are added into the initial network; sometimes this is done in real time, but this causes problems if the delays are caused late due to the contractors own problems (e.g. a VO instructed at a late stage merely because of earlier contractors delays);

www.scadacon.com.hk

THE INITIAL PROGRAMME (Carefully planned and resourced)

www.scadacon.com.hk VO1

VO2, VO3
-68d

VO4

THE INITIAL PROGRAMME IMPACTED WITH VO1-VO4

www.scadacon.com.hk

As-Planned Impacted Analysis


The impacts take no account of progress, or of any of the contractors own defaults. The resultant date is again a theoretical date, perhaps best described as the date for which the contractor would have programmed if it had know about all of the additionally instructed work at the outset; If the VOs are impacted in chronological order, then they all figure in this example: VO1=20d; VO2=28d*; VO3=10d; VO4=10d: Total = 68d (cf. 30d ABBF, 44d windows analysis) * Net delay given initial float and the prior occurrence of VO1

www.scadacon.com.hk

Advantages & Disadvantages


The static analyses (APIP, ABBF) are simple, requiring only two sheets of paper for a before and after effect; But their results are theoretical, there is no account of progress made, no account of changes to the plan, no account of mitigation The windows analysis does take account of such factors, which may account for the warm reception in the Mirant case; but this does come at a cost of complexity, and the programmes must be reliable also:

www.scadacon.com.hk

Advantages & Disadvantages


Although the status at the start and end of the window will allow any delay to be quantified it will not in itself demonstrate the cause or causes of delay. Analysis of these [intra-window] delaying events can be carried out by using any method which is applicable, dependant upon the activities and the events in question. It may be appropriate to use a collapsed as-built or an as-planned impacted methodology Lowsley, Linnett About Time, p.90

www.scadacon.com.hk

HK Standard Form (Private Form)


Upon it becoming reasonably apparent that the progress of the works is delayed, the MC shall forthwith give written notice and if in the opinion of the Architect the completion of the works is likely to be or has been delayed beyond the DfC by [the various reasons] then he shall as soon as he is able to estimate the length of the delay make a fair and reasonable extension of time for the completion of the Works

www.scadacon.com.hk

City Inn v Shepherd Construction [2007]


Scottish Decision (only of persuasive value in HK) JCT-style contract (actual and likely delay can give rise to EOT) Pursuers expert used some form of CPM; Defenders expert used an as-planned vs as-built chart (not a CPM analysis and seemingly not capable of discerning likely delay)

www.scadacon.com.hk

City Inn v Shepherd Construction [2007]


Consequently I think it necessary to revert to the methods that were in use before computer software came to be used extensively in the programming of complex construction The older methods are still plainly valid, and if computer-based techniques cannot be used accurately there is no alternative to using older non-computer-based techniques.

www.scadacon.com.hk

City Inn v Shepherd Construction [2007]


in the type of programme used to carry out CPM analysis any significant error in the information fed into the programme can invalidate the whole analysis it is easy to make such errors That seems to me to invalidate the use of an as-built CPM analysis to discover after the event where the critical path lay, at least where full electronic records are not available from the Contractor.

www.scadacon.com.hk

City Inn v Shepherd Construction [Appeal: 2010]


CONCURRENT DELAY (Lord Carloway) The initial exercise to be carried out by the architect occurs upon the application of the contractor, who will have requested an extension of time by intimating, under clause 25.2, that the progress of the Works "is being or is likely to be delayed". He will claim that a Relevant Event has been the, or at least a, cause of the delay. The architect then has to decide whether he considers that the completion of the Works is likely to be delayed by a Relevant Event beyond the Completion Date (clauses 25.3.1.1 and 2).

www.scadacon.com.hk

City Inn v Shepherd Construction [Appeal: 2010]


CONCURRENT DELAY (Lord Carloway) This provision is designed to allow the contractor sufficient time to complete the Works, having regard to matters which are not his fault (i.e. Relevant Events). This does not, at least strictly, involve any analysis of competing causes of delay or an assessment of how far other events have, or might have, caused delay beyond the Completion Date. It proceeds, to a large extent, upon a hypothetical assumption that the contract has proceeded, and will proceed, without contractor default. It involves an assessment, on that assumption, of the delay which would have been caused to the Completion Date purely as a result of the Relevant Event.

www.scadacon.com.hk

City Inn v Shepherd Construction [Appeal: 2010]


CONCURRENT DELAY (Lord Carloway) But the exercise remains one of looking at the Relevant Event and the effect it would have had on the original (or already altered) Completion Date. If a Relevant Event occurs (no matter when), the fact that the Works would have been delayed, in any event, because of a contractor default remains irrelevant. In that respect, the view of HHJ Seymour QC in Royal Brompton Hospital NHS Trust v Hammond & Others (No 7) [2001] 76 Con LR 148 (at para 31), that a Relevant Event falls to be disregarded if a pre-existing contractor default would nonetheless have caused the delay, appears to be in error.

www.scadacon.com.hk
2007 Jan 110 100 90 80 70 60 50 40 30 20 10 0 -10 -20 -30 -40 -50 -60 -70 Jan Feb Mar Apr May 2007 Time v Delay Chart Jun Jul Aug Sep Oct
S/C issued late Lack of paving materials Slow abutments progress
1st window [20d delay] 2nd window [48d delay] 3rd window [66d delay]

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep VO4

Oct 110 100 90 80 70 60 50 40 30 20 10 0 -10

10d

4th window [98d Bridge complete delay]

108d late

Falseworker Strike action

Poor falsework productivity

VO3

28d

10d

Approach Road construction completed

VO1

20d

VO2

Mitigation by increasing commissioning teams

KEY: BRIDGE APPROACH ROAD

-20 -30 -40 -50 -60 -70

www.scadacon.com.hk

City Inn v Shepherd Construction [Appeal: 2010]


CONCURRENT DELAY (Lord Carloway) VO1 = 20 days; VO2 = 28 days; VO3 = 10 days; VO4 = 10 days (So the Lord Carloway approach might give a 68 day entitlement the same as the as-planned-impacted in this example).

www.scadacon.com.hk

Common Programming and Planning Problems


Planner often a junior/inexperienced staff member; No resources are considered in programmes; Programmes are bar-charts, with no logic; The concertina effect programme depicts completion on time, even after several delays have occurred; OP = PC; PC certified for commercial (secret) reasons; The programme becomes a commercial or political document, not a project management tool

The Magic Circle


Produce a viable, working programme with full reasons for all revision(s)

www.scadacon.com.hk

Work to that programme until something occurs which makes it impossible

Examine and quantify the effects on the programme