TM-2001-210256
ESD Hazards
During
National John
Aeronautics Space
and
Space
F. Kennedy
Center,
June
2001
REDUCING/ELIMINATING PYRO
DURING
J. Francisco 1 Aerospace Systems Engineering, Engineer NASA and McNair John Scholar, Space
Mechanical Systems
Division,
ET/SRB
Accessories
Pyrotechnics
ABSTRACT Several OPF area the safety safety based concerns have occurred during and pyro operations (ESD). support at 30% These equipment or lower concerns (GSE). at 30% content. charge, located RH in the targeted Two or lower In order of the in
of electrostatic hardware
discharge ground
of personnel,
proposed methods considered to control ESDs during pyro operations RH are 1) the use of an ionizer blower and 2) to increase the moisture to demonstrate experimental that runs the were ionizer is effective in the in neutralizing Electrostatics static Laboratory conducted
a series
Operations & Checkout (O&C) Building PYRO Systems Engineering representative Dr. Rupert was metal effectiveness plate and angle Lee from NASA KSC blower Failure in charge of performing of the ionizer from initial of attack. 1000 the experiment to 400 volts.
NASA KSC assistant to who The of a charged distance, RH, we did not
A full factorial
(2 3 = 8) was
have a statistical analysis program, such manually based on the method of "ANOVA" curve) was not influencialvariable. situations be the would most into the charged increasing OPF ECS currently
SAS available, calculations were done (ANalyis of VAriances), but R 2 (fitness of distance that the as close below 30% was best found to be the major possible combination of and facing rate, second which directly would of
obtained. As conjectured, Therefore, we concluded be to position plate. This during the ionizer pyro blower scenario resulted operations
in the quickest
beneficial
method
in the work environment through a modification of the appeared to be dependent on budget constraints and Finally, some recommendations are discussed such a mockup pyro connector and a PPE to assess the realistic
to be modified.
as to test the ionizer in an actual field experiment with technician with all the NASA KSC Safety-compliant effectiveness of the ionizer blower.
GENERAL
ORDNANCE
OPERATIONS
Mechanical Operation The term "mechanical" refers to all operations where the pyro devices are hand-held, installed/removed as a single unit device or as part of an assembly where no electrical mechanical Uplock pyro connections/disconnections installation Release assemblies, are the Thruster, MPM with are performed. Avionics Bay guillotine/jettison, Faraday Caps Some Firex, of the pyro Strut Band Ku on and devices Thruster, Antenna involving MLG/NLG NLG
devices
on each SRB/MLP hold down post attachments between the Orbiter &
The
term
"electrical"
refers
to all
operations These
where
connections/disconnections
on pyro devices.
operations
during mating/demating
pyro connectors. The pyro system is intimately related to the electrical system of all the wiring, cabling, interconnects, power supply, and additional interfaces.
Docking
are category
A category "A" explosive because it initiates a chain to equipment. electricity emergency NSIs contain and escape They are are used systems.
is that which by expenditure of its own of events, causes injury or death to people for for a minimum all pyro probability initiation of initiation except for system
2 electrical
contacts,
which
lead to a bridgewire
that is surrounded
by 0.114
grams of granular mixture transforms electrical energy characteristics: 1) The bridgewire of 0.95 2) 3) 4) 5) 6) 1.05 + 0.10 _. An electrical ignition. current
Potassium Perchlorate (ZrKC104). An NSI energy. Specifically, they have the following stainless steel (304 Nilstain) results with a resistance resistance of
is a 0.002"
distance
of 0.118"
in a circuit
of 3.5 to 5 amps
Output pressure of 650 + 125 psi in a 10cc closed Will not fire if subjected to 1 amp for 5 minutes. Can auto-ignite An airtight shrapnel when if subjected to temperatures steel end closure thin stainless welded
in excess
to the cartridge
Although NSIs are used as NSI Detonators, NSI Charges (LSC), they have
other secondary/high explosive pyros such NSI Pressure Cartridges, and Linear Shape alone in some other Orbiter systems
to be used
suchas in the Crew ModuleFirex System,MPM Guillotine, and Aft Gas Samplers. An expended NSI will havea hole in the endwheretheexplosivechargewaslocated,andan unexpended NSI will havea smoothendcapwith no visible hole.
NSI Detonator An NSI Detonator is a category "A" explosive device, and consists of an
NSI threaded into a detonator acts on the detonator's Lead detonator's produce end. boosters, Electrostatic Apollo Cyclotrimethylene a 0.040"-dent
housing containing additional Azide (PbN6) primer/accelerator, Trinitramine block. (RDX) high An unexpended wrench used
mixtures. The NSI in turn acts on the Detonators a protrusion NSI detonators, and removal. from the will on its NSI
in a steel
detonator is expended.
This protrusion
on a design changes
era called
Apollo
Standard
Initiator.
One
of the design
incorporated was electrostatic protection. Electrostatic safety is achieved The NSI utilizes the spark gap/air gap method, and also the ordnance cavity isolated Spark from ground. gaps are located in the electrical connector cavity where arcing
is not dangerous.
The design scheme is to provide as high an internal breakdown voltage in the ordnance area and as low an external spark gap breakdown voltage as possible. Providing a spark gap between the pins and case involves the electrical breakdown of air dielectric. Electrical breakdown in an air gap happens after the onset of voltage on the pins. If voltage order is applied of Ix-seconds, to the pins an ionization process starts and a short time later, in the the spark jumps specification between 500 from pin to case. for the NSI is that it shall withstand the case and the pins shorted The initiator shall at the top surface not ignite an AC voltage nor otherwise of be
for 60 seconds
together.
Ix-amperes.
Isomica
are installed
of the propellant
with an epoxy impregnated washer or sealing tape as an electrically insulating The metal disk welded in place across the output end is for hermetic sealing. dielectric compromise safety specifications the design at the calling for no breakdown pins to case of the external spark gap and thus time adding nothing to functional
As a design consideration to 1500 volts AC can compromise reliability Electrostatic charged electrostatic
while
same
over the 500 volts DC specifications. specifications volts state that the EED from shall not function pins to case. when a 500-pF on capacitor is the
to 25,000
is discharged
A human
average
equivalent of 300 pF. NSIs are designed with a "no fire current" and "no fire power". That requirement specifies that all NSIs will not fire nor be degraded with 1 amp/1 watt applied Firing appeared for 5 minutes. System that the NSI-1 fast enough. According with required to Test NSI-I's -40 Report on TR82-106 Appendage of energy "Verification 2" dated to fire, July provided of Electrical 22, 1982, it this energy Compatibility
millijoules
was delivered
energy
analysis
follows: pF. Maximum energy human allowable to produce of energy voltage is 350 volts A calculated At is of 18.3 _t-joules.
of an average volts ignited in which Static Failure Voltage Technician Technician spark current
for an average
40 millijoules.
amount
that as a minimum
fire are: with the NSI spark the NSI at a level to dissipate way does NSIs. not static. touch the connector one backshell of the pins when and the gap. >16,000 volts.
A manufacturing
around
not measured
to touch wire
then to ground.
SAFETY
USED
DURING
to be relatively insensitive to static electricity and RF radiation (the pins may act as antenna to RF energy) as compared to other EEDs, if a high enough cause NSIs to be NASA/KSC
however they can still be initiated by either of these forms of energy level exists. Incorrect usage of meters or other energy sources may inadvertently safety practices initiated. Therefore, during pyro operations the and procedures must be followed.
following
KHB
1710.2
KENNEDY
SPACE
CENTER
SAFETY
PRACTICES
HANDBOOK
This is the governing document Revision D dated November requirements during design,
for safety at NASA/KSC. This 1998, establishes and specifies and maintenance activities under KSC. and property the completion
operations
Space Center and areas of jurisdiction minimize the hazards to personnel operations. It is intended to assure manner with maximum efficiency. This manual is divided control films areas, into seven operational tapes contains
These requirements identify and associated with daily industrial of the task to the safest possible
chapters safety,
ranging unique
from hazardous
general
information, areas.
weather, and
personnel,
facilities
requirements,
and adhesive
in Space eleven
NASA
requirements vessels
document,
National systems,
among
Of specific
interest
applicable
annexes: Annex D. KSC Supplement to NFPA 70--National Electric Code This section discusses all sources of static electricity discharges situations. tools, phase power It outlines connections. should handling wear EEDs cables should grounding when stand devices Caps when handling When surface. specific procedures grounding for grounding during hoisting equipment, materials,
controls
unsafe three-
of personnel, of flight
hardware,
hardware,
within
5 ft of
Faraday on
or Shorting
Plugs
are connected
to EEDs.
or conductive
a conductive
Resistance
prior to operations. shall be grounded explosives and wheels chocked fluids inside the OPF platforms. to facility Payloads ground
or canisters
containing
or hazardous mechanism.
shall be grounded
at the facility/handling
Pneumatictools usedon hardwarecontaining EEDs, within 10 ft of open grain, or in petroleum/oil/lubricant areas shall be fitted with a conductive air supply hose or connected to facility ground. All materialsin contactwith open grain shall be grounded. Conductiveplastic sheeting(velostat)shall be groundedto common groundwith railcar prior to installation.
Annex F. KSC Supplement Propellants_ and Pyrotechnics This section discusses the requirements. Relative operations. Humidity When (RH) The RH shall be recorded is not prior to start and every 4 hrs during devices then to NSS-1740.12-NASA Humidity Safety (RH) Standard for and Explosives, Explosive
Relative
requirements
RI-I_50%,
if personnel
wearing
grounding
AV<350 volts, and electrostatic time new equipment, personnel, RH<30%, Faraday operations Caps removed involving
scanning shall be done <lhr or hardware are introduced open grain except exposed, SRB shall circuits
area.
or firing
not be permitted. For SRB at 10-min segment intervals processing if propellant when RH=30%-10%: Electrostatic interval scanning if propellant case shall be done is covered. of segments
is exposed,
and 30-min
Operations shall not continue if AV>350 with propellant or equipment and personnel When segment has end rings with shipping
scan
readings
>lkv then stop operations (do not continue unless readings <1 kv). If scan readings on case of covered propellant > 4kv then notify safety and evacuate personnel from area at least 500-ft radius. If RH<10% then SRB segment processing shall not be permitted. General Explosives Requirements EEDs must be classified as category by certified personnel only, For operations requirements, connection/disconnection be in effect Plugs during these of pyro devices.
A or category
B, handled
only in approved
areas
and
and under control of the explosive storage facility doors and openings shall be closed Controlled the switching removal operations or during of Faraday
of pyro devices.
and RF silence
RF Transmission Cell phones and pagers in VHF & UHF shall not transmit or equipment containing EEDs. Mobile, KSC-controlled transmit S&As For safing within Rotation devices pin removal, of the 2 firing S&As inhibits during shall remain testing when and removing processing an S&A shall be pin. Rotation ground 50 ft. Unapproved radios shall not transmit within 20 fl of flight radio transceivers within 600 ft. hardware shall not
S&A
performedwith the ETA or CDF disconnected from the S&A or at the point of terminus. All the rotationtesting shall be doneprior to firing circuit electricalconnection. If firing circuits must be connectedduring rotation test, safety assessment shall be provided to assureno hazardous condition exists. Rotation testingof S&As (exceptSRB ignition) with only the initiators electricallyconnectedshall be donewith a minimum clearance of 10ft. SRB ignition S&As shall not be rotatedin the VAB. S&A rotation during Phase1 or 2 lightning warnings shall be prohibited. FaradayCaps shall remain on EEDs when installing/removingthe S&A.
Orbiter Hatch T-Handle explosives and TAL lock shall A the lock
The pyro activation T-handle enclosure lock shall be available at each landing site and shall be installed ASAP after Fwd Assessment Team inspection. The not be removed pyro engineer during processing until the T-6 BDA enclosure clear shall control the T-handle whenever is unlocked unless
is removed and transported to an approved explosive storage facility. Whenever the Thandle enclosure is unlocked, safety pip pins shall remain installed in the hatch and cabin vent T-handles. The through following and launch: OMI $5009 Part I, all vehicle Safety CDF, and GSE explosive Ignition items, S&A except control the Range cables, shall SSV safeguard (Orbiter, ET/SRB, and shall be Orbiter-installed followed from Payload) OMI $5009, explosive Part I,
operations
requirements
1)
During
Range
connection,
functional
on critical
MEC
3)
After completion of the functional tests, the MEC Critical Commands disabled and the SSV and GSE PIC racks shall be powered down. In parallel with the subsequent pad clear, the active version of TCS sequence
shall
be
4)
VFC81
shall be replaced with a dummy version (Rev. 0) in the C10 console and any hot spare console that is loaded with C10 software. Console dumps shall be performed to verify 5) After that VFC81 Rev. 0 is loaded tests, After in both consoles. shall be remotely powered-down. The MECs
the SRBs
are powered-down,
VFC81 Rev. 0 shall remain loaded at C10 and the hot spare(s). MEC Critical Commands shall remain disabled. GOAL programs capable of firing PICs, except SRSS PICs, shall not be activated.
SRB power shall be applied for instrumentationreadsonly, except in OMI S0024. Pre-launch Propellant Loading, OMI $5009 Part II, and OMI S007 Launch Countdown. 7) OMI $5009,PartII, shallbe performedin the following sequence:
8) SSV Closed SRBs, SRM powered Loop up for the Range Test. power CDF, removed, power off stray S&A voltage checks cables performed, NSIs, S&A SRSS sating and SRM Ignition control connected. Safety Open Loop Test, flight code insertion and the
pins removed. tests performed. position. SCO ingress. to verify loaded they are in the safe position. the following disabled. except SRSS PICs, shall not be activated. safeguards shall be in effect: at C10 and the hot spare(s).
SSV and GSE PIC resistance All S&As SRBs MECs S&As After VFC81 MEC GOAL rotated to the armed powered-down. After inspected remotely physically the SRBs Critical
powered-down,
programs
SRB power Pre-launch Countdown. OMI SSV Closed SRBs, SRM SSV SRBs MECs $5009, powered Loop
reads only, except in OMI S0024. Part II, and OMI S007 Launch
9)
Part II, shall be performed up for the Range Test. power CDF, Safety
power Ignition
voltage
performed,
control
connected.
pins removed. tests performed. position. SCO ingress. and ET/IT doors
and GSE PIC resistance rotated to the armed powered-down. After remotely
All S&As
powered-down,
S&As physically inspected to verify they are in the safe position. 10) After completion of explosives Part II (S&A hookup), the fwd skirts shall be controlled.
11)After SRB final power-down in OMI $5009 Part II, the following restrictions shall be in effect in addition to those in effect for Part I: 12) GOAL Ignition SRSS programs vehicle capable of arming/tiring off. the restrictions for Parts I and II shall SRSS PICs, or arming SRSS S&A devices, power shall not be activated. shall remain
safeguard or SRM
If OMI $5009,
apply.
down
required or isolated
connections/disconnections
to pyro circuits
GSOP
5400
USA GROUND
SAFETY
OPERATING
PROCEDURES
Vol.
HANDBOOK This document, which is a Revision C dated January 20, 2000, written per KHB 1710.2
Kennedy Space Center Safety Practices Handbook, is intended to identify the hazards associated with ground processing and integration operations. provides the requirements for safety of USA operations KSC. It outlines the applicability, responsibilities, safety of safety GSOP payload involving where reconnected responsibilities. 5400 Section 2.10 where except pyros ODS paragraph EED SRB are firing 2.10.1 processing, electrically where requires are an RH>30% exposed. More At for
general
STS
and
circuits
RH<30% for
specific,
or exposed
RH<30%.
Appendix G_ Space Shuttle Vehicle This section discusses the safeguards and safety information exactly Lightning procedures provided to prevent by this appendix,
(SSV) Ordnance Operations and Safe_,uards governing the installation, connection, verification, inadvertent firing of SSV ordnance. around The specific is and pertaining handbook. 5400 for major hazardous operations such as to pyro devices the SSV
in the previous
as it is outlined
in GSOP
not begin,
2, if already
in progress
10
PROCEDURES must hazardous time be established and depends the greatly per WAD most critical. upon the
Electrical
at the proper
of work
in this portion portions a pre-task This to safety person interaction personnel QC/QA. the task, operations.
the task
leader
(Pyro briefings
is be
of pre-task paper
overemphasized.
hardware
Also,
important
in a successful, be present
involved
in the
commencing
to initiating electrical
personnel
from
of pyro
if applicable,
to the affected
device if it's in an area different connectors require clear of middeck thruster, flame and retardant Fwd Sep Bolt). radios All coveralls safety Also, to be on or nomex
from the electrical along with clears essential bunny personnel suits (clean
Fire/Rescue standby
required
As part
of RF silence,
can be in effect
to any electrical
connection
to be isolated or turned off (controlled hardware from inadvertent initiation. power must be off, or an interruption
This protects both personnel and the no energy source is on, either orbiter circuit is required prior to reaching the separation verification provides bolt connection). of being isolated or controlled protection that would to send
PIC circuitry (i.e. pyro interrupt boxes installed for forward Each task involving electrical connections will call for some from energy sources. is required. and hardware to the pyro device For any pyro Power while disconnection, or controlled no accidental are working power switching personnel energy down personnel
down
is required
in that it ensures
test configuration
A second verification of no stray energy source in the pyro circuitry, voltage test is performed prior to any and all pyro NSI and ODS pyro test requires minutes allowable to connection, use of a stray another stray voltage voltage test meter. test should This test should of the planned actual connection to the NSI.
DC or AC voltage
is 50 millivolts.
the maximum
These allowable voltages are more voltage level required to initiate these
11
Also, to ensure the flight connection will be properly shielded from RF energy, verification is also madewith the stray voltage meter in the way of a shield-to-ground check. The shieldingof all pyro wires is terminatedat eachRF connectorbackshell. The shield-to-ground test requires less than one ohm resistancebetween the connector backshell and orbiter structure. After all verifications, the stray voltage meter is disconnected from the orbiterconnector. Next, in preparationfor handlinga live NSI (or ODS) pyro connector,don a wriststat. Connectthe wriststat ground clip to orbiter structureor an adjacentorbiter connector backshell. Next,perform a resistance checkusing a SimpsonDVOM betweenthe wearer and wriststat groundclip or orbiter structure. The resistancebetweenthe wearerand wriststatgroundclip/orbiter structuremust be between101_ and 1 MK2(10,000g2 and
1,000,000 within voltage DVOM and ODS After the if2). wriststat The limits from purpose between is high. the area. the energy of the the After current This meter wriststat and is to alleviate connector. level turn any The voltage resistor the where potential/electrostatic potential pyros charge difference wearer the pyro verification,
in a case
this wriststat
off the Simpson or degrade leads. technician cables or wire with the NSI's
and remove
to initiate
if the conductors is fully any The with one ready open hand
device
extension
grounded
and secondly
thus preventing
discharge. Once the pyro no bent pins, no contamination, exists (usually and tear when pins and sockets
pins are exposed, inspect to verify no and o-ring is in place at bottom of rubber from gold plating being removed brush as and are mated/demated), use an acid
If contamination
originating
compressed air to remove contaminants. minute waiting time is required to allow Next, after inspections Verify good connections connector required barrel-locking any longer (unless
Isopropyl alcohol can also be used but a 20all alcohol to flash off prior to final connections.
of the connectors to be mated are complete, mate the connectors. by identifying three bayonet-locking pins are visible through the ring. other Once mated, the pyro is safed and the wriststat made). is not Before pyro connections in same area are being
leaving this connection, inspect wires to verify no damage or defects, verify backshell and strain relief tang are not loose, and verify wire routing is such that no tight bends or interference with other hardware exists. In some electrical connections, an "upstream" break point test location is used to verify
connections are correct and intact. For example, after Bolt pyros are connected, a resistance check is made "upstream" boxes Fwd to measure Sep Bolt, resistance and across down the through NSI the ship harness, Typical bridgewire.
12
energy when
Simpson
DVOM, sufficient
Honeywell,
number
measuring
orbiter electro-explosive devices (EEDs). The safety controls for are the same as described earlier in this section for electrical safety clear area location includes both the circuit location from around where the pyro device test "break" in the pyro the resistance
SAFETY Orbiter Required (within without energy Power when "black power source Down mating boxes"). down that could live pyro
TERMS
AND
DEFINITIONS
unless
circuit from
from
PIC
card any to
isolated away
inadvertent
initiation
EXAMPLE - Energized initiate EED if contacted Controlled The purpose Switchin_ is the same
could
as outlined
in the previous
term.
EXAMPLE
- Test
Operations
switch throws requiring FLCAs/MECs may affect circuits that energize PIC cards/pyro initiation. Controlled Switching definition - No flight vehicle/element or GSE commands issued, connected unless no switches or circuit elements. breakers Safety operated on flight in previous elements example. or GSE live pyro electrically connectors to the flight is isolated requirement for demating
circuit
RF Silence The purpose is to prevent the two NSI connector pins from acting energy. Energy from handheld radios or other RF transmitters inadvertent Beacon pyro initiation. equipment Doors closed. Hand-held irons) within radios in OPF Bays 1 and 2. No beepers. No AC powered electrical as an antenna to RF can be enough for OPF bay. pyros. RF motors (i.e. fans)
off within
or heat producing Wriststats Don attach wearer Resistor Resistance should Wriststat ground and
(i.e. soldering
10 ft of open connector
verify
resistance
between is to remove
wearer
and
ground between
clip.
Then between
clip to designated
structural Wriststats
resistance electrostatic
The purpose
personnel energy.
and orbiter
pyro connectors.
will limit the static wearer 10kg2 and and ground 1 M_.
and
orbiter every
be between
precedes
13
pyro
connectors where
are
mated/demated
or Faraday
Caps/Shorting
Plugs
are
removed
(all
A 5 to Expanded
10-ft areas
clear
area
is typically required
required around
in the
area
of where
electrical inadvertent
are sometimes
the envelope
of a pyro system could cause injury to other personnel. EXAMPLE electrical connections require clear area of entire rotating swing platforms to OPF exterior door (per GP-1098). 10-ft clears do not go through floors, or platforms.
CURRENT
PROBLEMS
DURING
LOW
RH
ORBITER
PROCESSING
CONTROL
SYSTEM
The OPF ECS is used primarily for Space Shuttle Orbiter purge operations. ECS consists of four individual airflow ducts that are connected to the Forward,
Bay, Aft, and Cabin interface ducts of the Orbiter. The OPF ECS allows for the operator to control flow rate and air temperature through these ducts. The air entering the ducts is de-humidified Carbon filters. A typical OPF and filtered with a High Efficiency Particle Accumulator (HEPA) and
ECS
air process
starts
with
outside
ambient
air entering
the OPF
ECS
through an inlet filter. The air is drawn through this filter via a centrifugal compressor blower, which compresses and moves the air. Then the air goes through the cooling coil were the air is de-humidified to no more than 37 grains of moisture/lb of dry air per OPF ECS ICD requirements. After the air is de-humidified, chamber were it is mixed and distributed to the four purge Cabin. Then each circuit controls the purge airflow it enters the mixing/manifold ducts: FWD, PLB, AFT, and Finally, the
purge air is filtered and exits the OPF ECS via the ECS duct system. This filtered air enters the Orbiter through the LO2 T-0 for the FWD, PLB, and AFT circuits and through the white room for the Cabin circuit. Based on the current from be 29% design and thus assuming prohibit ambient pgro conditions of 50 F and Orbiter Pad The ECS 50% RH, is similar it in
psychrometric
equations
purge
RH and
design and operation to the OPF ECS except have humidifiers in the AFT, PLB, and Cabin allow Before pyro operations during low ambient
humidity
was measured
by a "squirrel
the OPF Bay humidity were misleading since within the Orbiter
in the OPF. However, these accurately the actual RH value were performed. Typically the
where
14
High the
is above RH inside
30% the
the
1996-1997 around 30%. of personnel Dept 1998, 5532 1999, and of pyro be affected, 11, 1999
time pyro
frame was
time,
a discrepancy
discovered:
devices,
Bay RH level
In order hardware submitted 31, 2000. in which Some when lengthy launch. The
delays
and
flight
operations,
USA Pyro (the latest 4 variances request situation and major V5032.002,
Engineering
discussed
in the
a hazardous of weeks
hardware,
requests
were
approved
for
pyro
operations
for RH<30%
and
specified
that
the
at an "acceptable level of risk" based coveralls and wriststats shall be used clip/Orbiter at Low structure, RH levels, within electrostatic a 5-ft radius
on the following and verified to be shall brief shall be to disconnect scanning prior
Pyro Engineering/TTL
on all personnel,
and at 10-minute
and finally,
ELECTROSTATIC
DISCHARGE (ESD) PRINCIPLES INFORMATION on surfaces ESD can materials, can result cause cause damage in uncontrolled of solid
AND BACKGROUND
High energy
electrical associated
potentials with
ESD. propellants,
of and
ignition
flammable/combustible
actuation
When an insulated person is charged, the charge will distribute itself all points on the person have the same voltage with respect to ground. the charge who will be densely leaning located against on areas a wall, close to the ground. distance For is not actually the shortest
is through
the floor covering. Consequently, most of the charge will be located on the soles feet and by induction bind an equally large, opposite charge in a conducting layer floor. The capacitance of a person can be determined C= ( ereo)A/d Where: er is the relative e0 = 8.85 permittivity or dielectric is the vacuum constant of the insulator. which is a fundamental by using equation:
x 10 -z2 (F)(m-l),
permittivity,
constant.
15
A is the area of the soles. d is the effective For a typical thickness person, of about person, and of the soles plus the insulating floor Er
=
A _= 300 cm 2, d = 5 to 10 mm, 100 to 300 pF. If the parameters 60 to 70% if the capacitance be about is also measured
capacitance for a given this fraction Under charged by being are formed Ionization
by this equation
will normally
indicating
is on the feet. atmospheric body body air is considered slowly its charge. very few charged neutralize a good when particles insulator, surrounded or ions, and which air ions a
by air.
The reason
for this is that air, as a rule, contains primarily causes by radioactive an electron radiation.
The "natural"
to be knocked
02 or N2,
leaving
the
molecule as a singly, positively charged elementary ion, which within second will attract 10 to 15 molecules, mostly HEO, forming a molecular positive air ion. will almost elementary immediately ion. attach to an uncharged elementary oxygen
molecule attract
a negative
The negative
12 H20 molecules to form a negative air ion. This ionization process will create, under normal circumstances, only a small number of ion pairs (about 5 to 10 ion pairs per cm 3 per sec.), pressure When but the production a critical has the value the electron gets rate will increase value, the breakdown very markedly strength, if the electric Eb, which field strength in the air exceeds field at atmospheric
field, the electron Eb, the electron large The to enable process
will move and be accelerated. may, before it collides with it to ionize place the molecule. in the whole discharge will take
If the accelerating a molecule, gain is called the field a transport where words,
sufficiently
strength exceeds Eb and will give rise to an electrical of charge by the ions being moved by the field. Many vapor-air of the static electric discharge problems are connected creating
in other
with
a charged hazard
person when
and
the
possibility
of spark mixtures
an ignition
explosive
may be present
charging across
resistance resistance
and a charge
grounding
Rm = V,,,/ nLlq
16
of the
voltage
depends than
the
explosive show
mixtures
Wmin, Vm has
to be smaller
explosion-safe
a typical
dissipation (charging/discharging) in two different scenarios, one insulated floor (top graph) and the other standing still (bottom graph).
" !-'.
............ _
t ea
',.I
Types There
Discharge, type
Brush of electric
Discharge, discharge In a
and Spark Discharge. Out of these three types, and is reserved for the
at different
potentials.
spark, ionization takes place between the two conductors. between by the conductors potential is C and their
along and the charge is transferred In this channel most of the If the partial is V, the energy W dissipated
through a narrow channel energy stored in the field of the two conductors in the discharge is given
capacitance
I,I1= (1/2) CV 2 Because the most gas/vapor The human the discharge density incendive channel (ability is very narrow and short and the discharge making as a whole or explosion very in a
the spark
discharge
to start an ignition
or dust/vapor body
an electrostatic
hazard
when
the
material
is
initiated
by electrical
17
Electrical Properties of ionized air In any solid or liquid material, the charge, carriers are constant at constant temperature
mobility,
and concentration
of possible
charge
as long as electrical
breakdown
place. In a metallic conductor, the charge carriers are characteristic for the metal in question; in a semiconductor the careers (Unit are always there to yield a current, when is _'2-1m -1) _' = nqk where ascribed charges n is the charge a constant carrier value concentration, the decay. Gases q is the charge, However, inherently
electrons with a concentration the carriers may be holes. But The conductivity _'
a field is applied.
during
medium.
few non-paired
independently
by an electric
in general and, more specifically, atmospheric however, differ from the charge carriers in other The concentration recombination out (deposition of air ions will change with other, of airborne oppositely particulates
air can be ionized. Atmospheric media in several ways. because with by of processes particles, an electric process may field)
like on
charged
surfaces, or simply because the actual field-induced neutralization the air of ions faster than they are re-supplied by the ionizing device. Explosive Mixtures of Gases and Powders Explosions may occur not only in vapor-gas powders. The minimum ignition and concentrations of the vapor Whereas mixtures of vapors
mixtures,
but
also,
in clouds
of dusts
or
energy for a vapor-gas mixture depends and the gas, but it is more complicated and gases in closed environments
homogeneous with the vapor concentration being the same throughout the concentration of powder particles in a cloud may vary from point determination The ignition of minimum energy depends ignition energy size very difficult. involved.
on grain
of the powder
Generally,
it takes
more energy to start an explosion in a cloud of powders than in an explosive vapor-gas mixture. The minimum ignition energies for vapors in atmospheric air are lower than 1 mJ, but powders We can assume will require that any a minimum electrical For of 10 to 100 rnJ to start combustion. discharge a capacitive voltage
Ves "- (2
less by
than
0.2
mJ
in the of 300
atmosphere
is not incendive.
with a typical
capacitance
that an "explosion-safe"
Wmin/C)
to 1200
v.
It should
be stressed
level
refers
only
to are as
with electronic ESD problems, the acceptable levels safe-voltage level only applies to insulated conductors, determined for an insulating material.
be meaningfully
18
MEANS To reduce personnel materials. eliminated, the potential must understand Non-conductive properly selected
for ESD,
potentials on surfaces are commonly induced from friction (rubbing reduced by the simple act of separating two dissimilar materials. ESD is not normally bleeder, of about do not a concern when RH>50%. potentials in ESD. will not Moisture in the
or sliding)
air will
act as a high
dissipating voltage 350 volts and result absorb moisture, where require be avoided RH<50% assessed
before they can build up (i.e., Teflon, vinyl, etc.), even in environments
ESD is a concern. special when attention. possible. resistor going before Operations Voltages, (100k_ direct where especially to 1 M_) to ground. RH<30% on large in series
be carefully wire
be dissipated
all conductors charged objects, discharges. machinery and fixed as all occurs.
that
might such
possibly
charged conductors,
to induction
as insulated
ground
necessary
as long
so that no voltage
properties
of footwear
and floor
coverings,
a person
may
constitute
a capacitive system, with with a leakage resistance This problem might be wriststats Blue-collar
his/her own capacitance in the range ranging from almost zero to maybe resolved by use of protective
fire-retardant
(Safety requirement per GP-1098). Both Personal Protective Equipment (PPE) are used at NASA KSC and provide excellent resistance to static electricity buildup. Cotton in blue-collar coveralls retains moisture and does not allow static buildup. Nomex coveralls have similar characteristics and are used for clean-room type environments. They provide protection against momentary flashes of high heat or fire. are made out of 100% cotton cloth impregnated with a proprietary the cloth to meet NASA KSC flammability requirements. Blue-collar coveralls chemical that allows Westex Corporation
19
manufactures
the particular
cloth under
the trade
names
and Indura.
It is used
for
civilian industry for protection Both Proban and Indura have Laboratory clothing just means heat source Wriststats This device consists of plastic a band and consistently such as the blue-collar that the clothing is removed.
against short duration undergone extensive ESD and flammability does not mean within self-extinguish coveralls
fires and electrical arcing. by the NASA KSC Test Flame time limit retardant it the when will not burn;
satisfy will
or
chain
made wire.
of
metal
to
an
watchband, of solid safety while There contact much resistor being are with body
and conductive
plastic
or fibers,
connected from
to ground accidentally
conductive
Normally
the shock
a live wire
some
problems
the
wrist
straps
though,
intermittent
skin
loose-fitting bands, bad skin contact caused by excessively dry skin or too hair, or sluffing of the band material, resulting in contamination of
components. Ioni_ation: moved charged Removal of ions from the Air structure where and hence and consequently cease has a limited lifetime. with It may be it may be neutralized. It may combine Or a small oppositely
to exist as an ion.
with aerosol particles and then either be neutralized or become a large ion; in both cases it again no longer exists as a small ion. The rate of combination is proportional to the concentration particle of the species involved. The inverse relation between level conductivity in the air. and concentration can be used as an indicator of the particle
process in air starts with the removal of an electron from a neutral necessary energy may be delivered to the molecule from a colliding a quantum of electromagnetic use: radioactive radiation ionization energy. Only two ionization technical and field ionization. will move in the field free path characteristic the energy and for
are in practical
In Field Ionization, collide with neutral the ions. However, the end of their mean Controlled strength field in front
if air is exposed to an electric field, ions molecules after having traveled the mean even at the highest possible field strengths, free path is not high enough is normally achieved electrodes to release by
of the ions at
ionization
creating form
of a set of conducting
in the
of sharp
points
or thin
wires, by keeping the electrodes at a high potential (-_-2-20 kv) with respect to some suitable counter electrode, which may even be the walls of the room. Discharge conditions necessary are different negative for positives under voltage. given and negative voltages. conditions The is about positive 30% voltage than to start ionization geometrical higher
the corresponding
20
Types of loni_ers Ionizers for neutralizing printing, parallel and plastic with and at a short
static
were cases
first
use
in the
textile,
industries.
these
distance
charged
types of ionizers: ionizer bars, blower, whole-room ionization, Radioactive ioniiers In a radioactive ionizer with an extremely material. hard-to-reach When such that the radiation dealing places,
upon
a base
thin protective
The
towards ionizers
relatively
charges
handy.
They do not require electrical discharges. use impractically Usually year. remain radioactive Thus unchecked
electrical installation and they cannot cause potential harmful Their limitation lies in the fact that at high charge levels, one has to activities utilize or the neutralization an a-active of time. nuclide process with intervals, will take too long. half a
a half-life and
of about
the active
is replaced periods
at regular
the device
does
not
21
INVESTIGATION
OF PROPOSED
OF CONTROLLING
ESD
AT
On February Laboratory
16, 1999,
there
NASA
Safety, and
NASA NASA
Materials Pyro
Test
representatives,
Engineering,
Systems
Engineering. In that connections/disconnections discussion, the Separation the NASA decision Pyro perform worst-case scenario,
proposed the use during conditions Hazard the Pad Analysis and
of ionizers during ordnance of RH<30%. During that should be performed initiation of assuming the Aft
it was identified
inadvertent
Bolts with personnel in the Orbiter Material Test Laboratory should be made taking on the proposed an action item ionizer
Aft compartment. It was concluded that conduct tests with the ionizer before a concept. The meeting resulted Material with USA Test Lab to task the NASA
could
to formally
test in conditions
variance approvals have been implemented in most the Orbiter, two extra avenues can be considered
"safety umbrella" even to increase the moisture use of a radioactive 1. Post-flight to PIC work. 2. 3. 4. 5. 6. 7. 8.
when RH<30%, and perhaps as low as RH__10%. One avenue is content in the air and the other is to ionize the surrounding air by combination where proceed as outlined in the following pyros and guidelines: is required, connecting connector and NSIs in
removal/installation cabling
of Faraday
at the
NSI operations involving pin probes, and adapter Russian category EED operations with Faraday exposed shall not be permitted. All personnel shall wear clean, and long legs. All personnel resistance. within 5 ft shall wear wriststats nomex
cabling shall not be permitted. Caps removed or tiring circuits coveralls reading with 10k_ long to sleeves of
or blue-collar
1 Mff2
Work-related paperwork should remain 5 ft from work area. Personnel should avoid activities that produce static charges. Electrostatic of the work area within 5 ft of the EED will maximum allowable of 350 volts at all times.
be performed
with
22
IONIZER The experiment the 2 nd Floor managed by Dr. was of the conducted Operations I. Calle arranged
EXPERIMENT/TEST Laboratory Building H. Gompf. Lee from located at NASA Mr. KSC in Room KSC, Failure Douglas 2275 which Kraft Analysis on is
Carlos
from
NASA
and Physical Testing Laboratory to be in charge KSC-MSL-0331-2000-00-00. Title: "ESD Testing demonstrate NASA assistant KSC that the ionizer Systems Lee. INSTRUMENTATION Charged A charged Lyndonville, composed attached Plexiglas plate
TM
of performing the experiment (Job #: of Nuclear Ionizers". Description: To static as well charge). I served as the research as a laboratory
is effective Engineering
in neutralizing representative
PYRO
to Dr. Rupert
AND 268A-1
EQUIPMENT
Plate/Probe plate NY
Model be used
analyzer
268A-1
by
Inc. is a
experiment.
components
connected portion
near the rear of the unit and lifted A _A-20-threaded mounting. Two elevate a unit the front
at the rear of the top section. for convenient of the control The Switches control tripod unit to panel is
receptacle is provided inside of the top section foldout legs are provided underneath the bottom of the cabinet 6.3/4' to permit wide, easy viewing of the meters. weighs 5 lbs. and 9 1/2" and
of 6 3/4" high,
on the front
panel are alternate action push-push type with the exception of the three used for "plate control". These are mechanically interlocked so that only one function can be selected at a time. Controls "PLATE lower condition "POLARITY" are center of grouped of the the by panel function. relate labeled The "HV" relate switch Three to meter "PLATE control pushbutton range knobs, and CONTROL" the switches function. affect "HV directly Three the ON" beneath switches the at the and the
VOLTAGE" plate.
meter
pushbutton
to the polarity
and magnitude
of the initial
voltage on the plate. The "TIMER LIMIT" switch sets the start/stop the timer. The "OUTPUT" BNC connector on the back panel allows recorder to be connected to the output of the field meter. The signal the actual switches. The charged 10% supply isolated voltage on the plate regardless of the settings of the meter
plate
tripod
mount below
plate
rated
for
a total discharge
of 20 + 2pF. output,
RH = 50%
maximum
_+1000 volts/+5000
plate available,
adjustable
< +1000
to > +5000
23
Ionizer
NRD
Model Number:
Ionmaster"
(Serial
with an articulated arm and a bracket for attachment to the blower, compact and source of ions for static control. The blower bracket contains four slots were metallic grill-like (sealed cartridge) plates (Model containing closure. 2U500, manufactured on NY 14072) by a plastic the radioactive material
May, 2000 by NRD, Inc. Grand Island, 500uCi Po210 sit and are held in position This unit is designed grounding continuous is contained calibration. The radiation methods. balance safely to remove by the unit's in the sealed static
charge
or in no
This apparatus
ionized
a-energy
o_-energy
which
no risk to personnel,
is replaced 210
from Alpha
is called
o_ radiation
and
is of
harmless
externally.
to a maximum
distance
24
1 3/oa' in still air, but have U.S. receives millirems ionization, ionization an average from occurs man-made
no power sources.
to penetrate As the
and about
dissipates
The greatest
Test plate
Chamber
TM
A transparent
Plexiglas
box was used as the test chamber and the relative high, 31" wide, humidity used and 72" probe. is usually
that housed
analyzer,
box 62"
31" deep,
on top of a 33"
on the outside near the test entrance and outfitted compressed breathing air (dm/dt) to regulate relative
25
Digital
C_ Omega" ) Omega"
Thermo-Hygrometer Thermo-Hygrometer with probe was used to record the required The probe was contacting any
A Digital
percentage of relative humidity and temperature inside the test chamber. attached to the ionizer's movable arm away from the blower and without metallic or non-metallic parts.
EXPERIMENTAL/TEST For the purposes during experimental The sequence for the of studying
one of the two proposed which is the main sequence: the ionizer reading
at RH<30%,
would and
work
under
the the
conditions operator's
required
experiment.
Aider carefully
understanding
manuals for both the replacement of ion cartridges into the ionizer blower and the charged plate analyzer section respectively, we conducted a set of four experimental runs. We measured the distance between the charged plate and ionizer blower, recorded the relative ionizer (inspected 21.4% humidity blower. 02) needed and temperature, Also, we identified and contained to achieve and oriented the charged plate with the time and amount of compressed spec: SES-0073-6.3-29 relative humidity. and its polarity When running was maintained 1000-100 at volt respect to the breathing air with a purity of
by SGS
in "K" Bottles,
in the operator's
in the
regime, the decay rate (timing) stopped the 5000 - 500-volt range where the reached 3000 volts. Also, indefinitely in the order of-200 contact Monroe Electronics Inc. charged plate behavior at those set up the voltage
below 300 volts. The same situation decay rate stopped at 1.7 sec when of 1000-100 volts, the decay rate
in the region
prompted Dr. Rupert Lee to 11:00 AM EST to report the we decided to arbitrarily
voltage
26
orifice in
and the installation to a common chamber, was after Also, ground which placing to speed
wire
for
the charge
blower,
charging/discharging 25 TM 16 Units it was verified Two ionizer flow, allowed depended plate
indicating experimental
that equilibrium
not completely
Type I desiccant bags into the test chamber that the decay rate was shorter as expected. were high used, direct remained distances impingement (charged at a fixed (near and
orientations flow,
plate
to was
parallel while
blower which
the charge
at different
far as we denoted
them),
chamber. RESULTS experimental properly position runs working inside to verify at the the following voltage range ionizer
EXPERIMENT/TEST As stated parameters: specified earlier, the we conducted charged plate 4 preliminary control RH meter panel probe
by the manufacturer,
blower positioning and minimum/maximum chamber. During these experimental runs, inside the chamber after each equilibrium conditions to re-establish, situation, all stands and metallic parts plate obtain was wiped-clean with Isopropanol, rates. faster charging/discharging
distance from charged plate inside the test it was noticed that some air ion pairs remained session and did not permit
charging/discharging
producing longer rates. In order to correct this were grounded to a common ground, the charged and venting of the chamber was achieved to
Once all the experimental setup was properly were conducted whose results are shown below:
chosen,
a total
of 21 experimental
runs
27
Ionizer Experiment for August 18, 2000 Position = Direct Impingement ( 90 ) Distance = 33.02 cm / 13 in _elative Humidity RH = 30% Temperature = 21 C 170 F Voltage Setup (v) = 1000 - 400 Average Decay Rate = 2.0 sec Exp. Run# 1 2 3 4 5 6 7 8 9 10 Decay Rate (sec) 2 2 2 2 2 2 2 2 2 2
Ionizer Experiment for August 21_ 2000 Position = Direct Impingement ( 90 ) Distance = 33.02 cm / 13 in _elative Humidity RH = 20% Temperature = 21 C 1 70 F Voltage Setup (v) = 1000 - 400 Average Decay Rate = 2.5 sec Exp. Run# 1 2 3 4 5 6 7 8 9 10 Decay Rate (sec) 2 2 2 3 3 2 3 3 3 2
Ionizer Experiment for August 28, 2000 Position = Direct Impingement ( 90 ) )istance = 33.02 cm / 13 in Relative Humidity RH = 10% temperature = 22 C / 72 F Voltage Setup (v) = 1000 - 400 Average Decay Rate = 2.2 sec Exp. Run# Decay Rate (sec) 1 2 2 2 3 2 4 2 5 6 7 8 9 10 2 2 2 3 2
Ionizer Experiment for August 16, 2000 Position = Direct Impingement ( 90 ) )istance = 33.02 cm / 13 in Relative Humidity RH = 31% - 29% temperature = 22 C 172 F Voltage Setup (v) = 1000 - 500 Average Decay Rate = 3.4 sec Decay Rate(sec) Exp. Run#
3 4 5 6 7 8 9 10
4 4 3 3 3 3 3
28
onizer Experiment for August 16, 2000 Position = Direct Impingement ( 90 ) Distance = 33.02 cm / 13 in F_elative Humidity RH - 31% - 29% Temperature = 22 C / 72 F Voltage Setup (v) = 1000 - 400 Average Decay Rate = 11.6 sec Exp. Run# Decay Rate (sec) 1 2 2 14 3 4 5 6 7 8 9 10 22 15 16 13 10 9 8 7
Ionizer Experiment for August 28, 2000 Position = Direct Impingement ( 90 ) Distance - 55.88 cm / 22 in Relative Humidity RH = 10% Temperature = 22 C ! 72 F Voltage Setup (v) = 1000 - 400 Average Decay Rate = 6.1 sec Exp. Run# Decay Rate (sec) 1 6 2 6 3 4 5 6 7 8 9 10 6 6 8 6 6 5 6 6
Ionizer Experiment for August 30, 2000 Position = Direct Impingement ( 90 ) Distance = 55.88 cm / 22 in Relative Humidity RH = 30% Temperature = 21 C / 70 F Voltage Setup (v) = 1000 - 400 Average Decay Rate = 7.1 sec Exp. Run# Decay Rate (sec) 1 8 2 9 3 6 4 6 5 6 6 7 7 8 8 8 9 10 7 6
Ionizer Experiment for August 30, 2000 Position = Direct Impingement ( 90 ) Distance = 55.88 cm / 22 in Relative Humidity RH = 30% Temperature ---21 C 1 70 F Voltage Setup (v) = 1000 - 300 Average Decay Rate = 12.2 sec Exp. Run# Decay Rate (sec) 1 13 2 9 3 9 4 10 5 8 6 11 7 16 8 16 9 10 11 13
29
Ionizer Experiment for August 18, 2000 Position = Horizontal Position ( 0 ) Distance = 33.02 cm / 13 in Relative Humidity RH --.30% Temperature = 21 C ! 70 F Voltage Setup (v) = 1000 - 400 Average Decay Rate = 3.6 sec Exp. Run# Decay Rate (sec) 1 4 2 3 3 3 4 4 5 6 7 8 9 10 4 4 4 3 3 4
Ionizer Experiment for August 29, 2000 Position = Horizontal Position ( 0 ) Distance = 33.02 cm / 13 in Relative Humidity RH -- 20% Temperature = 22 C / 72 F Voltage Setup (v) -- 1000 - 400 Average Decay Rate = 3.6 sec Exp. Run# 1 2 3 4 5 6 7 8 9 10 Decay Rate (sec) 3 4 3 4 4 4 3 4 4
Ionizer Experiment for August 28, 2000 Position = Horizontal Position ( 0 ) Distance = 55.88 cm / 22 in Relative Humidity RH = 10% Temperature = 22 C / 72 F Voltage Setup (v) = 1000 - 300 Average Decay Rate = 21.9 sec Exp. Run# Decay Rate (sec) 1 23 2 20 3 4 5 6 7 8 9 10 21 27 22 22 22 27 16 19
Ionizer Experiment for August 30, 2000 Position = Horizontal Position ( 0 ) Distance = 55.88 cm 1 22 in Relative Humidity RH = 30% Temperature = 21 C / 70 F Voltage Setup (v) - 1000- 400 Average Decay Rate = 7.6 sec Exp. Run# Decay Rate (sec) 1 6 2 8 3 4 9 5 6 7 8 9 10 9 6 8 7 8 7
3O
IonizerExperiment for August 29, 2000 Position = Horizontal Position ( 0) Distance = 33.02 cm / 13 in
Relative Humidity RH = 20% Temperature = 22 C / 72 F Voltage Setup (v) = 1000 - 300 Average Decay Rate = 4.9 sec Exp. Run# Decay Rate (sec) 1 4 2 5 3 4 5 6 7 8 9 10 4 5 5
Ionizer Experiment for August 29, 2000 Position -- Horizontal Position ( 0 ) Distance = 33.02 cm / 13 in Relative Humidity RH - 10% Temperature = 22 C / 72 F Voltage Setup (v) = 1000 - 400 Average Decay Rate = 3.8 sec Exp. Run# Decay Rate (sec) 1 4 2 4 3 4 5 6 7 8 9 10 4 4 4 3 3 3 5 4
5 5 6
Ionizer Experiment for August 30, 2000 _osition = Horizontal Position ( 0 ) Distance = 55.88 cm / 22 in F_elative Humidity RH = 30% Temperature = 21 C / 70 F Voltage Setup (v) = 1000 - 300 Average Decay Rate = 10.0 sec Exp. Run# Decay Rate (sec) 1 8 2 12 3 12 4 7 5 12 6 10 7 11 8 11 9 8 10 9
Ionizer Experiment for August 29, 2000 Position = Horizontal Position ( 0 ) Distance - 55.88 cm / 22 in IRelative Humidity RH - 6% Temperature - 21 C / 70 F Voltage Setup (v) = 1000 - 400 Average Decay Rate = 16.3 sec Exp. Run# Decay Rate (sec) 1 15 2 16 3 15 4 5 6 7 8 9 10 19 21 13 14 16 17 17
3]
Ionizer Experiment for August 29, 2000 Position = Horizontal Position ( 0 ) Distance = 33.02 cm / 13 in _elative Humidity RH = 20% Temperature = 22 C / 72 F Voltage Setup (v) = 1000 - 300 Average Decay Rate = 5.2 sec Exp. Run# Decay Rate (sec) 1 6 2 6 3 4 5 6 7 8 9 10 4 5 5 5 5 5 6 5
Ionizer Experiment for August 29, 2000 Position ---Horizontal Position ( 0 ) Distance = 55.88 cm / 22 in Relative Humidity RH = 20% Temperature = 21 C / 70 F Voltage Setup (v) = 1000 - 400 Average Decay Rate - 16.3 sec Exp. Run# Decay Rate (sec) 1 16 2 18 3 4 5 6 7 8 9 10 17 16 14 17 16 19 15 15
Ionizer Experiment for August 29, 2000 Position = Horizontal Position ( 0 ) Distance - 55.88 cm / 22 in Relative Humidity RH = 6% Temperature = 21 C / 70 F Voltage Setup (v) = 1000 - 300 Average Decay Rate = 21.7 sec Exp. Run# Decay Rate (sec) 1 20 2 3 4 5 6 7 8 9 10 27 17 19 21 21 23 26 24 19
Ionizer Experiment for August 29, 2000 Position -- Horizontal Position ( 0 ) Distance = 55.88 cm ! 22 in Relative Humidity RH = 20% Temperature = 21 C 170 F Voltage Setup (v) = 1000 - 300 Average Decay Rate = 20.6 sec Exp. Run# 1 2 3 4 5 6 7 8 9 10 Decay Rate (sec) 21 21 18 23 18 21 20 20 22 22
32
Ionizer Experiment
Position = Horizontal Position (0.) Distance = 55.88 cm / 22 in Relative Humidity RH = 10% Temperature = 22 C / 72 F Voltage Setup (v) = 1000 - 400 Average Decay Rate = 18.8 sec Exp. Run# Decay Rate (sec) 1 17 2 27 3 4 5 6 7 8 9 10 21 18 21 23 19 13 14 15
33
DATA From the experimental ionizer blower is the Humidity, The graph interaction meaning indicated 8. The "ANOVA" distance,
ANALYSIS
runs, it appeared that the distance from the charged plate to the ma,ior player of all three variables considered (i.e. Relative in this experiment. for depicting the experiment whose pattern = 23 = is called
and angle)
displayed at the bottom of the analysis section, is intended effect of the three variables simultaneously studied in the
is given by the statistical analysis of the experimental data. The results a factorial design, three factors tested at two levels, i.e. # of experiments statistical (ANalysis analysis process used to analyze this experimental data Of VAriances).
Low Distance = near (33.02 cm / 13 in) High Distance = far (55.88 cm / 22 in) Low RH = 10% High RH = 30% Low Angle = 0 (Horizontal Plate) High Angle = 90 (Direct Impingement) AVG = Average of 10 experimental values (no round off and with no decimal point)
In the following chart numbers 1 - 8 in the first column are the average values of 10 experimental A 1 2 3 4 5 6 7 8 0 1 0 1 0 1 0 1 B 0 0 1 t 0 0 1 1 C 0 0 0 0 1 1 1 1 AVG 3.8 18.8 3.6 7.6 2.2 6.1 2 7.1 Single Independent Variables A = Distance B=RH C = Angle
data.
34
In the following chart, AB, AC, BC, and ABC represent the combined interaction of 2 and 3 single independent variables. conditions. ABC -3.8 18.8 3.6 -7.6 2.2 -6.1 -2 7.1 12.2 3.05
** Number 4 here represents the number of differences or changes in the experimental A 1 2 3 4 5 6 7 8 Sum **Sum/4 -3.8 18.8 -3.6 7.6 -2.2 6.1 -2 7.1 28 7 B -3.8 -18.8 3.6 7.6 -2.2 -6.1 2 7.1 -10.6 -2.65 C -3.8 -18.8 -3.6 -7.6 2.2 6.1 2 7.1 -16.4 -4.1 AB 3.8 -18.8 -3.6 7.6 2.2 -6.1 -2 7.1 -9.8 -2.45 AC 3.8 -18.8 3.6 -7.6 -2.2 6.1 -2 7.1 -10 -2.5 BC 3.8 18.8 -3.6 -7.6 -2.2 -6.1 2 7.1 12.2 3.05
This chart represents the 4 paired scenarios where the distance changed from near to far. The first set (1,2), represents the combined effect of low RH and low angle. The second set (3,4), high RH and low angle. The third set (5,6), low RH and high angle. The last set (7,8), high RH and high angle. The graph below represents the average between shortest and farthest distance in each set. A 1 0 1 B 0 0 C 0 0 AVG 3.8 18.8 (3.8 + 18.8) / 2 = 11.3 11.3 - 5.6 = 5.7
(2.0 + 7.1)
2 = 4.6
35
Interaction
Effects
of Distance,
Experiment
14 12
A
= I
II
O O O
10
I _
:
II
:
I
8 6 4 2 0 0
n,
M O O
:
. ,,.
r | I I ,,,vQ b
.'b...
I I l
:
5.6 A.4.6
I I I
C_
10 Relative I-e--
20 Humidity _
40
Low Angle
A further
analysis
of these
experimental
data would
involve
the
use
of a statistical
the scope of the purpose for this experiment would involve the following interaction
sequence: TABC ----Average of the experimental values + main effect of A + main effect orb + main effect ofC + interaction effect ofAB + interaction effect ofBC + interaction effect of AC + interaction data). effect of ABC + experimental error (how good this model fits the experimental
36
INCREASE
OF MOISTURE
CONTENT
IN WORK
AREA
operations to continue while RH_<30%, is in This task wouM require a modification of the modification at Pad B. The PLB, and Cabin purge circuits associated water piping, control of controlling the RH of
OPF ECS configuration, similar to the ECS humidification Pad B ECS has the ability to control the RH to the AFT, individually. valves, The system and consists sensors. of a humidifier, The system boiler, controllers,
the purge air going to the Orbiter above 30% while maintaining the maximum specific moisture of no more than 37 grains of moisture per pound of dry air. Although this method DFRC scheme, would due work, it has two downsides: Portable would 1) this method Purge be costly Unit could as shown could below. is as follows (in not be implemented with such at a to the fact that the not be outfitted
down
Two Required Sensors Humidifier = $2,500.00 Humidifier Steam Piping Water Chamber Generator
= $300.00 = $1,500.00
(Boiler)
= $3,000.00
and Control Valves = $1,500.00 Softener = $2,600.00 = $5,000.00 Controllers = $250.00 each and Labor
= $4,000.00
Burden (Contractor Profit) = 1.8% of Parts Estimated Total = $24,000.00 If this modification approximately would be implemented
be
$72,000.00.
Dehumidifier
already
installed
at Pad 39-B
37
Boiler
Assembly
at Pad 39-B
Humidifier
Controller
38
RECOMMENDATIONS Some experimental issues Gompf, used and preliminary a NASA Professor adjunct
FOR findings
FUTURE about
ACTIONS ESDs and pyros were Area (BCC). we should Also body EEDs some discussed He pointed rather the small height, contact other
with Dr. Raymond Building we were vendor protective since Future the out that the ionizer just using to ask
consultant
at the O&C
and Mathematics
at Brevard and
operations,
if they details
and important
fat, weight,
equipment,
at low RH levels,
with volts.
RH<30% This
using be
ionizer
to verify
could
performed using wriststats, fire retardant coveralls, and personnel grounding. The key to provide electrostatic protection lies on timing because the faster the breakdown or switching better time of the protective will be. the experimental a bigger ionizer setup to a field experiment blower and try to obtain in the real some data. device after onset of applied electrostatic voltage, the the protection
Another possibility is to extend environment of the OPF with Perhaps in this OPF. However, for modifications
realistic setting, we may have different variables to consider within the if further testing does not satisfy the safety community, then budgeting to the OPF ECS must be considered. Also, to solve the low RH dehumidifier the proper may testing be considered. Of course, the portable and analysis before such a device could
39
Niels,
Chapman OS-400-LSC
2.
28, 1998. Moore, Press, Arnold, Inc., ORD Robert 1994. Jack 1996. M 7-224 September Ordnance 4, 1951. Corps Manual" Ordnance H. Jr., editors, "Aerospace Ordnance C., editors, "Fundamentals of Space
Pisacane, Systems"
Department
of the Army,
40