Anda di halaman 1dari 18

User Course Test Started Submitted Status Score Time Elapsed Instructions

Todd M Sayers Fall 2013:-00F-Systems Analysis & Design 203PQ01V6 8/20/13 7:21 PM 8/20/13 7:31 PM Completed 0 out of 0 points 9 minutes out of 20 minutes.

Question 1
0 out of 0 points

Which of the following is based on an iterative, incremental approach to systems development and has inception, elaboration, construction, and transition phases?
Answer Selected Answer:

RUP
Correct Answer:

RUP

Question 2
0 out of 0 points

All of the following are success factors for an SOA approach except:
Answer Selected Answer:

programmers would have to work in teams of three


Correct Answer:

programmers would have to work in teams of three

Question 3
0 out of 0 points

The person in an organization who has the primary responsibility for systems analysis and design is the:
Answer Selected Answer:

systems analyst
Correct Answer:

systems analyst

Question 4
0 out of 0 points

Principles identified in the Agile Manifesto include:


Answer Selected Answer:

All of these
Correct Answer:

All of these

Question 5
0 out of 0 points

The part of the design phase of the SDLC in which the logical specifications of the system from logical design are transformed into technology-specific details from which all programming and system construction can be accomplished best describes:
Answer Selected Answer:

physical design
Correct Answer:

physical design

Question 6
0 out of 0 points

Large, complex systems that consist of a series of independent system modules best describes:
Answer Selected Answer:

enterprisewide systems
Correct Answer:

enterprisewide systems

Question 7
0 out of 0 points

Turning system specifications into a working system that is tested and then put into use describes:
Answer Selected Answer:

implementation
Correct Answer:

implementation

Question 8
0 out of 0 points

The complex organizational process through which computer-based information systems are developed and maintained best defines:
Answer Selected Answer:

information systems analysis and design

Correct Answer:

information systems analysis and design

Question 9
0 out of 0 points

Critical factors that distinguish Agile and traditional approaches to the systems development life cycle include:
Answer Selected Answer:

All of these
Correct Answer:

All of these

Question 10
0 out of 0 points

Which of the following are deliverables for the implementation phase?


Answer Selected Answer:

code, documentation, training procedures, and support capabilities


Correct Answer:

code, documentation, training procedures, and support capabilities

User Course Test Started Submitted Status Score Time Elapsed Instructions

Todd M Sayers Fall 2013:-00F-Systems Analysis & Design 203PQ02 10/6/13 6:07 PM 10/6/13 6:10 PM Completed 0 out of 0 points 3 minutes out of 20 minutes.

Question 1
0 out of 0 points

Which of the following describes the internal staffing requirements when software components are acquired from enterprise wide solutions providers?
Answer Selected Answer:

Some IS and user staff to define requirements and evaluate packages are needed. Some internal staff are necessary, but mostly consultants are needed.

Correct Answer:

Question 2

0 out of 0 points

The reuse of object classes can result in:


Answer Selected Answer:

All of these
Correct Answer:

All of these

Question 3
0 out of 0 points

Which of the following software evaluation criteria refers to the ease with which you or the vendor can customize the software?
Answer Selected Answer:

flexibility
Correct Answer:

flexibility

Question 4
0 out of 0 points

The choice to acquire software from outside sources should be made:


Answer Selected Answer:

at the beginning of the analysis phase


Correct Answer:

at the end of the analysis phase

Question 5
0 out of 0 points

When considering reuse, which of the following issues should be addressed?


Answer Selected Answer:

All of these
Correct Answer:

All of these

Question 6
0 out of 0 points

One of the top three reasons for choosing to go with cloud computing is:
Answer Selected Answer:

freeing internal IT staff

Correct Answer:

freeing internal IT staff

Question 7
0 out of 0 points

According to a study cited in the textbook, which of the following development methods can lead to a larger maintenance burden?
Answer Selected Answer:

in-house development
Correct Answer:

in-house development

Question 8
0 out of 0 points

The most expensive and extensive reuse approach is:


Answer Selected Answer:

designed reuse
Correct Answer:

designed reuse

Question 9
0 out of 0 points

When purchasing off-the-shelf software, you should consider:


Answer Selected Answer:

All of these
Correct Answer:

All of these

Question 10
0 out of 0 points

Which of the following describes the internal staffing requirements when software components are acquired from packaged software producers?
Answer Selected Answer:

Some IS and user staff to define requirements and evaluate packages are needed. Some IS and user staff to define requirements and evaluate packages are needed.

Correct Answer:

User Course Test Started Submitted Status Score Time Elapsed Instructions

Todd M Sayers Fall 2013:-00F-Systems Analysis & Design 203PQ03V6 9/5/13 1:07 AM 9/5/13 1:20 AM Completed 0 out of 0 points 12 minutes out of 20 minutes.

Question 1
0 out of 0 points

When comparing a Gantt chart to a network diagram, which of the following is a true statement?
Answer Selected Answer:

Some forms of Gantt charts can show slack time available within an earliest start and latest finish duration, whereas a network diagram shows this by data within activity rectangles. Some forms of Gantt charts can show slack time available within an earliest start and latest finish duration, whereas a network diagram shows this by data within activity rectangles.
0 out of 0 points

Correct Answer:

Question 2

Which of the following project management activities is associated with project initiation?
Answer Selected Answer:

establishing a relationship with the customer


Correct Answer:

establishing a relationship with the customer

Question 3
0 out of 0 points

During which of the following activities do you use the information regarding tasks and resource availability to assign time estimates to each activity in the work breakdown structure?
Answer Selected Answer:

dividing the project into manageable tasks


Correct Answer:

develop a preliminary schedule

Question 4
0 out of 0 points

A graphical representation of a project that shows each task as a horizontal bar whose length is proportional to its time for completion defines:
Answer Selected Answer:

Gantt chart
Correct Answer:

Gantt chart

Question 5
0 out of 0 points

Which of the following occurs during project execution?


Answer Selected Answer:

monitoring project progress against the baseline plan


Correct Answer:

monitoring project progress against the baseline plan

Question 6
0 out of 0 points

The phase of the project management process in which activities are performed to assess the size, scope, and complexity of the project and to establish procedures to support later project activities best defines:
Answer Selected Answer:

project planning
Correct Answer:

project initiation

Question 7
0 out of 0 points

Optimistic time is:


Answer Selected Answer:

the planner's "best guess" of the amount of time the activity actually will require for completion the minimum period of time for an activity to be completed
0 out of 0 points

Correct Answer:

Question 8

Which of the following is a true statement regarding network diagrams?


Answer Selected Answer:

The critical path of a network diagram is represented by the sequence of connected activities that produce the longest overall time period. All of these.
0 out of 0 points

Correct Answer:

Question 9

A controlled process of initiating, planning, executing, and closing down a project best defines:
Answer Selected Answer:

project management
Correct Answer:

project management

Question 10
0 out of 0 points

A diagram that depicts project activities and their interrelationships is called a:


Answer Selected Answer:

network diagram
Correct Answer:

network diagram

User Course Test Started Submitted Status Score Time Elapsed Instructions

Todd M Sayers Fall 2013:-00F-Systems Analysis & Design 203PQ04V6 9/11/13 3:54 AM 9/11/13 4:06 AM Completed 0 out of 0 points 11 minutes out of 20 minutes.

Question 1
0 out of 0 points

Which of the following is an advantage of the bottom-up planning approach?


Answer Selected Answer:

IS plans can be created faster and are less costly to develop than using the

top-down approach.
Correct Answer:

IS plans can be created faster and are less costly to develop than using the top-down approach.
0 out of 0 points

Question 2

The method by which an organization attempts to achieve its mission and objectives best defines:
Answer Selected Answer:

competitive strategy
Correct Answer:

competitive strategy

Question 3
0 out of 0 points

Matrices of the target or "future" situation are sometimes called:


Answer Selected Answer:

forward-looking matrices
Correct Answer:

"to be" matrices

Question 4
0 out of 0 points

Which of the following is an advantage to the top-down planning approach over other planning approaches?
Answer Selected Answer:

All of these
Correct Answer:

All of these

Question 5
0 out of 0 points

"We are in the business of designing, fabricating, and selling to retail stores high-quality wood furniture" is what kind of statement?
Answer Selected Answer:

mission statement
Correct Answer:

mission statement

Question 6
0 out of 0 points

The extent to which the project is viewed as improving profits, customer service, etc., and the duration of these benefits best defines which of the following evaluation criteria?
Answer Selected Answer:

potential benefits
Correct Answer:

potential benefits

Question 7
0 out of 0 points

Which of the following best describes the top-down planning approach advantage, improved integration?
Answer Selected Answer:

If not viewed from the top, planners may lack the understanding necessary to implement information systems across the entire business rather than simply to individual operating units. If not viewed from the top, totally new management information systems may be implemented rather than planning how to evolve existing systems.
0 out of 0 points

Correct Answer:

Question 8

Which of the following is a true statement regarding the IS plan?


Answer Selected Answer:

All of these.
Correct Answer:

All of these.

Question 9
0 out of 0 points

Which of the following is a CASE tool feature that can help you make sense out of matrices?
Answer Selected Answer:

matrix construction
Correct Answer:

All of these

Question 10
0 out of 0 points

The second planning process that can play a significant role in the quality of project identification and selection decisions is called:
Answer Selected Answer:

cost/benefit analysis
Correct Answer:

information systems planning

User Course Test Started Submitted Status Score Time Elapsed Instructions

Todd M Sayers Fall 2013:-00F-Systems Analysis & Design 203PQ05V6 9/21/13 1:30 PM 9/21/13 1:43 PM Completed 0 out of 0 points 12 minutes out of 20 minutes.

Question 1
0 out of 0 points

At walkthrough meetings, there is a need to have individuals play specific roles such as:
Answer Selected Answer:

presenter
Correct Answer:

presenter

Question 2
0 out of 0 points

The reduction of waste creation is an example of a(n):


Answer Selected Answer:

intangible benefit
Correct Answer:

intangible benefit

Question 3
0 out of 0 points

At a walkthrough meeting, the person who plans the meetings and facilitates a smooth meeting process is referred to as the:

Answer Selected Answer:

coordinator
Correct Answer:

coordinator

Question 4
0 out of 0 points

A cost associated with project start-up and development or system start-up refers to a(n):
Answer Selected Answer:

one-time cost
Correct Answer:

one-time cost

Question 5
0 out of 0 points

At a walkthrough meeting, the person who ensures that the work product adheres to organizational technical standards is referred to as the:
Answer Selected Answer:

standards bearer
Correct Answer:

standards bearer

Question 6
0 out of 0 points

A peer group review of any product created during the system development process refers to:
Answer Selected Answer:

walkthrough
Correct Answer:

walkthrough

Question 7
0 out of 0 points

As a rule of thumb estimate, what percentage of the entire development effort should be devoted to the project initiation and planning process?
Answer Selected Answer:

between 10 and 20 percent

Correct Answer:

between 10 and 20 percent

Question 8
0 out of 0 points

The concept of comparing present cash outlays to future expected returns best defines:
Answer Selected Answer:

time value of money


Correct Answer:

time value of money

Question 9
0 out of 0 points

To gain an understanding of how key stakeholders within the organization view the proposed system is the purpose of:
Answer Selected Answer:

political feasibility
Correct Answer:

political feasibility

Question 10
0 out of 0 points

The analysis technique that finds the amount of time required for the cumulative cash flow from a project to equal its initial and ongoing investment is referred to as:
Answer Selected Answer:

break-even analysis (BEA)


Correct Answer:

break-even analysis (BEA)

User Course Test Started Submitted Status Score Time Elapsed Instructions

Todd M Sayers Fall 2013:-00F-Systems Analysis & Design 203PQ06V6 9/28/13 8:47 PM 9/28/13 9:04 PM Completed 0 out of 0 points 17 minutes out of 20 minutes.

Question 1
0 out of 0 points

Which of the following is the eXtreme Programming Planning Game phase where Business has a chance to see how the development process is progressing and to work with Development to adjust the plan accordingly?
Answer Selected Answer:

steering
Correct Answer:

steering

Question 2
0 out of 0 points

The trained individual who plans and leads Joint Application Design sessions is referred to as the:
Answer Selected Answer:

JAD session leader


Correct Answer:

JAD session leader

Question 3
0 out of 0 points

Which of the following technologies disrupted the business rule that information can appear only in one place at a time?
Answer Selected Answer:

distributed databases
Correct Answer:

distributed databases

Question 4
0 out of 0 points

Technologies that enable the breaking of long-held business rules that inhibit organizations from making radical business changes best defines:
Answer Selected Answer:

disruptive technologies
Correct Answer:

disruptive technologies

Question 5
0 out of 0 points

Which of the following is not an Agile Methodologies requirements determination technique?

Answer Selected Answer:

JAD
Correct Answer:

JAD

Question 6
0 out of 0 points

Prototyping is most useful for requirements determination when:


Answer Selected Answer:

communication problems have existed in the past between users and analysts communication problems have existed in the past between users and analysts

Correct Answer:

Question 7
0 out of 0 points

The search for, and implementation of, radical change in business processes to achieve breakthrough improvements in products and services best defines:
Answer Selected Answer:

business process reengineering


Correct Answer:

business process reengineering

Question 8
0 out of 0 points

Good interview guidelines consist of:


Answer Selected Answer:

seeking a variety of perspectives from the interviews


Correct Answer:

seeking a variety of perspectives from the interviews

Question 9
0 out of 0 points

Continual user involvement works best when:


Answer Selected Answer:

the development group is small

Correct Answer:

the development group is small

Question 10
0 out of 0 points

The reframing characteristic of a good systems analyst is represented by which of the following statements?
Answer Selected Answer:

You must challenge yourself to look at the organization in new ways.


Correct Answer:

You must challenge yourself to look at the organization in new ways.

User Course Test Started Submitted Status Score Time Elapsed Instructions

Todd M Sayers Fall 2013:-00F-Systems Analysis & Design 203PQ07V6 10/3/13 3:59 AM 10/3/13 4:15 AM Completed 0 out of 0 points 15 minutes out of 20 minutes.

Question 1
0 out of 0 points

If a data flow appears on the context diagram and is also represented at level-0, this would be referred to as:
Answer Selected Answer:

balancing
Correct Answer:

balancing

Question 2
0 out of 0 points

If an input from a source appears at level-0, it must:


Answer Selected Answer:

appear on the context diagram


Correct Answer:

appear on the context diagram

Question 3
0 out of 0 points

When you believe that you have shown each business form or transaction, computer screen, and report as a single data flow, you have probably reached the:
Answer Selected Answer:

primitive data flow diagrams


Correct Answer:

primitive data flow diagrams

Question 4
0 out of 0 points

Assume the first condition has two values; the second condition has two values; the third condition has three values. How many rules will there be?
Answer Selected Answer:

12
Correct Answer:

12

Question 5
0 out of 0 points

The origin and/or destination of data, sometimes referred to as external entities defines:
Answer Selected Answer:

source/sink
Correct Answer:

source/sink

Question 6
0 out of 0 points

A data flow diagram that represents a system's major processes, data flows, and data stores at a high level of detail refers to:
Answer Selected Answer:

level-0 diagram
Correct Answer:

level-0 diagram

Question 7
0 out of 0 points

To determine the number of rules required for the decision table, you would:
Answer Selected Answer:

multiply the number of values for each condition by the number of values

for every other condition


Correct Answer:

multiply the number of values for each condition by the number of values for every other condition
0 out of 0 points

Question 8

The part of a decision table that links conditions to actions is the section that contains the:
Answer Selected Answer:

rules
Correct Answer:

rules

Question 9
0 out of 0 points

Removing any rules with impossible actions to make which of the following simple as possible?
Answer Selected Answer:

decision table
Correct Answer:

decision table

Question 10
0 out of 0 points

By placing a data store between two processes, this:


Answer Selected Answer:

decouples the processes


Correct Answer:

decouples the processes

Anda mungkin juga menyukai