Alwin Engineering Builders

Construction of Civil and Allied works for TOESL Steam Supply Project at Madura Coats Pvt. Ltd., for

24-Oct-13

M/s. Thermax Ltd., Ambasamudram


RA Bill No: 12
Sl.
No.

Description of work

Nos

Qty

Unit

Remarks

1 Earthwork excavation
upto 1.50m depth
Auxillary Foundations

2.700

2.850

1.500

23.09

Econmizer foundations

12.150 6.150

1.500

112.08
135.17 Cum

From 1.50 to 3.0m depth


Auxillary Foundations

2.700

2.850

0.050

0.77
0.77 Cum

2 Providing and laying of Soling


Econmizer foundations

12.150 3.300

0.230

9.22

12.150 2.850

0.230

7.96
17.18 Cum

3 Providing and laying of Plain Cement Concrete


Auxillary Foundations

2.700

2.850

0.150

2.31

Econmizer foundations

2.700

2.800

0.150

4.54

2.250

2.400

0.150

3.24

30.000 2.550

0.100

7.65

Storm water Drain


17.74 Cum
4 Reinforced Cement Concrete grade M25
Control room
Ground floor beam & slab
for beams
Horizontal
B2

5.460

0.230

0.300

1.88

B2

5.250

0.230

0.300

0.72

B2

4.700

0.230

0.300

1.30

B2

2.335

0.230

0.300

0.32

B3

5.320

0.200

0.200

0.43

B3

4.770

0.200

0.200

0.38

for slab

5.460 18.480

0.150

15.14

for projection

1.000

2.826

0.150

0.42

d/d for staircase

-1

5.080

2.335

0.150

-1.78

d/d for opening

-1

0.500

2.100

0.150

-0.32

for Columns in GF

0.300

0.450

0.450

0.49

0.230

0.450

0.450

0.09

Vertical

Columns from GF roof to FF slab bottom


Page 1 of 17

Sl.
No.

Description of work

Nos

Qty

Grid J4, F8-C1

0.230

0.450

4.025

0.42

Grid H4, F9-C2

0.300

0.450

4.025

0.54

Grid J16, C1

0.230

0.450

4.025

0.42

Grid H16, C2

0.300

0.450

4.025

0.54

Grid G16, F9-C3

0.300

0.450

4.025

1.09

Grid G'4, F9-C3

0.300

0.450

4.025

0.54

Grid F'4, F9-C3

0.300

0.450

4.025

0.54

Grid E4, F6-C3

0.300

0.450

4.025

0.54

Grid E&F16, F5-C3

0.300

0.450

4.025

0.54

RB1

4.640

0.230

0.275

0.29

RB3

4.640

0.230

0.275

0.59

RB4

5.460

0.300

0.425

1.39

RB5

5.250

0.230

0.425

0.51

RB1

4.700

0.230

0.275

0.30

RB2

2.335

0.230

0.275

0.30

RB1

5.250

0.200

0.275

0.29

for slab

5.540 18.380

0.175

17.82

d/d for staircase

-1

5.080

2.335

0.175

-2.08

d/d for Deck slab portioin

-1

5.540

5.300

0.175

-5.14

for projection

1.000 11.355

0.175

1.99

for Plinth beam

1.150

0.230

0.350

0.09

1st flight

4.263

1.150

0.175

0.86

landing

1.073

2.370

0.175

0.45

SB1 at +2.70m LVL

2.370

0.230

0.350

0.19

2nd flight

4.263

1.028

0.175

0.77

landing

1.073

2.370

0.175

0.45

SB1 at +5.10m LVL

2.370

0.230

0.350

0.19

3rd flight

3.253

1.150

0.175

0.65

landing

1.337

2.370

0.175

0.55

SB1 at +7.133m LVL

2.370

0.230

0.350

0.19

4th flight

3.590

1.028

0.175

0.65

landing

1.340

2.370

0.175

Unit

Remarks

First floor beam & slab


for beams
Horizontal

Vertical

for Staircase

0.56
46.10 Cum

5 Reinforced Cement Concrete grade M20


Fuel Pit-2
Staircase
waist slab

2.750

0.750

0.200

0.83

3.400

0.800

0.200

0.54

Fuel Pit-1
Staircase
1st flight

Page 2 of 17

Sl.
No.

Description of work

Nos

Qty

landing

1.550

0.900

0.200

0.28

2nd flight

5.650

0.800

0.200

0.90

for raft

2.550

2.700

0.400

5.51

for pedestals

0.500

0.500

2.000

4.00

for Grid A1, B1, C1 & D1

2.250

2.100

0.380

7.18

for Grid A2, B2, C2 & D2

2.650

2.550

0.380

10.27

for Grid A1, B1, C1 & D1

0.650

0.700

2.180

3.97

for Grid A2, B2, C2 & D2

0.650

0.750

2.180

Unit

Remarks

Auxillary Foundations (E12A & E12B)

Econmizer foundations
for footings

for pedestals
4.25
37.73 Cum
6 Shuttering works
Control room
Ground floor beam & slab
for beams
Horizontal
B2

5.460

0.300

16.38

B2

5.250

0.300

6.30

B2

4.700

0.300

11.28

B2

2.335

0.300

2.80

B3

5.320

0.200

4.26

B3

4.770

0.200

3.82

for slab

5.460 18.480

for projection

1.000

add for sides

47.880

0.150

7.18

add for sides

1.000

0.150

0.30

d/d for staircase

-1

5.080

add for sides

14.830

d/d for opening

-1

0.500

add for sides

5.200

0.150

1.56

for Columns in GF

1.500

0.450

5.40

1.360

0.450

1.22

Grid J4, F8-C1

1.360

4.025

5.47

Grid H4, F9-C2

1.500

4.025

6.04

Grid J16, C1

1.360

4.025

5.47

Grid H16, C2

1.500

4.025

6.04

Grid G16, F9-C3

1.500

4.025

12.08

Grid G'4, F9-C3

1.500

4.025

6.04

Grid F'4, F9-C3

1.500

4.025

6.04

Grid E4, F6-C3

1.500

4.025

6.04

Grid E&F16, F5-C3

1.500

4.025

6.04

Vertical

100.90

2.826

2.83

2.335

-11.86
0.150

2.100

2.22
-2.10

Columns from GF roof to FF slab bottom

Page 3 of 17

Sl.
No.

Description of work

Nos

Qty

Unit

Remarks

First floor beam & slab


for beams
Horizontal
RB1

4.640

0.275

2.55

RB3

4.640

0.275

5.10

RB4

5.460

0.425

9.28

RB5

5.250

0.425

4.46

RB1

4.700

0.275

2.59

RB2

2.335

0.275

2.57

RB1

5.250

0.275

2.89

for slab

5.540 18.380

add for sides

47.840

d/d for staircase

-1

5.080

add for sides

14.830

d/d for Deck slab portioin

5.540

add for sides

21.680

for projection

1.000 11.355

add for sides

1.000

0.175

0.35

for Plinth beam

1.150

0.350

0.81

1st flight

4.263

add for sides

4.263

landing

1.073

add for sides

3.443

0.175

0.60

SB1 at +2.70m LVL

2.370

0.350

1.66

bottom

2.370

0.230

2nd flight

4.263

1.028

add for sides

4.263

landing

1.073

add for sides

3.443

SB1 at +5.10m LVL

2.370

bottom

2.370

0.230

0.55

3rd flight

3.253

1.150

3.74

add for sides

3.253

landing

1.337

add for sides

3.707

0.175

0.65

SB1 at +7.133m LVL

2.370

0.350

1.66

bottom

2.370

0.230

0.55

4th flight

3.590

1.028

3.69

add for sides

3.590

landing

1.340

add for sides

3.710

Vertical

101.83
0.175

2.335

8.37
-11.86

0.175
5.300

2.60
29.36

0.175

3.79
11.36

for Staircase
1.150

4.90
0.175

2.370

1.49
2.54

0.55
4.38
0.175

2.370

1.49
2.54

0.175

0.60

0.350

1.66

0.175
2.370

1.14
3.17

0.175
2.370

1.26
3.18

0.175

0.65

Fuel Pit-2
Staircase
Page 4 of 17

Sl.
No.

Description of work

Nos

B
0.750

Qty

waist slab

2.750

for sides

2.750

1st flight

3.400

for sides

3.400

landing

1.550

for sides

2.450

2nd flight

5.650

for sides

5.650

0.200

for raft

10.500

0.400

8.40

for pedestals

2.000

2.000

32.00

11.000

0.150

6.60

9.300

0.150

5.58

for Grid A1, B1, C1 & D1

8.700

0.380

13.22

for Grid A2, B2, C2 & D2

10.400

0.380

15.81

for Grid A1, B1, C1 & D1

2.700

2.180

23.54

for Grid A2, B2, C2 & D2

2.800

2.180

24.42

Unit

Remarks

4.13
0.200

2.20

Fuel Pit-1
Staircase
0.800

2.72
0.200

0.900

1.36
1.40

0.200
0.800

0.49
4.52
1.13

Auxillary Foundations (E12A & E12B)

Econmizer foundations
for footings-PCC
Econmizer foundations
for footings

for pedestals

577.97 Sqm
7 Reinforcement Steel
Control room
Ground floor beam & slab
for beams
Horizontal
B2
botom main-16mm

5.940

1.580

140.78

extra-16mm

4.440

1.580

105.23

spacer-16mm

0.230

1.580

9.09

top main-16mm

5.940

1.580

140.78

extra-16mm

2.040

1.580

96.70

spacer-16mm

0.230

1.580

10.90

stirrups-8mm

36

1.320

0.400

95.04

botom main-16mm

18.780

1.580

178.03

extra-16mm

4.450

1.580

42.19

spacer-16mm

0.230

1.580

3.63

extra-16mm

4.000

1.580

37.92

spacer-16mm

0.230

1.580

3.63

extra-16mm

4.000

1.580

37.92

Vertical
B2-B1

Page 5 of 17

Sl.
No.

Description of work

Nos

Qty

spacer-16mm

0.230

1.580

3.63

extra-16mm

2.080

1.580

19.72

spacer-16mm

0.230

1.580

2.18

top main-16mm

18.780

1.580

178.03

extra-16mm

1.890

1.580

17.92

spacer-16mm

0.230

1.580

1.45

extra-16mm

2.940

1.580

27.87

spacer-16mm

0.230

1.580

2.18

extra-16mm

2.800

1.580

26.54

spacer-16mm

0.230

1.580

2.18

extra-16mm

2.200

1.580

20.86

spacer-16mm

0.230

1.580

2.18

extra-16mm

1.080

1.580

10.24

spacer-16mm

0.230

1.580

1.45

stirrups-8mm

117 1.320

0.400

123.55

Unit

Remarks

B3
bottom main-16mm

11.180

1.580

105.99

extra-16mm

4.450

1.580

42.19

spacer-16mm

0.230

1.580

3.63

extra-16mm

4.000

1.580

37.92

spacer-16mm

0.230

1.580

3.63

top main-16mm

11.180

1.580

105.99

extra-16mm

1.820

1.580

17.25

spacer-16mm

0.230

1.580

1.45

extra-16mm

2.870

1.580

27.21

spacer-16mm

0.230

1.580

2.18

extra-16mm

1.680

1.580

15.93

spacer-16mm

0.230

1.580

1.45

stirrups-8mm

68

1.260

0.400

68.54

bottom main-16mm

0.650

1.580

6.16

top main-16mm

0.650

1.580

6.16

stirrups-8mm

0.740

0.400

3.55

bottom main-10mm

22

5.450

0.620

74.34

bottom main-10mm

23

7.180

0.620

102.39

top extra-10mm

45

0.730

0.620

20.37

top extra-10mm

45

2.480

0.620

69.19

top dist-10mm

5.540

0.620

17.17

top dist-10mm

13

5.540

0.620

44.65

dist-10mm

36

5.690

0.620

127.00

top extra-10mm

36

0.730

0.620

32.59

top dist-10mm

5.300

0.620

26.29

Chairs-12mm

24

1.650

0.890

35.24

CB

for Slab
S1 slab (10mm-125 & 150mm c/c)

Page 6 of 17

Sl.
No.

Description of work

Nos

Qty

Unit

Remarks

S2 slab (10mm-175 & 200mm c/c)


bottom main-10mm

30

3.960

0.620

73.66

top extra-10mm

30

0.630

0.620

23.44

top dist-10mm

5.000

0.620

18.60

dist-10mm

10

5.610

0.620

34.78

dist-10mm

10

7.490

0.620

46.44

top extra-10mm

20

2.555

0.620

31.68

top dist-10mm

10

3.810

0.620

47.24

Chairs-12mm

20

1.650

0.890

29.37

bottom main-10mm

30

3.960

0.620

73.66

top extra-10mm

30

0.630

0.620

23.44

top dist-10mm

5.000

0.620

18.60

dist-10mm

10

5.610

0.620

34.78

dist-10mm

10

7.490

0.620

46.44

top extra-10mm

20

0.780

0.620

9.67

top dist-10mm

10

3.810

0.620

47.24

Chairs-12mm

20

1.650

0.890

29.37

bottom main-10mm

0.900

0.620

4.46

dist-8mm

1.664

0.400

2.66

bottom main-10mm

0.900

0.620

3.91

dist-8mm

1.466

0.400

2.35

bottom main-10mm

30

0.900

0.620

16.74

dist-8mm

5.300

0.400

12.72

bottom main-10mm

17

0.900

0.620

9.49

dist-8mm

3.296

0.400

5.27

bottom main-10mm

31

0.900

0.620

17.30

dist-8mm

5.320

0.400

12.77

extra-10mm

20

1.730

0.620

21.45

bottom main-12mm

20

2.230

0.890

39.69

dist-8mm

2.870

0.400

9.18

extra bars-12mm (T&B)

3.500

0.890

37.38

extra bars-12mm (T&B)

10

1.100

0.890

29.37

cross bars-12mm (T&B)

1.110

0.890

23.71

extra bars-12mm (T&B)

3.514

0.890

37.53

extra bars-12mm (T&B)

10

1.100

0.890

29.37

cross bars-12mm (T&B)

1.110

0.890

23.71

Vertical-16mm

3.900

1.580

49.30

laps-16mm

0.800

1.580

10.11

S2 slab (10mm-175 & 200mm c/c)

S3 slab (10mm-175 & 8-150mm c/c)

S3 slab (10mm-175 & 8-150mm c/c)

projection
S4 slab (12mm-150 & 8-150mm c/c)

Columns from GF roof to FF slab bottom


Grid J4, F8-C1

Page 7 of 17

Sl.
No.

Description of work

Nos

Qty

stirrups-8mm

27

1.240

0.400

13.39

hook-8mm

27

0.570

0.400

6.16

Vertical-25mm

3.900

3.860

60.22

laps-25mm

1.250

3.860

19.30

Vertical-20mm

3.900

2.470

38.53

laps-20mm

1.000

2.470

9.88

stirrups-8mm

27

1.380

0.400

14.90

hook-8mm

27

0.570

0.400

6.16

Vertical-16mm

3.900

1.580

49.30

laps-16mm

0.800

1.580

10.11

stirrups-8mm

27

1.240

0.400

13.39

hook-8mm

27

0.570

0.400

6.16

Vertical-25mm

3.900

3.860

60.22

laps-25mm

1.250

3.860

19.30

Vertical-20mm

3.900

2.470

38.53

laps-20mm

1.000

2.470

9.88

stirrups-8mm

27

1.380

0.400

14.90

hook-8mm

27

0.570

0.400

6.16

Vertical-25mm

3.900

3.860

240.86

laps-25mm

1.250

3.860

77.20

stirrups-8mm

27

1.380

0.400

29.81

Vertical-25mm

3.900

3.860

120.43

laps-25mm

1.250

3.860

38.60

stirrups-8mm

27

1.380

0.400

14.90

Vertical-25mm

3.900

3.860

120.43

laps-25mm

1.250

3.860

38.60

stirrups-8mm

27

1.380

0.400

14.90

Vertical-25mm

3.900

3.860

120.43

laps-25mm

1.250

3.860

38.60

stirrups-8mm

27

1.380

0.400

14.90

Vertical-25mm

3.900

3.860

120.43

laps-25mm

1.250

3.860

38.60

stirrups-8mm

27

1.380

0.400

14.90

Unit

Remarks

Grid H4, F9-C2

Grid J16, C1

Grid H16, C2

Grid G16, F9-C3

Grid G'4, F9-C3

Grid F'4, F9-C3

Grid E4, F6-C3

Grid E&F16, F5-C3

First floor beam & slab


for beams
Horizontal
RB1
Page 8 of 17

Sl.
No.

Description of work

Nos

Qty

bottom main-16mm

5.940

1.580

28.16

top main-16mm

5.940

1.580

28.16

stirrups-8mm

36

1.320

0.400

19.01

bottom main-16mm

5.940

1.580

56.31

extra-16mm

4.440

1.580

42.09

spacer-16mm

0.230

1.580

3.63

top main-16mm

5.940

1.580

56.31

extra-16mm

2.040

1.580

38.68

spacer-16mm

0.230

1.580

4.36

stirrups-8mm

36

1.320

0.400

38.02

bottom main-32mm

6.315

6.320

239.46

extra-25mm

4.655

3.860

107.81

spacer-25mm

0.230

3.860

8.88

top main-32mm

6.315

6.320

239.46

extra-25mm

2.000

3.860

92.64

spacer-25mm

0.230

3.860

10.65

stirrups-10mm

39

1.620

0.620

78.34

bottom main-16mm

5.700

1.580

54.04

top main-16mm

5.700

1.580

54.04

stirrups-8mm

36

1.320

0.400

38.02

bottom main-12mm

3.265

0.890

17.44

top main-12mm

3.265

0.890

17.44

stirrups-8mm

20

1.320

0.400

21.12

bottom main-16mm

6.315

1.580

29.93

top main-16mm

6.315

1.580

29.93

stirrups-8mm

39

1.320

0.400

20.59

bottom main-10mm

22

5.475

0.620

74.68

bottom main-10mm

23

7.205

0.620

102.74

top extra-10mm

45

0.730

0.620

20.37

top extra-10mm

45

2.480

0.620

69.19

top dist-10mm

5.540

0.620

17.17

top dist-10mm

13

5.540

0.620

44.65

dist-10mm

36

5.715

0.620

127.56

top extra-10mm

36

0.730

0.620

32.59

top dist-10mm

5.300

0.620

26.29

Chairs-12mm

24

1.675

0.890

35.78

Unit

Remarks

RB3

Vertical
RB5

RB1

RB2

RB1

for slab
S1 slab (10mm-150 & 175mm c/c)

S1 slab (10mm-150 & 175mm c/c)


Page 9 of 17

Sl.
No.

Description of work

Nos

Qty

bottom main-10mm

20

5.715

0.620

70.87

bottom main-10mm

20

6.715

0.620

83.27

top extra-10mm

40

0.730

0.620

18.10

top extra-10mm

40

2.500

0.620

62.00

top dist-10mm

5.815

0.620

18.03

top dist-10mm

11

5.815

0.620

39.66

dist-10mm

33

5.990

0.620

122.56

top extra-10mm

36

0.780

0.620

17.41

top extra-10mm

36

2.250

0.620

50.22

top dist-10mm

5.540

0.620

13.74

top dist-10mm

12

5.540

0.620

41.22

Chairs-12mm

24

1.675

0.890

35.78

bottom main-10mm

77

2.500

0.620

119.35

dist-10mm

11.355

0.620

49.28

bottom main-16mm

1.380

1.580

6.54

top main-16mm

1.380

1.580

6.54

stirrups-8mm

1.120

0.400

4.03

bottom main-16mm

13

4.874

1.580

100.11

top extra-10mm

13

1.630

1.580

33.48

top extra-10mm

13

2.758

1.580

56.65

top extra-10mm

13

2.783

1.580

57.16

dist-8mm

33

1.150

0.400

15.18

dist-8mm

11

1.150

0.400

10.12

Chairs-12mm

1.700

0.890

12.10

dist-12mm

10

2.830

0.890

50.37

bottom main-16mm

13

6.234

1.580

128.05

top extra-10mm

13

2.583

1.580

53.05

top extra-10mm

13

2.758

1.580

56.65

top extra-10mm

13

2.783

1.580

57.16

dist-8mm

35

1.028

0.400

14.39

dist-8mm

11

1.028

0.400

9.05

Chairs-12mm

1.700

0.890

12.10

dist-12mm

10

2.830

0.890

50.37

bottom main-16mm

13

5.441

1.580

111.76

top extra-10mm

13

2.545

1.580

52.27

top extra-10mm

13

2.717

1.580

55.81

top extra-10mm

13

2.742

1.580

56.32

dist-8mm

27

1.150

0.400

12.42

dist-8mm

1.150

0.400

8.28

Unit

Remarks

projection

for Staircase
for Plinth beam

1st flight

2nd flight

3rd flight

Page 10 of 17

Sl.
No.

Description of work

Nos

Qty

Chairs-12mm

1.700

0.890

12.10

dist-12mm

10

2.830

0.890

50.37

bottom main-16mm

13

5.516

1.580

113.30

top extra-10mm

13

2.375

1.580

48.78

top extra-10mm

13

2.817

1.580

57.86

top extra-10mm

13

2.842

1.580

58.37

dist-8mm

27

1.028

0.400

11.10

dist-8mm

1.028

0.400

7.40

Chairs-12mm

1.700

0.890

12.10

dist-12mm

10

2.830

0.890

50.37

bottom main-12mm

3.230

0.890

25.87

top main-12mm

3.230

0.890

25.87

extra-16mm

1.250

1.580

35.55

stirrups-8mm

20

1.120

0.400

26.88

bottom main-12mm

4.150

0.890

44.32

top main-12mm

4.150

0.890

44.32

dist-12mm

19

0.750

0.890

25.37

dist-12mm

19

0.750

0.890

25.37

Chairs-12mm

1.750

0.890

18.69

bottom main-12mm

4.950

0.890

26.43

top main-12mm

4.950

0.890

26.43

dist-12mm

24

0.800

0.890

17.09

dist-12mm

24

0.800

0.890

17.09

Chairs-12mm

1.750

0.890

9.35

landing dist-12mm

1.550

0.890

19.31

bottom main-12mm

6.850

0.890

36.58

top main-12mm

6.850

0.890

36.58

dist-12mm

39

0.800

0.890

27.77

dist-12mm

39

0.800

0.890

27.77

Chairs-12mm

1.750

0.890

10.90

top & bottom main-10mm

19

3.150

0.620

148.43

dist-10mm

18

3.300

0.620

147.31

Chairs-12mm

2.150

0.890

15.31

12

3.200

1.580

121.34

Unit

Remarks

4th flight

SB1 at +2.70, +5.10, 7.133m LVL

Fuel Pit-2
Staircase waist slab

Fuel Pit-1
Staircase
1st flight

2nd flight

Auxillary Foundations (E12A & E12B)


for raft

for Pedestals
Vertical-16mm

Page 11 of 17

Sl.
No.

Description of work

Nos

Qty

stirrups-8mm

34

1.622

0.400

44.12

stirrups-8mm

34

1.622

0.400

44.12

bottom main-10mm

16

2.500

0.620

99.20

dist-10mm

15

2.650

0.620

98.58

bottom main-10mm

19

2.950

0.620

139.00

dist-10mm

18

3.050

0.620

136.15

Vertical-20mm

12

3.560

2.470

422.07

stirrups-8mm

36

2.200

0.400

126.72

stirrups-8mm

36

2.220

0.400

127.87

Vertical-20mm

10

3.560

2.470

351.73

Vertical-16mm

3.360

1.580

84.94

stirrups-8mm

36

2.364

0.400

136.17

hook-8mm

18

0.970

0.400

27.94

stirrups-8mm

36

2.320

0.400

133.63

Unit

Remarks

Econmizer foundations
for footings
for Grid A1, B1, C1 & D1

for Grid A2, B2, C2 & D2

for pedestals
for Grid A1, B1, C1 & D1-P1

for Grid A2, B2, C2 & D2

11818.15

Kg

11.82

MT

8 Random Rubble Masonry


Storm water Drain
1st layer

30.000 0.450

0.500

13.50

2nd layer

30.000 0.350

0.500

10.50
24.00 Cum

9 Brick work in CM 1:5


Fuel Pit-2
Staircase steps

18 0.5

2.750

0.300

0.250

1.86

1st flight

0.5

0.800

0.300

0.250

0.27

2nd flight

16 0.5

0.800

0.300

0.250

0.48

Fuel Pit-1

2.61 Cum
Fixing of MS / CS Foundation Bolts in Concrete to the required Lines and Level as per BOQ
Econmizer foundations
48mm dia bolt

56

15.520
Kg
MT

Page 12 of 17

ALWIN ENGINEERING BUILDERS


BILL ABSTRACT
BILL NO. : 63907 / RA-01, Date :05.05.2013
Work : Civil Works for Boiler House - TOESL - Madura Coats Ambasamudharam
LOI No. : WWS/MPG/BR/W660023/ 02 DT.-03.11.2009

SL
NO

PART NUMBER

1.a
1.b
1.c
1.d

WG6EA02001
WG6EA02093
WG6EA02094
WG6EA02095

WG6EA02009

3
4
5
6

WG6EA02010
WG6EA02011
WG6EA02012
WG6EA02013

WG6EA02015 P & L PCC 1:4:8 including Cement.

WG6EA02023

DESCRIPTION
Earth work excavations 0.0 M to 1.5 M Level
Earth work excavations 1.50 M to 3.0 M Level
Earth work excavations 3.0 M to 4.5 M Level
Earth work excavations 4.5 M to 6.0 M Level

UNIT

YOUR JOB NO : W735013


P.O NUMBER: 63907, Dated 03.05.2013 & 67062, Dated 24.07.2013
VENDOR CODE : 143747

QTY

UNIT RATE

CUM
CUM
CUM
CUM

2000.00

150.00
200.00
375.00
500.00

CUM

800.00

110.00

CUM
CUM
CUM
CUM

2000.00
300.00
50.00
900.00

150.00
650.00
1750.00
1200.00

CUM

350.00

3950.00

P & L in situ RCC M 20 grade as per the Design Mix without


Water proofing Compound admixture including Cement

CUM

350.00

5200.00

P & L in situ RCC M 25 grade as per the Design Mix without


Water proofing Compound admixture including Cement

CUM

Carting away Excess Excavated Earth from Site from a lead of


2 kms to 5 kms
Re-usable Excavated Earth
Back filling with Gravel / Murrum
Sand filling
Providing and laying 230 mm thick dry rubble soling

WG6EA02028

10

Providing and fixing plywood centering and shuttering at all


WG6EA02032 Levels complete

SQM

Providing and fixing plywood centering and shuttering at all


Levels complete (As per new ratte)

SQM

Cleaning, bending, hooking & placing in positions TOR steel


Reinforcement (INCLUDING SUPPLY OF RF STEEL)

MT

Cleaning, bending, hooking & placing in positions TOR steel


Reinforcement (INCLUDING SUPPLY OF RF STEEL) (As per
new rate)

MT

P & L Uncoarsed Rubble Masonry of all thickness with CM 1:5


at all Levels. ( INCLUDING CEMENT)

CUM

100.00

2850.00

CUM

200.00

4750.00

WG6EA02035

12

WG6EA02037

13

P & L first class Brick Masonry in CM 1:5 from 0.00 m to 6.00 m


WG6EA02038
level (Cement Free Supply)

2500.00

AMOUNT

135.17
0.77

QTY

AMOUNT

QTY

AMOUNT

20275.50
154.00
0.00

1845.16
624.21
14.5
0

276774.00
124842.00
5437.50
0.00

1980.33
624.98
14.5
0

297049.50
124996.00
5437.50
0.00

0.00
0.00

799
5.97

87890.00
895.50

799
5.97

87890.00
895.50

17.18

20616.00

17.18

20616.00

17.74

70073.00

111.83

441728.50

129.57

511801.50

37.730

196196.00

481.63

2504476.00

519.36

2700672.00

46.10

253550.00

310.09

1705495.00

356.19

1959045.00

824.98

247494.00

824.98

247494.00

1304.39

586975.50

1882.36

847062.00

35.959

2085622.00

35.959

2085622.00

300.00
450.00

80.00

QTY

Date:
24-Oct-13
UPTO DATE

5500.00

11

650.00

RA Bill No.
12
UPTO PREVIOUS

THIS BILL

577.97

260086.50

58000.00

63000.00
11.820

744660.00

38.301

2412963.00

50.121

3157623.00

24.00

68400.00

53.32

151962.00

77.32

220362.00

2.61

12397.50

2.61

12397.50
Page 13 of 17

SL
NO

PART NUMBER

DESCRIPTION

14

Prepare the surfaces of all ceiling and sofits of RC surfaces in


WG6EA02042 all floors and plastering in cm 1:3, 06 mm thick

15

WG6EA02045

16

WG6EA02047

17

WG6EA02049

18

WG6EA02050

19

Plaster in cm 1:4, 12mm thick at all Levels. (INCLUDING


CEMENT)
Plaster in cm 1:5, 18mm thick in two coats at all Levels. (
INCLUDING CEMENT)
Prepare the surface of all ceiling all height and sofits of RC
surfaces and apply 3 coats of white wash / colour
Prepare the surfaces of al internal wall at all heights and apply 2

coats of Oil bound Distemper paint


P & A 2 Coats of Acrylic Emulsion Paint over 1 coat of
WG6EA02051
compatible Primer at all height
P & F Aluminium Anodized (10 micron natural) powder coated
aluminium double leaf door
Supply, fabricating and fixing M.S panelled shutters Door

UNIT

QTY

UNIT RATE

SQM

250.00

250.00

SQM

900.00

230.00

SQM

900.00

300.00

SQM

600.00

40.00

SQM

600.00

120.00

SQM

600.00

180.00

SQM

30.00

4500.00

SQM

50.00

3000.00

20

WG6EA02054

21

WG6EA02055

22

WG6EA02056 Steel windows of standard dimensions

SQM

30.00

2500.00

23

P & F of anodized (10 microns) Aluminium Fixed / Openable /


WG6EA02057
Slinding Widows.

SQM

30.00

4000.00

24

WG6EA02058

SQM

30.00

4000.00

25

WG6EA02059 P & F of Gear Operated Rolling Shutters

SQM

50.00

4000.00

26

WG6EA02065

CUM

5.00

6000.00

27

WG6EA02066 Equipments / Pumps / column bases with Non-shrink grouting

CUM

2.00

50000.00

SQM

200.00

750.00

SQM

100.00

770.00

SQM

2300.00

275.00

SQM

1200.00

375.00

SQM

100.00

650.00

P & F Powder coated aluminium anodized (10 Microns,


Natural) fixed ventilators

Providing and Grouting the Pockets and Column bases with


cement concrete 1:1:5 3 etc complete ( Including Cement)

THIS BILL
QTY

AMOUNT

UPTO PREVIOUS
QTY

AMOUNT

UPTO DATE
QTY

AMOUNT

Providing and grouting the pockets and Foundations /

28
29
30

WG6EA02067

complete (Including Shuttering)


Supplying and laying of ceramic tile flooring of approved colour

and make
WG6EA02068 Do: as above but for ceramic dadoing
Prepare the surfaces of leveling course / RC slabs and lay 40
WG6EA02069
mm thick grano concrete flooring (I.P.S)

31

WG6EA02070

32

WG6EA02074

Prepare the surfaces of leveling course / RC slabs and lay 40


mm thick grano concrete flooring (I.P.S) with Metallic Hardener
Providing and laying Plinth protection around the proposed
main buildings & structures

Page 14 of 17

SL
NO
33
34
35
36

PART NUMBER

DESCRIPTION

Providing and fixing of 150 mm dia PVC rain water down take
WG6EA02076
pipes with necessary, shoes, bends, offset pieces etc ( 4
kg/cm2)
Providing Pockets for Equipments, Pumps, Blower to maximum
WG6EA02081
depth of 500 mm.
Providing and laying first class brick masonry in cm 1:5 in Plant
WG6EA02083
drains.
Prepare the surfaces of all internal & external walls of drains
WG6EA02084
and plaster in cm 1:5, 15mm thick

UNIT

QTY

UNIT RATE

RM

50.00

400.00

Nos

75.00

200.00

CUM

150.00

4750.00

SQM

200.00

230.00

37

Providing & Laying Water Bound Macadam Road in 2 layers


WG6EA02087 using Stone Metal of 50 mm to 65 mm with Gravel over stone
soling

SQM

300.00

340.00

38
39
40

WG6EA02093 Earth work excavations 1.5 M to 3.0 M Level


WG6EA02094 Earth work excavations 3.0 M to 4.5 M Level
WG6EA02095 Earth work excavations 4.5 M to 6.0 M Level

CUM
CUM
CUM

850.00
150.00
50.00

200.00
375.00
500.00

41

WG6EA02152 Roof Water Proofing - Brick Bat Coba (including Cement)

SQM

100.00

850.00

42

WG6EA02264

Providing & Laying GSB (Granular Sub Base) in Layers and


Compacting as per BOQ

CUM

300.00

150.00

43

WG6EA01640

Providing & laying Premix carpet with bitumen binder 40 mm


Thick above WBM

SQM

300.00

350.00

44

WG6EA01641

Providing & laying Seal coat of Bitumen with Fine Aggregate as


per specification

SQM

300.00

100.00

E1
E2

EXTRA ITEMS (APPROVED BY M/S. THERMAX)


Excavation in Soft Rock by Chiselling
Excavation in Hard Rock by Chiselling

CUM
CUM

QTY

AMOUNT

UPTO DATE
QTY

AMOUNT

114.68
139.96

57340.00
447872.00

114.68
139.96

57340.00
447872.00

100.00

680

68000.00

680.00

68000.00

9.641

192820.00

9.64

192820.00

28

28000.00

28.00

28000.00

0.897

74002.50

0.90

74002.50

Providing Diesel / Electric Operated Pumping System for


Dewatering of Open Excavated Pits as per BOQ

Hrs

E4

Fixing of MS / CS Foundation Bolts in Concrete to the required


Lines and Level as per BOQ

MT

E5

Providing Excavator Cum Dozer on Hire Basis for levelling

Hrs

1000.00

E6

Supplying and Fixing of MS / CS Insert plates in Concrete to the


required Lines and Level

MT

82500.00

VAT at 2%
Service Tax at 40% of 12%
Surcharge on Service Tax at 2%

UPTO PREVIOUS

AMOUNT

500.00
3200.00

E3

TOTAL

THIS BILL
QTY

20000.00

0.00

1646409
32928
79028
1581

11500589.50
230011.79
552028.3
11040.57

13146998.00
262939.96
631055.91
12621.12
Page 15 of 17

SL
NO

PART NUMBER

DESCRIPTION
Surcharge on Service Tax at 1%
Bill Amount

UNIT

QTY

UNIT RATE

THIS BILL
QTY

UPTO PREVIOUS

AMOUNT

790
1760735

QTY

AMOUNT

5520.28
12299190

UPTO DATE
QTY

AMOUNT

6310.56
14059926

Page 16 of 17

Pan No: AFPPC8687K

Service Tax No.: AFPPC8687KST001


TIN Number: 33645923772

ORGINAL INVOICE
INVOICE NO : 63907 RA12, Dated : 24-10-2013
YOUR P.O NO : 63907, Dated 03.05.2013
To : THERMAX LIMITED,
FATIMA AKHTAR COURT,
453, ANNA SALAI,
TEYNAMPET,
CHENNAI - 600018
VAT TIN: 33450820852 WEF 01.01.2007
CST TIN: 698994 WEF 28.05.1981
SL
NO

PART NUMBER

1.a
1.b
6
7

WG6EA02001
WG6EA02093
WG6EA02013
WG6EA02015

8
9
10

Earth work excavations 0.0 M to 1.5 M Level


Earth work excavations 1.50 M to 3.0 M Level
Providing and laying 230 mm thick dry rubble soling

P & L PCC 1:4:8 including Cement.


P & L in situ RCC M 20 grade as per the Design Mix without Water
WG6EA02023
proofing Compound admixture including Cement
P & L in situ RCC M 25 grade as per the Design Mix without Water
WG6EA02028
proofing Compound admixture including Cement
Providing and fixing plywood centering and shuttering at all Levels
WG6EA02032
complete (As per new ratte)

11

WG6EA02035

12

WG6EA02037

13

DESCRIPTION

Cleaning, bending, hooking & placing in positions TOR steel


Reinforcement (INCLUDING SUPPLY OF RF STEEL) (As per new rate)

P & L Uncoarsed Rubble Masonry of all thickness with CM 1:5 at all


Levels. ( INCLUDING CEMENT)
P & L first class Brick Masonry in CM 1:5 from 0.00 m to 6.00 m level
WG6EA02038
(Cement Free Supply)
TOTAL

UNIT

UNIT RATE

CUM
CUM
CUM
CUM

150.00
200.00
1200.00
3950.00

CUM

5200.00

CUM

5500.00

SQM

450.00

MT

63000.00

CUM

2850.00

CUM

4750.00

VAT at 2%
Service Tax at 40% of 12%
Surcharge on Service Tax at 2%
Surcharge on Service Tax at 1%
Bill Amount

QTY.

AMOUNT

135.17
0.77
17.18
17.74

20275.50
154.00
20616.00
70073.00

37.73

196196.00

46.10

253550.00

577.97

260086.50

11.820

744660.00

24.00

68400.00

2.61

12397.50
1646409
32928
79028
1581
790
1760735

(Rupees Seventeen Lakhs Sixty Thousand Seven Hundred and Thirty Five Only)