Anda di halaman 1dari 0

Determining Economic Production Quantities Determining Economic Production Quantities

in a Continuous Process
IIE Process Industries Webinar
J uly 14, 2009
Douglas R. Kroeger, PE
Agenda
The Basics
EPQ Overview
GettingStarted / Gaining Alignment Getting Started / Gaining Alignment
Understanding the Model g
Influence of Input Variables on EPQ & EPQ on other Factors
Sensitivity Analysis
A Case Study
Objectives
Case Description
EPQ Results EPQ Results
Run Strategy
Implementation
2
Douglas R. Kroeger, PE
Implementation
The Basics - EPQ Overview
A basic decision every production facility must make is how much product to
produce (the order quantity) and how frequently to produce it.
When deciding on an order quantity, 2 costs need to be considered:
Changeover costs the cost to change from product to the next
Inventory holding costs the costs associated with carrying finished goods
EPQ in continuous process differs from discrete/batch manufacturing
Discrete manufacturing will likely have EPQs for fabricated parts, assemblies and
finished goods, continuous processes will likely have 1 EPQ for each finished g , p y
good
Cleaning and sanitation requirements often dictate the duration of a changeover
in the process industries
Quantifying changeover costs in discrete manufacturing is very different than in
continuous processes.
There may be a limited number of available PQs in a continuous process as y Q p
determined by:
-Ingredient or pre-blend batch sizes (e.g. use full tanker quantities)
-Regulatory run length restrictions (e.g. FDA, USDA)
Shift schedule
3
Douglas R. Kroeger, PE
-Shift schedule
-Traceability
EPQ Overview (contd)
A high order quantity:
low changeover costs per production unit
high inventory holding costs
fosters higher production efficiencies
i it / d tili ti increases capacity / reduces utilization
A low order quantity:
hi h h t d ti it high changeover costs per production unit
low inventory holding costs
can negatively impact production efficiencies can negatively impact production efficiencies
decreases capacity / increases utilization
The EPQ Model identifies an order quantity which minimizes the sum of the q y
changeover costs and inventory holding costs, i.e. the model balances the two
opposing costs.
4
Douglas R. Kroeger, PE
The EPQ Model Formula
EPQ Variables:
A = annual demand (units/yr)
S = set up or changeover costs ($/changeover)
H = inventory holding cost penalty (%/unit/year)
C t d d it t C = standard unit cost
Q = order quantity
Changeover Cost per Year =[(A/Q) X S] Changeover Cost per Year [(A/Q) X S]
Holding Cost per Year = [(Q/2) X (HXC)] where Q/2 is the average inventory level.
Total Cost = [(A/Q) X S] + [(Q/2) X (HXC)] [( ) ] [( ) ( )]
Economic Order Quantity (Q
0
) can be determined by setting changeover costs =
holding costs and solving for Q (this is where the 2 cost curves intersect) or by
taking the first derivative of the total cost curve setting =0 and solving for Q this is taking the first derivative of the total cost curve, setting = 0 and solving for Q, this is
the minimum of the curve.
Q
0
= [(2 X S X A) / (H X C)]
1/2
5
Douglas R. Kroeger, PE
The EPQ Model Graph
$250,000
$200,000
TOT VAR COST
$150,000
L

C
O
S
T
HOLDING COST
TOT VAR COST
$120,000
$100,000
T
O
T
A
$50,000
CO COST
$0
0 20,000 40,000 60,000 80,000 100,000 120,000 140,000 160,000
75,000 cases
6
Douglas R. Kroeger, PE
ORDER QUANTITY (cases)
Sample Calculation: Q
0
= [(2 X S X A) / (H X C)]
1/2
EPQ Variables:
A = annual demand (units/yr) = 3.0MM
S = set up or changeover costs ($/changeover) = $10M
H = inventory holding cost penalty (%/unit/year) = 21%
C t d d it t $5 00 C = standard unit cost = $5.00
Q
0
= [(2 X S X A) / (H X C)]
1/2
= 240,000 units/order
Order Cost per Year = [(A/Q) X S] = $125M
Holding Cost per Year = [(Q/2) X (HXC)] where Q/2 is the average inventory level od g Cost pe ea [(Q/ ) ( C)] e e Q/ s t e a e age e to y e e
= $125M
Total Cost = [(A/Q) X S] + [(Q/2) X H] = $250M
7
Douglas R. Kroeger, PE
The EPQ Model (contd)
$1200000
$1,400,000
$1,000,000
$1,200,000
TC
min
= $250,000/yr
$800,000
Q
0
= 240,000 units/order
$400000
$600,000
$200,000
$400,000
HOLDING COST
TOT VAR COST
$0
0 100,000 200,000 300,000 400,000 500,000 600,000
CO COST
8
Douglas R. Kroeger, PE
Getting Started / Gaining Alignment
Determine what factors effect the duration of a changeover item last produced,
item produced next or a combination
Identifyhowmany changeover types there are in the process being studied e g : Identify how many changeover types there are in the process being studied, e.g.:
Push color change going from light to dark
Simple few raw materials used, not a lot of equipment to clean S pe e a a e as used, o a o o equp e o c ea
Complex many raw materials used, a lot of equipment to clean
Special Cases
-hard to clean materials
-packaging change vs. formula change vs. both
-long runs = more cleaning
t f d t ll f tti h d t t t l i f t d -nature of process doesnt allow for getting a head start at cleaning front end
9
Douglas R. Kroeger, PE
Getting Started / Gaining Alignment (contd)
Establish what costs will be included in changeover costs:
Labor direct & indirect
Variable overhead
Cleaning chemicals and supplies
P d t t i i i k i Product waste in processing, in packaging
Start-up costs
Determine howchangeover costs will be quantified Determine how changeover costs will be quantified
Actual vs. standard time, losses, crewing
Product losses material costs vs. variable costingg
Start-up costs labor and losses, need diligence to quantify
Validate the numbers!
10
Douglas R. Kroeger, PE
Getting Started / Gaining Alignment (contd)
Determine what will be included in holding costs:
Finished good cost
Benefits and fixed overheadare included in the finished good cost portion of -Benefits and fixed overhead are included in the finished good cost portion of
holding costs. Benefits and fixed overhead are excluded from the changeover
costs. This is a standard EPQ procedure.
I t h ldi lt i t i ll d 21% Inventory holding penalty is typically around 21%:
-Cost of capital - 9%
-Cost of obsolescence 4%
Actual warehousingcost 6% -Actual warehousing cost 6%
-Cost of complexity/seasonality 2%
11
Douglas R. Kroeger, PE
Questions on The Basics
12
Douglas R. Kroeger, PE
Understanding the Model - Changeover Costs Distribution
Changeover Cost Distribution Example
Chemical
Start Up (Wages &
VOH)
23%
2%
Filler Waste
0%
Process Waste
29%
Down Time (Wages &
VOH)
46% 46%
13
Douglas R. Kroeger, PE
Sensitivity Example Changeover Costs Affect on EPQ
AFFECT OF CHANGEOVER VARIABLES ON EOQ
Increase
AFFECT OF CHANGEOVER VARIABLES ON EOQ
(negative % represents a reduced EOQ)
Variable
Reduce Variable
by 50%
Variable by
100%
Changeover Downtime -11% 18% Changeover Downtime 11% 18%
Processing Waste -5% 9%
Start Up Time -4% 8%
Chemical Costs 0% 1% Chemical Costs 0% 1%
Barrel Waste 0% 0%
14
Douglas R. Kroeger, PE
Sensitivity Example The Flat Spot on the EPQ Curve
$250,000
A production quantitiy of +40%, -30% around the EPQ can be run
ithonl a 6% nfa orable impactontotal cost!
$200,000
TOT VAR COST CHANGE IN TOTAL COST
with only a 6% unfavorable impact on total cost!
$150,000
A
L

C
O
S
T
HOLDING COST
TOT VAR COST CHANGE IN TOTAL COST
$100,000
T
O
T
A
$50,000
CO COST
EPQ RANGE
$0
0 20,000 40,000 60,000 80,000 100,000 120,000 140,000 160,000
EPQ RANGE
15
Douglas R. Kroeger, PE
ORDER QUANTITY (cases)
Sensitivity The Flat Spot on the EPQ Curve
The total cost curve is relatively flat on either side of the EPQ.
This results in a very forgiving EPQ.
In the this case, for each SKU, the EPQ can vary up to +40%, -30% with only a 6%
penalty in total cost.
Increasingthe EPQ will increase inventory levels and increase holding costs while Increasing the EPQ will increase inventory levels and increase holding costs while
decreasing changeover costs and decreasing utilization.
Decreasing the EPQ will decrease inventory levels and decrease holding costs
while increasing changeover costs increasing utilization.
This is evident in data as well as the graph.
16
Douglas R. Kroeger, PE
EPQ Effect on Capacity
On an annual basis, hours required per SKU can be divided into 3 categories:
Changeover hours
Start uphours Start-up hours
Run hours
A l h Annual run hours
Fixed
Annual run hours required are equal to the units requireddivided by the expected Annual run hours required are equal to the units required divided by the expected
units per hour
Annual start up and changeover hours
Start up and changeover hours per occurrence are fixed, but the occurrences are
dependant on the order quantity.
The lower the order quantity, the higher the occurrence of changeovers and start- q y g g
ups and the higher the total changeover and start-up hours required.
The higher the order quantity the lower the machine utilization and the higher the
capacity.
17
Douglas R. Kroeger, PE
p y
EPQ Hours Used Profile & Utilization
Hours Used Profile - EPQ
(96% utilization)
TOTAL RUN
TOTAL C/ODT
TIME
89%
TOTAL S/UDT
TOTAL C/O DT
5%
AVAILABLE
TOTAL S/U DT
2%
AVAILABLE
TIME
4%
18
Douglas R. Kroeger, PE
EPQ - Utilization Sensitivity Graph
X Coordinate times EOQ vs. % Utilization
150%
140%
150%
120%
130%
t
i
o
n
AtEPQ(1xEPQ) utilizationis 96%
110%
%

U
t
i
l
i
z
a
tAt EPQ (1xEPQ), utilization is 96%.
At the lower end of our range, .6XEPQ, utilization is 100%
Atthe upper endof our acceptable range, 1.3XEPQ, utilizationis 94%
90%
100%
At the upper end of our acceptable range, 1.3XEPQ, utilization is 94%
80%
0 1 2 3 4 5 6 7 8 9 10
19
Douglas R. Kroeger, PE
X time EPQ
Questions on Understanding the Model
20
Douglas R. Kroeger, PE
The Case Study
21
Douglas R. Kroeger, PE
The Case Study - Objectives
To calculate economic production quantities (EPQ) based on actual costs.
To compare calculated EPQs to minimum order quantities and actual average
order quantities order quantities.
To understand how costs affect EPQ & how EPQ affects costs
how changeover cost buckets affect the calculated EPQ o c a geo e cos buc e s a ec e cacua ed Q
how the EPQ affects cost
how the EPQ affects utilization
how the EPQ affects inventory levels.
To ultimately determine run strategies that minimize total cost subject to the
constraints of capacity customer fill rate and shelf life constraints of capacity, customer fill rate and shelf life.
22
Douglas R. Kroeger, PE
The Case Study
A production line had a utilization over 100%.
Customer orders were not being met, service level was low.
Minimum order quantities had been calculated in the past.
Actual average order quantities were below minimum order quantities.
The EPQ was compared to actual average run quantities and to the facilitys
minimum production quantity.
The comparison showed that producing at the EPQs would result in a net savings.
Running calculated EPQs was not practical due to scheduling & other constraints.
A bl t t d l d A usable run strategy was developed.
23
Douglas R. Kroeger, PE
Summary - EPQ vs Minimum PQ vs YTD Average PQ
Comparison - EPQ vs. Minimum PQ and EPQ vs. YTD Ave PQ
3
C/O per
Average
C/O Cost
Holding Total Cost
A erage
Average
Inventory
(cs)
C/O per
Year
g
Production
Quantity
1
C/O Cost
per Year
g
Cost per
Year
per Year (C/O
& Holding)
Average
WFC
% Ute
( )
EPQ vs. Minimum Order 35,000 -$413,000 $331,000 -$82,000 2.1 -38 4% 410,000
EPQ vs. YTD Ave Order 52,000 -$760,000 $485,000 -$275,000 2.9 -65 -3% 595,000
N t
, , , , ,
Notes:
1. Average Order Quantity is weighted by orders per year.
2. Average WFC is a straight average over 27 SKUs.
24
Douglas R. Kroeger, PE
g g g
3. Negative numbers indicate a decrease if the EPQ quantity is used.
Positive numbers indicate an increase.
Run Strategy 1 EPQ Runs, All SKUs
SKU
GROUP
DESCRIPTION
ANNUAL
REQT'S
(units)
EOQ
T
(frequency
in weeks)
N
(runs/year)
TOTAL TIME REQ'D
(C/O + S/U + run)
FG ITEM #1 3,560,000 551,510 8.1 6.5 67
FG ITEM #2 2,919,756 462,490 8.2 6.3 57
FG ITEM #3 3,520,205 565,790 8.4 6.2 70
FG ITEM #4 2,220,369 405,110 9.5 5.5 50
FG ITEM #5 2,311,231 425,050 9.6 5.4 53
FG ITEM #6 3,372,191 623,200 9.6 5.4 77
FG ITEM #7 2,592,466 543,580 10.9 4.8 68
FG ITEM #8 2,584,143 553,740 11.1 4.7 69
A
(Size 1)
Total Hrs 510
Total Wks 3.0
FG ITEM #9 899,393 219,310 12.7 4.1 27
FG ITEM #10 1,789,282 437,590 12.7 4.1 55
FG ITEM #11 2,049,585 503,990 12.8 4.1 64
FG ITEM #12 716,525 187,500 13.6 3.8 24
B
FG ITEM #13 808,199 212,920 13.7 3.8 26
FG ITEM #14 765,024 205,000 13.9 3.7 26
FG ITEM #15 548,607 162,830 15.4 3.4 21
FG ITEM #16 500,622 169,060 17.6 3.0 21
FG ITEM #17 481,479 163,730 17.7 2.9 21
Total Hrs 285
Total Wks 1.7
B
(Size 1)
FG ITEM #18 5,291,405 648,720 6.4 8.2 78
FG ITEM #19 5,443,472 717,140 6.9 7.6 87
FG ITEM #20 3,950,128 534,450 7.0 7.4 65
FG ITEM #21 2,613,426 419,900 8.4 6.2 53
FG ITEM #22 3,510,930 585,850 8.7 6.0 72
FG ITEM #23 3,686,244 647,350 9.1 5.7 80
T t l H
C
(Size 2)
Total Hrs 435
Total Wks 2.6
FG ITEM #24 2,906,550 576,380 10.3 5.0 72
FG ITEM #25 2,005,704 416,390 10.8 4.8 52
FG ITEM #26 1,668,921 362,920 11.3 4.6 46
FG ITEM #27 697,902 173,130 12.9 4.0 22
T t l H 193
D
(Size 2)
25
Douglas R. Kroeger, PE
Total Hrs 193
Total Wks 1.1
`
Run Strategy 1 Run Block Example
Cycle
SKU G
CYCLE 1
C A AB CD SKU Goup
Weeks/group
T t El Ti 3 0
C A AB CD
3.0 2.6 4.7 3.7
10 4 5 6 14 1 Tot Elapse Time 3.0
Size Chng Occ # 1 2 3 4
10.4 5.6 14.1
It t k 3 0 k t d
Groups A and B are produced
together during this 4.7 week
block. This minimizes size
It takes 3.0 weeks to produce
1 EPQ of each of the 8 items
in group A
changes and leverages push
type changeovers (color
changes light to dark).
It takes 14.1 weeks to produce
2 EPQs of A and C items and
1 EPQ of B and D items.
26
Douglas R. Kroeger, PE
Run Strategy 1 EPQ Timeline
Cycle CYCLE 1 CYCLE 2 CYCLE 3
SKU Goup
Weeks/group
Tot Elapse Time 3.0
C
17.1 31.1
A
4.7 3.7
AB CD C A AB CD
3.0 2.6
CD AB A C
3.0 2.6 4.7 3.7 3.0 2.6 4.7 3.7
5.6 42.1 38.4 33.7 14.0 28.1 19.6 10.3 24.4 Tot Elapse Time 3.0
Size Chng Occ # 1 2 3 4 5 6 7 8 9 10 11 12
17.1 31.1 5.6 42.1 38.4 33.7 14.0 28.1 19.6 10.3 24.4
Every 42 weeks: y
Run group A SKUs 6 times, every 7 weeks on average.
Run group B SKUs 3 times, every 14 weeks on average.
Run group C SKUs 6 times, every 7 weeks on average.
Run group D SKUs 3 times, every 14 weeks on average.
12 size changes, or 1 size change every 3.5 weeks.
123 changeovers (all types) in 42 weeks, or 1 changeover every 2.4 days.
27
Douglas R. Kroeger, PE
Run Strategy 1 EPQ Run Frequency & Slack Time
SKU
GROUP
DESCRIPTION
ANNUAL
REQT'S
(A)
EOQ
T
(freq
In
AVE
FREQ
" PAD"
AVE F
REQ T
(A)
(units)
In
weeks)
Q
REQ - T
FG ITEM #9
389,737
95,031 12.7 14.0 -1.4 ,
FG ITEM #10 775,355 189,622 12.7 14.0 -1.3
FG ITEM #11
888,154
218,392 12.8 14.0 -1.3
FG ITEM #12
310,494
81,250
13.6 14.0 -0.4
B
FG ITEM #13 350,220
92,263
13.7 14.0 -0.3
FG ITEM #14
331,510
88,831
13.9 14.0 -0.1
FG ITEM #15
237,730
70,557
15.4 14.0 1.4
B
(Sz1)
FG ITEM #16
216,936 73,256
17.6 14.0 3.5
FG ITEM #17
208,641
70,947
17.7 14.0 3.6
28
Douglas R. Kroeger, PE
Run Strategy 1 EPQ Run Frequency & Slack Time
SKU
GROUP
DESCRIPTION
ANNUAL
REQT'S
(units)
EOQ
T
(frequency
in weeks)
N
(runs/year)
TOTAL TIME REQ'D
(S/U + run + C/O)
FREQUENCY
1
FREQUENCY
2
AVE
FREQ
" PAD"
AVE FREQ - T
FG ITEM #1 3,560,000 551,510 8.1 6.5 67 5.6 8.5 7.1 1.0
FG ITEM #2 2,919,756 462,490 8.2 6.3 57 5.6 8.5 7.1 1.2
FG ITEM #3 3,520,205 565,790 8.4 6.2 70 5.6 8.5 7.1 1.3
FG ITEM #4 2,220,369 405,110 9.5 5.5 50 5.6 8.5 7.1 2.4
FG ITEM #5 2,311,231 425,050 9.6 5.4 53 5.6 8.5 7.1 2.5
FG ITEM #6 3,372,191 623,200 9.6 5.4 77 5.6 8.5 7.1 2.6
FG ITEM #7 2,592,466 543,580 10.9 4.8 68 5.6 8.5 7.1 3.9
FG ITEM #8 2,584,143 553,740 11.1 4.7 69 5.6 8.5 7.1 4.1
A
(Size 1)
Total Hrs 510
Total Wks 3.0
FG ITEM #9 899,393 219,310 12.7 4.1 27 14.1 14.1 14.1 (1.4)
FG ITEM #10 1,789,282 437,590 12.7 4.1 55 14.1 14.1 14.1 (1.4)
FG ITEM #11 2,049,585 503,990 12.8 4.1 64 14.1 14.1 14.1 (1.3)
FG ITEM #12 716,525 187,500 13.6 3.8 24 14.1 14.1 14.1 (0.5)
B
FG ITEM #13 808,199 212,920 13.7 3.8 26 14.1 14.1 14.1 (0.4)
FG ITEM #14 765,024 205,000 13.9 3.7 26 14.1 14.1 14.1 (0.2)
FG ITEM #15 548,607 162,830 15.4 3.4 21 14.1 14.1 14.1 1.3
FG ITEM #16 500,622 169,060 17.6 3.0 21 14.1 14.1 14.1 3.5
FG ITEM #17 481,479 163,730 17.7 2.9 21 14.1 14.1 14.1 3.6
Total Hrs 285
Total Wks 1.7
B
(Size 1)
FG ITEM #18 5,291,405 648,720 6.4 8.2 78 7.3 6.8 7.1 (0.7)
FG ITEM #19 5,443,472 717,140 6.9 7.6 87 7.3 6.8 7.1 (0.2)
FG ITEM #20 3,950,128 534,450 7.0 7.4 65 7.3 6.8 7.1 (0.0)
FG ITEM #21 2,613,426 419,900 8.4 6.2 53 7.3 6.8 7.1 1.3
FG ITEM #22 3,510,930 585,850 8.7 6.0 72 7.3 6.8 7.1 1.6
FG ITEM#23 3,686,244 647,350 9.1 5.7 80 7.3 6.8 7.1 2.1
C
(Size 2)
FG ITEM #23 3,686,244 647,350 9.1 5.7 80 7.3 6.8 7.1 2.1
Total Hrs 435
Total Wks 2.6
FG ITEM #24 2,906,550 576,380 10.3 5.0 72 14.1 14.1 14.1 (3.8)
FG ITEM #25 2,005,704 416,390 10.8 4.8 52 14.1 14.1 14.1 (3.3)
FG ITEM #26 1,668,921 362,920 11.3 4.6 46 14.1 14.1 14.1 (2.8)
FG ITEM#27 697 902 173 130 12 9 4 0 22 14 1 14 1 14 1 (1 2)
D
(Size 2)
29
Douglas R. Kroeger, PE
FG ITEM #27 697,902 173,130 12.9 4.0 22 14.1 14.1 14.1 (1.2)
Total Hrs 193 # SKUs w/ Negative Slack 11
Total Wks 1.1 # SKUs w/ Positive Slack 16
Minimum Slack -4.5
` Maximum Slack 4.1
Run Strategy 2 Adjusted Run Quantities
Condition Meaning Options Actions
- SKU needed before scheduled Make more Increase OQ
Slack Weeks
- SKU needed before scheduled Make more Increase OQ
(Making it late)
Make sooner Decrease other OQ
+ SKU d d ft h d l d
M k l D OQ
+ SKU needed after scheduled
Make less Decrease OQ
(Making it early) Make later Increase other OQ
Hybrid run strategies were developed by increasing or decreasing order quantity
based on the condition of the Slack weeks.
Several iterations were performed varying the order quantity while monitoring the
time between runs and the slack weeks.
The objective was to eliminate/minimize negative slack while minimizing time
between runs.
30
Douglas R. Kroeger, PE
Run Strategy 2 Adjusted Run Quantities Timeline
Cycle
SKU Goup AB CD A A C
CYCLE 3
A C AB CD
CYCLE 4
C AB CD
CYCLE 1 CYCLE 2
C AB CD A
Weeks/group
Tot Elapse Time 2.6
Size Chng Occ # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
15.9 29.2 42.6
2.6 2.5
26.6
3.9 4.3 2.6 2.5 4.3 2.6 2.5 4.3 3.9
31.8 36.1 39.9
2.6 2.5 4.3 3.9
45.1 49.4 53.3
3.9
5.1 9.4 13.3 18.4 22.8
Every 53 weeks: y
Run group A SKUs 8 times, every 6.7 weeks on average.
Run group B SKUs 4 times, every 13.3 weeks on average.
Run group C SKUs 8 times, every 6.7 weeks on average.
Run group D SKUs 4 times, every 13.3 weeks on average.
12 size changes, or 1 size change every 4.4 weeks.
123 changeovers (all types) in 53 weeks, or 1 changeover every 3.0 days.
31
Douglas R. Kroeger, PE
Run Strategy 2 Adjusted Run Quantities & Slack Time
SKU
GROUP
DESCRIPTION
2008
ANNUAL
REQT'S
(units)
Adjusted
Production
Quantity
Total Time
Req'd (S/U
+ Run +
C/O)
Freq 1 Freq 2
Ave
Freq
Reqd
Freq
" SLACK"
(AVE FREQ -
T)
FG ITEM #1 3,560,000 468,801 58 5.3 8.3 6.8 6.9 0.0
G # FG ITEM #2 2,919,756 131,044 49 5.3 8.3 6.8 7.0 0.2
FG ITEM #3 3,520,205 160,313 60 5.3 8.3 6.8 7.1 0.3
FG ITEM #4 2,220,369 114,785 43 5.3 8.3 6.8 8.1 1.2
FG ITEM #5 2,311,231 120,435 46 5.3 8.3 6.8 8.1 1.3
FG ITEM #6 3,372,191 176,580 66 5.3 8.3 6.8 8.2 1.3
FG ITEM #7 2,592,466 154,020 58 5.3 8.3 6.8 9.3 2.4
FG ITEM #8 2,584,143 156,899 59 5.3 8.3 6.8 9.5 2.6
T t l H 439
A
(Size 1)
Total Hrs 439
Total Wks 2.6
FG ITEM #9 899,393 263,186 93 13.6 13.6 13.6 15.2 1.6
FG ITEM #10 1,789,282 525,135 186 13.6 13.6 13.6 15.3 1.6
FG ITEM #11 2,049,585 604,820 215 13.6 13.6 13.6 15.3 1.7
FG ITEM #12 716,525 225,012 80 13.6 13.6 13.6 16.3 2.7
FG ITEM#13 808 199 255 517 90 13 6 13 6 13 6 16 4 2 8
B
FG ITEM #13 808,199 255,517 90 13.6 13.6 13.6 16.4 2.8
FG ITEM #14 765,024 246,013 87 13.6 13.6 13.6 16.7 3.1
FG ITEM #15 548,607 138,411 50 13.6 13.6 13.6 13.1 -0.5
FG ITEM #16 500,622 143,706 52 13.6 13.6 13.6 14.9 1.3
FG ITEM #17 481,479 139,176 50 13.6 13.6 13.6 15.0 1.4
Total Hrs 809
Total Wks 4.8
(Size 1)
FG ITEM #18 5,291,405 778,505 272 7.0 6.7 6.8 7.7 0.8
FG ITEM #19 5,443,472 860,613 301 7.0 6.7 6.8 8.2 1.4
FG ITEM #20 3,950,128 641,374 225 7.0 6.7 6.8 8.4 1.6
FG ITEM #21 2,613,426 356,928 128 7.0 6.7 6.8 7.1 0.3
FG ITEM #22 3,510,930 497,991 177 7.0 6.7 6.8 7.4 0.6
FG ITEM #23 3,686,244 550,268 195 7.0 6.7 6.8 7.8 0.9
T t l H 1 298
C
(Size 2)
Total Hrs 1,298
Total Wks 7.7
FG ITEM #24 2,906,550 691,692 245 13.6 13.6 13.6 12.4 -1.3
FG ITEM #25 2,005,704 499,694 177 13.6 13.6 13.6 13.0 -0.7
FG ITEM #26 1,668,921 435,527 155 13.6 13.6 13.6 13.6 -0.1
FG ITEM #27 697,902 207,767 74 13.6 13.6 13.6 15.5 1.8
T t l H 650 # SKU / N ti Sl k 4
D
(Size 2)
32
Douglas R. Kroeger, PE
Total Hrs 650 # SKUs w/ Negative Slack 4
Total Wks 3.9 # SKUs w/ Positive Slack 23
Minimum Slack -1.3
Maximum Slack 3.1
Summary Adjusted OQ vs Min OQ vs YTD Average OQ
Comparison - EPQ vs. Minimum Order Quantity and EPQ vs. YTD Ave
Order Qty
3
Average
I t
Average
WFC
2
C/O per
Y
% Ute
Average
Productio C/O Cost
Y
Holding
Cost per
Total Cost
per Year
(C/O & Inventory
(cs)
Adjusted Production Qty vs. Min Production Qty 14,712 -$247,692 $155,804 -$91,888 0.6 -19 4.4% 191,067
WFC
2
Year n
Quantity
per Year
p
Year
(C/O &
Holding)
Adjusted Production Qty vs. YTD Ave Production Qty 31,327 -$594,659 $310,194 -$284,464 1.3 -45 -2.5% 376,531
Notes:
1. Average Order Quantity is weighted by orders per year.
2 Average WFC is a straight average over 27 SKUs 2. Average WFC is a straight average over 27 SKUs.
3. Negative numbers indicate a decrease if the EPQ quantity is used.
Positive numbers indicate an increase.
33
Douglas R. Kroeger, PE
Final Steps
Several iterations were performed to determine acceptable production quantities
(within +40%,-30% of EPQ) for each Finished Good Item that resulted in no
negative slack.
These production quantities were used in the actual plant finite scheduling model
which accounts for actual schedule downtime, consumption, inventory levels, raw
and packaging material availability etc.
After determining that EPQs do work when considering all real life variables, an
implementation plan was developed.
Implementation plan included phasing in acceptable EPQ quantities as production
schedules were developed.
34
Douglas R. Kroeger, PE
QUESTIONS?
Douglas R. Kroeger, PE
Contact information available through IIE membership directory.
35
Douglas R. Kroeger, PE

Anda mungkin juga menyukai