Anda di halaman 1dari 28

INSPECTION AND TESTING PLAN ( ITP )

2/28

ITP FOR FABRICATION OF MISCELLANEOUS STRUCTURAL STEEL WORKS

CONTRACTOR'S VERIFICATION STAMP


PURSUANT TO SPECIAL CONDITION 6, WE SKY ORYX JOINT VENTURE, VERIFY THAT THIS SUBMITTAL SATISFIES ALL REQUIREMENTS OF THE CONTRACT, WITH THE EXCEPTION OF THE FOLLOWING CLARIFICATIONS/ PROPOSALS ACCEPTED BY THE ENGINEER; CONTRACTOR'S PROJECT MANAGER;

M. HORIKAWA PRINT NAME SIGNATURE DATE DOCUMENT REVIEW STATUS STATUS 1: WORK MAY PROCEED. STATUS 2: REVISE & RESUBMIT.WORK MAY PROCEED SUBJECT TO INCORPORATION OF COMMENTS INDICATED . STATUS 3: REVISE & RESUBMIT. WORK MAY PROCEED. STATUS 4: REVIEW NOT REQUIRED. WORK MAY PROCEED. PERMISSION TO PROCEED SHALL NOT CONSTITUTE ACCEPTANCE OR APPROVAL OF DESIGN DETAILS, CALCULATIONS, ANALYSES, TEST METHODS, OR MATERIALS DEVELOPED OR SELECTED BY CONTRACTOR AND SHALL NOT RELIEVE CONTRACTOR FROM FULL COMPLIANCE WITH THE CONTRACT TECHNICAL SPECIFICATIONS AND DRAWINGS.

Overseas Bechtel, Inc.

Date

Document No:25045-A1126-18-ITP-S-027

Rev.No 02

Prepared Date Description QA/QC Syed Kausar

Checked QA/QC Struct Engg Cond.Mgr. Mgr.

FET Mgr.

Approved Project Manager

3/29

NDIA New Doha International Airpoet Project

INSPECTION AND TEST PLAN FOR FABRICATION OF MISCELLANEOUS STRUCTURAL STEEL WORKS
Contract No.:
25045-000FC1-maht-00018

Discipline: Structural Steel Activity No.: 1.0 1.1 Document Review Activity Description

Contract Title: Passenger Terminal Complex CCP-18 Reference Procedure/Method Statements/Specs. : Spec. 05120, 05060. Controlling Document Frequency

ITP No.
25045-A1126-18-ITP-S-027

Issue date:09-02-2009

Rev. no : 2 Page: 1 of 6 Inspection*

QAP No.25145-A1000-18-GQA-S-001 Rev.2, Verifying Documents


SSI/C

Acceptance Criteria

TPIA (NDT)

SOJV

OBI

TPIA (BOI)

Project Quality Assurance Plan (PQP) Method Statement Inspection and TestMethod Statement Plan (ITP) Shop drawings Material Submittals WPS, PQR&WQT NDT (TPIA) Procedures

Project Specifications Exhibit-F Exhibit-B

Before Work Commencement

As oer OBI Status code 1, 2 and 4

SOJV-QP-10-02/X-01

1.2

Fabrication Drawings

Project Specifications

Before Work Commencement

Fabrication Drawing acceptance to SOJV

SOJV-QP-10-02/X-01 H H H R

2 2.1

Meterials-Steel Framing (ASTM A572, ASTM A36)


Paint Material Inspection

Primer Paint

Spec-05120/Clause 2.1 Spec-05120 Each Supplier submittal Delivery Manufacturer product data, Safety Data & application procedure

ASTM, drawings, 05120

MRR, Drawings D.O. (SOJVMRR-014-01 rev 1 & x-004)

SR

Inspection H-Hold Point : Written notification required. Contractor may not proceed beyond this point without written confirmation of the Engineer

W - Witness : Written notification required but Contractor may not proceed if OBI do not attend

S - Surveillance : No notification required but activity may be subjected to OBI Surveillance/ Monitoring

R - Review : Record/ Document review

4/29

NDIA New Doha International Airpoet Project

INSPECTION AND TEST PLAN FOR FABRICATION OF MISCELLANEOUS STRUCTURAL STEEL WORKS
Contract No.:
25045-000FC1-maht-00018

Discipline: Structural Activity No.: 2.2


Welding Consumables

Contract Title: Passenger Terminal Complex CCP-18 Reference Procedure/Method Statements/Specs. : Spec 05120, 05060. Activity Description Controlling Document Spec-05120 Part2.1, 05060, part 2.1 Supplier submittal Calibration Procedure Each Delivery Frequency

ITP No.
25045-A1126-18-ITP-S-027

Issue date ;

Rev. no : 2 Page: 2 of 6 Inspection*


SSI/C TPIA (NDT) SOJV OBI TPIA (BOI)

QAP No.25145-A1000-18-GQA-S-001 Rev.0, Verifying Documents ASME Section ll, Part C/ AWS D 1.1, Section 5.3 D.O & Batch Certificate / Electrode log Register Calibration certificates Equipments Calibrationlog

Acceptance Criteria

3 3.1

SMAN FCAW SAW Calibration Equipments Calibration Measuring Instrument NDT Testing Equipments

SR

As per manufacturer/ calibration agency recommendations.

ISO10012-1:1992, Part 1 - Metrological conformation system for measuring equipment. For NDT Awa D1.1 & ASME BPVC Section V Dimensions tolerance shall be as per AISC Specification for Structural steel Building Part 16, Chapter M,M2,2 Fabrication Tolerances 6 mm. for AESS. Fabrication Tolerances are as per AISC for Non- AESS.

S/R

4 4.1

Fabrication Marking and Cutting Spec-05120 Part2.1,2.5c, 2.5.A.2, 2.5 I Approved shop Drawings 100% Material identification and tracesbility / Inspection Request (25045-A1000-18-ITRS-002& 001)

SR

Inspection H-Hold Point : Written notification required. Contractor may not proceed beyond this point without written confirmation of the Engineer

W - Witness : Written notification required but Contractor may not proceed if OBI do not attend

S - Surveillance : No notification required but activity may be subjected to OBI Surveillance/ Monitoring

R - Review : Record/ Document review

5/28

NDIA New Doha International Airpoet Project

INSPECTION AND TEST PLAN FOR FABRICATION OF MISCELLANEOUS STRUCTURAL STEEL WORKS
Contract No.:
25045-000FC1-maht-00018

Discipline: Structural Activity No.: Activity Description

Contract Title: Passenger Terminal Complex CCP-18 Reference Procedure/Method Statements/Specs. : Spec 05120, 05060. Controlling Document Frequency

ITP No.
25045-A1126-18-ITP-S-027

Issue date ;

Rev. no : 2 Page: 3 of 6

QAP No.25145-A1000-18-GQA-S-001 Rev.0, Verifying Documents AWS code for Weld joint preparation Marking the high strength steel as per ASTM A/A6 M. Camber if requied by IFC AWS D1.1 Complicance to production Drawing
SSI/C

Acceptance Criteria

Inspection*
TPIA (NDT)

SOJV

OBI

TPIA (BOI)

4.2

Fit-up

Spec -05120, Part 2.6.B Approved shop Drawings

100%

4.3

Welding Process

Spec-05120, Part 2.6 & 05060 Part 3.5 Production Drawings

100%

4.4

Welding Repair

Production Drawings

Repairs local surface imperfection depth below 1/16 inch or less Repair by welding where required Test on repair portion

Approved WPS & PQR AWS D1.1 APProved TPIA to review and certify weld procedures and all welder qualifications By grinding to smooth contour with a curvature of less than 1/2 inch (13 mm) in either direction. To ensure that defects have been temoved prior to depositing any weld metal, examine prepared areas by DPT.

Weld Visual Inspection Report / Inspection Request (25045-A1000-18ITR-S-003&001) Weld Visual Inspection Report / Inspection Request (25045-A1000-18-ITRS-003&001) Report/ Inspection Report (25045-A1000-18ITR-S-003&001) (NDT TPIA- Reports)

SR

SR

SR

Inspection H-Hold Point : Written notification required. Contractor may not proceed beyond this point without written confirmation of the Engineer

W - Witness : Written notification required but Contractor may not proceed if OBI do not attend

S - Surveillance : No notification required but activity may be subjected to OBI Surveillance/ Monitoring

R - Review : Record/ Document review

6/29

NDIA New Doha International Airpoet Project

INSPECTION AND TEST PLAN FOR FABRICATION OF MISCELLANEOUS STRUCTURAL STEEL WORKS
Contract No.:
25045-000FC1-maht-00018

Discipline: Structural Activity No.: 5 5.1 WELDING TESTING Visual inspection of Welding Activity Description

Contract Title: Passenger Terminal Complex CCP-18 Reference Procedure/Method Statements/Specs. : Spec 05120, 05060. Controlling Document Frequency

ITP No.
25045-A1126-18-ITP-S-027

Issue date ;

Rev. no : 2 Page: 4 of 6 Inspection*


SSI/C
TPIA (NDT)

QAP No.25145-A1000-18-GQA-S-001 Rev.0, Verifying Documents

Acceptance Criteria

SOJV

OBI

TPIA (BOI)

Spec -05060 Part 3.2 C Drawings

100%

Weld Visual for Surface holes, cracks, Undercut, Confirming to AWS D 1.1 2004 Section (6.9), Table 6.1

Weld Visual Inspection Report (25045-A1000-18ITR-S-004) (ITPA Endorsement on Report) Visual

SR

5.2

Liquid Penetration test for Back gauging of CP Welds UT on CP Welds UT on 38 mm and thicker plate subject throung thickness weld shrinkage strain. MPI on Fillet Welds MPI on Partial penetration Welds

Spec -05120, Part 2.9

As needed

AWS D1.1 - 2004 Section (6.10) AWS D1.1 - 2004 Section (6.13) ASTM E 164

H UT Report (TPIA -Report) & Weld map

SR

5.3

Spec-05060, Part 3.2,3.5 & 05120 part 2.9 Drawings

100%

SR

5.4

Spec-05060, Part 3.5J Drawings

Web- Flange AWS D1.1 - 2004 connection 10%,ii) 10% Section (6.10) Beam and Girder ASTM E 709 connection where they connection using a clip angle, otherwise 100% All other connection s-100%

MPI Report (TPIA-Report) & Weld map

SR

Inspection H-Hold Point : Written notification required. Contractor may not proceed beyond this point without written confirmation of the Engineer

W - Witness : Written notification required but Contractor may not proceed if OBI do not attend

S - Surveillance : No notification required but activity may be subjected to OBI Surveillance/ Monitoring

R - Review : Record/ Document review

7/28

NDIA New Doha International Airpoet Project

INSPECTION AND TEST PLAN FOR FABRICATION OF MISCELLANEOUS STRUCTURAL STEEL WORKS
Contract No.:
25045-000FC1-maht-00018

Discipline: Structural Activity No.: 5.5 RT on CP Welds Activity Description

Contract Title: Passenger Terminal Complex CCP-18 Reference Procedure/Method Statements/Specs. : Spec 05120, 05060. Controlling Document Spec-05120 part 2.9 E Drawings NDT Procedure Spec-05060 Part 3.2 & 3.2, 05120 Part 2.5, 2.6.B Approved shop Drawings 25% Frequency

ITP No.
25045-A1126-18-ITP-S-027

Issue date ;

Rev. no : 2 Page: 5 of 6 Inspection*


SSI/C
TPIA (NDT) TPIA (BOI)

QAP No.25145-A1000-18-GQA-S-001 Rev.0, Verifying Documents Rt Re[prt (TPIA-Report & Weld) map

Acceptance Criteria

SOJV

OBI

SR

6.0 6.1

Final Inspection (Fabrication) Final Inspection Visual Inspection Dimensional check

Before Painting

Check for dimension, tolerance, orientation, depth, camber, holes positions, distortion, straightness, Erection marks, etc & confirming to AISC "Code of Standards Practice for steel Buildings Section 6,6.4. Weld visual for surface holes, cracks, Undercut, Confirming to AWS D 1.12004 Section 6.9, Table 6.1 As per SSpc-sp 14/ NACE No.8 For AESS confirming with SSPC SP-6

Dimension Reports (25045-A1000-18ITR-S-005) (TPIA Endorsement on all fabrication Records)

SR

7.0 7.1

Sand blasting and Primer Painting Surface Preparation by Shot / Grit Blasting

Spec-05120, part 2.7 For AESS-Spec-09805 part 3.2.A.1

Each Fabricated component inspection

Paint Report (25045-A1000-18ITR-S-006)

SR

Inspection H-Hold Point : Written notification required. Contractor may not proceed beyond this point without written confirmation of the Engineer

W - Witness : Written notification required but Contractor may not proceed if OBI do not attend

S - Surveillance : No notification required but activity may be subjected to OBI Surveillance/ Monitoring

R - Review : Record/ Document review

8/28

NDIA New Doha International Airpoet Project

INSPECTION AND TEST PLAN FOR FABRICATION OF MISCELLANEOUS STRUCTURAL STEEL WORKS
Contract No.:
25045-000FC1-maht-00018

Discipline: Structural Activity No.: 7.2 Primer Paint Application & Inspection Activity Description

Contract Title: Passenger Terminal Complex CCP-18 Reference Procedure/Method Statements/Specs. : Spec 05120, 05060. Controlling Document Spec-05120, part 2.3,2.7 For AESS-Spec-09805 part 2.3 Each Batch random inspection Frequency

ITP No.
25045-A1126-18-ITP-S-027

Issue date ;

Rev. no : 2 Page: 6 of 6 Inspection*

QAP No.25145-A1000-18-GQA-S-001 Rev.0, Verifying Documents Check for Surface cleaning, Atmosphere conditions (Temperatures & Humidity), recommended maerials, Dry Film Thickness (DFT not less than 38) and confirming with Manufacturer's recommendations. For AESS primer DFT (76 12.7 ) Keep steel members off ground and spaced using pallets, dunnage, or other supports and spacers. Paint report (DFT) (25045-A1000-18ITR-S-006)
SSI/C

Acceptance Criteria

TPIA (NDT)

SOJV

OBI

TPIA (BOI)

SR

8.0

Final Inspection (Before Packing )

Inspection H-Hold Point : Written notification required. Contractor may not proceed beyond this point without written confirmation of the Engineer

W - Witness : Written notification required but Contractor may not proceed if OBI do not attend

S - Surveillance : No notification required but activity may be subjected to OBI Surveillance/ Monitoring

R - Review : Record/ Document review

9/28

INSPECTION REQUEST INSPECTION REQUEST NUMBER: CONTRACT NO: DRAWING NO: CONTRACTOR NAME: DATE: REPORT NO:

AREA / LOCATION / SUBJECT :

TYPE OF INSPECTION MATERIAL PAINTING FIT UP SURVEY WELDING FINAL INSPECTION NDT OTHER

DATE & TIME INSPECTION REQUIRED: CONTRATOR : RECEVIED BY : REPLY Approved DATE & TIME : DATE & TIME : Approved as noted Not Approved

SUB CON QC REP:


( PRINT NAME AND SIGN )

DATE:

SUB CONTRACTOR QC REP:


( PRINT NAME AND SIGN )

DATE:

OBI REP:
WITNESS & REVIEW ( PRINT NAME AND SIGN ) ONLY REVIEW

DATE:

Document No: 25045-A1126-18-ITR-S-001

10/28

Material Receiving Report

11/28

MATERIAL RECEIVING REPORT (RAW STEEL MATERIALS)


CONTRACT NO. CP - 18 CONTRACTOR NAME : SIAM STEEL INTERNATIONAL PLC. PROJECT : NEW DOHA INTERNATIONAL AIRPORT AREA : LOCATION : SIAM STEEL BANGNA FACTORY STORAGE AREA : SIAM STEEL BANGNA FACTORY YARD Weight Material Item No. Qty. Manufacturer Heat No. (kgs.) Specification Description DATE : REPORT NO. : SHEET NO. : Mill Test Date Certificate No. Received

Delivery Order No.

REMARKS : CONTRACTOR QC REPRESENTATIVE : DATE :

________________________________________________________________
(PRINT NAME AND SIGN)

SOJV QC REPRESENTATIVE :

DATE :

________________________________________________________________
(PRINT NAME AND SIGN)

OBI REPRESENTATIVE :

DATE :
(PRINT NAME AND SIGN)

__________________________________________________
WITHNESS & REVIEW ONLY REVIEW
Document No. : 25045-A1126-18-ITR-S-001,ForM a

12/28

Marking, Cutting and Drilling (Material Identification and Traceability)

13/28

MATERIAL IDENTIFICATION AND TRACEABILITY REPORT


INSPECTION REQUEST NO.: CONTRACT NO. CP - 18 PROJECT : NEW DOHA INTERNATIONAL AIRPORT PIECE MARK : Item Part No./Mark No. AREA : STRUCTURE TYPE : Material Specification DRAWING NO.: Heat No. Mill Test Certificate No. Marking/ Cutting DATE : CONTRACTOR NAME : SIAM STEEL INTERNATIONAL PLC. REPORT NO. : SHEET NO. : LOCATION : SIAM STEEL BANGNA FACTORY

Description

Qty.

CONTRACTOR QC REPRESENTATIVE :

DATE :

_________________________________________________________________________
(PRINT NAME AND SIGN)

SOJV QC REPRESENTATIVE :

DATE :

_________________________________________________________________________
(PRINT NAME AND SIGN)

OBI REPRESENTATIVE :

DATE :
(PRINT NAME AND SIGN)

_________________________________________________________
WITHNESS & REVIEW ONLY REVIEW
Document No. : 25045-18-ITR-S-002

14/28

Fit-Up Inspection

15/28

FIT- UP INSPECTION REPORT (WELD GROOVE)


INSPECTION REQUESTNO.: CONTRACT NO. CP - 18 CONTRACTOR NAME : SIAM STEEL INTERNATIONAL PLC. PROJECT : NEW DOHA INTERNATIONAL AIRPORT PIECE MARK : STRUCTURE TYPE : WELD JOINT KEYPLAN : DATE : REPORT NO. : SHEET NO. : AREA : LOCATION : SIAM STEEL BANGNA FACTORY DRAWING NO. :

(SEE ATTACHED SHEETS)

LEGEND: F = FILLTE WELD

P = PARTIAL PENETRATION WELD

C = COMPLETE PENETRATION WELD

Joint No. Root Gap

Root Face

Groove Angle

Remark

Joint No.

Root Gap

Root Face

Groove Angle

Remark

CONTRACTOR QC REPRESENTATIVE :

DATE :

__________________________________________________________
(PRINT NAME AND SIGN)

SOJV QC REPRESENTATIVE :

DATE :
(PRINT NAME AND SIGN)

__________________________________________________________
OBI REPRESENTATIVE : DATE : WITNESS &REVIEW ONLY REVIEW
Document No. :25045-A1126-18-ITR-S-003

______________________________
(PRINT NAME AND SIGN)

16/28

FIT- UP INSPECTION REPORT (WELD GROOVE)


INSPECTION REQUESTNO.: CONTRACT NO. CP - 18 CONTRACTOR NAME : SIAM STEEL INTERNATIONAL PLC. PROJECT : NEW DOHA INTERNATIONAL AIRPORT PIECE MARK : STRUCTURE TYPE : WELD JOINT KEYPLAN : DATE : REPORT NO. : SHEET NO. : AREA : LOCATION : SIAM STEEL BANGNA FACTORY DRAWING NO.

(SEE ATTACHED SHEETS)

LEGEND: F = FILLTE WELD

P = PARTIAL PENETRATION WELD

C = COMPLETE PENETRATION WELD

PIECE MARK

DRAWING NO.

REV.

Joint No.

Root Gap

Root Face

Groove Angle

Remark

CONTRACTOR QC REPRESENTATIVE :

DATE :
(PRINT NAME AND SIGN)

__________________________________________________________
SOJV QC REPRESENTATIVE : DATE :
(PRINT NAME AND SIGN)

__________________________________________________________
OBI REPRESENTATIVE : DATE : WITNESS &REVIEW ONLY REVIEW
Document No. :25045-A1126-18-ITR-S-003,Form b

______________________________
(PRINT NAME AND SIGN)

17/28

Weld Visual Inspection (VT)

18/28

19/28

20/28

WELD VISUAL INSPECTION REPORT


INSPECTION REQUESTNO.: CONTRACT NO. CP - 18 CONTRACTOR NAME : SIAM STEEL INTERNATIONAL PLC. PROJECT : NEW DOHA INTERNATIONAL AIRPORT PIECE MARK : STRUCTURE TYPE : DRAWING NO. : Joint No. WPS No. Welding Process Welder Id No. Marking / Cutting Report No. Fit-Up Report No. Visual DATE : REPORT NO. : SHEET NO. : AREA : LOCATION : SIAM STEEL BANGNA FACTORY MATERIAL SPECIFICATION:

VASUAL INSPECTION SUMMARY (As per AWS D1.1/D1.1M:2006 Sectuib 6.9, Tavle 6.1): Item No. Inspection Category Result Item No. Inspection Category Result

OTHER REMARKS (IF ANY): Refer to attached weld joint keyplan

CONTRACTOR QC REPRESENTATIVE :

DATE :
(PRINT NAME AND SIGN)

__________________________________________________________
SOJV QC REPRESENTATIVE : DATE :
(PRINT NAME AND SIGN)

__________________________________________________________
OBI REPRESENTATIVE : DATE : WITNESS &REVIEW ONLY REVIEW
Document No. : 25045-A1126-18-ITR-S-004

______________________________
(PRINT NAME AND SIGN)

21/28

Final Inspection

22/28

FINAL INSPECTION REPORT


(VISUAL INSPECTION & SUMMARY OF INSPECTION REPORTS)
INSPECTION REQUEST NO.: CONTRACT NO.: CP-18 CONTRACTOR NAME : SIAM STEEL INTERNATIONAL PLC. PROJECT : NEW DOHA INTERNATIONAL AIRPORT PIECE MARK : STRUCTURE TYPE: MATERIAL SPECIFICATION: ASTM A572 Grade 50 DATE : REPORT NO. : SHEET NO. : AREA : LOCATION : SIAM STEEL BANGNA FACTORY DRAWING No.:

INSPECTION REPORTS SUMMARY

Description

ITP Activity No.

Inspection Report No.

INSPECTION RESULT:

OTHER REMARKS (IF ANY):

CONTRACTOR QC REPRESENTATIVE :

DATE :

__________________________________________________________
(PRINT NAME AND SIGN)

TPIA REPRESENTATIVE

DATE :
(PRINT NAME AND SIGN)

__________________________________________________________
SOJV QC REPRESENTATIVE : DATE :
(PRINT NAME AND SIGN)

__________________________________________________________
OBI REPRESENTATIVE : DATE : WITNESS &REVIEW ONLY REVIEW
Document No. : 25045-A1126-18-ITR-S-005

______________________________
(PRINT NAME AND SIGN)

23/28

FINAL INSPECTION REPORT


(VISUAL INSPECTION & SUMMARY OF INSPECTION REPORTS)
INSPECTION REQUEST NO.: CONTRACT NO.: CP-18 CONTRACTOR NAME : SIAM STEEL INTERNATIONAL PLC. PROJECT : NEW DOHA INTERNATIONAL AIRPORT PIECE MARK : STRUCTURE TYPE: MATERIAL SPECIFICATION: ASTM A572 Grade 50 DATE : REPORT NO. : SHEET NO. : AREA : LOCATION : SIAM STEEL BANGNA FACTORY DRAWING No.:

Non-Destructive Examination (NDE) Report Summary Ultrasonic Testing (UT) Radiographic Testing (RT) Magnetic Particle Testing (MT)

Document No. : 25045-A1126-18-ITR-S-005, form b

24/28

Dimensional Inspection (Pre-Fit up)

25/28

DIMENSIONAL INSPECTION REPORT (SINGLE PRODUCT)


INSPECTION REQUEST NO.: CONTRACT NO. CP - 18 PROJECT : NEW DOHA INTERNATIONAL AIRPORT STRUCTURE TYPE: L1 PIEXE MARK DD (mm) e2 DD (mm) 4-6ARCH1 DD (mm) E
(mm)

DATE : CONTRACTOR NAME : SIAM STEEL INTERNATIONAL PLC. AREA : DRAWING NO.: L2 E (mm) B1 DD (mm) E (mm) B13 DD (mm) DD (mm) E (mm) B2 E (mm) B14 E (mm) DD (mm) E (mm) DD (mm) DD (mm) DD (mm) B3 E (mm) B15 E (mm) DD (mm) DD (mm) L3 E (mm) DD (mm) B4 E (mm) B16 E (mm) DD (mm) DD (mm) L4 E (mm) DD (mm) B5 E (mm) B17 E (mm) DD (mm) DD (mm) L5 E (mm) B6 E (mm) B18 E (mm) DD (mm) DD (mm) DD (mm) H1 E (mm) B7 E (mm) B19 E (mm) DD (mm) DD (mm) DD (mm) B8 E (mm) B20 E (mm) DD (mm) DD (mm) H2 E (mm) DD (mm) B9 E (mm) B21 E (mm) DD (mm) REPORT NO. : SHEET NO. : LOCATION : SIAM STEEL BANGNA FACTORY H3 E (mm) DD (mm) H4 E (mm) DD (mm) e1 E (mm)

B10 E (mm) B22 DD E DD DD

B11 E (mm) (mm)

B12 E (mm) DD

B23 E (mm)

(mm)

(mm) (mm) (mm) B34

B24 DD (mm) LEGEND: E (mm) DD

B25 E (mm) DD (mm)

B26 E (mm) DD (mm)

B27 E (mm) DD (mm)

B28 E (mm) DD (mm)

B29 E (mm) DD (mm)

B30 E (mm) DD (mm)

B31 E (mm) DD (mm)

B32 E (mm) DD (mm)

B33 E (mm) (mm)

B35 E DD E (mm)

DD

(mm) (mm) (mm)

SUBCONTRACTOR QC REPRESENTATIVE

DATE :
(PRINT NAME AND SIGN)

_________________________________________________________________________
SOJV QC REPRESENTATIVE : DATE :

_________________________________________________________________________
(PRINT NAME AND SIGN)

OBI REPRESENTATIVE :

DATE :
(PRINT NAME AND SIGN)

________________________________________________________________
WITHNESS & REVIEW ONLY REVIEW
Document No. : 25045-A1126-18-ITR-S-005,Form C

26/28

Painting Inspection

27/28

PAINTING INSPECTION REPORT


INSPECTION REQUEST NO.: CONTRACT NO. CP - 18 PROJECT : NEW DOHA INTERNATIONAL AIRPORT PIECE MARK : Surface Preparation: Sa 2.5 Paint Specification: 25045-a1100-18-ssd-s-xxxx Paint Material: Primer Coat DFT (microns) Gage Readings Average 1st 2nd 3rd AREA : STRUCTURE TYPE : No. of Coats: Required DFT: 76 microns DRAWING NO.: Blasting & Painting Date: Ambient Te,perature ( C) Weather : Steel Temperature ( C) Dew Point (C) Primer Coat DFT (microns) Gage Readings 2nd 3rd DATE : CONTRACTOR NAME : SIAM STEEL INTERNATIONAL PLC. REPORT NO.: SHEET NO.: LOCATION : SIAM STEEL BANGNA FACTORY

Spot No.

Spot No.

Relative Humidity (%): Primer Coat DFT (microns) Gage Readings Average 1st 2nd 3rd

Spot No.
1st

Average

OTHER REMARKS (IF ANY): Note: Refer to Sheet 3 of 3 for DFT Spot Measuring Keyplan.

CONTRACTOR QC REPRESENTATIVE :

DATE :

____________________________________________________________________________
(PRINT NAME AND SIGN)

SOJV QC REPRESENTATIVE :

DATE :

_____________________________________________________________________________
(PRINT NAME AND SIGN)

OBI REPRESENTATIVE :

DATE :
(PRINT NAME AND SIGN)

________________________________________________________________ WITHNESS &


REVIEW ONLY REVIEW
Document No. : 25045-A1126-18-ITR-S-006

28/28

PAINTING INSPECTION REPORT


INSPECTION REQUEST NO.: CONTRACT NO. CP - 18 PROJECT : NEW DOHA INTERNATIONAL AIRPORT PIECE MARK : Surface Preparation: Sa 2.5 Paint Specification: 25045-a1100-18-ssd-s-xxx Paint Material: AREA : STRUCTURE TYPE : No. of Coats: One (1) Required DFT: 76 microns DRAWING NO.: Blasting & Painting Date: Ambient Te,perature (C) Relative Humidity (%): Primer Coat DFT (microns) Gage Readings Spot No. Average 1st 2nd 3rd Weather : Steel Temperature (C) Dew Point (C) Average DFT (microns) Inspection Result DATE : CONTRACTOR NAME : SIAM STEEL INTERNATIONAL PLC. REPORT NO.: SHEET NO.: LOCATION : SIAM STEEL BANGNA FACTORY

Item No.

Piece Mark

Drawing No.

Rev.

CONTRACTOR QC REPRESENTATIVE :

DATE :

____________________________________________________________________________
(PRINT NAME AND SIGN)

SOJV QC REPRESENTATIVE :

DATE :

_____________________________________________________________________________
(PRINT NAME AND SIGN)

OBI REPRESENTATIVE :

DATE :
(PRINT NAME AND SIGN)

________________________________________________________________
WITHNESS & REVIEW ONLY REVIEW
Document No. : 25045-A1126-18-ITR-S-006,form b

Anda mungkin juga menyukai