manpower
costs.
Hence
modern
condition
based
Testing
procedure
to
be
evolved
after
detailed
General
cleaning
cleaning
of
all
insulators
of
Dust
protection
even
though
the
operating
Emptying and refilling of SF6 gas SF6 gas for the circuit
breaker is to be evacuated using the gas treatment
equipment.
SF6
gas
contained
in
the
electrical
Oil free
(Figure 1)
o
Vibration measurement
Testing procedure
A typical arrangement for measurement of operating timings
of circuit breaker is given in Figure 2.
(Figure 2)
contact
using
different
channel
of
the
analyzer.
Evolution of test results
The permissible pole discrepancy as per IEC 56 between 2
poles should not be beyond 1/6 of cycle (3.33 ms) and
between 2 breaks should not exceed 1/8th of a cycle (2.5
ms). As per the practice followed by the most power utilities
the limit for pole discrepancy between pole to pole is of the
9
base
values
is
generally
considered
acceptable.
Figure 3
The ohm meter is employed for measurement of pumping
resistance. To measure the value, connect the leads as per
above figure and adjust the varies so that approximately 100
ampere current flow through the contacts. The value of the
contact resistance is directly displayed on the digital LED
display screen. By using the 4 terminal method effects of
resistance of test lead is nullified is the input impedance of
the measuring device is very high.
If
the
value
of
the
contact
resistance
exceeds
the
(Figure 4 )
This another technique for measuring the contact resistance
during dynamic conditions i.e. during operations (close/trip)
of CB. A DC current is injected through the CB and the
current and voltage drop are measured and the resistance is
calculated. The graphs of resistance vs. time data provide
useful information on the condition of the main contact of CB
and is considered to be a modern diagnostic tool.
12
signature
are
compared
with
the
original
fluorides).
of
These
insulation
chemicals
and
results
corrosion
in
in
the
SF4
+ SOF2 + 2 HF
H2O .................
SOF2
+ SO2 + 2 HF
H2O ................
(b) When Moisture density is high
SF4
+ H2SO3 + 4 HF
3H2O ................
2SF2
+ H2SO3 + 4 HF
3H2O ...............
Sulphur oxifulorides, hydrogen fluorides and H 2SO3 formed
during these reactions attack the materials containing
silicon-dioxide (SIO2) viz. glass / porcelain. Primary and
secondary decomposition in the presence of moisture forms
corrosive
electrolytes
which
may
cause
damage
and
operation failure.
Testing procedure
A typical arrangement for dew point measurement is given
below in Figure 5.
15
(Figure 5)
Make the connection to the kit from circuit breaker ensuring
that regulating valve is fully closed at the time of connection
of the dew point kit. Regulate the flow rate of SF 6 (0.2-0.5
L/minute) as per IEC 480, the value of the dew point is
observed till it becomes stable.
Note.: If the regulating valve is provided at the outlet of the
dew point kit then dew point value for rated pressure are to
be monitored.
Frequency of Dew Point Measurement
The discharge of moisture from the organic insulating
material is faster initially and the rate of release becomes
almost negligible after 4 to 5 year of commissioning, and
thereafter moisture entry in the CB is through permeation.
Recommended frequency of dew point measurement is as
given below:
Dew point
Sl. Make of
No.
CB
Dew point at
at
rated
Atmospher
pressure
ic Pressure
(Min. C)
(limit) (Min
Remarks
C)
1.
BHEL
M&BG
CGL
ABB
NGEF
At the time of
-15
- 36
-7
-5
- 29
- 27
--
- 39
--
- 32
- 15
- 35
- 10
- 31
- 15
- 35
-5
- 26
-15
-36
-7
- 29
commissioning
During O&M
-5
- 27
Critical
17
commissioning
During O&M
Critical
At the time of
commissioning
During O&M
At the time of
commissioning
During O&M
At the time of
commissioning
During O&M
At the time of
18
Figure 6
Testing procedure
Connect
LV
cable
to
the
middle
of
the
double
interrupter
with
temperature.
A rising
temperature
to
of
increase
insulation
with
due
the
to
temperature.
aging
causes
0.015 C
(if the value is between .05 and 0.3 it considered as
questionable condition. Value of more than .03 is a
sign of alarming condition)
2. Deposit of surface moisture can have significant effect
on the surface losses and consequently on the results.
With a view to minimizing the errors the dissipation
measurements may be made when the weather is clear
and sunny and the relative humidity is less than 80%.
3. Surface leakages Any leakage over the insulation
surfaces of the specimen will get added to the losses in
the insulation and make a fake impression about the
condition of specimen. It is recommended that surfaces
of insulation should be cleaned and dry when taking a
measurement.
20
current
resulting
from
the
capacity
need
to
be
opened
when
taking
21
to
cellulose
material.
Depending
upon
the
vibrations
operations
experienced
are
recorded
during
with
closing
the
help
and
of
CB closing lockout
CB operation lockout
23
Pump start/stop
CB closing lockout
CB operation lockout
Techniques
for
Instrument
Transformer
Instrument transformers are generally the most reliable EHV
network equipment. However, violent failure/blasting due to
primary insulation of instrument transformers may lead to
considerable damage to nearby equipments and O&M
24
techniques
have
been
adopted
like
DGA
monitoring,
recovery
voltage
measurement etc.
Tan Delta and Capacitance Measurement (CT/CVT)
1. Testing mode for CTs: CTs provided with test steps
have to be tested in UST mode whereas CT with test
step are to be tested in GST mode. Before carrying out
the
test
it
may
be
ensured
that
jumpers
are
be
connected
between
HV/HF
points
and
described
for
CBs.
Major
factors
affecting
the
Figure 7
26
after
15,
60
and
600
seconds.
Ambient
voltages
using
0.2
or
0.5
accuracy
class
29
N2 pressure monitoring
Some of the CTs are provided with N2 cushion at the top of
the CT to avoid ingress of moist air from atmosphere during
normal contraction/expansion of oil due to change in
temperature (due to load or ambient variations). N2 pressure
is to be maintained at about 0.30 to 0.50 bar above
atmosphere hence monitoring of the same is very important.
In case of leakage of N2 gas, CT will breathe with
atmospheric
air
insulation.
This
moisture
may
moisture
enter
entry
in
will
CT
oil/paper
lead
to
regarding
shorting
of
turns
CT
secondary
31
by
the
manufacturers.
Recently,
another
33
its
capacitive
component,
the
sensitivity
in
the
arm
is
adjusted
to
balanced
the
capacitive
Compensating
the
capacitive
component
without
by
the
arrester
manufacturer
or
from
reduced
by
the
multiplication
and
integration
of
big
importance
to
the
operation
kit
should
be
properly
earthed
as
per
the
down
the
system
voltage
and
ambient
Checking
of
electrical
connection
for
battery
for
tightness
b) Battery charger
are
the
procedures
for
identifying
the
probable faults
Sr.
No.
1.
- Problem in
Remedial measures
- Check the control cards as
42
output
control cards
- Transformer
supply failure
- Fuse blown
- Replace
- Loose
connections in
transformer and
controller
DC voltage
not
2. building up
or dropped
- Rectifier fuse
blown
on load
- Current limit in - Check current limit setting
3.
operation
and adjust
- Problem in
control cards
Output
- Filter fuse
ripple high
blown
- Rectify
conducting
4.
- Potentiometer
setting
disturbed in
to be sent to factory/replace
Firing card
Output
- problem in
voltage
control card
shooting
high in
auto mode
Output
5.
voltage
low
- Loose
connection
- Stability
potentiometer
disturbed in
amplifier card
F. Protective Relays
A large number of different types of protection schemes /
arrangements have been under use at different sub-station.
Their quite diverse due to their being supplied by different
manufacturers having various design philosophy. In order
ensure healthiness and maximum availability of protective
relays it is necessary to carryout periodic testing. Presently,
manual as well as microprocessor based automatic testing
kits are available. While the manual kits have been in use by
utility engineers in past, automatic test kits are relatively
recent introduction. Apart from automatic testing capability,
these kits are also capable of replaying the fault recordings
captured by disturbance recorders as well as transient
simulation
done
using
Electro
Magnetic
Transient
be
0.05-200
amps.
With
negligible
harmonic
current,
ground
relays,
synchronizing,
47