3, 137143
137
Notation
CRR CSR D E H hi n N (N1 )60 W factor of improvement depth Cyclic resistance ratio (causing liquefaction) Cyclic stress ratio (earthquake induced) maximum effective depth of improvement (m) energy input (t) height of drop (m) imprint depth (m) number of drops measured (original) SPT blow count corrected SPT blow count weight of tamper (t)
(a) substituting the improper soil with a suitable one (b) removing the improper soil and starting construction of the structure from a lower level, if feasible (c) designing special foundations such as piles, provided enough time and budget could be assigned (d ) changing the site location if no other conventional remedies were applicable.
Introduction
What did we conventionally decide as geotechnical engineers if we encountered an improper soil texture at a site? Some of the conventional remedies were as follows
(GI 5250) Paper received 15 August 2005; last revised 21 July 2006; accepted 30 November 2006
By contrast, there are now various applicable soil improvement techniques by which the technical solution for an improper soil texture can be achieved quite economically. The CROS project included construction of nine oil tanks plus other facilities on a liqueable silty sand layer at Neka, Mazandaran Province, Iran. Evaluation of the applicable soil improvement methods led to two nal solutions: dynamic compaction and vibro-compaction. Vibro-compaction would have required the necessary equipment to be imported, which was out of question because of lack of time. Hence the chosen solution was dynamic compaction. Table 1 presents a rough comparison between dynamic compaction for the oil tanks and other facilities and the conventional method: concrete pile foundations. The table shows that, by applying the dynamic compaction method,
A. Majdi et al. penetration tests (SPTs) were performed inside S-boreholes at 1.5 m intervals. The oil tanks were 50 m in diameter and about 15 m high. G-boreholes and C-boreholes were drilled mainly to verify the stratication, as well as the CPTs. Figure 2 shows a typical geotechnical prole of the tank areas; for simplicity, just a few boreholes and CPTs are shown. The main layer is mostly loose silty sand and occasionally loose sand (SM and SP) at shallow depths, becoming gradually medium dense at depth. The main sublayer is soft to medium lean clay or elastic silt (CL or MH). Alternating sublayers of sand or silt with organic materials plus lenses of silty clay are observed at lower depths. The groundwater table is about 2 m below NGL. The liquefaction potential of the area was studied using both the SPT results (Seed et al., 1985) and the CPT results (Robertson and Campanella, 1985). Figs 3 and 4 show safety
Safety factor against liquefaction 0 0 100 200 300
Table 1. Comparison of the nal solutions Method Time: months Rough cost: US$m 1.3 0.5 DC/CPF Time 40% Budget 38%
10 4
remarkable savings could be gained: US$0.8 million in budget and half a year in time.
Depth: m
10 12 14
TK 103
TK 104
CPT 4
TK 108
Fig. 1. Layout of oil tanks and location of boreholes and CPTs. For simplicity only a few locations are shown
200 SM or SP CL or MH C1 300
Fig. 3. Plot of safety factor against liquefaction against depth for all tanks before improvement, based on SPT data, excluding cohesive layers
S1
400
500
28 25 12 6 14 3 17 28 26 29 32 29 26 28 16 15 12 49 39
Alternating sublayers of sand or silt with organic materials and/or lenses of silty clay S8 S7 33 11 30 S2 C4 12 50
18 28 35 41 37 2 24 19 28 17 28 28 13 32 15 36 12 21 21 50 33 26 14 17 25 4 28 26 14 32 20 33 13 50 38 30 12 40 36 29 20 20 3 16 31 42 22 26 50 7 20 17 19 10 12 47
Level: m
600
Fig. 2. Typical geotechnical section of tank areas. Boreholes C1 and C4 are outside the tank perimeters. Numbers along S-boreholes are SPT values
138
PLT 1
BH3
3 @ 50 m 150 m
10
Fig. 5. Sketch of trial tamping areas and related information. See Table 5
12
14
Fig. 4. Plot of safety factor against liquefaction against depth for all tanks before improvement, based on CPT data, excluding cohesive layers (only a few test results are shown)
factor against liquefaction potential plotted against depth for all nine oil tanks (TK101 to TK109) based on SPT and CPT respectively. The safety factor equals CRR/CSR: that is, cyclic resistance ratio divided by cyclic stress ratio. It should be noted that, for simplicity, only a few test results are shown in Fig. 4. Values corresponding to cohesive textures are eliminated in both gures. As observed, the whole area is subjected to liquefaction potential down to about 13 m.
properly taken into account. Cohesive sublayers have also a damping effect on the energy input. Hence a comprehensive trial tamping programme is usually an inevitable phase of the work in important projects. In the tamping programme, free fall drops were considered in order to have the maximum achievable energy. Initially, three drop groups (15, 12 and 9) and two tamping grid patterns (5 m and 6 m apart) were considered. These parameters were combined in two trial patterns, called the northern and southern trial areas, which are sketched in Fig. 5. The corresponding features, such as number of drops, weight of tamper and drop height for each pass, as well as the ironing pattern, are presented in Table 2. The static contact pressure of the tamper (the weight of the tamper divided by its contact area) is about 51 kPa. Prior to the commencement of tamping, and in order to evaluate the liquefaction potential of the trial areas, BH1 was drilled down to 15 m, with SPT performed at 1 m intervals. However, as pore water dissipation plays an important role in recovery period determination, two piezometers were installed inside BH1 and BH1-1 for measurements at 78 m and 1213 m intervals respectively. To evaluate the efciency of ironing for supercial compaction, one plate-loading test was performed on ground surface, referred to as PLT 1. To compare the trial dynamic compaction for the two areas, the related parameters are summarised in Table 3. SPT values at BH1 were analysed for liquefaction potential (Seed et al., 1985). The results, presented in Fig. 6, are (a) SPT blow counts against depth, both the originally
Number of drops, n 15 9 12 9 1 2
Height of drop, H: m 20 20 20 20 16 16
2 @ 50 m 100 m 50 m
Depth: m
2 @ 60 m 120 m
139
A. Majdi et al.
Table 3. Summary of parameters for trial areas Area Grid size: m Northern Southern Northern Southern 6 5 6 5 Total drop: m2 1.10 1.40 0.41 0.40 Average no. of drops at grid points 16.5 12 14.5 10 Total energy: t.m/m2 393 389 153 149 Average energy per grid point, E:* t.m 372 360 390 385 p E: (t.m)1=2
19.8 19.6
*E nWH/n, where W is weight of tamper (t), H is height of drop (m) and n is number of drops.
SPT blow count: blows per foot 0 2 4 6 0 10 20 30 40 50 0 2 4 6 0 Shear stress: kg/cm2 02 04 06 08 0 2 4 6 0 Safety factor against liquefaction 1 2 3
Depth: m
Depth: m
Depth: m
(b)
8 10 12 14 16
8 10 12 14 16 (c)
(a)
Fig. 6. Graphical presentation of liquefaction potential of trial area before improvement, based on BH1 (excluding cohesive layers): (a) measured and corrected SPT blow count against depth; (b) shear stresses against depth; (c) safety factor (against liquefaction) against depth
measured values (N), and values corrected for overburden pressure ((N1 )60 ) (b) comparison of the shear strength of the soil and the shear strength induced by earthquake (c) the safety factor against liquefaction (CRR/CSR). As anticipated, the liquefaction hazard exists down to 13 m. Two heave tests were performed to determine the optimum number of drops (corresponding to threshold energy), which is the value beyond which any increase in energy input causes less void ratio decrease, and thus no further practical improvement is expected. The test deals with the volumetric energy response during successive drops. It should be noted that the threshold energy or the corresponding optimum number of drops may not necessa14 1230 1099 895 782 688 479 271 091 0 2 4 6 8 10 Number of drops 12 14 16
rily be the target values, because, according to the geotechnical conditions of the site, a lower energy input might meet the project requirements and/or targets. Two points were selected for the heave test. The rst was selected on the trial tamping grid, and the second was outside the trial areas. Figs 7 and 8 show the heave test results for these two points. In Fig. 7, initially at eight drops the slope of the net volume line is decreased. Hence the corresponding energy input at eight drops is regarded as the threshold energy. In this gure, another rise is observed beyond 12 drops. This may be due to overtamping. Overtamping, by which the threshold energy is exceeded, may sometimes cause remoulding and dilation of the soil (Moseley, 1993). Although the plug of soil could be driven deeper, and
14
12 10 8 6 4 2 0
1061 945
16
140
Mitigation of liquefaction hazard by dynamic compaction consequently the densication would be driven to greater depths, the recommended maximum economic limit is ten drops (Welsh et al., 1987). As observed in Fig. 8, the optimum number of drops is determined as six. Although that is less than eight drops, at the trial stage no decrease in the number of drops was considered. By using the heave test data, the normalised imprint depth is plotted against the number of drops in Fig. 9. This plot is useful in highlighting anomalous areas requiring additional treatment or possible undercutting (Mayne et al., 1984). At this stage, pore water pressure measurements were also undertaken. Upon completion of the liquefaction potential survey and heave test performance, trial tamping was conducted at the two trial areas along with the excess pore water pressure measurements. On completion of passes I and II, the imprints were backlled by suitable granular materials. Pass III was conducted mainly for backll compaction, and nally ironing was conducted for treating the soil at shallow depths. Pore water pressure measurements revealed that a recovery period of about 3 days was needed between the tamping passes. About one week after the end of the trial tamping, boreholes BH2 and BH3 were drilled at the trial areas (see Fig. 5). A comparison of the measured SPT values, N, for the northern and the southern areas (i.e. BH2 and BH3 against BH1) is presented in Figs 10 and 11 respectively. Note that values corresponding to the cohesive layers are eliminated. The increase of SPT values is observed down to about 13 m. It is also obvious that, below 8 m, the improvement in the southern area has been more efcient. By taking the maximum effective depth of improvement as 13 m, by using the relation p p D WH E (1) where D is the maximum effective depth of improvement (m), W is the weight of the tamper (t), H is the drop height (m) and E is the energy input (t.m), the dimensionless factor in equation (1) was determined as 0.66. Table 4 presents some values for proposed in the literature. The safety factors against liquefaction based on BH2 and BH3 are plotted against depth and presented in Figs 12 and 13
Number of drops 0 0 On grid point of trial area 4 8 12 16 20 Measured SPT blow count, N: blows per foot 10 20 30 40 50
0 0
60
Depth: m
10
12
14
16
Fig. 10. Comparison of SPT values before and after improvement in northern trial area (excluding cohesive layers)
Depth: m
10
12
0050
16
Fig. 11. Comparison of SPT values before and after improvement in southern trial area (excluding cohesive layers)
0075
0100
respectively. The results reveal proper mitigation of the liquefaction hazard. PLT 2 was also performed on the treated ground. The results showed that more energy is needed for compaction of the supercial soil. This could be solved by some passes of a suitable roller. 141
A. Majdi et al.
Table 4. Values of factor Authors Menard and Broise Leonard et al. Lucas Mitchell and Katti Year 1975 1980 1980 1981 1 0.5 0.650.80 0.3750.700 Reference Moseley (1993) Moseley (1993) Mitchell and Katti (1981) Moseley (1993)
The results of the trial tamping programme can be summarised as follows. (a) The optimum number of drops may be considered as eight. (b) The maximum depth of improvement is 13 m. (c) The factor equals 0.66. (d ) The recovery period is about 3 days. (e) Below 8 m, more efcient compaction is achieved in the southern area. ( f ) For better compaction at shallow depths, the ironing energy should be increased slightly. (g) Rolling should be considered for supercial compaction.
3
0 0
Depth: m
10
12
14
16
Fig. 12. Plot of safety factor against liquefaction potential against depth for improved northern trial area, BH2 (excluding cohesive layers)
0 0
2 6
Depth: m
Depth: m
8 10 10 12 12 14 14
16
16
Fig. 13. Plot of safety factor against liquefaction potential against depth for improved southern trial area, BH3 (excluding cohesive layers)
Fig. 14. Comparison of SPT values before and after improvement for oil tanks (average of nine tanks, excluding cohesive layers)
142
200 20
400
40
600 TK101
Depth: m
60
TK102 800 TK103 TK104 1000 TK105 TK106 TK107 1200 TK108 TK109 1400
80
100
120
Fig. 16. Plot of tank contact pressure against average settlement in hydrostatic test for TK101
1600
Fig. 15. Plot of safety factor against liquefaction against depth for all tanks after improvement, based on SPT results
References
As can be seen, the safety factor values are increased remarkably in comparison with Figs 3 and 4, which implies that the liquefaction hazard is well mitigated. Considering the ageing effect phenomena, the values in Fig. 15 are expected to rise to higher values over time. The maximum improvement depth is about 13 m, which implies that the factor is 0.65, that is, quite close to what was investigated during the trial tamping. Because of the use of granular materials for backlling the craters, the average subsidence of the oil tank area was about 40 cm, that is, about 3% of the effective depth of improvement. Fig. 16 presents a typical result of hydrostatic tests performed on the oil tanks. Upon completion of the test, which lasted 28 days, the maximum settlement was registered as 112 mm. This is well below the limits considered in various codes (Klepikov, 1989).
Federal Highway Administration (FHWA) (2000) Dynamic Compaction: Ground Improvement Technical Summaries. FHWA, US Department of Transportation, FHWA-SA-98-086, Vol. 1, Ch. 4, pp. 4-1 to 4-55. Klepikov S. N. (1989) Performance criteria: allowable deformations of buildings and damages. Proceedings of the 12th International Conference on Soil Mechanics and Foundation Engineering, Rio de Janeiro, 4, pp. 27352744. Mayne P. W., Jones J. S. and Dumas J. C. (1984) Ground response to dynamic compaction. Journal of the Geotechnical Engineering Division, ASCE, 110, No. 6, 757773. Mitchell J. K. and Katti R. K. (1981) Soil improvement: state-ofthe-art report. Proceedings of the 10th International Conference on Soil Mechanics and Foundation Engineering, Stockholm, pp. 509 565. Moseley M. P. (1993) Hayward Baker Inc. Maryland, USA, Dynamic compaction, Ground Improvement, CRC Press, Boca Raton, FL, pp. 2039. Robertson P. K. and Campanella R. G. (1985) Liquefaction potential of sands using the cone penetration test, Journal of the Geotechnical Engineering Division, ASCE, 111, No. 3, 298307. Seed H. B., Tokimatsu K., Harder L. F. and Chung R. M. (1985) Inuence of SPT procedures in soil liquefaction resistance evaluations. Journal of the Geotechnical Engineering Division, ASCE, 111, No. 3, 14251445. Welsh J. P., Anderson R.D., Barksdale R. P., Satyapriya C. K., Tumay M.T. and Wahls H. E. (1987) Soil improvement: a ten year update. Proceedings of a Symposium Sponsored by the Committee on Placement and Improvement of Soils of the Geotechnical Engineering Division of ASCE, Geotechnical Special Publication no. 12, ASCE, Atlantic City, NJ, pp. 6775.
Conclusion
The liquefaction potential was successfully mitigated by the dynamic compaction method for the nine oil tanks and other facilities at the CROS project site. The applied method was both more cost-effective and less time-consuming than other available remedies. The trial tamping programme and the heave tests decreased the initial number of drops considered by the project consultant, causing the operations to be the most economical and least time-consuming possible. The maximum effective depth of improvement and the corresponding factor were determined as 13 m and 0.65 respectively. The average subsidence was 3% of the maximum effective depth. A maximum settlement of 112 mm was registered upon completion of the hydrostatic tests, which is below the limiting values.
Discussion contributions on this paper should reach the editor by 4 January 2008
143