Settlement Proposal
March 11, 2008
Outline
Summary of Proposed Power Supply
Agreement
Summary of the Existing Arrangement
Savings Analysis
Uncertainty Analysis
Conclusions
100
80
60
40
20
Carbon Legislation
Purchased Power Prices
Fuel Prices
Unit Outages
COA Load Growth
18%
Cumulative Nominal
(2008-2019)
16%
14%
Probability
12%
10%
8%
6%
4%
2%
0%
700 720 740 760 780 800 820 840 860 880 900 920 940 960 980
Cumulative Nominal
10%
(2008-2019)
8%
Probability
6%
4%
2%
0%
-20 -10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140
20%
Probability
15%
10%
5%
0%
500 510 520 530 540 550 560 570 580 590 600 610 620 630 640 650 660 670 680 690 700 710
10%
Probability
8%
6%
4%
2%
0%
-20 -15 -10 -5 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100
Fuel charge
Average system fuel cost adjusted for 2%
losses
Includes CO2 allowance costs beginning 2012
Reserve capacity assumed to be provided
by Cleco, other than for RPS2
COA incurs no additional DG Hunter O&M
cost resulting from dispatch by Cleco