Transfer Scheme

Incoming A 0.4kV

Incoming B 0.4kV

Bus Coupler

Modes of Bus Transfer

Manual Bus Transfer

Automatic Bus Transfer

Manual Bus Transfer

i: Without Voltage Interruption

ii: With Voltage Interruption:


Slow changeover Fast changeover

Manual Bus Transfer Without Voltage Interruption

Incoming A

Incoming B

Bus Coupler 0.4kV 0.4kV

Manual Bus Transfer Without Voltage Interruption

Involving Brief Parallel Operation Fault level rising Not used in the normal course In case of an emergency

Manual Bus Transfer With Voltage Interruption

Incoming A

Incoming B

Bus Coupler 0.4kV 0.4kV

Manual Changeover With Voltage Interruption


Slow Changeover

Fast Changeover

Slow Changeover
Not fault level rising Decay of residual voltage of motors connected to the bus to sufficiently (about 20 per cent of the rated voltage) Starting current inrush, heavy voltage drop Pre-selected number of non-essential auxiliary motors (less than 15% drop voltage )

Fast Changeover
Before residual motor voltage vector has fallen Motor speed dropped down only marginally Only a small rise of current Phase Comparison Relay

Automatic Bus Transfer

Under Fault Condition (Voltage Drop) Automatic Changeover with Voltage Interruption

ATS
The reduction of the voltage below a preselected value and after a pre selected time period the affected incoming breaker will trip. After the breaker has disconnected the main the bus-tie breaker will close. This operation will not take place if the incomer was tripped by any future protection device.

Transfer Scheme

Local

Remote Open ATS

Close 0.4kV 0.4kV

Transfer Scheme

Local Remote ATS

1
Open

Close 0.4kV 0.4kV

Return to Normal Operation (Re-Transfer)


It shall be manually. Re-closing of either incoming breaker results in momentary parallel switching of the main, followed by manually opening of the bus-tie breaker. Manually opening the bus tie breaker, followed by manually closing the incoming.

Transfer Scheme

ATS Remote

Close

Local

Open 0.4kV 0.4kV

Bus Coupler

I
3 0.4kV 0.4kV

3 S.S 27R

3 S.S 27R

Normal Operation

Incoming A 0.4kV

Incoming B 0.4kV

Bus Coupler 27R 27R

Initial Conditions
2 1
Open or No Service

4 3 6
In Service TCS Close Service No 27i

0.4kV

0.4kV

27R

B
Panel Ready Common Fault 50,51

Initial Conditions
4 3
Close Service No 27i

2 1 6
In Service TCS Open or No Service

0.4kV

0.4kV

A
27R
Panel Ready Common Fault 50,51

B
5

Closing Bus Coupler Test ATS Remote

Closing in Test position


+
Test Position

Start

Stop

Closing Coil

Initial Conditions
Incoming A Open or No Service Relay not operated Incoming B Close & Service & Relay not operated 27i not operated Service Position TCS Relay

Local

&
Close PB

ATS

&

&

Local ATS Remote

Selector Switch

Closing Coil

Remote

Busbar A (27R)
Close Command

&

Opening

Local Trip Remote

Opening-Local
+

OFF

Shunt Trip

Air Circuit Breaker

Opening-Trip

2
Both Incomings are Open or Closed Or no in Service. Incoming A 0.4kV Incoming B 0.4kV

Bus Coupler 27R 27R

Opening-Remote
+

Remote

Shunt Trip

Air Circuit Breaker

Signal Lamp
+

Close Open Fault Service Deactivate Test