SA
M
PL
TABLE OF CONTENTS
SA
M
PL
-3-
SA
M
PL
-4-
Introduction
One of the most important and expensive items of capital equipment in a substation is
a power transformer. If maintained correctly they will give very long service life. It
is not uncommon to encounter units which have been in service for greater than 40
years. They are used to transform voltages either up or down as required for
distribution between substations and customers.
Apart from power transformers there are instrument transformers used in the
substation environment. These devices are used to monitor the power levels, or are
used for protection purposes to trigger circuit breakers and other current breaking
devices.
There are also other inductive coil devices that resemble transformers called
reactors. These are used to limit surge currents, and have maintenance regimes
similar to transformers.
M
PL
This module will review the theory of transformers, especially as used in high voltage
power applications. It will then explain the maintenance and testing requirements for
these devices.
The following high voltage devices are described and their maintenance requirements
reviewed:
Power transformers
Voltage (potential) transformers
Current transformers
Reactors (series and shunt)
Auxiliary Transformers
SA
-9-
SA
M
PL
Student Exercise
Obtain a listing of the types of maintenance tasks (work procedures) performed
upon power and instrument transformers in your organisation.
Obtain copies of a number of these work procedures and review the steps involved
to perform the task.
Attach copies to this Learner Guide of some of the appropriate organisational
work procedures in your organisation.
- 10 -
M
PL
A transformer may receive energy at a lower voltage and deliver it at higher voltage
(step up transformer) or it may receive energy at higher voltage and deliver it at a
lower voltage (step down transformer). Any transformer may operate as a step-up or
step-down transformer depending on the requirements of the system, the supply
voltage available and the desired output voltage.
High
Voltage
Low
Voltage
Low
Voltage
High
Voltage
SA
Transformers are very efficient machines, often operating at close to 99%. (They
are generally regarded as the most efficient machines invented so far.)
They are reliable when correctly maintained.
To overcome the I2R losses of long transmission lines between generating power
stations to population regions, very high voltages such as 330kV and above are
used. (Without the use of transformers most of the energy from the power station
generators would be lost as heat in the transmission lines, or the transmission line
would need to be increased in diameter enormously, making them impractical or
too expensive to use.)
Transformers are used to reduce the high voltages used for transmission to lower
voltages suitable for distribution to consumers.
- 11 -
Figure 2: Transformers are used in the distribution and supply chain to transform voltages up
and down so as minimise energy losses due to power line resistance losses.
M
PL
Construction of Transformers
The transformers you will encounter in a substation, whether they are power
transformers or instrument transformers, are constructed of the same basic
components.
Core
(hidden by the windings)
SA
Tank
(cutaway to show interior
of transformer)
Windings
(wound onto the core)
Insulation, typically
Cellulose paper
Wood
Mineral oil
Transformer Theory
All transformers use the same basic principle, and only the finer points ever change.
A transformer works on the principle of magnetic coupling to transfer the energy from
one side (winding) to the other. The construction and physical appearance of a power
transformer in a substation may look very different from a transformer used for radio
frequency (RF) applications in a radio transmitter, yet the theory remains the same.
Transformers are a passive device there are no active components such as
Maintain HV power system transformers Learner Guide
- 12 -
SA
M
PL
TABLE OF CONTENTS
SA
M
PL
-3-
Instructional Content
Notes to Trainer
Introduction
Display Slide 1
Timing
One of the most important and expensive items of capital equipment in a substation is a power
transformer. If maintained correctly they will give very long service life. It is not uncommon to
encounter units which have been in service for greater than 40 years. They are used to transform
voltages either up or down as required for distribution between substations and customers.
PL
Apart from power transformers there are instrument transformers used in the substation
environment. These devices are used to monitor the power levels, or are used for protection
purposes to trigger circuit breakers and other current breaking devices.
There are also other inductive coil devices that resemble transformers called reactors. These are
used to limit surge currents, and have maintenance regimes similar to transformers.
This module will review the theory of transformers, especially as used in high voltage power
applications. It will then explain the maintenance and testing requirements for these devices.
SA
M
Learning Outcomes
Display Slide 2, 3, 4
Display Slide 5
Transformer theory
Three-phase transformer theory
Transformer cooling
Supplemental power transformer components
Autotransformers, auxiliary transformers, and reactors
Instrument transformers
Oil sampling and testing
Transformer tests
-8-
Display Slide 6
Power transformers
Current transformers
Auxiliary Transformers
PL
The following high voltage devices are described and their maintenance requirements reviewed:
Ratio checks
Oil sampling
SA
M
-9-
Display Slide 7
PL
Transformers are probably the single most valuable asset located in a transformer substation.
When maintained correctly they will remain serviceable for many decades. It is the job of a
substation operator to understand the working principles of power and instrument transformers
and the subsequent maintenance and testing procedures that are required to keep them serviceable.
Poorly maintained power transformers can result in catastrophic failure of the unit, with the
potential to cause major damage to other substation plant equipment and network outages.
Included in the Appendix of the Learner Guide is a Maintenance Instruction from an electrical
supply utility. This lists the typical types of tasks that substation operators are required to perform
when maintaining power transformers. (This document should be regarded as indicative only as
all electrical supply utilities will have their own version of this Work Procedure as applicable to
that organisation.)
Trainer Note:
SA
M
Student Exercise
Obtain a listing of the types of maintenance tasks (work procedures) performed upon power and
instrument transformers in your organisation.
Obtain copies of a number of these work procedures and review the steps involved to perform the
task.
Transformers provide a simple means of changing an alternating voltage (AC) from one value to
another. (Note: A transformer cannot transform direct current voltages. Where you may see
examples that appear to do this it is actually achieved by converting the DC voltage to an AC
waveform first, and then applying it to the primary side of a transformer. It may then be rectified
back to a DC voltage if required.)
A transformer may receive energy at a lower voltage and deliver it at higher voltage (step up
transformer) or it may receive energy at higher voltage and deliver it at a lower voltage (step down
transformer). Any transformer may operate as a step-up or step-down transformer depending on
- 10 -
Instructions to Assessors
M
PL
This Assessment Guide is part of a suite of resources that have been developed to
support 8 core units of competency from the Certificate IV in ESI Substation
(UET40206) as follows:
UETTDRIS05A
UETTDRIS22A
UETTDRIS23A
UETTDRSB01A
UETTDRSB02A
UETTDRIS03A
UETTDRIS04A
UETTDRIS05A
SA
This Assessment Guide together with a Trainer Guide and a Learner Guide are
designed for UETTDRSB05A - Maintain HV power system transformers and
instrument transformers. This guide is intended to provide some direction to assessors
who are determining competence of students who have completed the theoretical and
practical instruction in this learning module. Assessors are expected to use their own
judgement in designing appropriate assessment questions and tasks and putting them
into context for the assessment candidate. At all times the evidence requirements as
set out in the unit and the principles of assessment, that is, validity, reliability,
flexibility and fairness must be complied with.
Use these guidelines to assist in preparing your own assessment instruments and tools.
The checklist should be treated as a starting point. You may choose to add more
checkpoints to highlight particular aspects of knowledge and skill that you want to see
evidence of. This could be through practical tasks or problem-based questions.
Evidence Required
Evidence for competence in this unit shall be considered holistically. Each element
and associated Performance Criteria shall be demonstrated on at least two occasions in
accordance with the Assessment Guidelines UET06. Evidence must also reflect
the critical aspects of evidence which includes the following:
M
PL
SA
At least
following:
At least
following:
At least
following:
one
of
two
of
two
of
the
the
the
Item List
Power transformer
High voltage reactor (series or parallel)
Auxiliary transformer
Current transformer
Voltage transformer
Insulation resistance tests
Dielectric dissipation factor tests
Low voltage excitation checks
Frequency response analysis
Recovery voltage measurements
Ratio checks
Winding resistance checks
Oil sampling
-2-
SA
M
PL
TABLE OF CONTENTS
SA
M
PL
-3-
SA
M
PL
-4-
Introduction
Substation switching operations may be required for a number of purposes. These
include:
M
PL
The most common substation switching activity is associated with feeders and
transformers, and this learning module will focus upon these activities as examples.
The same principles are utilised for switching and isolation of other substation
equipment.
The procedure for performing the substation switching operation will be provided to
you by the System Operator (or equivalent) in the form of a Switching Instruction
(also known as a Disconnection and Reconnection Instruction). It is possible to be
lulled into a false sense of security through the use of these instructions. Switching
operators must have the knowledge and skill to recognise mistakes or omissions in the
Switching Instruction, which can occur because of local substation variations and
conditions which the System Operator, who is located elsewhere, may be unaware of.
SA
-8-
Standard Abbreviations
People working in substation environments and performing substation switching often
abbreviate technical terminology or use acronyms. The following is a list of those
which may be encountered, and which may be used in these learning resources.
ABBREVIATION
AA / AAs
ABS
ACB
A/R
ATW
AS/by
AUX
BUS
CVT
CAP
CO
CB
CT
DT
D&R
SA
M
PL
ITEM
Access Authority(s)
Air Break Switch
Air Circuit Breaker
Auto Reclose
Approval to Work
Auto Standby
Auxiliary
Busbar
Capacitive Voltage Transformer
Capacitor
Changeover
Circuit Breaker
Current Transformer
Danger Tag
Disconnection and Reconnection
Instruction
Drop-out Fuse or Expulsion Drop-out
Earth Switch
Feeder
Ganged Tripping Drop-out Fuse
Gas Circuit Breaker
Group
Hazemeyer
High Voltage
Hours
Independent
Joint Use
Lightning Arrester
Line Drop Compensation
Live Line Clamp (or Connection)
Low Voltage
Low Voltage Link
Maintenance
Minutes
Non-auto
DOF / EDO
ESW
FDR
GDO / DDO
GCB
GRP
HAZ
HV
HRS
INDEP
JU
LA
LDC
LLC
LV
LVL
MAINT
MINS
NA
-9-
SA
M
PL
Normally Open
N/O
Normally Closed
N/C
No-volt
NV
Number
No
Numbers
Nos
Oil Circuit Breaker
OCB
Oil Fuse Switch
OFS
Open Circuit
OC
Open, Locked and Danger Tagged
OLDT
Operating Agreement
OA
Operations
OPS
Overhead
O/H
Overground Box (Pillar Box)
OG Box
Out of Service
O/S
Parallel
//
Permanent
PERM
Primary
PRIM / PRI
Protection
PROTN / PTN
Reclosing Circuit Breaker
RecCB
Ring Main Isolator
RMI
Supervisory Control And Data
SCADA
Acquisition
Secondary
Sec
Seconds
SECS
Section
SECT
Sectionaliser
SEC SW/AS
Sensitive Earth Fault
SEF
Short Circuit
SC
Single Pole Switch
SP SW
Standby
S/BY
Switch
SW
Switchgear
SWGR
Tap Changer
TC
Temporary
TEMP
Transformer
TRANSF / TX / TXR
Underground
UG
Underground to Overhead Termination
UGOH
Underslung Link
USL
Unserviceable
US
Voltage Regulator (or Voltage
VR
Regulation)
Voltage Transformer
VT
Table 1: Common Abbreviations in the Substation Environment
- 10 -
SA
M
PL
TABLE OF CONTENTS
SA
M
PL
-3-
Instructional Content
Notes to Trainer
Timing
Introduction
PL
Display Slide 2
SA
M
The most common substation switching activity is associated with feeders and
transformers, and this learning module will focus upon these activities as examples. The
same principles are utilised for switching and isolation of other substation equipment.
The procedure for performing the substation switching operation will be provided to you
by the System Operator (or equivalent) in the form of a Switching Instruction (also
known as a Disconnection and Reconnection Instruction). It is possible to be lulled
into a false sense of security through the use of these instructions. Switching operators
must have the knowledge and skill to recognise mistakes or omissions in the Switching
Instruction, which can occur because of local substation variations and conditions which
the System Operator, who is located elsewhere, may be unaware of.
Learning Outcomes
Display Slide 3
-7-
E
Display Slide 6
Access Authority
Switching Instruction
Preparation
SA
M
PL
-8-
Network Overview
Display Slide 8
SA
M
PL
Figure 1: Typical supply distribution network, indicating substations where switching occurs.
-9-
Instructions to Assessors
M
PL
This Assessment Guide is part of a suite of resources that have been developed to
support 8 core units of competency from the Certificate IV in ESI Substation
(UET40206) as follows:
UETTDRIS05A
UETTDRIS22A
UETTDRIS23A
UETTDRSB01A
UETTDRSB02A
UETTDRIS03A
UETTDRIS04A
UETTDRIS05A
SA
This Assessment Guide together with a Trainer Guide and a Learner Guide are
designed for UETTDRIS05A Perform substation switching operation to a given
schedule. This guide is intended to provide some direction to assessors who are
determining competence of students who have completed the theoretical and practical
instruction in this learning module. Assessors are expected to use their own
judgement in designing appropriate assessment questions and tasks and putting them
into context for the assessment candidate. At all times the principles of assessment,
that is, validity, reliability, flexibility and fairness must be complied with.
Use these guidelines to assist in preparing your own assessment instruments and tools.
The checklist should be treated as a starting point. You may choose to add more
checkpoints to highlight particular aspects of knowledge and skill that you want to see
evidence of. This could be through practical tasks or problem-based questions.
Evidence Required
Evidence for competence in this unit shall be considered holistically. Each element
and associated Performance Criteria shall be demonstrated on at least two occasions in
accordance with the Assessment Guidelines UET06. Evidence must also reflect
the critical aspects of evidence which includes the following:
M
PL
SA
Item List
Approvals/clearances
Access permits
Operating sticks
Operating earths
Voltage detectors
Phasing equipment
Ground equipment isolating handles and earths
Links
Air break switches
Fuses
Reclosers
Ring main units
Circuit breakers
-2-
SA
M
PL
Education and Training. The NSW Department of Education and Training do not give warranty or
accept any liability in relation to the content of this work.
TABLE OF CONTENTS
SA
M
PL
-3-
SA
M
PL
-4-
Many workers had no protection at all due to gaps in the coverage of the laws.
The number of laws and regulations often made their enforcement difficult, and if
many types applied to one workplace, there was often much confusion for both the
employers and employees.
Standards laid down by these laws were the bare minimum, often leaving workers
grossly under protected.
There was no systematic review of the laws.
There were major problems in monitoring and enforcement. This was mainly due
to insufficient inspectors, a reluctance to prosecute due to lack of resources, and
the intricacies and ambiguities of the numerous Acts and Regulations.
There was no scope for employee or union involvement.
M
PL
This pattern of developing legislation for each specific problem or issue continued
until the 1970s, resulting in numerous Acts and Regulations. Unfortunately, and
partly due to the ad hoc approach, the legislation was significantly flawed, in that:
In 1972 the Robens Report was published in Britain, recommending much needed
reforms for OH&S laws. The South Australian Parliament passed an Act based on the
Robens Report that year, and all other jurisdictions (States) have followed suit. The
major recommendation made by this report was to have OH&S legislation that was:
SA
-8-
how to achieve this end but rather will monitor employers to ensure that the objectives
and aims of the legislation are being achieved.
The objectives of the Act are to:
M
PL
secure and promote the health, safety and welfare of people at work.
protect people at a place of work against risk to health or safety arising out of the
activities of persons at work.
promote a safe and healthy work environment for people at work that protects
them from injury and illness and is adapted to their physiological and
psychological needs.
provide for consultation and cooperation between employers and employees in
achieving the objects of the Act.
ensure that risks to health and safety at a place of work are identified, assessed and
eliminated or controlled.
develop and promote community awareness of occupational health & safety
issues.
provide a legislative framework that allows for progressively higher standards of
occupational health and safety to take account of changes in technology and work
practices.
protect people (whether or not at a place of work) against risks to health and
safety arising from the use of plant that affects public safety.
The aim of Occupational Health and Safety Acts is to prevent anyone being killed,
injured, or contracting an illness due to a workplace, workplace activities, or specified
high risk plant. This is achieved by preventing or minimising exposure to risk.
SA
The NSW Occupational Health and Safety Act 2000 replaces the 1983 Act and
contains new provisions that require employers to consult with employees on health,
safety and welfare matters. The Act has been written in plain-English and lays down
general requirements for health, safety and welfare, which must be met at all places of
work in New South Wales. The Act covers self-employed people as well as
employees and employers. It therefore applies to you if you are:
an employer
a worker, employee
a self-employed person
a person in control of workplaces
a principal contractor
a designer, manufacturer, importer or supplier of plant
a manufacturer, importer or supplier of substances
an owner of specified high risk plant
a visitor to a workplace: for example, customer or a sales representative.
The Act places an obligation on every person associated with a workplace in any way
to ensure his or her own workplace health and safety and the workplace health and
safety.
-9-
SA
M
PL
TABLE OF CONTENTS
SA
M
PL
-3-
SA
M
PL
General Hazards.......................................................................................................64
Exposed Electrical Conductors ................................................................................64
Voltage Gradients ....................................................................................................67
Safe Approach Distances .........................................................................................68
Transferred Earthed Potential ..................................................................................68
Electrical Induction..................................................................................................70
Working at Heights ..................................................................................................70
-4-
Instructional Content
Notes to Trainer
Timing
Introduction
Display Slide 1
PL
This Unit, Implement and monitor the organisational OHS policies, procedures and
programs, covers a range of topics that apply to the everyday tasks when working around a
substation. It includes the identification, assessment and control (or minimisation) of health
and safety risks that may occur from substation operations and maintenance. It also includes
some revision material on significant workplace hazards in substations that arise from the high
voltage and extra high voltages that are present.
Because of the high voltages present and the amount of energy flowing through substations
they have the potential to be extremely hazardous environments. Policies and procedures have
been implemented by electricity distributors to control the risks presented by these hazards,
but it is important that you, in your role as a team leader, supervisor or senior operator have an
understanding of hazard prevention and management strategies as applied in electrical
substations.
SA
M
As this learning module is aligned to a CIV Unit of Competence there is an expectation that
you will be proactive in your attitude to OH&S matters. This means being actively involved in
the process of ensuring that your organisations work procedures are continually improved
upon and standardised so as to protect the health and safety of workers.
Display Slide 2
Learning Outcomes
-9-
NSWDET 2009
PL
The first pieces of legislation introduced into Australia that related to Occupational Health and Display Slide 4
Safety (OH&S) were on an as needed basis, and closely followed (if not copied) British
OH&S Legislation. In 1873 the first Act was passed in Victoria which specified penalties
applying to breaches of the Act and allowed for government inspection and enforcement. It
took approximately another 25 years for the other States (then separate colonies) to introduce
similar legislation.
This pattern of developing legislation for each specific problem or issue continued until the
1970s, resulting in numerous Acts and Regulations. Unfortunately, and partly due to the ad
hoc approach, the legislation was significantly flawed, in that:
Many workers had no protection at all due to gaps in the coverage of the laws.
The number of laws and regulations often made their enforcement difficult, and if many
types applied to one workplace, there was often much confusion for both the employers
and employees.
Standards laid down by these laws were the bare minimum, often leaving workers grossly
under protected.
There was no systematic review of the laws.
There were major problems in monitoring and enforcement. This was mainly due to
insufficient inspectors, a reluctance to prosecute due to lack of resources, and the
intricacies and ambiguities of the numerous Acts and Regulations.
There was no scope for employee or union involvement.
SA
M
In 1972 the Robens Report was published in Britain, recommending much needed reforms for
OH&S laws. The South Australian Parliament passed an Act based on the Robens Report that
year, and all other jurisdictions (States) have followed suit. The major recommendation made
- 10 -
NSWDET 2009
Instructions to Assessors
M
PL
This Assessment Guide is part of a suite of resources that have been developed to
support 8 core units of competency from the Certificate IV in ESI Substation
(UET40206) as follows:
UETTDRIS05A
UETTDRIS22A
UETTDRIS23A
UETTDRSB01A
UETTDRSB02A
UETTDRIS03A
UETTDRIS04A
UETTDRIS05A
SA
This Assessment Guide together with a Trainer Guide and a Learner Guide are
designed for UETTDRIS22A - Implement and monitor the organisational OHS
policies, procedures and programs. This guide is intended to provide some direction to
assessors who are determining competence of students who have completed the
theoretical and practical instruction in this learning module. Assessors are expected to
use their own judgement in designing appropriate assessment questions and tasks and
putting them into context for the assessment candidate. At all times the evidence
requirements as set out in the unit and the principles of assessment, that is, validity,
reliability, flexibility and fairness must be complied with.
Use these guidelines to assist in preparing your own assessment instruments and tools.
The checklist should be treated as a starting point. You may choose to add more
checkpoints to highlight particular aspects of knowledge and skill that you want to see
evidence of. This could be through practical tasks or problem-based questions.
Evidence Required
Evidence for competence in this unit shall be considered holistically. Each element
and associated Performance Criteria shall be demonstrated on at least two occasions in
accordance with the Assessment Guidelines UET06. Evidence must also reflect
the critical aspects of evidence which includes the following:
M
PL
SA
This assessment guide covers all tasks and equipment included in the section of the
Unit: Critical aspects for assessment and evidence required to demonstrate
competency in this unit, as shown in the table below.
-2-
SA
M
PL
Education and Training. The NSW Department of Education and Training do not give warranty or
accept any liability in relation to the content of this work.
TABLE OF CONTENTS
SA
M
PL
Diagnose and rectify faults in power systems substation environment Trainer Guide
-3-
Instructional Content
Notes to Trainer
Timing
Introduction
PL
This learning module encompasses the application of the full range of knowledge and skills
from the other learning modules associated with Substation Maintenance. It requires the
application of recognised fault finding techniques, combined with the use of test equipment, to
diagnose and rectify faults in power system substations. Diagnosis of faults also requires the
ability to read and interpret enterprise technical documentation such as schematic diagrams
associated with control panels. Tracing and testing of substation wiring and cabling requires
knowledge of enterprise coding systems.
Fault finding also requires a recognition that the initial fault indication may in fact be a
symptom, rather than the actual fault. For example, a circuit breaker trip failure may not in
fact be the circuit breaker but rather a control panel relay failure or a low voltage wiring fault
caused by a rodent.
SA
M
Much of the content of this learning module is enterprise-specific. Trainees need to clearly
understand that whilst the principles are transferable to other ESI organisations, many of the
standards used (e.g. wiring identification codes) are potentially unique to that enterprise and
are not necessarily transferable.
Risk Assessment
Emphasise the importance of conducting a risk assessment before commencing fault finding
activity. This is especially important when performing fault finding. The pressure to resolve
faults quickly can potentially lead operators/fitters to take short cuts. However the very fact
that a fault has occurred suggests that new hazards may have been introduced into the
substation that need to be taken into consideration.
If necessary, refer trainees back to the material in the learning module: Implement and
monitor the organisational OHS policies, procedures and programs.
Learning Outcomes
Diagnose and rectify faults in power systems substation environment Trainer Guide
-7-
Trainers should develop a session which incorporates the range of enterprise documentation
that operators/fitters are expected to be able to access in order to perform fault finding activity.
These will likely include:
Service Instructions or Work Method Statements
Manufacturers manuals
Schematic diagrams
PL
Detail should also be provided about where and how these documents can be accessed.
SA
M
Whilst Australian Standards do exist, they are not always followed, or enterprises have found
it necessary to modify or depart from the Standards to take account of organisation-specific
requirements. Furthermore, often within the one enterprise a range of coding systems may be
in use due to historical factors.
Trainers need to develop content on the topic of coding and identification of wiring, cabling,
bays and equipment/plant for their enterprise. Topics may include:
Cable Identification
Diagnose and rectify faults in power systems substation environment Trainer Guide
-8-
Instructions to Assessors
M
PL
This Assessment Guide is part of a suite of resources that have been developed to
support 8 core units of competency from the Certificate IV in ESI Substation
(UET40206) as follows:
UETTDRIS05A
UETTDRIS22A
UETTDRIS23A
UETTDRSB01A
UETTDRSB02A
UETTDRIS03A
UETTDRIS04A
UETTDRIS05A
SA
This guide is intended to provide some direction to assessors who are determining
competence of students who have completed the theoretical and practical instruction
in this learning module. Assessors are expected to use their own judgement in
designing appropriate assessment questions and tasks and putting them into context
for the assessment candidate. At all times the evidence requirements as set out in the
unit and the principles of assessment, that is, validity, reliability, flexibility and
fairness must be complied with.
Use these guidelines to assist in preparing your own assessment instruments and tools.
The checklist should be treated as a starting point. You may choose to add more
checkpoints to highlight particular aspects of knowledge and skill that you want to see
evidence of. This could be through practical tasks or problem-based questions.
Evidence Required
Evidence for competence in this unit shall be considered holistically. Each element
and associated Performance Criteria shall be demonstrated on at least two occasions
in accordance with the Assessment Guidelines UET06. Evidence must also
reflect the critical aspects of evidence which includes the following:
M
PL
SA
Item List
Diagnose and rectify faults in power systems substation environment Assessment Guide - 2 -
SA
M
PL
TABLE OF CONTENTS
SA
M
PL
-3-
M
PL
Data collected during routine inspections is fed back into operational planning so that
equipment can be repaired or replaced before it fails. It is therefore crucial that you
note and record all data about what was observed and done during the inspection, and
that this information is provided to the appropriate person or input into organisational
systems such as databases.
..
..
..
..
SA
..
..
Substation inspections should also include the rectification and repair of minor defects
during the inspection.
-8-
M
PL
Equipment to be inspected
(Some general principles when conducting the inspection :)
1.
2.
3.
4.
SA
5.
(!!) Advise the System Operator that you are on site and about to commence
inspection activities.
(!!) Confirm that the DC battery volts is correct. This will ensure that
protection equipment will operate correctly if required during the inspection.
(!!) Check and confirm that all exits are operational and clear of obstructions.
This will ensure that the substation can be exited quickly if an emergency
situation should arise.
Switch alarms to local, switch on the indicating lamps (if fitted) and leave on
for the duration of the visit. This applies even if only a brief visit is made, the
purpose being to ensure that a Substation Maintainer can promptly advise the
System Operator of any irregularity which may occur. (Ensure they are
switched back at the completion of the inspection.)
All equipment is to be inspected whether it is in service or not. Even
equipment standing in the substation partially or completely erected but
disconnected from the system should be examined for correct oil level and
breather condition, and any leaks. This requirement is necessary because
electrical equipment will normally deteriorate more quickly when out of
service.
Similarly all readings on transformers, circuit breakers and capacitors are to be
taken irrespective of whether they are in service or not, even if it is known that
they have not been in service since the last reading. All cyclo readings are
entered in equipment log book.
Attention must be paid to items such as broken relay or annunciator glasses
and similar minor defects. These should be serviced or repaired at the time, if
possible, otherwise reported. Correctness and completeness of equipment
labelling should also be constantly checked.
For all relevant matters in the main reports and for all readings taken it is
important that approximately correct times be given. This information may be
particularly valuable in the analysis of a fault but it is required in any case in
the preparation of reliable statistics.
6.
7.
8.
-9-
SA
M
PL
TABLE OF CONTENTS
SA
M
PL
-3-
Instructional Content
Notes to Trainer
Timing
equipment
buildings
surroundings
fencing and gates
PL
are checked to confirm that they are in operational condition, safe and secure.
SA
M
Data collected during routine inspections is fed back into operational planning so
that equipment can be repaired or replaced before it fails. It is therefore crucial
that you note and record all data about what was observed and done during the
inspection, and that this information is provided to the appropriate person or
input into organisational systems such as databases.
Learning Outcomes
Visual checks
DC Systems
HV Equipment
-8-
Display Slide 5
Environmental inspections
Ancillary Slides
SA
M
PL
-9-
E
Display Slide 6
PL
Display Slide 7
SA
M
The major Substation Inspection is carried out every three months, and each
second major inspection is aligned with a six monthly environmental inspection
and Security inspections.
Equipment, security, and environmental inspections are typically conducted
sequentially using a pre-prepared organisation checklist. It will normally take a
few hours to conduct a major inspection (depending upon the size of the
substation and the amount of equipment and plant to be inspected).
Substation inspections should also include the rectification and repair of minor
defects during the inspection.
- 10 -
Instructions to Assessors
M
PL
This Assessment Guide is part of a suite of resources that have been developed to
support 8 core units of competency from the Certificate IV in ESI Substation
(UET40206) as follows:
UETTDRIS05A
UETTDRIS22A
UETTDRIS23A
UETTDRSB01A
UETTDRSB02A
UETTDRIS03A
UETTDRIS04A
UETTDRIS05A
SA
This Assessment Guide together with a Trainer Guide and a Learner Guide are
designed for UETTDRSB02A Carry out Substation Inspections. This guide is
intended to provide some direction to assessors who are determining competence of
students who have completed the theoretical and practical instruction in this learning
module. Assessors are expected to use their own judgement in designing appropriate
assessment questions and tasks and putting them into context for the assessment
candidate. At all times the evidence requirements as set out in the unit and the
principles of assessment, that is, validity, reliability, flexibility and fairness must be
complied with.
Use these guidelines to assist in preparing your own assessment instruments and tools.
The checklist should be treated as a starting point. You may choose to add more
checkpoints to highlight particular aspects of knowledge and skill that you want to see
evidence of. This could be through practical tasks or problem-based questions.
Evidence Required
Evidence for competence in this unit shall be considered holistically. Each element
and associated Performance Criteria shall be demonstrated on at least two occasions
in accordance with the Assessment Guidelines UET06. Evidence must also
reflect the critical aspects of evidence which includes the following:
M
PL
SA
At least
following:
one
of
the
Item List
Transmission substation
Distribution substation
Traction substation
Substation plant and equipment
Substation environmental systems
Substation security systems
-2-
SA
M
PL
TABLE OF CONTENTS
SA
M
PL
-3-
SA
M
PL
-4-
Introduction
High voltage circuit breakers form a critical component of the HV switching network.
They ensure that network operation can continue by automatically disconnecting
faulty branches of the distribution network. They are also the primary means used to
off-load the supply, in conjunction with isolators, to isolate the supply so that
maintenance can be performed on the transmission lines and other switching gear.
Because of the high voltages and currents that the circuit breakers are required to
switch, the circuit breakers can be subjected to routine wear of the contacts and arc
chutes, and in cases of extreme fault switching, the circuit breaker may be physically
damaged. Routine maintenance performed at regular intervals is used to detect and
repair wear and damage of circuit breakers.
This learning module will review the principles of operation of the major categories
of HV circuit breakers. The common types of maintenance procedures used will then
be covered.
M
PL
Because of the wide range of types and models of circuit breakers this learning
module cannot cover all specific cases. You will need to refer to manufacturers data
and local work procedures to gain a full appreciation of how to maintain particular
models of circuit breakers.
The interruption of electric power circuits has always been an essential function,
especially in cases of overloads or short circuits when immediate interruption of the
current flow becomes necessary as a protective measure.
In earliest times, circuits could be broken only by separation of contacts in air
followed by drawing the resulting electric arc out to such a length that it can no longer
be maintained. This means of interruption soon became inadequate and special
devices called circuit breakers had to be developed.
SA
The basic problem has been to control and quench or extinguish the high power arc,
which necessarily occurs at the separating contacts of a breaker when opening high
current circuits. The problem of arc extinction is worsened when the power factor is
low, that is, when the voltage and current are significantly out-of-phase. Since arcs
generate a great deal of heat energy, most often destructive for the breaker's contacts,
technology had to find ways to limit the arc duration and develop contacts that can
withstand the arc effect time after time.
-9-
HV circuit breakers contain the contacts within a sealed enclosure, with an insulating
dielectric surrounding the contacts and other ancillary parts of the circuit breaker.
Despite the range of types of circuit breakers available they all share common
principles; they all have to provide two main functionalities which are inter-related:
Electrical functionality (Interrupter, or contacts)
M
PL
The difference between these two functions is shown in the graphic (Figure 1) which
illustrates these two aspects of the circuit breaker.
SA
High voltage circuit breakers generally fall into one of four categories (defined by the
type of dielectric used), each often having its own sub-categories. These are:
Compressed Air
SF6
Vacuum
- 10 -
SA
M
PL
TABLE OF CONTENTS
SA
M
PL
-3-
Timing
Instructional Content
Notes to Trainer
Introduction
PL
Display Slide 2
High voltage circuit breakers form a critical component of the HV switching network. They
ensure that network operation can continue by automatically disconnecting faulty branches of the
distribution network. They are also the primary means used to off-load the supply, in conjunction
with isolators, to isolate the supply so that maintenance can be performed on the transmission lines
and other switching gear.
Because of the high voltages and currents that the circuit breakers are required to switch, the
circuit breakers can be subjected to routine wear of the contacts and arc chutes, and in cases of
extreme fault switching, the circuit breaker may be physically damaged. Routine maintenance
performed at regular intervals is used to detect and repair wear and damage of circuit breakers.
This learning module will review the principles of operation of the major categories of HV circuit
breakers. The common types of maintenance procedures used will then be covered.
SA
M
Because of the wide range of types and models of circuit breakers this learning module cannot
cover all specific cases. Learners will need to refer to manufacturers data and local work
procedures to gain a full appreciation of how to maintain particular models of circuit breakers.
Learning Outcomes
Mechanical functionality
Maintenance program
-8-
Display Slide 5
PL
The interruption of electric power circuits has always been an essential function, especially in
cases of overloads or short circuits when immediate interruption of the current flow becomes
necessary as a protective measure.
In earliest times, circuits could be broken only by separation of contacts in air followed by
drawing the resulting electric arc out to such a length that it can no longer be maintained. This
means of interruption soon became inadequate and special devices called circuit breakers had to
be developed.
SA
M
The basic problem has been to control and quench or extinguish the high power arc, which
necessarily occurs at the separating contacts of a breaker when opening high current circuits. The
problem of arc extinction is worsened when the power factor is low, that is, when the voltage and
current are significantly out-of-phase. Since arcs generate a great deal of heat energy, most often
destructive for the breaker's contacts, technology had to find ways to limit the arc duration and
develop contacts that can withstand the arc effect time after time.
Summary of functions of Circuit Breakers
CLOSE onto and maintain full load current for long periods.
Display Slide 6
HV circuit breakers contain the contacts within a sealed enclosure, with an insulating dielectric
surrounding the contacts and other ancillary parts of the circuit breaker. Despite the range of types
of circuit breakers available they all share common principles; they all have to provide two main
-9-
Instructions to Assessors
M
PL
This Assessment Guide is part of a suite of resources that have been developed to
support 8 core units of competency from the Certificate IV in ESI Substation
(UET40206) as follows:
UETTDRIS05A
UETTDRIS22A
UETTDRIS23A
UETTDRSB01A
UETTDRSB02A
UETTDRIS03A
UETTDRIS04A
UETTDRIS05A
SA
This Assessment Guide together with a Trainer Guide and a Learner Guide are
designed for UETTDRSB04A Maintain HV power system circuit breakers. This
guide is intended to provide some direction to assessors who are determining
competence of students who have completed the theoretical and practical instruction
in this learning module. Assessors are expected to use their own judgement in
designing appropriate assessment questions and tasks and putting them into context
for the assessment candidate. At all times the principles of assessment, that is,
validity, reliability, flexibility and fairness must be complied with.
Use these guidelines to assist in preparing your own assessment instruments and tools.
The checklist should be treated as a starting point. You may choose to add more
checkpoints to highlight particular aspects of knowledge and skill that you want to see
evidence of. This could be through practical tasks or problem-based questions.
Evidence Required
Evidence for competence in this unit shall be considered holistically. Each element
and associated Performance Criteria shall be demonstrated on at least two occasions in
accordance with the Assessment Guidelines UET06. Evidence must also reflect
the critical aspects of evidence which includes the following:
M
PL
SA
At least
following:
two
of
At least
following:
two
of
the
the
Item List
SA
M
PL
TABLE OF CONTENTS
SA
M
PL
-3-
SA
M
PL
-4-
Introduction
DC systems are installed in substations to supply power for control, protection,
alarms, communications, and other critical auxiliary circuits where maximum
reliability of supply is essential.
AC supplies can be unreliable, whether it is obtained from the local supply or from
on-site alternator sets. In the event of AC supply failure, DC electricity is stored in
batteries with sufficient capacity to provide enough power until the AC supply
becomes available again.
M
PL
Substation staff need to have an understanding of how batteries are maintained, the
principles of charging and discharging of batteries, how to recognise and diagnose
battery faults, and how to diagnose faults which may occur in the DC distribution
network. Installation in the context of this Learning Module refers to replacement
of defective units. (Installation and commissioning of battery banks will be generally
performed by contractors from the supplier.)
The principles contained within this module are also appropriate to other electrical
and electronic fields that use DC storage systems, including telecommunications,
security, computer and renewable energy.
There are a number of hazards that may be present when working with DC systems in
electrical substations. These include:
Electrical shock DC voltages and large currents may be high enough to cause
severe burns or electrocution.
Large mass batteries and cells are very heavy and can cause injury if not lifted
and transferred using appropriate techniques.
Confined spaces gases from battery cells can build up and require ventilation
before battery rooms can be entered.
SA
This list is not definitive. A risk assessment should always be performed before
commencing any activity. The work method statement for your organisation can also
provide guidance about how to work safely.
Treatment of these injuries is covered in the section on First Aid later in this
Learning Guide.
For more detail on working safely in electrical substations refer to Learning Module:
UETTDRIS22A - Implement and monitor the organisational OHS policies,
procedures and programs.
-8-
Environmental Considerations
As you will learn, battery cells may be constructed using the heavy metals of lead or
cadmium. Both of these metals are known to be detrimental to the environment, and
if absorbed by the human body they can be very detrimental to health. If nickel
cadmium cells are carelessly disposed of in landfills the cadmium eventually
dissolves and the toxic substance can seep into the water supply, causing serious
health problems.
Cells which have reached the end of their life or are faulty are returned to the
manufacturer on an exchange basis for replacement new cells, or are sent to specialist
recycling facilities where the metals are recovered and reused.
Battery rooms must be kept clean. Liquid spills or leaking electrolyte must be
cleaned up.
M
PL
SA
The battery is required to supply the electrical requirements of the system substation
when there is no output from the battery charger. This may be due to a loss of the
A.C. supply to the substation or a fault in the battery charger or its supply. Under
these conditions the battery is required to supply the loads it is connected to for a
period of 10 hours.
The battery should be able to be recharged from its design end-of-discharge voltage to
full charge in 5 hours.
-9-
common metal rusting is a type.) The common zinc-carbon dry cell and alkaline dry
cell is an example of this type of battery. A typical voltage of such a primary cell is
1.5 volts. Lithium dry cells may have voltages higher to 3 volts due to the higher
electrochemical potential of this metal and its compounds. The name dry cell is
given because the electrolyte is in a paste-form rather than liquid form.
Primary cells must not be recharged as they may explode.
Secondary Cells
Also called storage or accumulator cells, these battery cells can be recharged because
the chemical reaction that occurs during discharge can be reversed by applying a
reverse current into the cell. The cell can be discharged and recharged many times
(often many thousand times) before it is degraded to the point where it can no longer
provide reliable service.
M
PL
SA
Figure 1
Cell charged
+ve plate -ve plate
Cell discharged
+ve plate
-ve plate
PbO2
+ Pb
+ 2H2SO4
PbSO4
+ PbSO4
+ 2H2O
(lead
peroxide)
(lead)
(sulphuric
acid)
(lead
sulphate)
(lead
sulphate)
(Water
peroxide)
The open circuit voltage of a fully charged lead acid cell is between 2.3 volts and 2.4
volts. Under load the voltage will typically be between 2.0 volts and 2.2 volts.
Lead acid batteries have reduced life expectancy if they are left in a discharged
condition. Ordinarily they do not deal well with deep discharge cycles, although
recent advances in design have produced lead acid batteries more suitable to such
tasks.
- 10 -
SA
M
PL
TABLE OF CONTENTS
SA
M
PL
-3-
Instructional Content
Notes to Trainer
Timing
Introduction
PL
AC supplies can be unreliable, whether it is obtained from the local supply or from
on-site alternator sets. In the event of AC supply failure DC electricity is stored in
batteries with sufficient capacity to provide enough power until the AC supply
becomes available again.
While the battery provides the reserve of stored energy, this is only normally used
in an emergency, or for supplying the short time heavy current drain of circuit
breaker closing solenoids. Under normal conditions the station load and the small
current required to maintain the battery in a fully charged state is supplied by the
battery charger.
SA
M
The storage batteries may be of a few main types: lead-acid, alkaline, and nickelcadmium; each type with its own characteristics.
Substation staff need to have an understanding of how batteries are maintained, the
principles of charging and discharging of batteries, how to recognise and diagnose
battery faults, and how to diagnose faults which may occur in the DC distribution
network. Installation in the context of this Learning Module refers to
replacement of defective units. (Installation and commissioning of battery banks
will be generally performed by contractors from the supplier.)
The principles contained within this module are also appropriate to other electrical
and electronic fields that use DC storage systems, including telecommunications,
security, computer and renewable energy.
-9-
Display Slide 4
Learning Outcomes
(As per those listed on Page 5 of this Trainer Guide.)
Display Slide 5
DC Equipment in Substations
Lead-acid cells
Alkaline cells
Cell capacity
Battery maintenance
Battery testing
SA
M
PL
- 10 -
E
Display Slide 6
There are a number of hazards that may be present when working with DC
systems in electrical substations. These include:
Electrical shock DC voltages and large currents may be high enough to cause
severe burns or electrocution.
Large mass batteries and cells are very heavy and can cause injury if not
lifted and transferred using appropriate techniques.
Confined spaces gases from battery cells can build up and require ventilation
before battery rooms can be entered.
PL
SA
M
This list is not definitive. A risk assessment should always be performed before
commencing any activity. The work method statement for your organisation can
also provide guidance about how to work safely.
Treatment of these injuries is covered in the section on First Aid later in this
Learning Guide.
For more detail on working safely in electrical substations refer to Learning
Module: UETTDRIS22A - Implement and monitor the organisational OHS
policies, procedures and programs.
Environmental Considerations
Display Slide 7
As you will learn, battery cells may be constructed using the heavy metals of lead
or cadmium. Both of these metals are known to be detrimental to the environment,
and if absorbed by the human body they can be very detrimental to health. If
nickel cadmium cells are carelessly disposed of in landfills the cadmium
eventually dissolves and the toxic substance can seep into the water supply,
causing serious health problems.
Cells which have reached the end of their life or are faulty are returned to the
- 11 -
Instructions to Assessors
M
PL
This Assessment Guide is part of a suite of resources that have been developed to
support 8 core units of competency from the Certificate IV in ESI Substation
(UET40206) as follows:
UETTDRIS05A
UETTDRIS22A
UETTDRIS23A
UETTDRSB01A
UETTDRSB02A
UETTDRIS03A
UETTDRIS04A
UETTDRIS05A
SA
This Assessment Guide together with a Trainer Guide and a Learner Guide are
designed for UETTDRSB03A Install and maintain substation DC systems. This
guide is intended to provide some direction to assessors who are determining
competence of students who have completed the theoretical and practical instruction
in this learning module. Assessors are expected to use their own judgement in
designing appropriate assessment questions and tasks and putting them into context
for the assessment candidate. At all times the evidence requirements as set out in the
unit and the principles of assessment, that is, validity, reliability, flexibility and
fairness must be complied with.
Use these guidelines to assist in preparing your own assessment instruments and tools.
The checklist should be treated as a starting point. You may choose to add more
checkpoints to highlight particular aspects of knowledge and skill that you want to see
evidence of. This could be through practical tasks or problem-based questions.
Evidence Required
Evidence for competence in this unit shall be considered holistically. Each element
and associated Performance Criteria shall be demonstrated on at least two occasions in
accordance with the Assessment Guidelines UET06. Evidence must also reflect
the critical aspects of evidence which includes the following:
M
PL
SA
At least
following:
At least
following:
one
of
one
of
two
of
the
the
the
Item List
SA
M
PL
TABLE OF CONTENTS
SA
M
PL
-3-
SA
M
PL
-4-
Introduction
This Unit, Implement and monitor environmental and sustainable energy
management policies and procedures, covers a range of topics that apply to the
everyday tasks when working around a substation. It includes the identification,
assessment and control (or minimisation) of environmental risks that may occur from
substation operations and maintenance. It also covers aspects such as dealing with
waste products of various types, recycling, and responding to an environmental
incident.
M
PL
When you have completed this unit, you should be able to apply relevant
environmental and sustainable energy procedures to specific projects or sites,
including incorporating energy conservation principles and recycling procedures.
SA
-8-
The Environment
The substations that are owned and operated by electrical supply organisations operate
in an environment that includes:
Land
Water
Air
M
PL
The operation and maintenance of substations has the potential to result in a range of
environmental problems. Some of these are:
Historical contamination (such as oil or chemical contamination caused by past
industrial activities)
SA
Visual impacts
Dust generation
-9-
Student Exercise
List other types of environmental hazards that you may be aware of existing (or
potentially existing) in and around substations.
SA
M
PL
The diagram in Figure 1 shows a typical graphic of an EMS. Whilst the graphic
representing the EMS may look different in your organisation, the EMS will still have
the following characteristics:
There is a Planning Phase where hazards are identified and the risks they pose
are assessed.
- 10 -
SA
M
PL
TABLE OF CONTENTS
SA
M
PL
-3-
SA
M
PL
-4-
Instructional Content
Notes to Trainer
Timing
Introduction
Display Slide 1
PL
This Unit, Implement and monitor environmental and sustainable energy management
policies and procedures, covers a range of topics that apply to the everyday tasks when
working around a substation. It includes the identification, assessment and control (or
minimisation) of environmental risks that may occur from substation operations and
maintenance. It also covers aspects such as dealing with waste products of various types,
recycling, and responding to an environmental incident.
As this learning module is aligned to a CIV Unit of Competence there is an expectation that
you will be proactive in your attitude to environmental matters. This means being actively
involved in the process of ensuring that your organisations work procedures are continually
improved upon and standardised so as to protect the environment.
SA
M
When you have completed this unit, you should be able to apply relevant environmental and
sustainable energy procedures to specific projects or sites, including incorporating energy
conservation principles and recycling procedures.
Learning Outcomes
-8-
Dust suppression
Greenhouse gas pollution
Heritage items
Vegetation control
Waste management
Non-liquid waste
Liquid waste
Waste poles, towers and columns
Recycling
Asbestos
Environmental incidents
PL
Sites include buildings, plant, construction and maintenance sites, workshops, laboratories,
catchments, flood plains, irrigation sites, wetlands, drainage sites, waste disposal sites,
easements.
SA
M
-9-
Instructions to Assessors
M
PL
This Assessment Guide is part of a suite of resources that have been developed to
support 8 core units of competency from the Certificate IV in ESI Substation
(UET40206) as follows:
UETTDRIS05A
UETTDRIS22A
UETTDRIS23A
UETTDRSB01A
UETTDRSB02A
UETTDRIS03A
UETTDRIS04A
UETTDRIS05A
SA
This Assessment Guide together with a Trainer Guide and a Learner Guide are
designed for UETTDRIS23A - Implement and monitor environmental and sustainable
energy management policies and procedures. This guide is intended to provide some
direction to assessors who are determining competence of students who have
completed the theoretical and practical instruction in this learning module. Assessors
are expected to use their own judgement in designing appropriate assessment
questions and tasks and putting them into context for the assessment candidate. At all
times the evidence requirements as set out in the unit and the principles of assessment,
that is, validity, reliability, flexibility and fairness must be complied with.
Use these guidelines to assist in preparing your own assessment instruments and tools.
The checklist should be treated as a starting point. You may choose to add more
checkpoints to highlight particular aspects of knowledge and skill that you want to see
evidence of. This could be through practical tasks or problem-based questions.
Evidence Required
Evidence for competence in this unit shall be considered holistically. Each element
and associated Performance Criteria shall be demonstrated on at least two occasions in
accordance with the Assessment Guidelines UET06. Evidence must also reflect
the critical aspects of evidence which includes the following:
M
PL
SA
This assessment guide covers all tasks and equipment included in the section of the
Unit: Critical aspects for assessment and evidence required to demonstrate
competency in this unit, as shown in the table below.
The minimum number of items
on which skill is to be
demonstrated.
Item List
-2-