Anda di halaman 1dari 2

Civil Engineering Measurement Disputes

John B Molloy, LLB (Hons), BSc (Hons), FHKIS, FRICS, MCIArb, FInstCES, RPS (QS), Managing Director,
James R Knowles (Hong Kong) Limited

In building contracts, where Standard which is required for the works but
Methods of Measurement with mandatory which has not been measured in the Bills
rules are normal and quantity surveyors take of Quantities.
considerable (some would say too much)
time preparing accurate and detailed bills of Such claims are normally fairly clear cut
quantities, disputes concerning and valid, based upon the wording of
measurement matters are quite rare. General Conditions of Contract Clause
59(1):
In civil engineering contracts, however,
where the approach to bills of quantities has "Except where any statement in the Bills of
traditionally been somewhat more cavalier, Quantities expressly shows to the contrary
claims based upon measurement matters the Bills of Quantities shall be deemed to
have become more and more common, and have been prepared and measurements shall
are now, in my experience, one of the most be made according to the procedures set
common claims to be raised on civil forth in the Method of Measurement stated
engineering projects, particularly if the bills in the Preambles to the Bills of Quantities."
of quantities have been measured in
accordance with the Government of Hong with Standard Method of Measurement Part
Kong Standard Method of Measurement for II - General Principles paragraph 4:
Civil Engineering Works.
"Unless expressly stated otherwise in the
The Government of Hong Kong Standard Contract the Bills of Quantities are to
Method of Measurement for Civil contain all those items compounded in
Engineering Works was first issued in 1986 accordance with the foregoing paragraph 3
(and has since been republished twice with required to comprise the Works."
only minor modifications) and it replaced
the ICE Standard Method of Measurement and the case of A E Farr -v- Ministry of
1954 Edition which remarkably was still in Transport (1977) 5BLR 94, where it was
general use at that time. held that if the Standard Method of
Measurement required measurement of an
Claims deriving from this Standard Method item that formed part of the works, such an
of Measurement are principally that there item must be measured in the Bills of
are items omitted from or errors in Quantities.
description in the Bills of Quantities. These
claims, made under General Conditions of Secondly - where there is a specific item
Contract Clause 59(3): in the Standard Method of Measurement
which is required for the works and
"...The Engineer shall correct any such which has been measured in the Bills of
error or omission, shall ascertain the value Quantities, but is measured either with a
of the work actually carried out in different description or a different unit of
accordance with Clause 61, and shall measurement.
certify in accordance with Clause 79.
Again such claims are normally fairly clear
generally fall into three types. cut and valid, based upon the above
reasoning.
Firstly - where there is a specific item in
the Standard Method of Measurement
However, to counter this, it is sometimes saving the need to put items such as labour,
argued that the wording of the item in the plant and materials in each and every item
Bills of Quantities itself is clear and coverage.
amounts to an express statement that the
Bills of Quantities have not been measured What this means is that the general
in accordance with the Standard Method of preamble items do not stand alone, they can
Measurement. only be read in conjunction with the items in
the Standard Method of Measurement.
I do not consider such a counter argument is Therefore where works are required, but
valid because the Standard Method of there is no applicable item in the Standard
Measurement requires at General Preamble Method of Measurement, it is not possible
paragraph 9 that wherever methods of to allow for them by way of the General
measurement are adopted which are not in Preamble Items because there is no item in
accordance with the Standard Method of the Bills of Quantities to start with, i.e. no
Measurement such must be stated by way of item to read the general preambles in
a Particular Preamble, and not simply by conjunction with, with regard to the
measuring matters in a different manner in particular works concerned.
the Bills of Quantities.
Many of the problems which have arisen
Thirdly - where works are required but and which give rise to so many
there is no applicable item in the measurement claims have arisen because of
Standard Method of Measurement nor Government's choice of the 'item coverage'
are the works covered by an 'item system of Standard Method of Measurement.
coverage' of another item. If the item in the Standard Method of
Measurement simply said 'construct precast
This is the most difficult situation. It is concrete manhole 1000mm in diameter x
commonly argued by Engineers that the 2000mm deep as shown on drawing no....
contractor should have allowed for such then the contractor would have to allow for
items because the General Preamble all matters necessary to construct the
paragraph 2 provides, inter alia, that the manhole. However, once the item coverage
rates inserted in the Bills of Quantities shall system is adopted, and a list of all the items
be deemed to be the full inclusive value of which the contractor must allow for, e.g.
the work covered by the respective items concrete, formwork, reinforcement, etc, is
including the following: included, if something is omitted from the
list it automatically becomes an item
"x) liabilities, obligations, and risks omitted from the Bills of Quantities and a
involved in the execution of the Works set claim is formed.
forth or reasonably implied in the
Contract." Had the Government adopted the more
radical CESMM produced by the Institute of
I do not believe that this is correct. The Civil Engineers (as the KCRC have done for
General Preambles, paragraph 2 items (i) to their West Rail projects) rather than writing
(xi) provide a list of general items, including their own Standard Method of Measurement
the item above, and including such items as based upon the 'item coverage' system, then
labour, plant and materials. It is my many of the item omitted claims, which are
understanding that these are to be read as now so prevalent, would not arise.
being included in the item coverage for each
item in the Standard Method of (Adopted from the HKIS Newsletter 9(8) September
Measurement, and that the General 2000)
Preamble is simply a convenient way of

Anda mungkin juga menyukai