155.
Foundation Vol. = [ x (1.85 m / 2) + (2.0 m x 0.4 m) ] x 0.15 m 3 = 0.5 m 3.2 CONCRETE SLAB (Dosage 320 kg/m - 1:2:4) Slab Concrete = [ x 0.925 + (2.0 x 0.4) ] x 0.2 2 - [ x 0.825 + (2.1 x 0.2) ] x 0.1 3 = 0.43 m 3 3 Cement = 0.43 m x 320 kg/m = 138 kg (2 bags) 3 Sand = 0.43 m x 0.45 3 = 0.19 m 3 Gravel = 0.43 m x 0.9 3 = 0.39 m
2 3
For drainage canal, assume 6 mm reinforcement bars spaced every 10 cm both ways. Reinforcing Bar = ((2.5 m / 0.10 m) x 0.35 m) + (2.5 m x 3) = 16.25 m (1.5 bars) 3.3 PUMP PILLAR (Dosage 320 kg/m - 1:2:4) Pillar Concrete = 0.45 m x 0.45 m x 0.5 m 3 = 0.1 m 3 3 Cement = 0.1 m x 320 kg/m = 32 kg (2/3 bag) 3 Sand = 0.1 m x 0.45 3 = 0.05 m 3 Gravel = 0.1 m x 0.9 3 = 0.09 m
3
2.0 BILL OF QUANTITIES Item 1.0 1.1 1.2 1.3 1.4 2.0 2.1 2.2 3.0 3.1 Description Local Material Gravel Cement (50kg Sack) Sand Crushed Stone Ironwork Iron Reinforcement Bars 6mm x 12m Tying Wire 1mm Miscellaneous Items Used Engine Oil for Formwork liter 1 pc kg 1.5 0.25 m m m
3
Unit
Qty
sack
3 3
154.