Proposed Liquefied Natural Gas (LNG) Projects in Northern B.C.

Liquefied Natural Gas (LNG) Facilities


Name Status Partners Location Capacity billion cubic feet per day (Bcf/d) 0.09 - 0.24 In-service Date 2015 Peak Power Requirements 45 MW (Power currently available) 525 MW (Current transmission infrastructure sufficient) Unknown Tankers per year 3 Small: 130,000 m 3 Large: 260,000 m Small: 12 - 32 Large: 6 16 Name Status

Pipelines
Proponent Details Gas Source

Douglas Channel LNG

Kitimat LNG

EA: not required Export license: approved by NEB Take off agreements signed. EA: Complete under BC EA. Export license: approved by NEB No Take Off agreements EA: Pre-application under CEAA. Public comment on issues to be considered closed. Export license: application submitted. EA: Pre-application under BC EA. Public comment period on draft Application Information Requirements: Nov 13Dec 13, 2013 Export license: approved by NEB. EA: Pre-application under BC EA. Public comment period on draft Application Information Requirements: Nov 13Dec 13, 2013 Export license: application submitted. Proposed. Export license: application submitted. Responded to BC Govs EO. Export license: application submitted Responded to BC Govs EOI Responded to BC Govs EOI Responded to BC Govs EOI

BC LNG Export Cooperative Haisla Nation/LNG Partners Chevron/Apache 50/50 equity of LNG facility, pipeline,upstream production BG Group/Spectra Energy (50/50)

Kitimat Barge facility

Existing PNG pipeline

EA not required

Pacific Northern Gas

Existing - 0.115 Bcf/d, 10 diameter.

Bish Cove, Kitimat

0.75 -1.3

2016

Small: 99 176 Large: 50 - 80

Pacific Trails Pipeline

EA: Complete under BC EA.

Chevron/ Apache

36 diameter.462 km 1.4 Bcf/d Summit Lake to Kitimat via Morice R. 36- 48 diameter. 870 km. Up to 2 pipelines. Cypress to Ridley Is. via Babine and Nass Valleys. 48 Diameter .650 km. 1.7 5.0 Bcf/d Dawson Creek to Ktimat. Parallels PTP corridor except west of Burnie River.

Chevron/ Apaches holdings in Horn River and Liard Basin

Prince Rupert LNG

Ridley Island, Prince Rupert Kitimat

up to 4.2

2020

Small: 555 Large: 277

Westcoast Connector Gas Transmission Project Coastal GasLink Pipeline Ltd.

EA: Pre-Application under BC EA. Comment period on draft Application Information requirements closed. EA: Pre-Application under BC EA. Comment period on draft Application Information Requirements closed.

Spectra

LNG Canada Gas

Shell/PetroChina/ Mitsubishi/Kogas

1.7 - 3.2

2018

1200 MW (1.7 bcf/d) Requires a 500 kV line from PG to Terrace

Small: 225 425 Large: 112 - 213

TransCanada

Pacific Northwest LNG

Petronas/Japex (80/10)

Lelu Island, Port Edward

1.2 - 2.0

2018

Unknown

Small: 158 - 264 Large: 79 - 132

Prince Rupert Gas Transmission Project

EA: Pre-application. Screening to find out if federal EA required temporarily terminated on July 16, 2013.

TransCanada

48 diameter. Up to 900 km. Hudsons Hope to Lelu Island. Proceeding with South Central Alternative route.

Progresss holdings in North Montney plus other

Triton LNG LP

AltaGas Ltd/ Idemitsu Kosan Imperial Oil/ Exxon Mobil Nexen/Impex Woodside Petroleum SK E&S (Korea) TBA

Kitimat or Prince Rupert Grassy Point Grassy Point Grassy Point Grassy Point Kitsault

0.36

2017

Unknown

Small: 48 Large: 24 TBA

PNG Looping Project (twinning of existing line) TBA

EA: Pre-application under BC EA.

Pacific Northern Gas

0.6 Bcf/d, 24 diameter, 525 km. Summit Lake to Kitimat.

WCC LNG Ltd

TBA

20212023 TBA TBA TBA TBA

TBA

TBA TBA TBA Kitsault Energy

TBA TBA TBA TBA

TBA TBA TBA TBA

TBA TBA TBA TBA

TBA TBA TBA TBA

Updated: November 7, 2013