Snamprogetti Saudi Arabia Ltd.

Job 315900

KHURAIS Crude Contract (KCC)


00-ZA-E-02018, Attachment 1

Test Packs Flow Chart


SPDH SP
SP HOME OFFICE DEFINES PRESSURE TESTS CIRCUITS SPDH TECHNICAL OFFICE (Prepare TP Documents collecting in a folder all agreed eng. Documents i.e. marked P&ID, sketches with test limits line list etc.)
If A PL Items

SA

Certificates

PIPING DEPT - TUB (Check Documents)

SPDH Release for check after Mechanical Completion of the TP

If no A PL Items

SP MECH DS (Mech. Check)

Notification TP Ready for Review

SP TUB (Mech/Eng. Check)

SP COM (Pre-COM Check)


If A PL Items (Line not mechanically Completed)

If no A PL Items

SP QCS (QCS & WI verify QC Documents / NDT Reports)

SA to include PL Items if any and Accept or Reject the TP

SPDH (Clean PL Issue by SP/SA)

If A PL Items

SPDH (Issue the RFI for Pressure Test)

If no A PL Items (Notification Ready for test)

QCS (Verification issue of Flushing / Blowing Report T.C. PC12.1)

SA (Sign RFI)

If A PL Items

SPDH (Execution of Pressure Test)

If no A PL Items

If A PL Items

MDT.TB.CDQ. 0112/SATR-A2008 If no A PL Items

SPDH (Reinstate the Line)

QCS Check Reinstatement ( B Items Signed off )

SA (Final Acceptance Line Reinstatement)

If B PL Items

If no B PL

If B PL Items

If no B PL The reports for reinstatement is sign

MDT.TB.CDQ. 0114/SATR-A2007

End Of Process Remarks : A)- For Each Transmission of Document , Site Transmittal shall be done and managed by HTC B)- HTC. Is responsible foro the Updating of the "TED FLOW" SOFTWARE for each movement of the TP, he is also the responsible for the followup of the TP to avoid any delay in the clearance by each Department (example 10 days with COM or TUB , or 1 week with WI, etc.) Legend : Decision Process
205452142.xls.ms_office 1/1 1/21/2014