Task Name Construction of Three-Storey Office Building Mobilize on Site Install temporary power Install temporary water service Set up site office Set line and grade benchmarks Prepare site - lay down yard and temporary fencing Site Grading and Utilities Clear and grub site Stone site access and temporary parking area Rough grade site (cut and fill) Install storm drainage Install exterior fire line and building fire riser Perform final site grading Erect building batter boards and layout building Foundations Excavate foundations Excavate elevator pit Form column piers and spread foundations Rough-in electric and plumbing in elevator Form elevator pit walls Set reinforcing and anchor bolts Pour column piers and foundations Pour concrete elevator walls Cure elevator wall concrete Cure piers and foundations Strip wall forms Strip column piers and foundation forms Install pneumatic tube in elevator pit Prepare and pour concrete floor in elevator pit Steel Erection Erect steel columns, beams and joist - 1st and 2nd floors Erect steel columns, beams and joist - 3rd floor and roof Install miscellaneous iron and bracing - 1st and 2nd floors Install miscellaneous iron and bracing - 3rd floor and roof Install stairs and miscellaneous iron railing Task Critical Task
Duration 383 days 10 days 2 days 2 days 3 days 3 days 2 days 41 days 3 days 2 days 1 wk 2 wks 2 wks 2 wks 1 wk 35 days 2 wks 2 days 4 days 4 days 4 days 4 days 5 days 1 day 7 days 7 days 1 day 3 days 3 days 1 day 54 days 2 wks 2 wks 2 wks 2 wks 2 wks Rolled Up Task
Start Mon 4/1/13 Mon 4/1/13 Mon 4/1/13 Mon 4/1/13 Wed 4/3/13 Sat 4/6/13 Wed 4/10/13 Fri 4/12/13 Fri 4/12/13 Tue 4/16/13 Thu 4/18/13 Thu 4/25/13 Thu 4/25/13 Thu 5/9/13 Thu 5/23/13 Thu 5/23/13 Thu 5/23/13 Thu 5/23/13 Thu 6/6/13 Sat 5/25/13 Thu 5/30/13 Tue 6/11/13 Sat 6/15/13 Tue 6/4/13 Wed 6/5/13 Fri 6/21/13 Thu 6/13/13 Sat 6/29/13 Fri 6/14/13 Tue 6/18/13 Wed 7/3/13 Wed 7/3/13 Wed 7/17/13 Wed 7/17/13 Wed 7/31/13 Wed 8/14/13
Finish
W T F S Fri 6/20/14 Thu 4/11/13 Install temporary power Tue 4/2/13 Tue 4/2/13 Install temporary water service Set up site office Fri 4/5/13 Set line and grade benchmarks Tue 4/9/13 Prepare site - lay down yard and tempo Thu 4/11/13 Wed 5/29/13 Mon 4/15/13 Stone site Wed 4/17/13 Wed 4/24/13 Wed 5/8/13 Wed 5/8/13 Wed 5/22/13 Wed 5/29/13 Tue 7/2/13 Wed 6/5/13 Fri 5/24/13 Mon 6/10/13 Wed 5/29/13 Mon 6/3/13 Fri 6/14/13 Thu 6/20/13 Tue 6/4/13 Wed 6/12/13 Fri 6/28/13 Thu 6/13/13 Tue 7/2/13 Mon 6/17/13 Tue 6/18/13 Tue 9/3/13 Tue 7/16/13 Tue 7/30/13 Tue 7/30/13 Tue 8/13/13 Tue 8/27/13 External Tasks Project Summary Group By Summary Deadline
ID 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72
Task Name
Duration
Start
Finish
Touch-up paint on steel 1 wk Form and Pour Concrete - Floors and Roof 80 days Form 2nd floor including all floor openings 5 days Install rebar and in-floor utilities (inc mechl, elect, plumbing) 5 days Pour 2nd floor slab 4 days Cure 2nd floor slab 7 days Strip forms from 2nd floor slab 2 days Form 3rd floor including all floor openings 5 days Install rebar and in-floor utilities (including mechanical, electrical, plumbing) 5 days Pour 3rd floor slab 4 days Cure 3rd floor slab 7 days Strip forms from 3rd floor slab 2 days Form roof slab including all floor openings 5 days Install rebar and in-floor utilities (including mechanical, electrical, plumbing) 5 days Pour roof slab 4 days Cure roof slab 7 days Strip forms from roof slab 2 days Form 1st floor 4 days Install electrical underground 1 wk Install plumbing underground 1 wk Install rebar and in-floor utilities 4 days Pour 1st floor slab 4 days Cure 1st floor slab 7 days Strip forms from 1st floor slab 2 days Carpentry Work 18 days Install exterior sheathing and metal studs 3 wks Masonry Work 122 days Rough-in plumbing at toilets and masonry walls 4 wks Lay masonry at core, mechanical, and toilets 4 wks Install exterior masonry work 5 wks Install roof drains 2 days Install tile in toilet rooms 2 wks Clean masonry 1 wk Clean toilet room tile 1 wk Roofing 33 days Install flashing at parapet walls 4 days Task Critical Task
Wed 8/28/13 Tue 9/3/13 Wed 7/31/13 Thu 10/31/13 Wed 9/4/13 Mon 9/9/13 Wed 7/31/13 Mon 8/5/13 Tue 9/10/13 Fri 9/13/13 Sat 9/14/13 Sat 9/21/13 Mon 9/23/13 Tue 9/24/13 Mon 9/23/13 Fri 9/27/13 Mon 9/23/13 Fri 9/27/13 Sat 9/28/13 Wed 10/2/13 Thu 10/3/13 Thu 10/10/13 Fri 10/11/13 Sat 10/12/13 Fri 10/11/13 Wed 10/16/13 Fri 10/11/13 Wed 10/16/13 Thu 10/17/13 Mon 10/21/13 Tue 10/22/13 Tue 10/29/13 Wed 10/30/13 Thu 10/31/13 Wed 9/25/13 Sat 9/28/13 Wed 9/25/13 Tue 10/1/13 Wed 9/25/13 Tue 10/1/13 Wed 9/25/13 Sat 9/28/13 Thu 10/17/13 Mon 10/21/13 Tue 10/22/13 Tue 10/29/13 Wed 10/30/13 Thu 10/31/13 Fri 11/1/13 Thu 11/21/13 Fri 11/1/13 Thu 11/21/13 Wed 8/14/13 Thu 1/2/14 Fri 11/1/13 Thu 11/28/13 Wed 8/14/13 Tue 9/10/13 Fri 11/22/13 Thu 12/26/13 Fri 12/27/13 Sat 12/28/13 Fri 11/29/13 Thu 12/12/13 Fri 12/27/13 Thu 1/2/14 Fri 12/13/13 Thu 12/19/13 Fri 12/27/13 Mon 2/3/14 Fri 12/27/13 Tue 12/31/13 External Tasks Project Summary Group By Summary Deadline
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 2
Task Name Pour lightweight concrete roof fill Install seamless roofing material Spread stone ballast on seamless roof Set rooftop equipment Window wall and store front closures Install window wall aluminum and glass Install interior stud walls and drywall Install interior doors and hardware Install store front doors and hardware Building Finishes Install millwork and wood trim Paint walls and woodwork Install conduit at ceiling plenum space Install duct in ceiling plenum space Install ceiling grid Install ceiling tile Hang wallpaper Install building carpet Install hardware and accessories Complete interior and exterior sod and plantings Pave, curb, and stripe parking lot Elevators Set elevator equipment in shafts Set equipment in mechanical room Test and align doors and equipment Plumbing Rough-in plumbing in drywall walls Tie-in fire line riser and set valves Set plumbing fixtures and trim Flush, test, and clean piping and fixtures Electrical Rough-in electrical in masonry walls Rough-in electrical in drywall walls Pull wire in conduit and set area transformers Install and terminate electrical devices Make electrical terminations for HVAC equipment Task Critical Task
Duration 2 days 5 days 5 days 2 wks 72 days 5 wks 5 wks 2 wks 3 wks 96 days 3 wks 4 wks 3 wks 3 wks 2 wks 2 wks 2 wks 4 wks 3 wks 2 wks 2 wks 48 days 4 wks 2 wks 2 wks 108 days 4 wks 2 wks 3 wks 2 wks 150 days 4 wks 4 wks 3 wks 3 wks 2 days
Start Wed 1/1/14 Thu 1/9/14 Wed 1/15/14 Tue 1/21/14 Fri 12/27/13 Fri 12/27/13 Fri 1/31/14 Fri 3/7/14 Fri 12/27/13 Fri 1/31/14 Fri 3/7/14 Fri 3/28/14 Fri 1/31/14 Fri 3/7/14 Fri 3/28/14 Fri 4/11/14 Fri 4/11/14 Fri 4/25/14 Fri 4/25/14 Fri 4/25/14 Fri 5/9/14 Wed 9/11/13 Wed 9/11/13 Wed 10/9/13 Wed 10/23/13 Fri 1/3/14 Fri 1/31/14 Fri 1/3/14 Fri 2/28/14 Fri 4/25/14 Fri 11/1/13 Fri 11/1/13 Fri 1/31/14 Fri 2/21/14 Fri 3/14/14 Fri 3/14/14
Finish Thu 1/2/14 Tue 1/14/14 Mon 1/20/14 Mon 2/3/14 Thu 3/20/14 Thu 1/30/14 Thu 3/6/14 Thu 3/20/14 Thu 1/16/14 Thu 5/22/14 Thu 3/27/14 Thu 4/24/14 Thu 2/20/14 Thu 3/27/14 Thu 4/10/14 Thu 4/24/14 Thu 4/24/14 Thu 5/22/14 Thu 5/15/14 Thu 5/8/14 Thu 5/22/14 Tue 11/5/13 Tue 10/8/13 Tue 10/22/13 Tue 11/5/13 Thu 5/8/14 Thu 2/27/14 Thu 1/16/14 Thu 3/20/14 Thu 5/8/14 Thu 4/24/14 Thu 11/28/13 Thu 2/27/14 Thu 3/13/14 Thu 4/3/14 Sat 3/15/14
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 3
ID 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129
Task Name Install light fixtures - test and clean Heating and Ventilating - AC Set equipment in mechanical room Rough-in mechanical in masonry walls Rough-in mechanical in drywall walls Install duct in building chase Set HVAC trim and test and balance system Final Clean-up and Occupancy Install hard tile flooring in common areas Clean hard tile floors Remove debris from building and do final clean-up Substantial completion date Complete Final Inspections Complete elevator inspection and certification Perform architect's inspection Perform local building agency inspection Perform Fire Marshal's inspection Complete punch list items from all inspections Obtain certificate of occupancy Issue final completion documents including warranties Issue final request for payment
Duration 2 wks 206 days 2 wks 4 wks 2 wks 3 wks 4 wks 71 days 1 wk 4 days 4 days 1 day 21 days 3 days 1 day 1 day 1 day 2 wks 2 days 1 day 1 day
Start Fri 4/11/14 Wed 9/11/13 Wed 9/11/13 Fri 11/1/13 Fri 1/31/14 Fri 1/31/14 Fri 4/11/14 Fri 3/7/14 Fri 3/7/14 Fri 3/14/14 Fri 5/23/14 Wed 5/28/14 Wed 5/28/14 Wed 5/28/14 Sat 5/31/14 Mon 6/2/14 Tue 6/3/14 Wed 6/4/14 Wed 6/18/14 Wed 6/18/14 Fri 6/20/14
Finish Thu 4/24/14 Thu 5/8/14 Tue 9/24/13 Thu 11/28/13 Thu 2/13/14 Thu 2/20/14 Thu 5/8/14 Wed 5/28/14 Thu 3/13/14 Tue 3/18/14 Tue 5/27/14 Wed 5/28/14 Fri 6/20/14 Fri 5/30/14 Sat 5/31/14 Mon 6/2/14 Tue 6/3/14 Tue 6/17/14 Thu 6/19/14 Wed 6/18/14 Fri 6/20/14
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 4
Apr 7, '13 S M T
May 5, '13 S M T
orary fencing Clear and grub site e access and temporary parking area Rough grade site (cut and fill) Install storm drainage Install exterior fire line and building fire riser Perform final site grading Erect building batter boards and layout build Excavate foundatio Excavate elevator Rough-in electric and plumbing
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 5
Apr 7, '13 S M T
May 5, '13 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 6
Apr 7, '13 S M T
May 5, '13 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 7
Apr 7, '13 S M T
May 5, '13 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 8
Jun 2, '13 S M T
Jun 9, '13 S M T
lding ions r pit Form column piers and spread foundations g in elevator Form elevator pit walls Set reinforcing and anchor bolts Pour column piers and foundations Pour concrete elevator walls Cure elevator wall concrete Cure piers and foundations Strip wall forms Strip column piers and foundation forms Install pneumatic tube in elevator pit Prepare and pour concrete floor in elevator pit Erect steel columns, beams and joist - 1st and 2nd floors Erect steel c Install miscell
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 9
Jun 2, '13 S M T
Jun 9, '13 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 10
Jun 2, '13 S M T
Jun 9, '13 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 11
Jun 2, '13 S M T
Jun 9, '13 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 12
Jul 7, '13 S M T
Aug 4, '13 S M T
columns, beams and joist - 3rd floor and roof llaneous iron and bracing - 1st and 2nd floors Install miscellaneous iron and bracing - 3rd floor and roof Install stairs and miscellaneous iron railing Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 13 External Tasks Project Summary Group By Summary Deadline
Jul 7, '13 S M T
Aug 4, '13 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 14
Jul 7, '13 S M T
Aug 4, '13 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 15
Jul 7, '13 S M T
Aug 4, '13 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 16
'13 T
Sep 1, '13 S M T
Sep 8, '13 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 17
'13 T
Sep 1, '13 S M T
Sep 8, '13 S M T
Form 2nd floor including all floor openings Pour 2nd floor slab Cure 2nd floor slab Strip forms from 2nd floor slab Form 3rd floor including all floor openings Install rebar and in-floor utilities (including mechanical, electrical, plumbing) Pour 3rd floor slab Cure 3rd floor slab Stri Form roof slab i Install rebar and in-floor utilities (including mec
Form 1st floor Install electrical underground Install plumbing underground Install rebar and in-floor utilities
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 18
'13 T
Sep 1, '13 S M T
Sep 8, '13 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 19
'13 T
Sep 1, '13 S M T
Sep 8, '13 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 20
Oct 6, '13 S M T
Nov 3, '13 S M T
Nov S
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 21
Oct 6, '13 S M T
Nov 3, '13 S M T
Nov S
trip forms from 3rd floor slab b including all floor openings chanical, electrical, plumbing) Pour roof slab Cure roof slab Strip forms from roof slab
Pour 1st floor slab Cure 1st floor slab Strip forms from 1st floor slab Install exterior sheathing and metal studs Rough-in plumbing at toilets and masonry walls Install exterior
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 22
Oct 6, '13 S M T
Nov 3, '13 S M T
Nov S
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 23
Oct 6, '13 S M T
Nov 3, '13 S M T
Nov S
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 24
17, '13 M T
Dec 1, '13 S M T
Dec 8, '13 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 25
17, '13 M T
Dec 1, '13 S M T
Dec 8, '13 S M T
or masonry work Install roof drains Install tile in toilet rooms Clean masonry Clean toilet room tile Install flashing at parapet walls Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 26 External Tasks Project Summary Group By Summary Deadline
17, '13 M T
Dec 1, '13 S M T
Dec 8, '13 S M T
Dec 22, '13 Dec 29, '13 S M T W T F S S M T Pour lightweight concrete roof fill
W Instal
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 27
17, '13 M T
Dec 1, '13 S M T
Dec 8, '13 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 28
Jan 5, '14 S M T
Feb 2, '14 S M T
Feb 9, '14 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 29
Jan 5, '14 S M T
Feb 2, '14 S M T
Feb 9, '14 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 30
Jan 5, '14 S M T
Feb 2, '14 S M T
Feb 9, '14 S M T
all seamless roofing material Spread stone ballast on seamless roof Set rooftop equipment
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 31
Jan 5, '14 S M T
Feb 2, '14 S M T
Feb 9, '14 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 32
Mar 2, '14 S M T
Mar 9, '14 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 33
Mar 2, '14 S M T
Mar 9, '14 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 34
Mar 2, '14 S M T
Mar 9, '14 S M T
Install millwork and wood trim Paint walls and woodwork Install duct in ceiling plenum space Install ceiling grid
set area transformers Install and terminate electrical devices Make electrical terminations for HVAC equipment Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 35 External Tasks Project Summary Group By Summary Deadline
Mar 2, '14 S M T
Mar 9, '14 S M T
Set HVA Install hard tile flooring in common areas Clean hard tile floors
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 36
Apr 6, '14 S M T
May 4, '14 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 37
Apr 6, '14 S M T
May 4, '14 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 38
Apr 6, '14 S M T
May 4, '14 S M T
Install ceiling tile Hang wallpaper Install building carpet Install hardware and accessories Complete interior and exterior sod and plantings Pave, curb, and stripe parking lot
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 39
May 4, '14 S M T
Co
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 40
Jun 1, '14 S M T
Jun 8, '14 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 41
Jun 1, '14 S M T
Jun 8, '14 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 42
Jun 1, '14 S M T
Jun 8, '14 S M T
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 43
Jun 1, '14 S M T
Jun 8, '14 S M T
ing and do final clean-up Substantial completion date omplete elevator inspection and certification Perform architect's inspection Perform local building agency inspection Perform Fire Marshal's inspection Complete punch list items from all inspections Obtain certificate of occupancy Issue final completion documents including warranties Issue final request for payment
Task Critical Task Project: Project 5 CONSTRUCTION O Date: Mon 8/5/13 Progress Milestone Summary
Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split Page 44