8 MGD Seawater Desalination Project Tender Enquiry Document for 110 kV Switchyard

SECTION B1.1 EHV CIRCUIT BREAKERS

1.0.0 1.1.0 1.2.0

EQUIPMENT TO BE SUPPLIED 110 kV 1250 Amp, 40 kA for 3 sec, SF6 puffer type circuit breaker shall be provided. Specific requirement a) Tie beams between foundations of breakers of different phases are recommended, since additional load in the form of vibration may be transferred to the foundations during closing / opening operation. Design of circuit breaker shall be such that contacts shall not close automatically upon loss of gas/air pressure. SF6 breakers shall be provided with temperature compensated SF6 density switch with separate trip, alarm and blocking contacts. D.C circuits for two trip coils shall be separate and each of them shall be monitored. Manually operated energy tripping push button or any other device conveniently located for mechanical tripping of all the three phases simultaneously shall be provided. SF6 topping up kit along with SF6 bottles having at least 10% capacity of the Total SF6 gas in 5 nos. SF6 breakers.

b) c) d) e)

f) 1.3.0

Technical Requirements The circuit breakers shall comply with requirements in the following table :

-----------------------------------------------------------------------------------------------------------------------Sl.No Description Requirements -----------------------------------------------------------------------------------------------------------------------1. 2. 3. 4. 5. Quantity Type Execution of poles Nominal / highest system voltage Rated current 5 nos. (As per SLD) SF6 outdoor 3 nos. single pole, gang operated with trip free mechanism. 110 kV / 123 kV 1250 Amps

P2Sec B1-Swyd

FICHTNER India

Doc. No.6104-EL-SPC-610-001 Rev. : R0 Page : B1 : 4

5.8 MGD Seawater Desalination Project Tender Enquiry Document for 110 kV Switchyard

-----------------------------------------------------------------------------------------------------------------------Sl.No Description Requirements -----------------------------------------------------------------------------------------------------------------------6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. Short circuit breaking current & duration Making current Operating duty First pole clear factor Impulse with stand voltage One minute power frequency withstand voltage Line charging current breaking Cable charging current breaking Small inductive current breaking Over voltage factor while switching off above current Type of operating mechanism Operating mechanism to be suitable Control voltage No. of trip coils per pole No.of aux. contacts Environment at the location of installation Reference ambient temperature SF6 gas filling plant Gas evacuation & filling unit 40 kA for 3 sec. 100 kAp O - 0.3 sec CO - 3 min - CO 1.3 550 KVp 230 kV (rms) As per IEC-56 As per IEC-56 To switch the associated transformers magnetising currents. Not more than 2.3 p.u. Stand alone pneumatic mechanism 3 phase 415 / 1 phase 240V operation 110V DC, +10%, -15% 2 nos. 10 NO+10NC (min) Heavily polluted saline and dusty 50C Required no. of gas cylinder to be provided required

P2Sec B1-Swyd

FICHTNER India

Doc. No.6104-EL-SPC-610-001 Rev. : R0 Page : B1 : 5

5.8 MGD Seawater Desalination Project Tender Enquiry Document for 110 kV Switchyard

-----------------------------------------------------------------------------------------------------------------------Sl.No Description Requirements -----------------------------------------------------------------------------------------------------------------------25. 26. 27. Gas reprocessing &filling unit Cantilever strength Creepage distance a) b) 28. 29. 30. for support insulator for interrupt insulator 3800 mm 3800 mm 60 m.sec 100.m.sec Control cubicle Outdoor, weather & vermin proof, sheet steel (3mm thick)clad with hinged type front door with locking device, housing operating mechanism, other controls / selection such as local-remote selector switch, close-normal-trip control switch, thermostat controlled space heater with ON-OFF switch, all aux. contacts wired up to terminal block with 20% spare terminals shall be provided. Support structures Hot dip galvanised supporting steel structures specifically designed for breaker mounting shall be supplied. Each equipment shall be provided with 2 Nos. grounding pad with 2 Nos M10 bolts. not required 800 Kg

Total break time (max) Total make time(max)

31

32. 33. 33.1 33.2 33.3 33.4 33.5 33.6

Earthing pads Applicable Standards Circuit breakers Insulators Large hollow porcelain Clamps and connectors Hop dip galvanising Spec. and acceptance sulphur hexafluride (SF6)

IEC-56 IS:2544 IS:5621 IS:617 IS:2629 & IS:2633 IEC:376

P2Sec B1-Swyd

FICHTNER India

Doc. No.6104-EL-SPC-610-001 Rev. : R0 Page : B1 : 6

5.8 MGD Seawater Desalination Project Tender Enquiry Document for 110 kV Switchyard

2.0.0 2.1.0 2.1.1 2.1.2

TESTS Shop testing. Each circuit breaker and accessories shall be subjected to routine tests as laid down in relevant standard. Each circuit breaker along with base frame and operating mechanism shall be completely assembled and checked at manufacturer's works for correct alignment and operation before despatch. DRAWING, DATA AND MANUALS Along with the Bid Following drawings, data and details shall be furnished with the bid: a. b. c. d. e. General arrangement drawings of circuit breaker showing constructional feature and also disposition of various fittings. Completely filled in sheets of Technical schedules. Technical leaflets on EHV circuit breakers offered explaining the function of various parts, principle of operation and special features. Type test report and typical routine test report of identical circuit breakers as offered in bid. A list of manufacturing and supply record of identical circuit breaker as offered.

3.0.0 3.1.0 3.1.1

3.2.0

After award of contract The contractor shall submit four (4) copies of the following drawings / data for Purchaser's approval : a. b. c. d. e. f. g. i. General arrangement drawing. Transport dimension with weight The foundation and anchor bolt details for all equipment including dead load and impact load with direction. Drawing and data sheets for each piece of equipment. Complete control schematics and electrical inter-connecting diagrams. Assembly drawing for erection at site with part numbers and schedule of materials. Maintenance manual for individual equipment Any other relevant data, drawings and information necessary for review of the equipment and also erection, operation and maintenance.

P2Sec B1-Swyd

FICHTNER India

Doc. No.6104-EL-SPC-610-001 Rev. : R0 Page : B1 : 7