BADER AL MULLA & BROS. CO. W.L.L.

VARIATION SUMMARY
PROJECT: AL BASSAM OFFICE TOWER AT TECOM
DISCIPLINE: ELECTRICAL
Submitted Agreed BMB
Variatio OH&P(10% TotalCost TEC
S.No. Description Value By Value Corresponden Status Remarks
n Ref. ) (AED) Correspondence
BMB (AED) (AED) ce

on discussion with
1 V-EL-01 GSM Cable Laying 149,176.00 0.00 BMB/TEC/PJ/232TEC/P289/WHB/1565-09
consultant

on discussion with
2 V-EL-02 GSM DU Cable Containment 136,255.00 0.00 BMB/TEC/PJ/232TEC/P289/WHB/1565-09
consultant

3 V-EL-03 External Lighting (Facade) 159,622.00 130,522.72 13,052.27 ### BMB/TEC/PJ/408 Accepted

TEC/P289/WHB/2235-
BMB/TEC/PJ/301
09, on discussion with
4 V-EL-04 Structured Cabling 563,385.00 0.00 ,
TEC/P289/WHB/2393- consultant
BMB/TEC/PJ/364
09
TEC/P289/WHB/2392-
09,
5 V-EL-05 Fire Alarm 233,788.07 159,090.90 15,909.09 ### BMB/TEC/PJ/358 Accepted
TEC/P289/WHB/2468-
09
TEC/P289/WHB/2392-
09,
6 V-EL-06 Central Battery System 530,263.00 381,044.54 38,104.45 ### BMB/TEC/PJ/334 Accepted
TEC/P289/WHB/2468-
09
on discussion with
7 V-EL-08 LV Switch Gear 132,828.17 BMB/TEC/PJ/539
consultant

Additional Power Supply as


8 V-EL-09 41,748.00 41,946.36 4,194.64 46,141.00 BMB/TEC/PJ/369 Accepted
per Du comments

9 V-EL-10 Garbage Chute 25,011.00 23,593.64 2,359.36 25,953.00 BMB/TEC/PJ/409 Accepted

10 V-EL-11 Civil Defence Control Panel 39,298.00 34,352.73 3,435.27 37,788.00 BMB/TEC/PJ/441 Accepted

BMB/TEC/PJ/456
Containment for Intelligent on discussion with
11 V-EL-13 22,994.00 0.00 ,
Metering System consultant
BMB/TEC/PJ/514

Additional light points for on discussion with


12 V-EL-14 34,130.00 0.00 BMB/TEC/PJ/544
ground floor consultant

Cable tray Containment on discussion with


13 V-EL-15 2,086.00 0.00 BMB/TEC/PJ/540
CCTV consultant
Electrical Provisions in on discussion with
14 V-EL-16 24,675.00 0.00 BMB/TEC/PJ/542
Podium Toilets consultant

TOTAL ### ###


BADER AL MULLA & BROS. CO. W.L.L.
VARIATION SUMMARY

PROJECT: AL BASSAM OFFICE TOWER AT TECOM


DISCIPLINE: HVAC
Submitted Agreed BMB
Variation OH&P(10 TotalCost TEC
S.No. Description Value By Value Corresponde Status Remarks
Ref. %) (AED) Correspondence
BMB (AED) (AED) nce

On discussion with
1 V-HVAC-01 Rise pipe configuration 103,400.00 BMB/TEC/PJ/400TEC/P289/CHN/2577-09
consultant

On discussion with
2 V-HVAC-02 Valves across PHE 92,950.00 BMB/TEC/PJ/322
consultant

Additional Diffusers & On discussion with


3 V-HVAC-03 15,530.24 BMB/TEC/PJ/537
Grills consultant

211,880.24
BADER AL MULLA & BROS. CO. W.L.L.
VARIATION SUMMARY

PROJECT: AL BASSAM OFFICE TOWER AT TECOM


DISCIPLINE: PLUMBING
Submitted Agreed BMB
Variation OH&P(10 TotalCos TEC
S.No. Description Value By Value Corresponden Status Remarks
Ref. %) t (AED) Correspondence
BMB (AED) (AED) ce
Extra requirement BMB/TEC/PJ/267
1 V-P-01 of water supply 234,238.87 ### 19,067.27 ### , TEC/P289/CHN/1723-09 Accepted
pipes BMB/TEC/PJ/133

234,238.87 ###
BADER AL MULLA & BROS. CO. W.L.L.
VARIATION SUMMARY

PROJECT: AL BASSAM OFFICE TOWER AT TECOM


DISCIPLINE: FIREFIGHTING
Submitted Agreed Total
Variatio OH&P(10% BMB TEC
S.No. Description Value By Value Cost Status Remarks
n Ref. ) Correspondence Correspondence
BMB (AED) (AED) (AED)
TEC/P289/WHB/2392-
BMB/TEC/PJ/331,
09,
1 V-FF-01 Fire Pump 133,125.00 104,500.00 10,450.00 ### BMB/TEC/PJ/307, Accepted
TEC/P289/WHB/2044-
BMB/TEC/PJ/160
09
TEC/P289/WHB/2392-
09,
2 V-FF-02 Fire Fighting Accessories 727,210.00 373,870.90 37,387.09 ### BMB/TEC/PJ/353 Accepted
TEC/P289/WHB/2468-
09
TEC/P289/WHB/2392-
09,
3 V-FF-03 FM 200 System 328,750.00 289,300.00 28,930.00 ### BMB/TEC/PJ/323 Accepted
TEC/P289/WHB/2468-
09

4 V-FF-04 Pre Action System 79,375.00 69,850.00 6,985.00 76,835.00 BMB/TEC/PJ/363 Accepted

TEC/P289/WHB/2392-
Diesel Engine Exhaust
09, on discussion
5 V-FF-05 Piping, Insulation & 45,702.88 952.72 95.27 1,047.99 BMB/TEC/PJ/333
TEC/P289/CHN/2588- with consultant
Cladding
09
Additional Firefighting
6 V-FF-07 541,973.00 140,909.09 14,090.91 ### BMB/TEC/PJ/360 TEC/P289/WHB/2392-09 Accepted
Works

### ###
BADER AL MULLA & BROS. CO. W.L.L.
VARIATION SUMMARY

PROJECT: AL BASSAM OFFICE TOWER AT TECOM


DISCIPLINE: DRAINAGE
Submitted Agreed
Variation OH&P(10 Total Cost BMB
S.No. Description Value By Value TEC Correspondence Status Remarks
Ref. %) (AED) Correspondence
BMB (AED) (AED)
TEC/P289/WHB/2392-
09,
1 V-DR-05Rain Water Outlet - Roof Floor 1,100.00 952.72 95.27 1,047.99 BMB/TEC/PJ/305 Accepted
TEC/P289/KHA/1586-
09
TEC/P289/WHB/2392-
09,
2 V-DR-06 Car Park Gulley 4,162.50 3,146.36 314.64 3,461.00 BMB/TEC/PJ/304 Accepted
TEC/P289/WHB/2045-
09
TEC/P289/WHB/2392-
09,
3 V-DR-07Manhole Cover - Ground Floor 3,407.50 2,989.09 298.91 3,287.99 BMB/TEC/PJ/306 Accepted
TEC/P289/WHB/2043-
09
Floor Drain Cover - TEC/P289/WHB/2392-
4 V-DR-08 1,050.00 1,168.18 116.82 1,285.00 BMB/TEC/PJ/302 Accepted
Swimming Pool 09

Additional Rain Water TEC/P289/WHB/2392-


5 V-DR-09 1,948.00 1,800.00 180.00 1,980.00 BMB/TEC/PJ/303 Accepted
Outlet - 23rd Floor 09

11,668.00 10,056.34