PT NUSAKURA STANDARINDO

API SPEC.4E & 4F : Specification for drilling & well structure API RP. 8B : Recommended Practice for hoisting tool Inspection & Maintenance Procedures API SPEC. 9A : Specification for Wire Rope API SPEC. 9B : Recommended practice on application, case & use of wire rope for oil field service.

API RP 7L : Procedure for Inspection, Maintenance repair and remanufacture of Drilling Equipment API RP 14 G : Fire prevention & control on open type offshore production platforms API RP 53 : Recommended practice for Blowout Prevention Equipment System for Drilling Wells. 13 API RP : Occupational Safety for Oil and Gas Well Drilling and Service Operations

Company provided Surat Permohonan Penunjukkan PT Nusakura Standarindo as PJIT to Migas. Migas issue Surat Persetujuan Penunjukkan PJIT. PT Nusakura Standarindo begin to inspect. Company provide inviting letter to migas for witness load testing. Report ( Data SILO Required next slide). Submit document to migas. (Company provide surat permohonan SILO)
note : flow chart 1 & flow chart 2

Drilling line certificate. BOP certificate and pressure test chart. (3 years validity) Weight indicator calibration certificate. (1 year validity) HSE / safety management program. Standard operating procedure. Maintenance program and record. Rig manual & specification. Load test / performance test report. Engineering calculation. Crew certificate. NDT report. Visual inspection report. Documentation. Corrective action. ( if any ) list silo

SOP No.: NS 007 CHECK LIST ITP

Rig Structural Hoisting Equipment Circulating System Generating and Electrical system Safety Equipment BOP Equipment System Engine / Prime Mover

Documentation Review Physical Field Inspection Load / Performance Test Reporting

According to SILO Data Required Fabrication Data : material certificate, welding procedure, welder certificate, NDT procedure and report, load testing report and engineering calculation. Manual Data Book Drawing Equipment list of unit Rig

Visual Inspection : This involves all the equipments such us mast and substructure, draw work & wire rope, BOP system, mud system, engine and generator, safety equipments, hoisting tools, fuel tank and others.

Non Destructive Testing (NDT) : Review NDT report, performed on mast, substructure, drawwork, BOP system, stand pipe, hoisting tools, crown block, traveling block etc.

Performance Test : After finish inspection, rig shall be given an operational or performance test to ensure that rig are fit for operations. This test shall be witness by MIGAS.

procedure

Load Test : The purpose of load test to verify that structure and other components are fit for operations. Also to measure the strain on structure being loaded using the strain gauge. Load test shall be performed on new rig / record of load test from manufacturer is not available or after the mayor repair. This test will be witness by MIGAS
procedure load test

Executive Summary of Inspection result Project Description Scope of Work References Methodology General Design Code Executions Summary Conclusion Non Conformance Records (if any) NS Certificate of Inspection