REKAPITULASI RENCANA ANGGARAN BIAYA

PEKERJAAN
LOKASI
TAHUN ANGGARAN

NO
A

: PEMBANGUNAN PANTI ASUHAN &GEDUNG PENDIDIKAN BIMA BHAKTI (AL MUJIIB)


TAHAP I &II
: PONDOK SURUH BIMOMARTANI NGEMPLAK SLEMAN
: 2010

URAIAN PEKERJAAN

JUMLAH

PANTI ASUHAN &RUMAH PENGELOLA TAHAP I

I
II
III
IV
V
VI
VII
VIII
IX

PEKERJAAN PERSIAPAN PELKSANA


PEKERJAAN TANAH &PASIR
PEKERJAAN PASANGAN &PLESTERAN
PEKERJAAN LANTAI &KERAMIK
PEKERJAAN BETON
PEKERJAAN INSTALASI LISTRIK
PEKERJAAN INSTALASI AIR
PEKERJAAN ATAP & PINTU JENDELA
PEKERJAAN CAT
JUMLAH A (PANTI ASUHAN &RUMAH PENGELOLA)

Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp

9,100,000.00
25,946,422.33
295,602,035.02
125,260,096.17
683,844,616.71
17,062,830.90
26,745,935.91
452,175,589.27
45,128,635.48
1,680,866,161.79

B
I
II
III
IV
V
VI
VII
VIII
IX

GEDUNG PENDIDIKAN TAHAP II


PEKERJAAN PERSIAPAN & PELAKSANA
PEKERJAAN TANAH & PASIR
PEKERJAAN PASANGAN & PLESTERAN
PEKERJAAN LANTAI & KERAMIK
PEKERJAAN BETON
PEKERJAAN INSTALASI LISTRIK
PEKERJAAN INSTALASI AIR
PEKERJAAN ATAP & PINTU JENDELA
PEKERJAAN CAT
JUMLAH B (GEDUNG PENDIDIKAN)

Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
RP
RP

2,000,000.00
20,718,833.89
166,593,008.87
94,041,109.64
739,383,847.50
15,373,115.30
19,596,710.44
452,175,589.27
31,457,967.09
1,363,835,758.49

C
I
II
III
IV
V
VI

PAGAR & HALAMAN


PEKERJAAN PERSIAPAN PELAKSANAAN
PEKERJAAN TANAH DAN PASIR
PEKERJAAN PERSIAPAN&PLESTERAN
PEKERJAAN LANTAI
PEKERJAAN BETON
PEKERJAAN CAT
JUMLAHAN C ( HALAMAN & TAMAN)

RP
RP
RP
RP
RP
RP
RP

900,000,.00
4,666,898.96
80,655.053.67
38,932,925.96
37,472,93.29
5,734,600.39
168,362,417.26

JUMLAH OTAL FISIK (A+B+C)


JASA PERENCANAAN
JASA PENGAWASAN
JUMLAH TOTAL
DIBULATKAN

RP
RP
RP
RP
RP

3,213,064,337.54
96,391,390.13
80,326,608.44
3,389,782,876.11
3,389,780,000.00

RENCANA ANGGARAN BIAYA


PEKERJAAN
LOKASI
TAHUN ANGGARAN
NO
A

I
1
2
3
4

: PEMBANGUNAN PANTI ASUHAN &GEDUNG PENDIDIKAN


BIMA BHAKTI (AL MUJIIB)
: PONDOK SURUH BIMOMARTANI NGEMPLAK SLEMAN
: 2010

URAIAN PEKERJAAN

VOLUME

PANTI ASUHAN & RUMAH PENGELOLA


PEKERJAAN PERSIAPAN PELAKSANAAN
Mobilitas alat-alat kerja
1.00
Direksiket
1.00
Pengukuran bouplank
1.00
Papan Nama
1.00

SATUAN

Is
Is
Is
Is

HARGA SATUAN

2,000,000.00
6,000,000.00
1,000,000.00
100,000.00

JUMLAH

TOTAL

2,000,000.00
6,000,000.00
1,000,000.00
100,000.00
9,100,000.00

II
1
2
3

III
1
2
3
4
5
6
7
8

PEKERJAAN TANAH & PASIR


Galian tanah
281.44
Urug tanah kembali
93.81
Urug pasir
105.22
LUAS LANTAI
52.42
PEKERJAAN PASANGAN & PLESTERAN
Pondasi batu kali 1pc:3kp:8bps
326.31
Pas bata Rollag
0.72
pasangan batu bata1pc:3kp:8ps
1645.15
Plester beton 1pc:3ps
591.05
Plester batu bata 1pc:3kp:8ps
3290.30
Ban banan
151.92
Sponengan 1pc:ps
2828.26
Tali air
515.30

m3
m3
m3

28,482.68
14,241.34
157.716.75

8,016,164.05
1,336,027.34
16,594,230.94
25,946,422.33

m2
m2
m2
m2
m2
m2
m2
m2

319,539.49
356,520.55
56,453.84
22,803.98
18,660.64
35,000.00
5,000.00
7,500.00

104,269,729.01
25,694.80
92,875,041.05
13,478,261.37
1,399,103.79
5,317,200.00
14.141,300.00
3,864,750.00
295,602,035.02

IV
1
2
3
4
5
6
7
8
9

PEKERJAAN LANTAI DAN KERAMIK


Floor lantai 7 cm
Karamik lantai 40/40
Keramik tangga
Karamik lantai wc 20/20
Keraik dinding wc 20/25
Roster 10/30+banbanan
Batu alam
Paving blok
Plint lantai

369.78
731.80
15.30
47.75
150.60
10.00
5.60
42.00
515.30

m2
m2
m2
m2
m2
m2
bh
m2
m1

22,809.59
108,423.85
162,635.78
95.038.04
102,077.27
26,061.95
163,201.16
83,758.80
20,205.29

8,411,652.11
79,345,010.33
2,488,327.46
4,358,066.53
15,372,837.52
260,619.53
913,926.48
3,517,869.60
10,411,786.61
125,260,096.17

V
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

PEKERJAAN BETON
Lantai kerja 7cm 1pc 3ps 5 kr
Pondasi footplat 1.25x1,25
Sloof 20/30
Sloof 15/20
Kolom struktur 30/30
Kolom struktur 12/30
Kolom praktis 12/12
Balok struktur 20/35
Balok 12/35
Plot lantai 12 cm
Plot atap 10 cm
Lat tangga
Plat kanopi 10 cm
Ring balk 12/20
Balk lantai 12/20

2.63
11.25
15.51
0.33
27.95
1.64
2.82
18.38
8.44
49.29
10.76
1.20
1.39
4.61
3.94

m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3

555,242.13
3,957,092.70
3,957,029.70
4,157,736.70
4,916,736.04
4,916,736.04
4,157,792.70
4,849,836.04
4,849,836.04
4,028,733.26
4,028,733.26
4,028,733.26
4,028,733.26
4,157,792.70
4,157,792.70

1,457,510.58
44,517,92.90
61,374,507.81
1,372,071.59
137,398,188.51
137,398,188.51
8,053,613.63
11,705,018.01
89,115,737.15
198,589,315.81
43,349,169.88
4,834,479.91
5,616,054.16
19,154,269.22
16,365,072.08
683,844,616.71

VI
1
2
3
4
5
6

PEKERJAAN INSTALASI LISTRIK

VII
1
2
3

PEKERJAN INSTALASI AIR

Saklar ganda
Saklar tunggal
Stop kontak + instalasi
Lampu xl 18 watt + instalasi
Meteran
Box MCB 4 panel

27.00
13.00
34.00
71.00
1.00
1.00

Titik
Titik
Titik
titik
Is
is

83,022.90
71,125.85
95,466.30
102,122.85
3,000,000.00
400,000.00

2,241,618.30
924,636.05
3,245,854.20
7,250,722.35
3,000,000.00
400,000.00
17,062,830.90

Kran kamar mandi


Kran shower kloset duduk
Pipa pvc 4

18.00
1.00
56.00

bh
bh
m1

32,056
177,842.25
33,979.63

577,012.50
177,842.50
1,902,859.00

4
5
6
7
8
9
10
11
12
13
14

Pipa pvc 3
Pipa pvc 3/4
Closet duduk
Closet jongkok
Box sabun
Floor drain
Septytank
Sumur air bersih
Resapan air
Bak kontrol
Meja dapur

131.00
122.50
1.00
8.00
9.00
9.00
2.00
1.00
5.00
2.00
1.00

m1
ml
bh
bh
bh
bh
bh
bh
bh
bh
Is

28,516.13
15,317.31
1,566,575.00
219,097.50
97,701.88
41,951.88
1,500,000.00
2,500,000.00
1,250,000.00
75,000.00
2,000,000.00

3,735,612.38
1,876,370.78
1,566,575.00
1,752,780.00
879,316.88
377,566.88
3,000,000.00
2,500,000.00
6,250,000.00
150,000.00
2,000,000.00

26,745,935.91
VIII
1
2
3
4
5
6
7
8
9
10
12
13
14
15
16

PEKERJAAN ATAP & PINTU JENDELA


Kuda-kuda bengkirai 8/12
Nok gording blandarbengkirai 8/12
Rangka atapbengkirai
Atap genting beton
Bubungan beton
Papan lisplang 2/20 bk
Talang 2x2/20 + seng 18cm
Kuzen alumunium alexindo 4
Daun jendela kaca
Daun boven
Foldinggate
Pintu paga besi tempa
Raling besi tempa
Plavon Gypsum
List profil Gypsum

4.07
4.07
540.42
540.42
96.50
134.75
51.50
692.00
48.00
89.00
204.00
9.00
35.50
958.19
668.00

m1
m1
m2
m2
m1
m1
m1
m1
bh
bh
m2
m2
m1
m2
m1

8,606,908.00
8,439,825.25
98,680.29
70,095.59
96,857.26
48,898.33
120,202.58
780,000.00
350,000.00
200,000.00
750,000.00
500,000.00
300,000.00
80,000.00
17,500.00

35,026,672.80
34,353,464.70
53,328,377.08
37,880,757.64
9,346,725.83
6,589,021.06
6,190,432,61
47,575,000.00
31,150,000.00
40,800,000.00
9,000,000.00
4,500,000.00
10,650,000.
76,655,137.55
11,690,000.00
452,175,589.27

IX
1
2
3

PEKERJAAN CAT

Cat dinding Catylac


Cat talang seng meni
Cat papan lisplang emco

3881.35
82.40
67.37

m2
m2
m2

JUMLAH A ( PANTI ASUHAN & RUMAH PENGELOLA)

10,855.64
12,279.50
29,422.06

42,134,5022.13
1,011,830.39
1.982,302.97
45,128,635.48
1,680,866,161.79

B
I
1
2

GEDUNG PENDIDIKAN
PEKERJAAN PERSIAPAN PALAKSANAAN
Mobilisasi alat-alat kerja
1.00
Pengukuran bouplank
1.00

Is
Is

1,000.000.00
1,000.000.00

1,000.000.00
1,000.000.00
2,000.000.00

II
1
2
3

PEKERJAAN TANAH DAN PASIR

Galian tanah
Urug tanah kembali
Urug pasir

352.42
117.47
57.12

m3
m3
m3

28,482.68
14,241.34
157,716.75

10,037,864,32
1,672,977.39
9,007,992.18
20,718,833.89

III
1
2
3
4
5
6
7

PEKERJAAN PASANGAN & PLESTERAN

Pondasi batu kali 1pc: 3kp: 8ps


Pasangan batu bata 1pc: 3kp: 8ps
Plester beton 1 pc : 3ps
Plester batu bata 1pc : 3kp: 8ps
Ban banan
Sponengan 1pc: 2ps
Tali air

79.07
1041.71
666.11
2083.42
338. 38
2676.76
430.00

m3
m2
m2
m2
m1
m1
m1

319,539.49
56,453. 84
22,803. 98
18,660.78
35.000. 00
5,000. 00
7,500. 00

25,264,389.58
58,808,533.57
15,190,035.13
38,887,950.59
11,843,300.00
13,383,800.00
3,225,000.00
166,593,008.87

IV

1
2
3
4
5
6
7

PEKERJAAN LANTAI & KERAMIK

Floor lantai 7 cm
Keramik lantai 40/40
Keramik tangga
Keramik lantai wc 20/20
Keramik dinding wc 20/25
Batu alam
Plint lantai

296.00

m2

22,809. 59

6,751,638.59

574.00
64.40
4.80
18.00
22.05
430.00

m2
m2
m2
m2
m2
m1

108,423. 85
162,635.78
95,038. 04
102,007.27
163,201.16
20,205. 29

62,235,292.41
10,473,744. 33
456,182 . 60
1,837,390. 94
3,598,390. 50
8,688,275.26
94 ,041,10.64

V
1
2
3

PEKERJAAN BETON
Lantai kerja 7cm 1pc 3 ps 5 kr
Pondasi footplat 1,25 x 1,25
Sloof 20/30

5. 36
22.97
12.00

m3
m3
m3

4
5
6
7
8
9
10
11
12
13
14

Kolom struktur 30/30 . 20/20

29.52
3.56
0.10
13.47
9.20
3.82
8.24
34.08
29.50
2.40
1.39

25.00
5.00
24.00
71.00
1.00
1.00

555, 242.13
3,957,0 92.70
3,957,0

2,975,750.76
90,886,473.00
47,485,112.42

m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3

4,916,736.04
4,916,736.04
4,157,792.70
4,849,836.04
4,849,836.04
4,157,792.70
4,157,792.70
4,028,733.26
4,028,733.26
4,028,733.26
4,028,733.26

145,142,047.
17,523,247.23
419,105.50
65,327,291.40
44,608,791.85
13,620,928.89
39,960,224,01
147,299,229.50
118,847,631.17
9,668,959.82
5,616,054.16

titik
titik
titik
titik
Is
Is

83,022.9
71,125.85
95,466.30
102,122.85
3,000,000.00
400,00.00

2,075,572.50
355,629.25
2.291,191.20
7,250,722.35
3,000,000.00
400,00.00

92.70

Kolom struktur 12/30


Kolom praktis 12/12
Balok struktur 20/30
Balok ring 12/30
Balok lantai 12/20
Kuda-kuda beton 15/30
Plat lantai 12 cm
Plat atap 10 cm
Plat tangga
Plat kanopi 10 cm

VI
1
2
3
4
5
6

PEKERJAAN INTALASI LISTRIK

VII
1
2
3
4
5
6
7

PEKERJAAN INSTALASI AIR

Saklar ganda
Saklar tunggal
Stop kontak + intalasi
Lampu xl 18 watt + instalasi
Meteran
Box MCB 4 panel

15,373,115.30
Kran kamar mandi
Pipa pvc 4
Pipa pvc 3
Pipa pvc 3/4
Closet jongkok
Box sabun
Floor drain

5.00
57.00
173.00
75.00
2.00
2.00
2.00

bh
m1
m1
m1
bh
bh
bh

32,065.25
33,979.63
28,516.13
15,317.31
219,097.50
97,701.88
41,951.88

160,281.25
1,936,838.63
4,933,289.63
1,148,798.44
438,195.00
195,403.75
83,903.75

8
9
10

Septytank

1.00

bh

1,500,000.00

1,500,000.00

Resapan air
Bak kontrol

7.00
6.00

bh
bh

1,250,000.00
75,000.00

8,750,000.00
450,000.00
19,596,710.44

VIII
1
2
3
4
5
6
7
8
9
10
11
12
13

PEKERJAAN ATAP & PINTU JENDELA


Nok gording blandar bengkirai 8/12

Rangka atap bengkirai


Atap genting beton
Bubungan atapbeton
Papan lisplang 2/20
Talang 2x2/20 + seng beton 80cm
Kuzen alumunium alexindo
Daun pintu panil
Daun jendela kaca
Daun boven
Ralling besi tempa
Plavon gypsun
Lis provil gypsum

2.06
316.92
316.92
72.00
101.43
6.00
553.00
19.00
105.400
143.00
57.00
584.00
520.00

m1
m2
m2
m1
m1
m1
m1
bh
bh
bh
m1
m2
m1

8,439,825.25
9,680.29
70,095.59
96,857.26
48,898.33
120,202.58
68,750.00
780,000.00
350,000.000
200,000.00
300,000.00
80,000.00
17,500.

17,419,799.32
31,237,446.77
22,214,446.5
6,937,722.90
4,959,757.10
721,215.45
36,018,750.00
14,920,000.00
36,750,000.00
28,600,000.00
17,100,000.00
46,720,000.00
9,100,000.00
274,671,165.76

IX
1
2
3

PEKERJAAN CAT
Cat dinding catylac
Cat talang seng meni
Cat papanlisplang emco

2,749.53
9.60
50.72

m2
m2
m2

10,855.64
12,279.50
29,422.06

29,847,944.03
117,883.15
1,492,39.90
31,457,967.09
1,363,835,758.49

JUMLAH B (GEDUNG PENDIDIKAN)


C

PAGAR & HALAMAN


1
1
2

PEKERJAAN PERSIAPAN PELAKSANAAN


Mobilisasi alat-alat kerja
1.00
Pengukuran bouplang
1.00

Is
Is

500,000.00
400,000.00

500,000.00
400,000.00

900,000.00
II

PEKERJAAN TANAH DAN PASIR

1
2
3

Galian tanah
Urug tanah kembali
Urug pasir
LUAS LANTAI

III
1
2
3
4
5
6
7

88.092
29.38
11,0184

m3
m3
m3

28,482.68
14,241.34
157,716.75

2,510,668.05
418,444.67
1,737,786.24
4,666,898.96

PEKERJAAN PASANGAN DAN PLESTERAN

Pondasi batu kali 1pc:3pc:8ps


Pasangan batu bata 1pc:3kp:8ps

Plester batu bata


Ban banan
Sponengan 1pc : 2pc

Ralling pagar besi tempa


Pintu pagar besi tempa

55.059
264.13
528.26
199.06
513.46
68.53
12.00

m3
m2
m2
m1
m1
m1
m2

319,539.49
56,453.84
22,803.98
35,000.00
5,000.00
300,000.00
500.000.00

17,604,069.45
14,911,153.75
12,046,430.43
6,967,100.0
2,567,300.00
20,559,000.00
6,000,000.00
80,655,053.67

IV
1
2
3
4

PEKERJAAN LANTAI
Taman rumput
Pohon palm
Paving blok diamond
Kanstin beton1:3:5 15/30

V
1

PEKERJAAN BETON
Sloof 15/20

4.13

m3

4,157,792.70

2
3
4

Kolom 20/20
Kolom praktis 12/12
Ring balik 12/20

2.50
0.86
1.52

m3
m3
m3

4,157,792.70
4,157,792.70
4,157,792.70

VI
1

PEKERJAAN CAT
Cat dinding Catylac

136.30
28.00
304.37
48.41

m2
bh
m2
m1

55,000.00
150,000.00
83,758.80
36.000

7,496,500.00
4,200,000.00
25,493,665.96
1,742,760.00
39,932,925.96
17,6178,583.6
7
10,394,481.75
3,592,332.89
6,306,539.97
37,472,938.29

528.26

m2

JUMLAH C (HALAMAN & TAMAN)

10,855.64

5,734,600.39
5,734,60039
168,362,417.26

REKAPITULASI RENCANA ANGGARANBIAYA


PEKERJAAN
LOKASI
TAHUN ANGGARAN

NO

: PEMBANGUNAN PANTI ASUHAN BIMA BHAKTI (AL MUJIIB)


: PONDOK SURUH BIMOMARTANI NGEMPLAK SLEMAN
: 2010

URAIAN PEKERJAAN

JUMLAH

PANTI ASUHAN & RUMAH PENGELOLA

PEKERJAAN PERSIAPAN PELAKSANAAN

Rp

9,100,000,00

II

PEKERJAAN TANAH & PASIR

Rp

25,946,422.33

III

PEKERJAAN PASANGAN & PLESTERAN

Rp

295,602,053.02

IV

PEKERJAAN LANTAI & KERAMIK

Rp

125,260,096.17

PEKERJAAN BETON

Rp

683,844,616.71

VI

PEKERJAAN INSTALASI LISTRIK

Rp

17,062,830.90

VII

PEKERJAAN INSTALASI AIR

Rp

26,745,935.91

VII

PEKERJAAN ATAP & PINTU JENDELA

Rp

452,175,589.27

IX

PEKERJAAN CAT

Rp

45,128,635.48

JUMLAH

Rp

1,680,866,161.79

DIBULATKAN

Rp

1,680,850,000.00