DAFTAR HARGA
UPAH KERJA DAN BAHAN / MATERIAL
NO.

URAIAN JENIS TENAGA / BAHAN

SATUAN

HARGA

UPAH TENAGA KERJA

Tukang

O/H

Rp37,000.00

Pekerja

O/H

Rp30,000.00

Rp720.00

HARGA BAHAN / MATERIAL

Anker Besi beton polos dia 10 mm Kusen

Bh

Pasangan Atap Seng BJLS 20 cm

kaki

Rp6,600.00

Nok Atap Seng Plat Lebar 50cm

M1

Rp46,000.00

Batu Koral / Batu Pecah

M3

Rp148,000.00

Batu gunung

M3

Rp118,000.00

Batu Bata

Bh

Rp400.00

Besi beton Polos

Kg

Rp11,200.00

Balok Kayu Kalapai

M3

Rp3,500,000.00

Balok Kayu Komea

M3

Rp1,890,000.00

10

Balok Kayu Meranti

M3

Rp1,650,000.00

11

Closed Jongkok Satndart

Bh

Rp110,000.00

12

Cat Residu / Anti Rayap

Ltr

Rp3,500.00

13

Cat Tembok

Kg

Rp9,000.00

14

Cat Dasar / Meni

Kg

Rp11,000.00

15

Cat Minyak

Kg

Rp7,000.00

16

Cat Atap Ex. AGA

Kg

Rp15,000.00

17

Dempul Tembok / Plamur

Kg

Rp15,000.00

18

Engsel Pintu 4" Model H

Bh

Rp12,000.00

19

Engsel Jendela 3" Model Kupu-kupu

Bh

Rp8,000.00

20

Fitting Duduk / Plafond

Bh

Rp8,500.00

21

Floor Drain Stainlisst

Bh

Rp25,000.00

22

Grendel Pintu Panjang

Bh

Rp6,500.00

23

Grendel Jendela Sedang

Bh

Rp3,500.00

24

Instalasi Titik Lampu

Titik

Rp100,000.00

25

Kaca Bening 5 mm

M2

Rp101,000.00

26

Kawat Beton

Kg

Rp18,900.00

27

Kran Air Croom Cristal dia 1/2"

Bh

Rp17,500.00

28

Kunci Tanam Standart 2 x putar

Set

Rp68,000.00

29

Kait Angin

Bh

Rp3,000.00

30

List Sudut Plafond 4 cm / Kayu Profil

M'

Rp3,500.00

31

Lampu SL 40 Watt

Bh

Rp23,500.00

32

Lampu Pijar 40 Watt

Bh

Rp15,000.00

33

Minyak Bekisting

Ltr

Rp7,000.00

34

Mini Circuit Breaker (MCB) 1 Group

Set

Rp65,000.00

35

Portland Cement (PC)

Kg

Rp1,260.00

36

Pasir Urug / Timbunan

M3

Rp110,250.00

37

Pasir Pasang

M3

Rp125,000.00

38

Pasir Beton

M3

Rp125,000.00

39

Papan Kayu Jati

M3

Rp2,700,000.00

KET.

DAFTAR HARGA
UPAH KERJA DAN BAHAN / MATERIAL
NO.

URAIAN JENIS TENAGA / BAHAN

SATUAN

HARGA

40

Papan Kayu Bekisting Kls.III

M3

Rp1,650,000.00

41

Papan Kayu Meranti

M3

Rp1,650,000.00

42

Paku Campur

Kg

Rp18,000.00

43

Paku Tripleks

Kg

Rp22,500.00

44

Paku Seng

Kg

Rp23,000.00

45

Semen Warna

Kg

Rp10,500.00

46

Saklar Ganda Tanam

Bh

Rp13,650.00

47

Saklar Tunggal Tanam

Bh

Rp12,960.00

48

Stop Kontak Tanam

Bh

Rp9,900.00

49

Seal Tape

Bh

Rp5,000.00

50

Septic Tank dan Peresapan

Unit

Rp1,500,000.00

51

Tegel Keramik 30 x 30 cm Polos Putih

Bh

Rp3,090.91

52

Tegel Keramik 20 x 20 cm Polos Putih

Bh

Rp1,640.00

53

Tegel Keramik Anti Slip KM 20 x 20 cm INA

Bh

Rp1,640.00

54

Tripleks 3 mm

Lbr

Rp42,500.00

55

Tanah Urug / Timbunan

M3

Rp50,000.00

56

Lem Fox Kuning

Tube

Rp2,500.00

57

Daun Pintu PVC

Set

Rp280,000.00

KET.

DAFTAR ANALISA
HARGA SATUAN PEKERJAAN
NO

URAIAN

KOEF.

SATUAN

HARGA SATUAN

JUMLAH HARGA

6=3x5

ANALISA PEMASANGAN :
1

1 M' Pengukuran dan Pasangan Bouwplank


Tukang
Pekerja
Kayu Balok / Papan Kls.II
Paku Campuran

0.100
0.100
0.025
0.020

Org/Hari
Org/Hari
m3
kg

Rp37,000.00
Rp30,000.00
Rp1,650,000.00
Rp18,000.00

Rp3,700.00
Rp3,000.00
Rp41,250.00
Rp360.00
Rp48,310.00

1 M2 Pekerjaan Pembersihan Lokasi


Pekerja

0.040

Org/Hari

Rp30,000.00

Rp1,200.00
Rp1,200.00

1 M3 Pek. Galian Tanah Biasa Sedalam 1 M maksimal


Pekerja
0.400

Org/Hari

Rp30,000.00

Rp12,000.00
Rp12,000.00

1 M3 Pek. Urugan Kembali


Pekerja

0.192

Org/Hari

Rp30,000.00

Rp5,760.00
Rp5,760.00

1 M3 Pek. Urugan Tanah


Pekerja
Tanah urug

0.300
1.200

Org/Hari
m3

Rp30,000.00
Rp50,000.00

Rp9,000.00
Rp60,000.00
Rp69,000.00

1 M3 Pek. Urugan Pasir


Pekerja
Pasir urug

0.300
1.200

Org/Hari
m3

Rp30,000.00
Rp110,250.00

Rp9,000.00
Rp132,300.00
Rp141,300.00

1 M3 Pek. Timbrisan Pondasi Batu Kosong


Tukang
Pekerja
Batu gunung
Pasir Urug

0.390
0.780
1.100
0.300

Org/Hari
Org/Hari
m3
m3

Rp37,000.00
Rp30,000.00
Rp118,000.00
Rp110,250.00

Rp14,430.00
Rp23,400.00
Rp129,800.00
Rp33,075.00
Rp200,705.00

1 M3 Pek. Pasangan Pondasi Batu Kali 1 Pc : 5 Psr


Tukang
0.600
Pekerja
1.500
Batu gunung
1.100
Semen Portland
136.000
Pasir Pasang
0.544

Org/Hari
Org/Hari
m3
kg
m3

Rp37,000.00
Rp30,000.00
Rp118,000.00
Rp1,260.00
Rp125,000.00

Rp22,200.00
Rp45,000.00
Rp129,800.00
Rp171,360.00
Rp68,000.00
Rp436,360.00

1 M2 Pek. Pasangan Bata Merah 1/2 Bata 1 Pc : 3 Psr


Tukang
0.100
Pekerja
0.320
Batu Bata
70.000
Semen Portland
14.370
Pasir Pasang
0.040

Org/Hari
Org/Hari
m3
kg
m3

Rp37,000.00
Rp30,000.00
Rp400.00
Rp1,260.00
Rp125,000.00

Rp3,700.00
Rp9,600.00
Rp28,000.00
Rp18,106.20
Rp5,000.00
Rp64,406.20

1 M2 Pek. Pasangan Bata Merah 1/2 Bata 1 Pc : 5 Psr


Tukang
0.100
Pekerja
0.320
Batu Bata
70.000
Semen Portland
9.680
Pasir Pasang
0.045

Org/Hari
Org/Hari
m3
kg
m3

Rp37,000.00
Rp30,000.00
Rp400.00
Rp1,260.00
Rp125,000.00

Rp3,700.00
Rp9,600.00
Rp28,000.00
Rp12,196.80
Rp5,625.00
Rp59,121.80

KET.

DAFTAR ANALISA
HARGA SATUAN PEKERJAAN
NO

URAIAN

KOEF.

SATUAN

HARGA SATUAN

JUMLAH HARGA

6=3x5

10

11

12

13

14

1 M3 Membuat Beton Tanpa Tulangan 1 Pc : 3 Psr : 5 Krl


Tukang
0.250 Org/Hari
Pekerja
1.650 Org/Hari
Semen
218.000
kg
Pasir Beton
0.520
m3
Koral Beton
0.870
m3

Rp37,000.00
Rp30,000.00
Rp1,260.00
Rp125,000.00
Rp148,000.00

Rp9,250.00
Rp49,500.00
Rp274,680.00
Rp65,000.00
Rp128,760.00
Rp527,190.00

1 M3 Membuat Kolom Beton Bertulang


Tukang
Tukang
Tukang
Pekerja
Kayu papan / balok
Paku campur
Minyak bekisting
Besi Beton
Kawat Beton
Semen
Pasir Beton
Koral/Batu Pecah

0.350
1.560
1.400
4.850
0.270
2.000
2.000
200.000
3.000
323.000
0.520
0.780

Org/Hari
Org/Hari
Org/Hari
Org/Hari
m3
kg
ltr
kg
kg
kg
m3
m3

Rp37,000.00
Rp37,000.00
Rp37,000.00
Rp30,000.00
Rp1,650,000.00
Rp18,000.00
Rp7,000.00
Rp11,200.00
Rp18,900.00
Rp1,260.00
Rp125,000.00
Rp148,000.00

Rp12,950.00
Rp57,720.00
Rp51,800.00
Rp145,500.00
Rp445,500.00
Rp36,000.00
Rp14,000.00
Rp2,240,000.00
Rp56,700.00
Rp406,980.00
Rp65,000.00
Rp115,440.00
Rp3,647,590.00

1 M3 Membuat Sloof Beton Bertulang


Tukang
Tukang
Tukang
Pekerja
Kayu papan / balok
Paku campur
Minyak bekisting
Besi Beton
Kawat Beton
Semen
Pasir Beton
Koral/Batu Pecah

0.350
1.040
1.050
3.900
0.200
1.500
0.600
150.000
2.250
323.000
0.520
0.780

Org/Hari
Org/Hari
Org/Hari
Org/Hari
m3
kg
ltr
kg
kg
kg
m3
m3

Rp37,000.00
Rp37,000.00
Rp37,000.00
Rp30,000.00
Rp1,650,000.00
Rp18,000.00
Rp7,000.00
Rp11,200.00
Rp18,900.00
Rp1,260.00
Rp125,000.00
Rp148,000.00

Rp12,950.00
Rp38,480.00
Rp38,850.00
Rp117,000.00
Rp330,000.00
Rp27,000.00
Rp4,200.00
Rp1,680,000.00
Rp42,525.00
Rp406,980.00
Rp65,000.00
Rp115,440.00
Rp2,878,425.00

0.020
0.020
0.020
0.060
0.002
0.010
3.000
0.450
4.000
0.006
0.009

Org/Hari
Org/Hari
Org/Hari
Org/Hari
m3
kg
kg
kg
kg
m3
m3

Rp37,000.00
Rp37,000.00
Rp37,000.00
Rp30,000.00
Rp1,650,000.00
Rp18,000.00
Rp11,200.00
Rp18,900.00
Rp1,260.00
Rp125,000.00
Rp148,000.00

Rp740.00
Rp740.00
Rp740.00
Rp1,800.00
Rp3,300.00
Rp180.00
Rp33,600.00
Rp8,505.00
Rp5,040.00
Rp750.00
Rp1,332.00
Rp56,727.00

1 M1 Membuat Ringbalk Penguat Beton Bertulang


Tukang
0.033
Tukang
0.033
Tukang
0.033
Pekerja
0.100
Kayu papan / balok
0.003

Org/Hari
Org/Hari
Org/Hari
Org/Hari
m3

Rp37,000.00
Rp37,000.00
Rp37,000.00
Rp30,000.00
Rp1,650,000.00

Rp1,221.00
Rp1,221.00
Rp1,221.00
Rp3,000.00
Rp4,950.00

1 M1 Membuat Kolom Beton Bertulang


Tukang
Tukang
Tukang
Pekerja
Kayu papan / balok
Paku campur
Besi Beton
Kawat Beton
Semen
Pasir Beton
Koral/Batu Pecah

KET.

DAFTAR ANALISA
HARGA SATUAN PEKERJAAN
NO

URAIAN

KOEF.

SATUAN

HARGA SATUAN

JUMLAH HARGA

6=3x5

Paku campur
Besi Beton
Kawat Beton
Semen
Pasir Beton
Koral/Batu Pecah
15

16

17

18

19

20

kg
kg
kg
kg
m3
m3

Rp18,000.00
Rp11,200.00
Rp18,900.00
Rp1,260.00
Rp125,000.00
Rp148,000.00

Rp360.00
Rp40,320.00
Rp945.00
Rp6,930.00
Rp1,125.00
Rp2,220.00
Rp63,513.00

1 M2 Pek. Plesteran 1 Pc : 3 Psr, Tebal 15 mm


Tukang
0.150
Pekerja
0.200
Semen Portland
6.480
Pasir Pasang
0.019

Org/Hari
Org/Hari
kg
m3

Rp37,000.00
Rp30,000.00
Rp1,260.00
Rp125,000.00

Rp5,550.00
Rp6,000.00
Rp8,164.80
Rp2,375.00
Rp22,089.80

1 M2 Pek. Plesteran 1 Pc : 5 Psr, Tebal 15 mm


Tukang
0.150
Pekerja
0.200
Semen Portland
4.320
Pasir Pasang
0.022

Org/Hari
Org/Hari
kg
m3

Rp37,000.00
Rp30,000.00
Rp1,260.00
Rp125,000.00

Rp5,550.00
Rp6,000.00
Rp5,443.20
Rp2,750.00
Rp19,743.20

1 M2 Pasangan Lantai Tegel Keramik


Tukang
Pekerja
Tegel keramik 40 x 40 cm
Tegel keramik 20 x 20 cm
Semen warna
Semen portland
Pasir Pasang

0.228
0.403
11.000
25.000
1.500
11.380
0.042

Org/Hari
Org/Hari
bh
bh
kg
kg
m3

Rp37,000.00
Rp30,000.00
Rp3,090.91
Rp1,640.00
Rp10,500.00
Rp1,260.00
Rp125,000.00
Tegel 40/40 cm
Tegel 20/20 cm

Rp8,417.50
Rp12,090.00
Rp34,000.00
Rp41,000.00
Rp15,750.00
Rp14,338.80
Rp5,250.00
Rp89,846.30
Rp96,846.30

0.032
0.315
3.330
0.100
1.650
0.003

Org/Hari
Org/Hari
m'
kg
kg
m3

Rp37,000.00
Rp30,000.00
#REF!
Rp10,500.00
Rp1,260.00
Rp125,000.00

Rp1,165.50
Rp9,450.00
#REF!
Rp1,050.00
Rp2,079.00
Rp400.00
#REF!

1 M2 Pasangan Lantai Keramik Anti Slip 20 x 20 Cm


Tukang
0.228
Pekerja
0.403
Tegel keramik 20 x 30 cm
25.000
Semen warna
1.500
Semen portland
9.300
Pasir Pasang
0.042

Org/Hari
Org/Hari
bh
kg
kg
m3

Rp37,000.00
Rp30,000.00
Rp1,640.00
Rp10,500.00
Rp1,260.00
Rp125,000.00

Rp8,417.50
Rp12,090.00
Rp41,000.00
Rp15,750.00
Rp11,718.00
Rp5,250.00
Rp94,225.50

1 M2 Pasangan Dinding Keramik 20 x 30 Cm


Tukang
0.263
Pekerja
0.450
Tegel keramik 20 x 30 cm
25.000
Semen warna
1.500
Semen portland
11.380
Pasir Pasang
0.018

Org/Hari
Org/Hari
bh
kg
kg
m3

Rp37,000.00
Rp30,000.00
Rp1,640.00
Rp10,500.00
Rp1,260.00
Rp125,000.00

Rp9,712.50
Rp13,500.00
Rp41,000.00
Rp15,750.00
Rp14,338.80
Rp2,250.00

1 M' Pasangan Tegel Plint Keramik 20 x 40 Cm


Tukang
Pekerja
Tegel plint keramik 20 x 40 cm
Semen warna
Semen portland
Pasir Pasang

0.020
3.600
0.050
5.500
0.009
0.015

KET.

DAFTAR ANALISA
HARGA SATUAN PEKERJAAN
NO

URAIAN

KOEF.

SATUAN

HARGA SATUAN

JUMLAH HARGA

6=3x5

Rp96,551.30

21

22

23

24

25

26

27

28

29

1 M3 Pek. Gawang Kusen Pintu / Jendela Kayu Kalapi


Tukang
18.000
Pekerja
6.000
Kayu Kalapi
1.200

Org/Hari
Org/Hari
M3

Rp37,000.00
Rp30,000.00
Rp3,500,000.00

Rp666,000.00
Rp180,000.00
Rp4,200,000.00
Rp5,046,000.00

1 M2 Pek. Pasang Daun Pintu Panil Jati


Tukang
Pekerja
Kayu Kalapi

Org/Hari
Org/Hari
M3

Rp37,000.00
Rp30,000.00
Rp3,500,000.00

Rp92,500.00
Rp30,000.00
Rp140,000.00
Rp262,500.00

1 M2 Pek. Pasang Bingkai Daun Jendela Kaca Kayu Jati


Tukang
2.000 Org/Hari
Pekerja
0.800 Org/Hari
Kayu Kalapi
0.035
M3

Rp37,000.00
Rp30,000.00
Rp3,500,000.00

Rp74,000.00
Rp24,000.00
Rp122,500.00
Rp220,500.00

1 M2 Pek. Pasang Jalusi Datar / Miring Kayu Jati


Tukang
2.000
Pekerja
0.500
Kayu Kalapi
0.060
Paku campuran
0.150

Org/Hari
Org/Hari
M3
Kg

Rp37,000.00
Rp30,000.00
Rp3,500,000.00
Rp18,000.00

Rp74,000.00
Rp15,000.00
Rp210,000.00
Rp2,700.00
Rp301,700.00

1 M2 Pek. Pasangan Kaca Polos Bening 5 mm


Tukang
0.150
Pekerja
0.015
Kaca Polos Bening T. 5 mm
1.100

Org/Hari
Org/Hari
M2

Rp37,000.00
Rp30,000.00
Rp101,000.00

Rp5,550.00
Rp450.00
Rp111,100.00
Rp117,100.00

1 M3 Pek. Pasang Konstruksi Kuda-Kuda Kayu Klas II Jenis Komea


Tukang
12.000 Org/Hari
Pekerja
4.000 Org/Hari
Kayu Jenis Komea
1.100
m3
Beugel/baut/Angker Besi, Besi Streep
15.000
kg
Paku Biasa
0.800
kg

Rp37,000.00
Rp30,000.00
Rp1,890,000.00
Rp11,200.00
Rp18,000.00

Rp444,000.00
Rp120,000.00
Rp2,079,000.00
Rp168,000.00
Rp14,400.00
Rp2,825,400.00

1 M3 Pek. Pasang Gording, Balok Angin Kayu Kls II Jenis Komea


Tukang
6.000 Org/Hari
Pekerja
2.000 Org/Hari
Kayu Jenis Komea
1.100
m3
Paku 2" - 5"
0.800
kg

Rp37,000.00
Rp30,000.00
Rp1,890,000.00
Rp18,000.00

Rp222,000.00
Rp60,000.00
Rp2,079,000.00
Rp14,400.00
Rp2,375,400.00

1 M' Pek. Pasang Listplank 2x2x20 cm, Kayu Kalapi


Tukang
0.100
Pekerja
0.100
Kayu Papan Kalapi
0.012
Paku Campur
0.060

Org/Hari
Org/Hari
m3
kg

Rp37,000.00
Rp30,000.00
Rp3,500,000.00
Rp18,000.00

Rp3,700.00
Rp3,000.00
Rp42,000.00
Rp1,080.00
Rp49,780.00

1 M2 Pek. Pasangan Atap Multi Roof


Tukang

Org/Hari

Rp37,000.00

Rp2,220.00

2.500
1.000
0.040

0.060

KET.

DAFTAR ANALISA
HARGA SATUAN PEKERJAAN
NO

URAIAN

KOEF.

SATUAN

HARGA SATUAN

JUMLAH HARGA

6=3x5

30

31

32

33

34

35

36

37

Pekerja
Multi roof
Paku seng

0.120
5.700
0.020

Org/Hari
Lbr
kg

Rp30,000.00
Rp6,600.00
Rp23,000.00

Rp3,600.00
Rp37,620.00
Rp460.00
Rp43,900.00

1 M1 Pek. Atap Nok Atap Multiroof


Tukang
Pekerja
Multi roof
Paku seng

0.070
0.150
0.300
0.040

Org/Hari
Org/Hari
lbr
kg

Rp37,000.00
Rp30,000.00
Rp46,000.00
Rp23,000.00

Rp2,590.00
Rp4,500.00
Rp13,800.00
Rp920.00
Rp21,810.00

1 m1 Pasangan Talang Miring, Seng Bjls 20


Tukang
Pekerja
Seng plat BJLS 20
Paku biasa 1/2" - 1"
Kayu Meranti , Papan
Flincote/Meni Besi

0.400
0.040
0.500
0.015
0.019
0.300

Org/Hari
Org/Hari
lbr
kg
lbr
kg

Rp37,000.00
Rp30,000.00
Rp46,000.00
Rp18,000.00
Rp1,650,000.00
Rp7,000.00

Rp14,800.00
Rp1,200.00
Rp23,000.00
Rp270.00
Rp31,350.00
Rp2,100.00
Rp72,720.00

Rp37,000.00
Rp30,000.00
Rp1,650,000.00
Rp18,000.00

Rp9,250.00
Rp4,500.00
Rp19,800.00
Rp1,800.00
Rp35,350.00

1 M2 Pek. Pasangan Langit-Langit Tripleks 3 mm ( 60x120 cm )


Tukang
0.100 Org/Hari
Pekerja
0.060 Org/Hari
Tripleks tebal 3 mm
0.333
Lbr
Paku Tripleks
0.030
kg

Rp37,000.00
Rp30,000.00
Rp42,500.00
Rp22,500.00

Rp3,700.00
Rp1,800.00
Rp14,152.50
Rp675.00
Rp20,327.50

1 M' Pek. Pasang List Sudut Plafond Kayu Profil


Tukang
Pekerja
Kayu profil 4x4
Paku Campur

0.021
0.021
1.050
0.010

Org/Hari
Org/Hari
m'
kg

Rp37,000.00
Rp30,000.00
Rp3,500.00
Rp18,000.00

Rp777.00
Rp630.00
Rp3,675.00
Rp180.00
Rp5,262.00

1 M2 Pek. Acian Tembok


Tukang
Pekerja
Semen PC

0.100
0.050
0.050

Org/Hari
Org/Hari
kg

Rp37,000.00
Rp30,000.00
Rp1,260.00

Rp3,700.00
Rp1,500.00
Rp63.00
Rp5,263.00

1 M2 Pek. Plamir, Cat Dasar, Cat Kilap Kayu 3 x


Tukang
Pekerja
Cat meny
Plamir
Cat dasar
Cat penutup/kilap 3 x

0.105
0.070
0.200
0.150
0.170
0.350

Org/Hari
Org/Hari
kg
kg
kg
kg

Rp37,000.00
Rp30,000.00
Rp11,000.00
Rp15,000.00
Rp11,000.00
Rp7,000.00

Rp3,885.00
Rp2,100.00
Rp2,200.00
Rp2,250.00
Rp1,870.00
Rp2,450.00
Rp14,755.00

1 M2 Pek. Pasang Rangka Langit-Langit ( 60x120 cm ), Kayu Meranti


Tukang
0.250 Org/Hari
Pekerja
0.150 Org/Hari
Kayu Meranti
0.012
m3
Paku 2" - 5"
0.100
kg

1 M2 Pek. Cat Tembok / Plafond ( 1xPlamir, 1xCat Dasar, 2xCat Penutup )

KET.

DAFTAR ANALISA
HARGA SATUAN PEKERJAAN
NO

URAIAN

KOEF.

SATUAN

HARGA SATUAN

JUMLAH HARGA

6=3x5

Tukang
Pekerja
Plamir
Cat dasar
Cat tembok/penutup 2 x

38

39

0.063
0.020
0.100
0.100
0.260

Org/Hari
Org/Hari
kg
kg
kg

Rp37,000.00
Rp30,000.00
Rp15,000.00
Rp11,000.00
Rp9,000.00

Rp2,331.00
Rp600.00
Rp1,500.00
Rp1,100.00
Rp2,340.00
Rp7,871.00

1 M2 Pengecatan Permukaan Seng Secara Manual


Tukang
0.060
Pekerja
0.006
Cat Penutup
0.300

Org/Hari
Org/Hari
kg

Rp37,000.00
Rp30,000.00
Rp15,000.00

Rp2,220.00
Rp180.00
Rp4,500.00
Rp6,900.00

1 M2 Pekerjaan Residu Rangka Kayu


Pekerja
Residu jadi

Org/Hari
kg

Rp30,000.00
Rp3,500.00

Rp3,000.00
Rp1,225.00
Rp4,225.00

0.100
0.350

KET.

RENCANA ANGGARAN BIAYA ( R A B )


PEMBANGUNAN RUMAH TINGGAL PERMANEN
KAB.MUNA PROV. SULAWESI TENGGARA

PEKERJAAN :
PEMBANGUNAN RUMAH TINGGAL PERMANEN
NO

URAIAN PEKERJAAN

VOL.

SAT.

HARGA SAT

JML. HARGA

6=3x5

A. PEKERJAAN PENDAHULUAN
1

Pekerjaan Pengukuran dan Pas. Bouwplank

Pekerjaan Pembersihan Loaksi

57.30

M1

Rp48,310.00

Rp2,768,163.00

184.00

LS

Rp1,200.00

Rp220,800.00

JUMLAH = A

Rp2,988,963.00

B. PEKERJAAN TANAH & PASIR


1

Pekerjaan Galian Tanah Pondasi Garis

61.92

M3

Rp12,000.00

Rp743,040.00

Pekerjaan Urugan kembali bekas Galian tanah

15.48

M3

Rp5,760.00

Rp89,164.80

Pekerjaan Urugan pasir alas Pondasi

7.74

M3

Rp141,300.00

Rp1,093,662.00

Pekerjaan Urugan Tanah Bawah Lantai

9.93

M3

Rp69,000.00

Rp685,239.00

Pekerjaan Urugan pasir alas Rabat beton

1.42

M3

Rp141,300.00

Rp200,137.32

JUMLAH = B

Rp2,811,243.12

C. PEKERJAAN BATU & PASANGAN


1

Pekerjaan Timbrisan Batu Kosong Pondasi

15.48

M3

Rp200,705.00

Rp3,106,913.40

Pekerjaan Pondasi Batu Gunung camp. 1 Pc : 5 Psr

33.11

M3

Rp436,360.00

Rp14,447,879.60

Pekerjaan Dinding Batu Bata biasa camp. 1 Pc : 5 Psr

232.79

M2

Rp59,121.80

Rp13,762,963.82

Pekerjaan Dinding Batu Bata Trastram camp. 1 Pc : 3 Psr

21.69

M2

Rp64,406.20

Rp1,396,970.48

Pekerjaan Plesteran Dinding Biasa camp. 1 Pc : 5 Psr

465.58

M2

Rp19,743.20

Rp9,192,039.06

Pekerjaan Plesteran Beton camp. 1 Pc : 3 Psr

48.23

M2

Rp22,089.80

Rp1,065,391.05

JUMLAH = C

Rp42,972,157.41

D. PEKERJAAN BETON
1

Pekerjaan Rabat Beton Keliling T.8 cm camp. 1 : 3 : 5

2.83

M3

Rp527,190.00

Rp1,493,423.83

Pekerjaan Rabat Beton Lantai T.7 cm camp. 1 : 3 : 5

6.95

M3

Rp527,190.00

Rp3,664,866.72

Pekerjaan Sloof Beton 15 x 20 cm camp. 1 : 2 : 3

1.75

M3

Rp2,878,425.00

Rp5,049,908.82

Pekerjaan Kolom 13.5 x 13.5 cm camp. 1 : 2 : 3

100.05

M1

Rp56,727.00

Rp5,675,536.35

Pek. Ringbalk Beton 13.5 x 20 cm camp. 1 : 2 : 3

84.50

M'

Rp63,513.00

Rp5,366,848.50

JUMLAH = D

Rp21,250,584.23

E. PEKERJAAN PLESTERAN & ACIAN


1

Pekerjaan Plesteran Dinding Biasa camp. 1 : 5

465.58

M2

Rp19,743.20

Rp9,192,039.06

Pekerjaan Plesteran Dinding Traseram camp. 1 : 3

118.15

M2

Rp22,089.80

Rp2,609,909.87

Pekerjaan Plesteran Beton camp. 1 : 3

96.46

M2

Rp22,089.80

Rp2,130,782.11

Pekerjaan Acian Pasta ( PC ) Semua Plesteran

680.19

M2

Rp5,263.00

Rp3,579,839.97

JUMLAH = E

Rp17,512,571.00

F. PEKERJAAN PASANGAN LANTAI


1

Pekerjaan Tegel Lantai Ruangan Keramik Uk. 30/30

93.55

M2

Rp89,846.30

Rp8,405,121.37

Pekerjaan Tegel lantai Kamar Mandi Keramik Uk. 20/20

10.92

M2

Rp96,846.30

Rp1,057,561.60

Pekerjaan Tegel Dinding Kamar Mandi Keramik Uk. 20/30

22.60

M2

Rp94,225.50

Rp2,129,496.30

JUMLAH = D

Rp11,592,179.26

KET.

10

RENCANA ANGGARAN BIAYA ( R A B )


PEMBANGUNAN RUMAH TINGGAL PERMANEN
KAB.MUNA PROV. SULAWESI TENGGARA

PEKERJAAN :
PEMBANGUNAN RUMAH TINGGAL PERMANEN
NO

URAIAN PEKERJAAN

VOL.

SAT.

HARGA SAT

JML. HARGA

6=3x5

M3

Rp5,046,000.00

G. PEKERJAAN KUSEN PINTU, DAUN JENDELA


1

Pekerjaan Kosen Pintu/Jendela kayu Klass 1 uk. 5/13,5

0.66

Rp3,330,360.00

Pekerjaan Pasangan angker Kusen D. 10 mm

34.00

Bh

Rp870.00

Rp29,580.00

Pekerjaan Pasangan Daun Pintu Panil Jati

12.44

M2

Rp262,500.00

Rp3,265,500.00

Pekerjaan Pasangan Daun Pintu Pvc

2.00

Bh

Rp280,000.00

Rp560,000.00

Pekerjaan Daun Jendela Bingkai kayu Jati uk. 2,5 x 8 cm

8.22

M2

Rp220,500.00

Rp1,812,510.00

Pekerjaan Pasangan Semua Kaca Uk. 5 mm

12.81

M2

Rp117,100.00

Rp1,500,051.00

JUMLAH = G

Rp10,498,001.00

H. PEKERJAAN KUDA - KUDA KAP

I.

Pekerjaan Rangka Kuda - Kuda kayu klass II

1.89

M3

Rp2,825,400.00

Rp5,340,006.00

Pekerjaan Gording, Nok & skoor angin kayu klass II

1.60

M3

Rp2,375,400.00

Rp3,800,640.00

Pekerjaan Pasangan List Plank

Pekerjaan Pasangan Atap Seng BJLS 20cm

Pekerjaan Pasangan Talang Atap

Pekerjaan Pasangan Bumbungan Atap Seng

50.00

M1

Rp49,780.00

Rp2,489,000.00

157.34

M2

Rp43,900.00

Rp6,907,226.00

7.46

M1

Rp72,720.00

Rp542,491.20

43.39

M1

Rp21,810.00

Rp946,335.90

JUMLAH = H

Rp20,025,699.10

PEKERJAAN RANGKA PLAFOND


1

Pekerjaan Rangka Plafond Kayu Klass II

134.72

M2

Rp35,350.00

Rp4,762,352.00

Pekerjaan Plafond Tripleks Uk. 5 mm

134.72

M2

Rp20,327.50

Rp2,738,520.80

Pekerjaan List Profil Sudut Plafond

217.46

M2

Rp5,262.00

Rp1,144,274.52

JUMLAH = I

Rp8,645,147.32

J. PEKERJAAN PENGGANTUNG / PENGUNCI


1

Pekerjaan Pasangan kunci tanan 2x Putar

7.00

Set

Rp35,327.50

Rp247,292.50

Pekerjaan Pasangan Engsel pintu Model H

21.00

Psg

Rp19,500.00

Rp409,500.00

Pekerjaan Pasangan Engsel Jendela Model kupu - Kupu

74.00

Psg

Rp13,000.00

Rp962,000.00

Pekerjaan Pasangan Grendel daun Pintu

7.00

Psg

Rp10,000.00

Rp70,000.00

Pekerjaan Pasangan Grendel daun Jendela

37.00

Psg

Rp5,500.00

Rp203,500.00

Pekerjaan Pasangan Kait Angin Daun Jendela

37.00

Set

Rp3,150.00

Rp116,550.00

JUMLAH = J

Rp2,008,842.50

K. PEKERJAAN INTALASI LISTRIK


1

Pekerjaan Pasangan Titik Lampu Intalasi

20.00

Titik

Rp100,000.00

Rp2,000,000.00

Pekerjaan Pasangan Lampu SL 40 Watt

8.00

Bh

Rp23,500.00

Rp188,000.00

Pekerjaan Pasangan Lampu Pijar 40 Watt

4.00

Bh

Rp15,000.00

Rp60,000.00

Pekerjaan Pasangan Lampu Fiting Duduk

12.00

Bh

Rp8,500.00

Rp102,000.00

Pekerjaan Pasangan Stop Kontak tanam

7.00

Bh

Rp9,900.00

Rp69,300.00

Pekerjaan Saklar Ganda

4.00

Bh

Rp13,650.00

Rp54,600.00

Pekerjaan Saklar Tunggal

3.00

Bh

Rp12,960.00

Rp38,880.00

Pekerjaan pasangan MCB

1.00

Set

Rp65,000.00

Rp65,000.00

Pekerjaan Pemasangan penyambungan Daya Dari unit Lain

1.00

Ls

Rp2,500,000.00

Rp2,500,000.00

KET.

11

RENCANA ANGGARAN BIAYA ( R A B )


PEMBANGUNAN RUMAH TINGGAL PERMANEN
KAB.MUNA PROV. SULAWESI TENGGARA

PEKERJAAN :
PEMBANGUNAN RUMAH TINGGAL PERMANEN
NO

URAIAN PEKERJAAN

VOL.

SAT.

HARGA SAT

JML. HARGA

6=3x5

JUMLAH = K

Rp5,077,780.00

L. PEKERJAAN PENGECATAN
1

Pekerjaan Pengecatan tembok 3x Sapu

680.19

M2

Rp7,871.00

Rp5,353,775.49

Pekerjaan Pengecatan plafon 3x Sapu

134.72

M2

Rp7,871.00

Rp1,060,381.12

Pekerjaan PengecatanKusen+Daun,Konsol 3x Sapu

355.20

M2

Rp14,755.00

Rp5,240,976.00

Pekerjaan Pengecatan List-Plank 3x Sapu

17.50

M2

Rp14,755.00

Rp258,212.50

Pekerjaan Pengecatan Atap 3x Sapu

157.34

M2

Rp6,900.00

Rp1,085,646.00

Pekerjaan Residu/Anti rayap Kap&Rangka Plafond

97.35

M2

Rp4,225.00

Rp411,317.83

JUMLAH = L

Rp13,410,308.94
Rp555,000.00

M. PEKERJAAN INTALASI PLUMBING


1

Pekerjaan Pas. Closet Jongkok Standart

3.00

Set

Rp185,000.00

Pekerjaan Pas. Floor-drine Plastik Lavatory

3.00

Set

Rp32,500.00

Rp97,500.00

Pekerjaan Pas. Kran Air Bersih 1/2" standart

4.00

Set

Rp30,000.00

Rp120,000.00

Pekerjaan Pas. Jaringan Pipa PVC 1/2" ut. Air Bersih

1.00

Ls

Rp200,000.00

Rp200,000.00

Pekerjaan Pas. Jaringan Pipa PVC 3"-4" ut. Air Kotor

1.00

Ls

Rp200,000.00

Rp200,000.00

Pasangan ACC semua pekerjaan Jaringan Plumbing

1.00

Ls

Rp100,000.00

Rp100,000.00

Pembuatan Bak Septictank Pas. Batu Bata Camp. 1 : 3

1.00

Unit

Rp1,500,000.00

Rp1,500,000.00

JUMLAH =M

Rp2,772,500.00

N. PEKERJAAN LAIN-LAIN
1

Pekerjaan Pembersihan Akhir Tapak

1.00

Ls

Rp200,000.00

Rp200,000.00

JUMLAH = N

Rp200,000.00

KET.

REKAPITULASI ANGGARAN
PEMBANGUNAN RUMAH TINGGAL PERMANEN
KAB.MUNA PROV. SULAWESI TENGGARA

PEKERJAAN :
PEMBANGUNAN RUMAH TINGGAL PERMANEN
NO

URAIAN PEKERJAAN

JUMLAH HARGA

A.

PEKERJAAN PENDAHULUAN

Rp2,988,963.00

PEKERJAAN TANAH & PASIR

Rp2,811,243.12

PEKERJAAN BATU & PASANGAN

Rp42,972,157.41

D.

PEKERJAAN BETON

Rp21,250,584.23

E.

PEKERJAAN PLESTERAN & ACIAN

Rp17,512,571.00

F.

PEKERJAAN PASANGAN LANTAI

Rp11,592,179.26

G.

PEKERJAAN KUSEN PINTU, DAUN JENDELA

Rp10,498,001.00

H.

PEKERJAAN KUDA - KUDA KAP

Rp20,025,699.10

I.

PEKERJAAN RANGKA PLAFOND

Rp8,645,147.32

J.

PEKERJAAN PENGGANTUNG / PENGUNCI

Rp2,008,842.50

K.

PEKERJAAN INTALASI LISTRIK

Rp5,077,780.00

L.

PEKERJAAN PENGECATAN

M.

PEKERJAAN INTALASI PLUMBING

N.

PEKERJAAN LAIN-LAIN

Rp13,410,308.94
Rp2,772,500.00
Rp200,000.00

REAL-COST = I :
JUMLAH HARGA

Rp161,765,976.88
Rp3,235,319.54
Rp165,001,296.42

DIBULATKAN :

Rp165,000,000.00

IMB 2%

Terbilang :

SERATUS ENAM PULUH LIMA JUTA RUPIAH


Kendari,

Maret 2009

Di Buat Oleh

Nura Hendrika
Cost Estimator

REKAPITULASI ANGGARAN
PEMBANGUNAN RUMAH TINGGAL PERMANEN
KAB.MUNA PROV. SULAWESI TENGGARA

PEKERJAAN :
PEMBANGUNAN RUMAH TINGGAL PERMANEN
NO

URAIAN PEKERJAAN

JUMLAH HARGA

REKAPITULASI ANGGARAN

ANGUNAN RUMAH TINGGAL PERMANEN


B.MUNA PROV. SULAWESI TENGGARA

PEKERJAAN :
NGUNAN RUMAH TINGGAL PERMANEN
KET.

REKAPITULASI ANGGARAN

ANGUNAN RUMAH TINGGAL PERMANEN


B.MUNA PROV. SULAWESI TENGGARA

PEKERJAAN :
NGUNAN RUMAH TINGGAL PERMANEN
KET.