Mobilization

5 Days
Demolition Works (Machine)
1.5 Days
Demolition Works (Manual)
3 Days
Clearing and Grubbing
(New Area)
3.5 Days
Site Grading
12 Days
Excavation
23 Days
Rebar Fabrication
(Parking Lot)
8.5 Days
Rebar Installation
(Parking
Lot)
4 Days
Concreting
(Parking
Lot)
3.5 Days Rebar Installation
(Foundation)
11 Days
Plumbing Rough-in
2 Days
Concreting
(Wall Footing)
1.5 Days
Rebar Installation
(Drainage)
1 Day
Rebar Installation
(CR Foundation)
1 Day
Installation of CHB
(Underlying Chb, Septic tank
& Drainage)
6 Days
Concreting
(Drainage)
2 Days
Concreting
(Septic tank)
0.5 Day
Installation
(Columns)
3 Days
Rebar
Fabrication
(Market
Stands)
2 Days
Rebar
Installation
(Market
Stands)
2 Days
Installation of CHB
(Market
Stands)
6 Days
Concreting
(Market
Stands)
1 Day
Tileworks
(Market
Stands)
17.5 Days
Concreting
(Foundation)
37 Days
Hauling common
borrow
2 Days
Manual backfill
2 Days
Rebar Installation
(Lateral
Ties)
2 Days
Rebar Installation
(C.R. Lateral
Ties)
0.5 Day
Installation of
Formworks
(Columns)
4 Days
Concreting
(Columns)
10 Days
Backfilling
2.5 Days
Hauling common borrow
20.5 Days
Installation of Wall CHB
34.5 Days
Installation of Wall Rebars
2.5 Days
Installation of Wall CHB (CR)
1 Day
Installation of Wall Rebars
(CR)
2.5 Days
Installation Rebar
(Slabs G.F)
11 Days
Concreting
(Slab ground floor
and CR)
31 Days
Installation Rebar
(Slabs C.R)
2 Days
Installation Rebar
(Beams)
10 Days
Installation Rebar
(Stirrups)
3 Days
Installation of
Formworks
(Beam 2nd floor)
6 Days
Concreting
(Beam)
13.5 Days
Fabrication Rebar
(Slab S.F.)
33.5 Days
Fabrication Rebar
(Wall S.F.)
3 Days
Fabrication Rebar
(Column S.F.)
3.5 Days
Fabrication Rebar
(Column Lateral
Ties S.F.)
2 Days
Fabrication Rebar
(Beams S.F.)
9 Days
Fabrication Rebar
(Stirrups S.F.)
2.5 Days
Rebar Installation
(Cr Column
& Footing)
2 Days
Rebar Fabrication
(Drainage)
1 Day
Rebar Fabrication
(CR Foundation)
1 Day
Rebar Fabrication
(CR Column
and Footing)
1 Day
Rebar Fabrication
(Foundation)
22.5 Days
Rebar Fabrication
(Lateral Ties)
1 Day
Rebar Fabrication
(CR Lateral Ties)
0.5 Day
Rebar Fabrication
(Wall)
3.5 Day
Rebar Fabrication
(CR Wall)
1 Day
Rebar Fabrication
(Slab G.F.)
57.5 Days
Rebar Fabrication
(Slab C.R.)
1 Day
Rebar Fabrication
(Beams)
22 Day
Rebar Fabrication
(Stirrups)
6 Days
Formwork Fabrication
(Column 1st floor)
11 Days
Formwork Fabrication
(Beam 1st floor)
39 Days
Formwork Fabrication
(Column 2nd floor)
18.5 Days
Formwork Fabrication
(Beams 2nd floor)
14.5 Days
Removal of
Formworks
(Columns)
4 Days
Removal of
Formworks
(Beam 2nd floor)
6 Days
Installation of
Formworks
(Slab)
7 Days
Concreting
(Slab 2nd floor)
20.5 Days
Installation Rebar
(Slab)
7 Days
Installation Rebar
(Columns S.F.)
2 Days
Installation of
Formworks
(Columns S.F.)
3 Days
Installation Rebar
(Lateral ties S.F.)
2 Days
Concreting
(Column 2nd floor)
7.5 Days
Removal of
Formworks
(Columns S.F.)
3 Days
Installation of Wall CHB S.F.
29.5 Days
Installation of Wall Rebars
S.F.
2 Days
Installation Rebar
(Beams Roof)
4 Days
Installation Rebar
(Stirrups Roof)
3 Days
Installation of
Formworks
(Roof beam)
3 Days
Concreting
(Roof beam)
4 Days
Removal of
Formworks
(Roof beam)
3 Days
Installation of Truss
(B1 Wings)
15 Days
Installation of Truss
(B1 lower mid)
11 Days
Installation of Truss
(B1 upper mid)
6 Days
Installation of Truss
(B2 Wings)
10Days
Installation of Truss
(B2 mid)
7 Days
Plastering
(Septic tank, Drainage,
Market Stands)
7.5 Days
Installation of Steel Doors
51 Days
Installation of Wooden Doors
1 Day
Plastering
(Wall)
65.5 Days
Plastering
(Columns, beams,
market stands)
31.5 Days
Installation of
Roofing
46.5 Days
Installation Gutter
and Flashing
16.5 Days
Installation of
Ridge Roll
2 Days
Installation of
Downspout
6 Days
Installation of
Solar Lighting
3 Days
Concreting Pathway
2 Days
Installation of Cyclone Wire
6.5 Days
Installation of Railings
2 Days
Painting
wall, beams, columns
43.5 Days
Installation of
Ceiling
12 Days
Painting
roof
38 Days
Painting
Ceiling
11.5 Days
Demobilization
10 Days
306.5 Days
190.5 Days
Clearing and
Grubbing
(Existing)
2.5 Days
Demolition Works (Manual)
0.5 Day
Excavation
0.5 Day
Hauling Soil (removing and carrying back)
2 Day
Rebar Fabrication (Footing)
1 Day
0.5 Day
Rebar Installation
(footing)
1 Day
Rebar Fabrication
(Pedestal)
0.5 Day
Rebar Installation
(Pedestal)
3 Day
Concreting
(footing)
0.5 Day
Concreting
(pedestal)
0.5 Day
Backfilling
0.5 Day
Rebar Fabrication
(Lateral Ties)
0.5 Day
Rebar Installation
(Lateral Ties)
1 Day
Installation of
Columns (Landing)
1 Day
Stair Framework
Installation
1 Day
Installation of
Beams (Landing)
4 Day
Stair Slab
Installation
3Day
Stair Railings
Installation
Installation of
Columns (Main)
Installation of
Beams (Main
3 Day
4 Day
Installation of
Slabs
3 Day 5Day
Roofing
Installation
3 Day
Roof
Painting
1Day
Pedestal
Painting
Frame Installation
1 Day
Slab Installation
1 Day
Water Tank Installation
1 Day
Electrical Rough-in G.F.
2 Days
Plumbing Finishing
14 Days
Electrical Finishing G.F.
7 Days
Electrical Rough-in S.F.
2 Days
Electrical
Finishing
S.F.
7 Days
Mobilization
5 Days
Demolition Works (Machine)
1.5 Days
Demolition Works (Manual)
3 Days
Clearing and Grubbing
(New Area)
3.5 Days
Site Grading
12 Days
Excavation
23 Days
Rebar Fabrication
(Parking Lot)
8.5 Days
Rebar Installation
(Parking
Lot)
4 Days
Concreting
(Parking
Lot)
3.5 Days Rebar Installation
(Foundation)
11 Days
Plumbing Rough-in
2 Days
Concreting
(Wall Footing)
1.5 Days
Rebar Installation
(Drainage)
1 Day
Rebar Installation
(CR Foundation)
1 Day
Installation of CHB
(Underlying Chb, Septic tank
& Drainage)
6 Days
Concreting
(Drainage)
2 Days
Concreting
(Septic tank)
0.5 Day
Installation
(Columns)
3 Days
Rebar
Fabrication
(Market
Stands)
2 Days
Rebar
Installation
(Market
Stands)
2 Days
Installation of CHB
(Market
Stands)
6 Days
Concreting
(Market
Stands)
1 Day
Tileworks
(Market
Stands)
17.5 Days
Concreting
(Foundation)
37 Days
Hauling common
borrow
2 Days
Manual backfill
2 Days
Rebar Installation
(Lateral
Ties)
2 Days
Rebar Installation
(C.R. Lateral
Ties)
0.5 Day
Installation of
Formworks
(Columns)
4 Days
Concreting
(Columns)
10 Days
Backfilling
2.5 Days
Hauling common borrow
20.5 Days
Installation of Wall CHB
34.5 Days
Installation of Wall Rebars
2.5 Days
Installation of Wall CHB (CR)
1 Day
Installation of Wall Rebars
(CR)
2.5 Days
Installation Rebar
(Slabs G.F)
11 Days
Concreting
(Slab ground floor
and CR)
31 Days
Installation Rebar
(Slabs C.R)
2 Days
Installation Rebar
(Beams)
10 Days
Installation Rebar
(Stirrups)
3 Days
Installation of
Formworks
(Beam 2nd floor)
6 Days
Concreting
(Beam)
13.5 Days
Fabrication Rebar
(Slab S.F.)
33.5 Days
Fabrication Rebar
(Wall S.F.)
3 Days
Fabrication Rebar
(Column S.F.)
3.5 Days
Fabrication Rebar
(Column Lateral
Ties S.F.)
2 Days
Fabrication Rebar
(Beams S.F.)
9 Days
Fabrication Rebar
(Stirrups S.F.)
2.5 Days
Rebar Installation
(Cr Column
& Footing)
2 Days
Rebar Fabrication
(Drainage)
1 Day
Rebar Fabrication
(CR Foundation)
1 Day
Rebar Fabrication
(CR Column
and Footing)
1 Day
Rebar Fabrication
(Foundation)
22.5 Days
Rebar Fabrication
(Lateral Ties)
1 Day
Rebar Fabrication
(CR Lateral Ties)
0.5 Day
Rebar Fabrication
(Wall)
3.5 Day
Rebar Fabrication
(CR Wall)
1 Day
Rebar Fabrication
(Slab G.F.)
57.5 Days
Rebar Fabrication
(Slab C.R.)
1 Day
Rebar Fabrication
(Beams)
22 Day
Rebar Fabrication
(Stirrups)
6 Days
Formwork Fabrication
(Column 1st floor)
11 Days
Formwork Fabrication
(Beam 1st floor)
39 Days
Formwork Fabrication
(Column 2nd floor)
18.5 Days
Formwork Fabrication
(Beams 2nd floor)
14.5 Days
Removal of
Formworks
(Columns)
4 Days
Removal of
Formworks
(Beam 2nd floor)
6 Days
Installation of
Formworks
(Slab)
7 Days
Concreting
(Slab 2nd floor)
20.5 Days
Installation Rebar
(Slab)
7 Days
Installation Rebar
(Columns S.F.)
2 Days
Installation of
Formworks
(Columns S.F.)
3 Days
Installation Rebar
(Lateral ties S.F.)
2 Days
Concreting
(Column 2nd floor)
7.5 Days
Removal of
Formworks
(Columns S.F.)
3 Days
Installation of Wall CHB S.F.
29.5 Days
Installation of Wall Rebars
S.F.
2 Days
Installation Rebar
(Beams Roof)
4 Days
Installation Rebar
(Stirrups Roof)
3 Days
Installation of
Formworks
(Roof beam)
3 Days
Concreting
(Roof beam)
4 Days
Removal of
Formworks
(Roof beam)
3 Days
Installation of Truss
(B1 Wings)
15 Days
Installation of Truss
(B1 lower mid)
11 Days
Installation of Truss
(B1 upper mid)
6 Days
Installation of Truss
(B2 Wings)
10Days
Installation of Truss
(B2 mid)
7 Days
Plastering
(Septic tank, Drainage,
Market Stands)
7.5 Days
Installation of Steel Doors
51 Days
Installation of Wooden Doors
1 Day
Plastering
(Wall)
65.5 Days
Plastering
(Columns, beams,
market stands)
31.5 Days
Installation of
Roofing
46.5 Days
Installation Gutter
and Flashing
16.5 Days
Installation of
Ridge Roll
2 Days
Installation of
Downspout
6 Days
Installation of
Solar Lighting
3 Days
Concreting Pathway
2 Days
Installation of Cyclone Wire
6.5 Days
Installation of Railings
2 Days
Painting
wall, beams, columns
43.5 Days
Installation of
Ceiling
12 Days
Painting
roof
38 Days
Painting
Ceiling
11.5 Days
Demobilization
10 Days
306.5 Days
190.5 Days
Clearing and
Grubbing
(Existing)
2.5 Days
Demolition Works (Manual)
0.5 Day
Excavation
0.5 Day
Hauling Soil (removing and carrying back)
2 Day
Rebar Fabrication (Footing)
1 Day
0.5 Day
Rebar Installation
(footing)
1 Day
Rebar Fabrication
(Pedestal)
0.5 Day
Rebar Installation
(Pedestal)
3 Day
Concreting
(footing)
0.5 Day
Concreting
(pedestal)
0.5 Day
Backfilling
0.5 Day
Rebar Fabrication
(Lateral Ties)
0.5 Day
Rebar Installation
(Lateral Ties)
1 Day
Installation of
Columns (Landing)
1 Day
Stair Framework
Installation
1 Day
Installation of
Beams (Landing)
4 Day
Stair Slab
Installation
3Day
Stair Railings
Installation
Installation of
Columns (Main)
Installation of
Beams (Main
3 Day
4 Day
Installation of
Slabs
3 Day 5Day
Roofing
Installation
3 Day
Roof
Painting
1Day
Pedestal
Painting
Frame Installation
1 Day
Slab Installation
1 Day
Water Tank Installation
1 Day
Electrical Rough-in G.F.
2 Days
Plumbing Finishing
14 Days
Electrical Finishing G.F.
7 Days
Electrical Rough-in S.F.
2 Days
Electrical
Finishing
S.F.
7 Days
Mobilization
5 Days
Demolition Works (Machine)
1.5 Days
Demolition Works (Manual)
3 Days
Clearing and Grubbing
(New Area)
3.5 Days
Site Grading
12 Days
Excavation
23 Days
Rebar Fabrication
(Parking Lot)
8.5 Days
Rebar Installation
(Parking
Lot)
4 Days
Concreting
(Parking
Lot)
3.5 Days Rebar Installation
(Foundation)
11 Days
Plumbing Rough-in
2 Days
Concreting
(Wall Footing)
1.5 Days
Rebar Installation
(Drainage)
1 Day
Rebar Installation
(CR Foundation)
1 Day
Installation of CHB
(Underlying Chb, Septic tank
& Drainage)
6 Days
Concreting
(Drainage)
2 Days
Concreting
(Septic tank)
0.5 Day
Installation
(Columns)
3 Days
Rebar
Fabrication
(Market
Stands)
2 Days
Rebar
Installation
(Market
Stands)
2 Days
Installation of CHB
(Market
Stands)
6 Days
Concreting
(Market
Stands)
1 Day
Tileworks
(Market
Stands)
17.5 Days
Concreting
(Foundation)
37 Days
Hauling common
borrow
2 Days
Manual backfill
2 Days
Rebar Installation
(Lateral
Ties)
2 Days
Rebar Installation
(C.R. Lateral
Ties)
0.5 Day
Installation of
Formworks
(Columns)
4 Days
Concreting
(Columns)
10 Days
Backfilling
2.5 Days
Hauling common borrow
20.5 Days
Installation of Wall CHB
34.5 Days
Installation of Wall Rebars
2.5 Days
Installation of Wall CHB (CR)
1 Day
Installation of Wall Rebars
(CR)
2.5 Days
Installation Rebar
(Slabs G.F)
11 Days
Concreting
(Slab ground floor
and CR)
31 Days
Installation Rebar
(Slabs C.R)
2 Days
Installation Rebar
(Beams)
10 Days
Installation Rebar
(Stirrups)
3 Days
Installation of
Formworks
(Beam 2nd floor)
6 Days
Concreting
(Beam)
13.5 Days
Fabrication Rebar
(Slab S.F.)
33.5 Days
Fabrication Rebar
(Wall S.F.)
3 Days
Fabrication Rebar
(Column S.F.)
3.5 Days
Fabrication Rebar
(Column Lateral
Ties S.F.)
2 Days
Fabrication Rebar
(Beams S.F.)
9 Days
Fabrication Rebar
(Stirrups S.F.)
2.5 Days
Rebar Installation
(Cr Column
& Footing)
2 Days
Rebar Fabrication
(Drainage)
1 Day
Rebar Fabrication
(CR Foundation)
1 Day
Rebar Fabrication
(CR Column
and Footing)
1 Day
Rebar Fabrication
(Foundation)
22.5 Days
Rebar Fabrication
(Lateral Ties)
1 Day
Rebar Fabrication
(CR Lateral Ties)
0.5 Day
Rebar Fabrication
(Wall)
3.5 Day
Rebar Fabrication
(CR Wall)
1 Day
Rebar Fabrication
(Slab G.F.)
57.5 Days
Rebar Fabrication
(Slab C.R.)
1 Day
Rebar Fabrication
(Beams)
22 Day
Rebar Fabrication
(Stirrups)
6 Days
Formwork Fabrication
(Column 1st floor)
11 Days
Formwork Fabrication
(Beam 1st floor)
39 Days
Formwork Fabrication
(Column 2nd floor)
18.5 Days
Formwork Fabrication
(Beams 2nd floor)
14.5 Days
Removal of
Formworks
(Columns)
4 Days
Removal of
Formworks
(Beam 2nd floor)
6 Days
Installation of
Formworks
(Slab)
7 Days
Concreting
(Slab 2nd floor)
20.5 Days
Installation Rebar
(Slab)
7 Days
Installation Rebar
(Columns S.F.)
2 Days
Installation of
Formworks
(Columns S.F.)
3 Days
Installation Rebar
(Lateral ties S.F.)
2 Days
Concreting
(Column 2nd floor)
7.5 Days
Removal of
Formworks
(Columns S.F.)
3 Days
Installation of Wall CHB S.F.
29.5 Days
Installation of Wall Rebars
S.F.
2 Days
Installation Rebar
(Beams Roof)
4 Days
Installation Rebar
(Stirrups Roof)
3 Days
Installation of
Formworks
(Roof beam)
3 Days
Concreting
(Roof beam)
4 Days
Removal of
Formworks
(Roof beam)
3 Days
Installation of Truss
(B1 Wings)
15 Days
Installation of Truss
(B1 lower mid)
11 Days
Installation of Truss
(B1 upper mid)
6 Days
Installation of Truss
(B2 Wings)
10Days
Installation of Truss
(B2 mid)
7 Days
Plastering
(Septic tank, Drainage,
Market Stands)
7.5 Days
Installation of Steel Doors
51 Days
Installation of Wooden Doors
1 Day
Plastering
(Wall)
65.5 Days
Plastering
(Columns, beams,
market stands)
31.5 Days
Installation of
Roofing
46.5 Days
Installation Gutter
and Flashing
16.5 Days
Installation of
Ridge Roll
2 Days
Installation of
Downspout
6 Days
Installation of
Solar Lighting
3 Days
Concreting Pathway
2 Days
Installation of Cyclone Wire
6.5 Days
Installation of Railings
2 Days
Painting
wall, beams, columns
43.5 Days
Installation of
Ceiling
12 Days
Painting
roof
38 Days
Painting
Ceiling
11.5 Days
Demobilization
10 Days
306.5 Days
190.5 Days
Clearing and
Grubbing
(Existing)
2.5 Days
Demolition Works (Manual)
0.5 Day
Excavation
0.5 Day
Hauling Soil (removing and carrying back)
2 Day
Rebar Fabrication (Footing)
1 Day
0.5 Day
Rebar Installation
(footing)
1 Day
Rebar Fabrication
(Pedestal)
0.5 Day
Rebar Installation
(Pedestal)
3 Day
Concreting
(footing)
0.5 Day
Concreting
(pedestal)
0.5 Day
Backfilling
0.5 Day
Rebar Fabrication
(Lateral Ties)
0.5 Day
Rebar Installation
(Lateral Ties)
1 Day
Installation of
Columns (Landing)
1 Day
Stair Framework
Installation
1 Day
Installation of
Beams (Landing)
4 Day
Stair Slab
Installation
3Day
Stair Railings
Installation
Installation of
Columns (Main)
Installation of
Beams (Main
3 Day
4 Day
Installation of
Slabs
3 Day 5Day
Roofing
Installation
3 Day
Roof
Painting
1Day
Pedestal
Painting
Frame Installation
1 Day
Slab Installation
1 Day
Water Tank Installation
1 Day
Electrical Rough-in G.F.
2 Days
Plumbing Finishing
14 Days
Electrical Finishing G.F.
7 Days
Electrical Rough-in S.F.
2 Days
Electrical
Finishing
S.F.
7 Days
Mobilization
5 Days
Demolition Works (Machine)
1.5 Days
Demolition Works (Manual)
3 Days
Clearing and Grubbing
(New Area)
3.5 Days
Site Grading
12 Days
Excavation
23 Days
Rebar Fabrication
(Parking Lot)
8.5 Days
Rebar Installation
(Parking
Lot)
4 Days
Concreting
(Parking
Lot)
3.5 Days Rebar Installation
(Foundation)
11 Days
Plumbing Rough-in
2 Days
Concreting
(Wall Footing)
1.5 Days
Rebar Installation
(Drainage)
1 Day
Rebar Installation
(CR Foundation)
1 Day
Installation of CHB
(Underlying Chb, Septic tank
& Drainage)
6 Days
Concreting
(Drainage)
2 Days
Concreting
(Septic tank)
0.5 Day
Installation
(Columns)
3 Days
Rebar
Fabrication
(Market
Stands)
2 Days
Rebar
Installation
(Market
Stands)
2 Days
Installation of CHB
(Market
Stands)
6 Days
Concreting
(Market
Stands)
1 Day
Tileworks
(Market
Stands)
17.5 Days
Concreting
(Foundation)
37 Days
Hauling common
borrow
2 Days
Manual backfill
2 Days
Rebar Installation
(Lateral
Ties)
2 Days
Rebar Installation
(C.R. Lateral
Ties)
0.5 Day
Installation of
Formworks
(Columns)
4 Days
Concreting
(Columns)
10 Days
Backfilling
2.5 Days
Hauling common borrow
20.5 Days
Installation of Wall CHB
34.5 Days
Installation of Wall Rebars
2.5 Days
Installation of Wall CHB (CR)
1 Day
Installation of Wall Rebars
(CR)
2.5 Days
Installation Rebar
(Slabs G.F)
11 Days
Concreting
(Slab ground floor
and CR)
31 Days
Installation Rebar
(Slabs C.R)
2 Days
Installation Rebar
(Beams)
10 Days
Installation Rebar
(Stirrups)
3 Days
Installation of
Formworks
(Beam 2nd floor)
6 Days
Concreting
(Beam)
13.5 Days
Fabrication Rebar
(Slab S.F.)
33.5 Days
Fabrication Rebar
(Wall S.F.)
3 Days
Fabrication Rebar
(Column S.F.)
3.5 Days
Fabrication Rebar
(Column Lateral
Ties S.F.)
2 Days
Fabrication Rebar
(Beams S.F.)
9 Days
Fabrication Rebar
(Stirrups S.F.)
2.5 Days
Rebar Installation
(Cr Column
& Footing)
2 Days
Rebar Fabrication
(Drainage)
1 Day
Rebar Fabrication
(CR Foundation)
1 Day
Rebar Fabrication
(CR Column
and Footing)
1 Day
Rebar Fabrication
(Foundation)
22.5 Days
Rebar Fabrication
(Lateral Ties)
1 Day
Rebar Fabrication
(CR Lateral Ties)
0.5 Day
Rebar Fabrication
(Wall)
3.5 Day
Rebar Fabrication
(CR Wall)
1 Day
Rebar Fabrication
(Slab G.F.)
57.5 Days
Rebar Fabrication
(Slab C.R.)
1 Day
Rebar Fabrication
(Beams)
22 Day
Rebar Fabrication
(Stirrups)
6 Days
Formwork Fabrication
(Column 1st floor)
11 Days
Formwork Fabrication
(Beam 1st floor)
39 Days
Formwork Fabrication
(Column 2nd floor)
18.5 Days
Formwork Fabrication
(Beams 2nd floor)
14.5 Days
Removal of
Formworks
(Columns)
4 Days
Removal of
Formworks
(Beam 2nd floor)
6 Days
Installation of
Formworks
(Slab)
7 Days
Concreting
(Slab 2nd floor)
20.5 Days
Installation Rebar
(Slab)
7 Days
Installation Rebar
(Columns S.F.)
2 Days
Installation of
Formworks
(Columns S.F.)
3 Days
Installation Rebar
(Lateral ties S.F.)
2 Days
Concreting
(Column 2nd floor)
7.5 Days
Removal of
Formworks
(Columns S.F.)
3 Days
Installation of Wall CHB S.F.
29.5 Days
Installation of Wall Rebars
S.F.
2 Days
Installation Rebar
(Beams Roof)
4 Days
Installation Rebar
(Stirrups Roof)
3 Days
Installation of
Formworks
(Roof beam)
3 Days
Concreting
(Roof beam)
4 Days
Removal of
Formworks
(Roof beam)
3 Days
Installation of Truss
(B1 Wings)
15 Days
Installation of Truss
(B1 lower mid)
11 Days
Installation of Truss
(B1 upper mid)
6 Days
Installation of Truss
(B2 Wings)
10Days
Installation of Truss
(B2 mid)
7 Days
Plastering
(Septic tank, Drainage,
Market Stands)
7.5 Days
Installation of Steel Doors
51 Days
Installation of Wooden Doors
1 Day
Plastering
(Wall)
65.5 Days
Plastering
(Columns, beams,
market stands)
31.5 Days
Installation of
Roofing
46.5 Days
Installation Gutter
and Flashing
16.5 Days
Installation of
Ridge Roll
2 Days
Installation of
Downspout
6 Days
Installation of
Solar Lighting
3 Days
Concreting Pathway
2 Days
Installation of Cyclone Wire
6.5 Days
Installation of Railings
2 Days
Painting
wall, beams, columns
43.5 Days
Installation of
Ceiling
12 Days
Painting
roof
38 Days
Painting
Ceiling
11.5 Days
Demobilization
10 Days
306.5 Days
190.5 Days
Clearing and
Grubbing
(Existing)
2.5 Days
Demolition Works (Manual)
0.5 Day
Excavation
0.5 Day
Hauling Soil (removing and carrying back)
2 Day
Rebar Fabrication (Footing)
1 Day
0.5 Day
Rebar Installation
(footing)
1 Day
Rebar Fabrication
(Pedestal)
0.5 Day
Rebar Installation
(Pedestal)
3 Day
Concreting
(footing)
0.5 Day
Concreting
(pedestal)
0.5 Day
Backfilling
0.5 Day
Rebar Fabrication
(Lateral Ties)
0.5 Day
Rebar Installation
(Lateral Ties)
1 Day
Installation of
Columns (Landing)
1 Day
Stair Framework
Installation
1 Day
Installation of
Beams (Landing)
4 Day
Stair Slab
Installation
3Day
Stair Railings
Installation
Installation of
Columns (Main)
Installation of
Beams (Main
3 Day
4 Day
Installation of
Slabs
3 Day 5Day
Roofing
Installation
3 Day
Roof
Painting
1Day
Pedestal
Painting
Frame Installation
1 Day
Slab Installation
1 Day
Water Tank Installation
1 Day
Electrical Rough-in G.F.
2 Days
Plumbing Finishing
14 Days
Electrical Finishing G.F.
7 Days
Electrical Rough-in S.F.
2 Days
Electrical
Finishing
S.F.
7 Days
Mobilization
5 Days
Demolition Works (Machine)
1.5 Days
Demolition Works (Manual)
3 Days
Clearing and Grubbing
(New Area)
3.5 Days
Site Grading
12 Days
Excavation
23 Days
Rebar Fabrication
(Parking Lot)
8.5 Days
Rebar Installation
(Parking
Lot)
4 Days
Concreting
(Parking
Lot)
3.5 Days Rebar Installation
(Foundation)
11 Days
Plumbing Rough-in
2 Days
Concreting
(Wall Footing)
1.5 Days
Rebar Installation
(Drainage)
1 Day
Rebar Installation
(CR Foundation)
1 Day
Installation of CHB
(Underlying Chb, Septic tank
& Drainage)
6 Days
Concreting
(Drainage)
2 Days
Concreting
(Septic tank)
0.5 Day
Installation
(Columns)
3 Days
Rebar
Fabrication
(Market
Stands)
2 Days
Rebar
Installation
(Market
Stands)
2 Days
Installation of CHB
(Market
Stands)
6 Days
Concreting
(Market
Stands)
1 Day
Tileworks
(Market
Stands)
17.5 Days
Concreting
(Foundation)
37 Days
Hauling common
borrow
2 Days
Manual backfill
2 Days
Rebar Installation
(Lateral
Ties)
2 Days
Rebar Installation
(C.R. Lateral
Ties)
0.5 Day
Installation of
Formworks
(Columns)
4 Days
Concreting
(Columns)
10 Days
Backfilling
2.5 Days
Hauling common borrow
20.5 Days
Installation of Wall CHB
34.5 Days
Installation of Wall Rebars
2.5 Days
Installation of Wall CHB (CR)
1 Day
Installation of Wall Rebars
(CR)
2.5 Days
Installation Rebar
(Slabs G.F)
11 Days
Concreting
(Slab ground floor
and CR)
31 Days
Installation Rebar
(Slabs C.R)
2 Days
Installation Rebar
(Beams)
10 Days
Installation Rebar
(Stirrups)
3 Days
Installation of
Formworks
(Beam 2nd floor)
6 Days
Concreting
(Beam)
13.5 Days
Fabrication Rebar
(Slab S.F.)
33.5 Days
Fabrication Rebar
(Wall S.F.)
3 Days
Fabrication Rebar
(Column S.F.)
3.5 Days
Fabrication Rebar
(Column Lateral
Ties S.F.)
2 Days
Fabrication Rebar
(Beams S.F.)
9 Days
Fabrication Rebar
(Stirrups S.F.)
2.5 Days
Rebar Installation
(Cr Column
& Footing)
2 Days
Rebar Fabrication
(Drainage)
1 Day
Rebar Fabrication
(CR Foundation)
1 Day
Rebar Fabrication
(CR Column
and Footing)
1 Day
Rebar Fabrication
(Foundation)
22.5 Days
Rebar Fabrication
(Lateral Ties)
1 Day
Rebar Fabrication
(CR Lateral Ties)
0.5 Day
Rebar Fabrication
(Wall)
3.5 Day
Rebar Fabrication
(CR Wall)
1 Day
Rebar Fabrication
(Slab G.F.)
57.5 Days
Rebar Fabrication
(Slab C.R.)
1 Day
Rebar Fabrication
(Beams)
22 Day
Rebar Fabrication
(Stirrups)
6 Days
Formwork Fabrication
(Column 1st floor)
11 Days
Formwork Fabrication
(Beam 1st floor)
39 Days
Formwork Fabrication
(Column 2nd floor)
18.5 Days
Formwork Fabrication
(Beams 2nd floor)
14.5 Days
Removal of
Formworks
(Columns)
4 Days
Removal of
Formworks
(Beam 2nd floor)
6 Days
Installation of
Formworks
(Slab)
7 Days
Concreting
(Slab 2nd floor)
20.5 Days
Installation Rebar
(Slab)
7 Days
Installation Rebar
(Columns S.F.)
2 Days
Installation of
Formworks
(Columns S.F.)
3 Days
Installation Rebar
(Lateral ties S.F.)
2 Days
Concreting
(Column 2nd floor)
7.5 Days
Removal of
Formworks
(Columns S.F.)
3 Days
Installation of Wall CHB S.F.
29.5 Days
Installation of Wall Rebars
S.F.
2 Days
Installation Rebar
(Beams Roof)
4 Days
Installation Rebar
(Stirrups Roof)
3 Days
Installation of
Formworks
(Roof beam)
3 Days
Concreting
(Roof beam)
4 Days
Removal of
Formworks
(Roof beam)
3 Days
Installation of Truss
(B1 Wings)
15 Days
Installation of Truss
(B1 lower mid)
11 Days
Installation of Truss
(B1 upper mid)
6 Days
Installation of Truss
(B2 Wings)
10Days
Installation of Truss
(B2 mid)
7 Days
Plastering
(Septic tank, Drainage,
Market Stands)
7.5 Days
Installation of Steel Doors
51 Days
Installation of Wooden Doors
1 Day
Plastering
(Wall)
65.5 Days
Plastering
(Columns, beams,
market stands)
31.5 Days
Installation of
Roofing
46.5 Days
Installation Gutter
and Flashing
16.5 Days
Installation of
Ridge Roll
2 Days
Installation of
Downspout
6 Days
Installation of
Solar Lighting
3 Days
Concreting Pathway
2 Days
Installation of Cyclone Wire
6.5 Days
Installation of Railings
2 Days
Painting
wall, beams, columns
43.5 Days
Installation of
Ceiling
12 Days
Painting
roof
38 Days
Painting
Ceiling
11.5 Days
Demobilization
10 Days
306.5 Days
190.5 Days
Clearing and
Grubbing
(Existing)
2.5 Days
Demolition Works (Manual)
0.5 Day
Excavation
0.5 Day
Hauling Soil (removing and carrying back)
2 Day
Rebar Fabrication (Footing)
1 Day
0.5 Day
Rebar Installation
(footing)
1 Day
Rebar Fabrication
(Pedestal)
0.5 Day
Rebar Installation
(Pedestal)
3 Day
Concreting
(footing)
0.5 Day
Concreting
(pedestal)
0.5 Day
Backfilling
0.5 Day
Rebar Fabrication
(Lateral Ties)
0.5 Day
Rebar Installation
(Lateral Ties)
1 Day
Installation of
Columns (Landing)
1 Day
Stair Framework
Installation
1 Day
Installation of
Beams (Landing)
4 Day
Stair Slab
Installation
3Day
Stair Railings
Installation
Installation of
Columns (Main)
Installation of
Beams (Main
3 Day
4 Day
Installation of
Slabs
3 Day 5Day
Roofing
Installation
3 Day
Roof
Painting
1Day
Pedestal
Painting
Frame Installation
1 Day
Slab Installation
1 Day
Water Tank Installation
1 Day
Electrical Rough-in G.F.
2 Days
Plumbing Finishing
14 Days
Electrical Finishing G.F.
7 Days
Electrical Rough-in S.F.
2 Days
Electrical
Finishing
S.F.
7 Days
Mobilization
5 Days
Demolition Works (Machine)
1.5 Days
Demolition Works (Manual)
3 Days
Clearing and Grubbing
(New Area)
3.5 Days
Site Grading
12 Days
Excavation
23 Days
Rebar Fabrication
(Parking Lot)
8.5 Days
Rebar Installation
(Parking
Lot)
4 Days
Concreting
(Parking
Lot)
3.5 Days Rebar Installation
(Foundation)
11 Days
Plumbing Rough-in
2 Days
Concreting
(Wall Footing)
1.5 Days
Rebar Installation
(Drainage)
1 Day
Rebar Installation
(CR Foundation)
1 Day
Installation of CHB
(Underlying Chb, Septic tank
& Drainage)
6 Days
Concreting
(Drainage)
2 Days
Concreting
(Septic tank)
0.5 Day
Installation
(Columns)
3 Days
Rebar
Fabrication
(Market
Stands)
2 Days
Rebar
Installation
(Market
Stands)
2 Days
Installation of CHB
(Market
Stands)
6 Days
Concreting
(Market
Stands)
1 Day
Tileworks
(Market
Stands)
17.5 Days
Concreting
(Foundation)
37 Days
Hauling common
borrow
2 Days
Manual backfill
2 Days
Rebar Installation
(Lateral
Ties)
2 Days
Rebar Installation
(C.R. Lateral
Ties)
0.5 Day
Installation of
Formworks
(Columns)
4 Days
Concreting
(Columns)
10 Days
Backfilling
2.5 Days
Hauling common borrow
20.5 Days
Installation of Wall CHB
34.5 Days
Installation of Wall Rebars
2.5 Days
Installation of Wall CHB (CR)
1 Day
Installation of Wall Rebars
(CR)
2.5 Days
Installation Rebar
(Slabs G.F)
11 Days
Concreting
(Slab ground floor
and CR)
31 Days
Installation Rebar
(Slabs C.R)
2 Days
Installation Rebar
(Beams)
10 Days
Installation Rebar
(Stirrups)
3 Days
Installation of
Formworks
(Beam 2nd floor)
6 Days
Concreting
(Beam)
13.5 Days
Fabrication Rebar
(Slab S.F.)
33.5 Days
Fabrication Rebar
(Wall S.F.)
3 Days
Fabrication Rebar
(Column S.F.)
3.5 Days
Fabrication Rebar
(Column Lateral
Ties S.F.)
2 Days
Fabrication Rebar
(Beams S.F.)
9 Days
Fabrication Rebar
(Stirrups S.F.)
2.5 Days
Rebar Installation
(Cr Column
& Footing)
2 Days
Rebar Fabrication
(Drainage)
1 Day
Rebar Fabrication
(CR Foundation)
1 Day
Rebar Fabrication
(CR Column
and Footing)
1 Day
Rebar Fabrication
(Foundation)
22.5 Days
Rebar Fabrication
(Lateral Ties)
1 Day
Rebar Fabrication
(CR Lateral Ties)
0.5 Day
Rebar Fabrication
(Wall)
3.5 Day
Rebar Fabrication
(CR Wall)
1 Day
Rebar Fabrication
(Slab G.F.)
57.5 Days
Rebar Fabrication
(Slab C.R.)
1 Day
Rebar Fabrication
(Beams)
22 Day
Rebar Fabrication
(Stirrups)
6 Days
Formwork Fabrication
(Column 1st floor)
11 Days
Formwork Fabrication
(Beam 1st floor)
39 Days
Formwork Fabrication
(Column 2nd floor)
18.5 Days
Formwork Fabrication
(Beams 2nd floor)
14.5 Days
Removal of
Formworks
(Columns)
4 Days
Removal of
Formworks
(Beam 2nd floor)
6 Days
Installation of
Formworks
(Slab)
7 Days
Concreting
(Slab 2nd floor)
20.5 Days
Installation Rebar
(Slab)
7 Days
Installation Rebar
(Columns S.F.)
2 Days
Installation of
Formworks
(Columns S.F.)
3 Days
Installation Rebar
(Lateral ties S.F.)
2 Days
Concreting
(Column 2nd floor)
7.5 Days
Removal of
Formworks
(Columns S.F.)
3 Days
Installation of Wall CHB S.F.
29.5 Days
Installation of Wall Rebars
S.F.
2 Days
Installation Rebar
(Beams Roof)
4 Days
Installation Rebar
(Stirrups Roof)
3 Days
Installation of
Formworks
(Roof beam)
3 Days
Concreting
(Roof beam)
4 Days
Removal of
Formworks
(Roof beam)
3 Days
Installation of Truss
(B1 Wings)
15 Days
Installation of Truss
(B1 lower mid)
11 Days
Installation of Truss
(B1 upper mid)
6 Days
Installation of Truss
(B2 Wings)
10Days
Installation of Truss
(B2 mid)
7 Days
Plastering
(Septic tank, Drainage,
Market Stands)
7.5 Days
Installation of Steel Doors
51 Days
Installation of Wooden Doors
1 Day
Plastering
(Wall)
65.5 Days
Plastering
(Columns, beams,
market stands)
31.5 Days
Installation of
Roofing
46.5 Days
Installation Gutter
and Flashing
16.5 Days
Installation of
Ridge Roll
2 Days
Installation of
Downspout
6 Days
Installation of
Solar Lighting
3 Days
Concreting Pathway
2 Days
Installation of Cyclone Wire
6.5 Days
Installation of Railings
2 Days
Painting
wall, beams, columns
43.5 Days
Installation of
Ceiling
12 Days
Painting
roof
38 Days
Painting
Ceiling
11.5 Days
Demobilization
10 Days
306.5 Days
190.5 Days
Clearing and
Grubbing
(Existing)
2.5 Days
Demolition Works (Manual)
0.5 Day
Excavation
0.5 Day
Hauling Soil (removing and carrying back)
2 Day
Rebar Fabrication (Footing)
1 Day
0.5 Day
Rebar Installation
(footing)
1 Day
Rebar Fabrication
(Pedestal)
0.5 Day
Rebar Installation
(Pedestal)
3 Day
Concreting
(footing)
0.5 Day
Concreting
(pedestal)
0.5 Day
Backfilling
0.5 Day
Rebar Fabrication
(Lateral Ties)
0.5 Day
Rebar Installation
(Lateral Ties)
1 Day
Installation of
Columns (Landing)
1 Day
Stair Framework
Installation
1 Day
Installation of
Beams (Landing)
4 Day
Stair Slab
Installation
3Day
Stair Railings
Installation
Installation of
Columns (Main)
Installation of
Beams (Main
3 Day
4 Day
Installation of
Slabs
3 Day 5Day
Roofing
Installation
3 Day
Roof
Painting
1Day
Pedestal
Painting
Frame Installation
1 Day
Slab Installation
1 Day
Water Tank Installation
1 Day
Electrical Rough-in G.F.
2 Days
Plumbing Finishing
14 Days
Electrical Finishing G.F.
7 Days
Electrical Rough-in S.F.
2 Days
Electrical
Finishing
S.F.
7 Days
Mobilization
5 Days
Demolition Works (Machine)
1.5 Days
Demolition Works (Manual)
3 Days
Clearing and Grubbing
(New Area)
3.5 Days
Site Grading
12 Days
Excavation
23 Days
Rebar Fabrication
(Parking Lot)
8.5 Days
Rebar Installation
(Parking
Lot)
4 Days
Concreting
(Parking
Lot)
3.5 Days Rebar Installation
(Foundation)
11 Days
Plumbing Rough-in
2 Days
Concreting
(Wall Footing)
1.5 Days
Rebar Installation
(Drainage)
1 Day
Rebar Installation
(CR Foundation)
1 Day
Installation of CHB
(Underlying Chb, Septic tank
& Drainage)
6 Days
Concreting
(Drainage)
2 Days
Concreting
(Septic tank)
0.5 Day
Installation
(Columns)
3 Days
Rebar
Fabrication
(Market
Stands)
2 Days
Rebar
Installation
(Market
Stands)
2 Days
Installation of CHB
(Market
Stands)
6 Days
Concreting
(Market
Stands)
1 Day
Tileworks
(Market
Stands)
17.5 Days
Concreting
(Foundation)
37 Days
Hauling common
borrow
2 Days
Manual backfill
2 Days
Rebar Installation
(Lateral
Ties)
2 Days
Rebar Installation
(C.R. Lateral
Ties)
0.5 Day
Installation of
Formworks
(Columns)
4 Days
Concreting
(Columns)
10 Days
Backfilling
2.5 Days
Hauling common borrow
20.5 Days
Installation of Wall CHB
34.5 Days
Installation of Wall Rebars
2.5 Days
Installation of Wall CHB (CR)
1 Day
Installation of Wall Rebars
(CR)
2.5 Days
Installation Rebar
(Slabs G.F)
11 Days
Concreting
(Slab ground floor
and CR)
31 Days
Installation Rebar
(Slabs C.R)
2 Days
Installation Rebar
(Beams)
10 Days
Installation Rebar
(Stirrups)
3 Days
Installation of
Formworks
(Beam 2nd floor)
6 Days
Concreting
(Beam)
13.5 Days
Fabrication Rebar
(Slab S.F.)
33.5 Days
Fabrication Rebar
(Wall S.F.)
3 Days
Fabrication Rebar
(Column S.F.)
3.5 Days
Fabrication Rebar
(Column Lateral
Ties S.F.)
2 Days
Fabrication Rebar
(Beams S.F.)
9 Days
Fabrication Rebar
(Stirrups S.F.)
2.5 Days
Rebar Installation
(Cr Column
& Footing)
2 Days
Rebar Fabrication
(Drainage)
1 Day
Rebar Fabrication
(CR Foundation)
1 Day
Rebar Fabrication
(CR Column
and Footing)
1 Day
Rebar Fabrication
(Foundation)
22.5 Days
Rebar Fabrication
(Lateral Ties)
1 Day
Rebar Fabrication
(CR Lateral Ties)
0.5 Day
Rebar Fabrication
(Wall)
3.5 Day
Rebar Fabrication
(CR Wall)
1 Day
Rebar Fabrication
(Slab G.F.)
57.5 Days
Rebar Fabrication
(Slab C.R.)
1 Day
Rebar Fabrication
(Beams)
22 Day
Rebar Fabrication
(Stirrups)
6 Days
Formwork Fabrication
(Column 1st floor)
11 Days
Formwork Fabrication
(Beam 1st floor)
39 Days
Formwork Fabrication
(Column 2nd floor)
18.5 Days
Formwork Fabrication
(Beams 2nd floor)
14.5 Days
Removal of
Formworks
(Columns)
4 Days
Removal of
Formworks
(Beam 2nd floor)
6 Days
Installation of
Formworks
(Slab)
7 Days
Concreting
(Slab 2nd floor)
20.5 Days
Installation Rebar
(Slab)
7 Days
Installation Rebar
(Columns S.F.)
2 Days
Installation of
Formworks
(Columns S.F.)
3 Days
Installation Rebar
(Lateral ties S.F.)
2 Days
Concreting
(Column 2nd floor)
7.5 Days
Removal of
Formworks
(Columns S.F.)
3 Days
Installation of Wall CHB S.F.
29.5 Days
Installation of Wall Rebars
S.F.
2 Days
Installation Rebar
(Beams Roof)
4 Days
Installation Rebar
(Stirrups Roof)
3 Days
Installation of
Formworks
(Roof beam)
3 Days
Concreting
(Roof beam)
4 Days
Removal of
Formworks
(Roof beam)
3 Days
Installation of Truss
(B1 Wings)
15 Days
Installation of Truss
(B1 lower mid)
11 Days
Installation of Truss
(B1 upper mid)
6 Days
Installation of Truss
(B2 Wings)
10Days
Installation of Truss
(B2 mid)
7 Days
Plastering
(Septic tank, Drainage,
Market Stands)
7.5 Days
Installation of Steel Doors
51 Days
Installation of Wooden Doors
1 Day
Plastering
(Wall)
65.5 Days
Plastering
(Columns, beams,
market stands)
31.5 Days
Installation of
Roofing
46.5 Days
Installation Gutter
and Flashing
16.5 Days
Installation of
Ridge Roll
2 Days
Installation of
Downspout
6 Days
Installation of
Solar Lighting
3 Days
Concreting Pathway
2 Days
Installation of Cyclone Wire
6.5 Days
Installation of Railings
2 Days
Painting
wall, beams, columns
43.5 Days
Installation of
Ceiling
12 Days
Painting
roof
38 Days
Painting
Ceiling
11.5 Days
Demobilization
10 Days
306.5 Days
190.5 Days
Clearing and
Grubbing
(Existing)
2.5 Days
Demolition Works (Manual)
0.5 Day
Excavation
0.5 Day
Hauling Soil (removing and carrying back)
2 Day
Rebar Fabrication (Footing)
1 Day
0.5 Day
Rebar Installation
(footing)
1 Day
Rebar Fabrication
(Pedestal)
0.5 Day
Rebar Installation
(Pedestal)
3 Day
Concreting
(footing)
0.5 Day
Concreting
(pedestal)
0.5 Day
Backfilling
0.5 Day
Rebar Fabrication
(Lateral Ties)
0.5 Day
Rebar Installation
(Lateral Ties)
1 Day
Installation of
Columns (Landing)
1 Day
Stair Framework
Installation
1 Day
Installation of
Beams (Landing)
4 Day
Stair Slab
Installation
3Day
Stair Railings
Installation
Installation of
Columns (Main)
Installation of
Beams (Main
3 Day
4 Day
Installation of
Slabs
3 Day 5Day
Roofing
Installation
3 Day
Roof
Painting
1Day
Pedestal
Painting
Frame Installation
1 Day
Slab Installation
1 Day
Water Tank Installation
1 Day
Electrical Rough-in G.F.
2 Days
Plumbing Finishing
14 Days
Electrical Finishing G.F.
7 Days
Electrical Rough-in S.F.
2 Days
Electrical
Finishing
S.F.
7 Days