ID Task Name Duration Start Finish Predecessors

1 33 KV dedicated supply for M/s. Sundaram Fasteners


Limited, Hosur from 230 KV TNEB substation
108 days Fri 11/2/12 Sat 3/30/13
2 33 KV Line and Bay extension works 101.63 days Fri 11/2/12 Thu 3/21/13
3 Receipt of PO 1 day Fri 11/2/12 Fri 11/2/12
4 Receipt of advance amount 1 day Fri 11/16/12 Fri 11/16/12 3
5 submission of application to TNEB 1 day Sat 11/10/12 Sat 11/10/123
6 Registration of application byTNEB 10 days Sat 11/10/12 Sat 11/24/125
7 conducting route surveyand concluding on the BOM 5 days Sat 11/24/12 Sat 12/1/126
8 Receipt of EMD advice 15 days Sat 12/1/12 Sat 12/22/127
9 Payment of EMD amount to TNEB 2 days Sat 12/22/12 Wed 12/26/128
10 Ordering of materials 5 days Wed 12/26/12 Tue 1/1/139
11 Receipt of Developmental charges 15 days Wed 1/2/13 Tue 1/22/1310
12 Payment of developmental charges 3 days Tue 1/22/13 Fri 1/25/13 11
13 Executing agreement with TNEB 2 days Fri 1/25/13 Tue 1/29/1312
14 Receipt of materials 20 days Tue 1/29/13 Sat 2/23/1313
15 Foundation for Poles 5 days Tue 2/26/13 Sat 3/2/1314
16 Erection of poles with cross arms 5 days Sat 3/2/13 Sat 3/9/1315
17 Stringing of line 5 days Sat 3/9/13 Sat 3/16/1316
18 Testing 3 days Sat 3/16/13 Thu 3/21/1317
19 33 KV works in substation 97 days Sat 11/3/12 Sat 3/16/13
20 Ordering of major materials like Transformer
and VCB panels, Cables etc
1 day Sat 11/17/12 Sat 11/17/123,4
21 Ordering of other materials 12 days Sat 11/3/12 Tue 11/20/123
22 Receipt of major materials 70 days Sat 11/17/12 Fri 2/22/13 20
23 Receipt of other materials 20 days Tue 11/20/12 Tue 12/18/1221
24 Civil foundation for all equipments 15 days Tue 11/20/12 Tue 12/11/1220,21
25 Erection of Transformer 2 days Fri 2/22/13 Tue 2/26/1322,23,24
26 Erection of VCB panels 2 days Fri 2/22/13 Tue 2/26/1322,23,24
27 Erection of other equipment and cable laying 10 days Fri 2/22/13 Thu 3/7/1322,23,24
28 Earthing works 5 days Fri 3/8/13 Thu 3/14/1325,26,27
29 Cable termination works 3 days Fri 3/8/13 Tue 3/12/1325,26,27
30 Testing 2 days Thu 3/14/13 Sat 3/16/1328,29
31 CEIG works 107 days Sat 11/3/12 Sat 3/30/13
32 Submission of drawings 20 days Sat 11/3/12 Fri 11/30/12 3
33 Getting drawing approval 30 days Fri 11/30/12 Thu 1/10/1332
34 Arranging for inspection 5 days Sat 3/16/13 Sat 3/23/1330,33
35 Getting safetycertificate 5 days Sat 3/23/13 Sat 3/30/1334
36 TNEB energising supply 3 days Sat 3/23/13 Thu 3/28/1334,18
37 Handing over 2 days Thu 3/28/13 Sat 3/30/1336,18
18%
20%
100%
100%
100%
70%
100%
0%
0%
100%
0%
0%
0%
0%
0%
0%
0%
0%
25%
100%
100%
0%
100%
20%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
3/30
3/28
3/30
Oct Nov Dec J an Feb Mar Apr
4th Quarter 1st Quarter 2nd Quarter
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Baseline
Baseline Split
Baseline Milestone
Milestone
SummaryProgress
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 1
Project: sundaramfasteners
Date: Thu 11/29/12