Anda di halaman 1dari 8

5/20/2014 Turbine load rejection N300-16.

7/537/537 Study | Science and Technology


http://www.nt20.com/index.php/archives/1468 1/8
Turbine load rejection N300-
16.7/537/537 Study
sd / December 5, 2013
Abstract: China Resources Power Hunan Liyujiang Limited Unit 2 (300 MW) using the
conventional method of load rejection test, and for the suppression overspeed protection
control (OPC) of the frequent movement and preventing secondary soaring speed issues
, proposes to optimize digital electro-hydraulic control system (DEH) in logic and OPC
operation as soon as possible after the load rejection reheat steam pressure reducing
insights for large load rejection test reference and learn from.
words: steam turbine; digital electro-hydraulic control system; overspeed protection
control device; 300 MW unit; load rejection; speed; quadratic soaring
Abstract: The load rejecting test with conventional method on Unit 2 (300 MW) of China
Resources Power Hunan Liyujiang Co., Ltd. is described. To restrain the frequent action
of over speed protection control (OPC) and to prevent secondary acceleration over
speed, it is suggested that OPC acting logic in digital electronichydraulic system (DEH)
should be optimized and the reheat steam pressure be lowered as soon as possible
after load rejection, thus providing reference for load rejecting test on large units.
Key words: steam turbine; DEH; OPC; 300 MW unit; load rejection; rotational speed;
secondary acceleration overspeed
Hunan, China Resources Power Liyujiang Turbine Co., the No. 2 Department of Harbin
Steam Turbine Co., Ltd. introduced the U.S. Westinghouse technology to produce
N300-16.7 / 537/537 type subcritical, single reheat, twin dual exhaust, uniaxial,
condensing steam turbine. Original State Power Corporation September 28, 2000
release of power to prevent major accidents Twenty-five key requirements in the
Prevention and shaft turbine overspeed fault accident clause provides for the
Science and Technology
Home
5/20/2014 Turbine load rejection N300-16.7/537/537 Study | Science and Technology
http://www.nt20.com/index.php/archives/1468 2/8
assessment of digital electro-hydraulic control system (DEH ) rocketing speed after load
shedding suppression function on technical solutions, testing instruments, meters,
DEH, the unit body and auxiliary equipment, ancillary equipment made full preparation,
on 27 August 2003 and 28 am, at the Unit 2 (300 MW) implemented a routine method
validation load rejection test, and achieved success.
load rejection test by a conventional method, to find out the Carp River Power Plant Unit
2 control system dynamic performance tests on the equipment throughout the plant load
rejection condition adaptability trials to achieve the desired purpose.
1 unit Introduction
China Resources Power Hunan Liyujiang Limited Unit 2 turbine DEH Control
Engineering from the Harbin Turbine Company Limited, using the Beijing Symphony
Bailey distributed control system to achieve.
design crew hanging gates, the high-pressure bypass can not be put into, in Bypass
Off state. Medium pressure regulating valve IV work is to take two valve approach, that
is, it does not participate in the regulation of unit speed or load. Thus, after the load
rejection, the pressure regulating valve opening IV inevitably lead unit speed soaring
again, there is the danger of speeding.
DEHs OPC (overspeed protection control) function actually contains two aspects: load
drop anticipator LDA; fly speed increased 103% of rated speed, overspeed protection
action. And the net does not make electrical or mechanical overspeed test the speed of
more than 3 090 r / min, OPC trigger until the speed is lower than 3 090 r / min reset;
generator main switch off instantly, and if the pressure cylinder exhaust steam pressure
(IEP ) Rating 15%, or greater than the measuring point fails, regardless of the rotational
speed at this time does not exceed 3 090 r / min, OPC operation of the solenoid valve to
be, the preset duration of 2 s. The two OPC function is actually complementary.
after the load rejection, DEH will automatically be forced to Operator Auto mode, the
speed, target and Setpoint are 3 000r/min.
2 pre-test preparation and improvement
2.1OPC
Given OPC simulation test load rejection characteristics essential stationary simulated
LDA trial, access to the main switch off open instantly to steam doors start closing time
delay, and close to empty the load position and a fully closed time and other
parameters; steam engine idling, when they actually tested the OPC at rated speed
103% when the loop action value and the valve closed time to confirm quickly and
reliably.
2.2LDA duration of action after the original design
LDA action, duration of 2 s. LDA action after the preset delay fundamental purpose is to
ensure that when LDA reset, the speed is still 3 090 r / min or more, the OPC 103% of
the set value circuit continues to operate. Fearing time is short, the time to delay 5 s.
2.3103% of the set value of the reset circuit is activated at speeds below the speed
if 3 090 r / min immediately reset, because the pressure regulator valve on the hydraulic
system limitations IV fixed-rate open faster, and The medium-pressure regulating valve
flow area is large, easy to cause the rotor to fly again rose to a higher speed. To this
5/20/2014 Turbine load rejection N300-16.7/537/537 Study | Science and Technology
http://www.nt20.com/index.php/archives/1468 3/8
end, the 103% value of the reset circuit is activated speed to 3 000 r / min.
2.4 to reheat steam pressure treatment
pressure bypass due after the load rejection can not be opened, cold reheat steam,
high-temperature reheat steam pipe must rely on a huge volume of steam in the
pressure regulator valve repeated IV Opening and low pressure bypass vent out. Load
shedding, it can quickly reheat steam pressure drops to a lower level is the key to
controlling the number of OPC operation. To this end, the development of the measures:
Considering the low pressure bypass pipeline longer and domestic 200 MW unit bypass
system had many incidents of strong vibrations and even blasting accidents, pre-open
low pressure bypass 5% for heating pipe;
load shedding, confirm reheat piping trap interlock open; immediately manually open low
pressure bypass to 40% to 50%, and then depending on the capacity of the bypass
itself and pipes situation quickly fully open; boiler reheater open-air assist relief valve
discharge, but must be closed before the pressure drops 0.3 MPa.
3 50% load rejection test results and analysis
rejection 50% load 100% load rejection test is a preliminary test by 50% load rejection
test, assessment of the OPC operating characteristics, LDA movement duration, high
pressure regulating valve (GV, IV) and the operating characteristics of the transient
process and characteristics rocketing speed. 50% load rejection and speed of operation
of the relationship between OPC shown in Figure 1.
right DEH control system, the first after the load rejection to prevent rocketing speed
function is achieved via OPC. Thus, from the moment the main switch tripping close to
the regulator valve to empty the load position determines the time interval of the first
rotor fly appreciation, requiring the sooner the better. The first rotor soaring extremum
3.064 r / min, the speed of 3 000r/min before load rejection of 2.13%, far less than the
industry standard DL/T711-1999 and experts recommend 5% of the required value, and
verify the OPC (LDA and 103% value) loop speed and reliability, can be 100% load
rejection test. 50% rejection of the second fly-load test appreciation 3 123 r / min higher,
but also shows the LDA operation delay of 5.0 s after the preset time (measured as
4.811 s) for rejection 50% load condition is not appropriate , it is recommended DEH no
quick closing valve (fast valving) functions under the premise of the release of the LDA
logical conditions to until the speed is lower than 3 000 r / min, the logic 100% load
rejection is also very effective.
4 100% load rejection test
4.1 rocketing speed transient process and analyze
load rejection before Turbine Speed 3 005 r / min, the generator main switch is turned
off, after 0.027 s delay , rotor speed began soaring, 2.573 s after rocketing speed up to
the first extreme 3 145 r / min.
, due to valve has been closed, the rotor begins to -0.489 5rad/s2 average angular
acceleration decreased by 32.303 s later reduced to 2 994 r / min. At this moment
before 0.937 s, OPC solenoid valves release, 0.653 s after the pressure regulator valve
starts to open IV, with IVs turn, speed up the secondary to continue soaring.
5/20/2014 Turbine load rejection N300-16.7/537/537 Study | Science and Technology
http://www.nt20.com/index.php/archives/1468 4/8
fly to second by 3.600 s Extreme 3 106 r / min, the average angular acceleration
3258rad/s2. Before the second extremum reached 1.067 s, because speed has
exceeded 3 090 r / min, OPC 103% setting circuit is activated, the valve closed loop
delay and it takes time (IV1 off time 0.12 s, IV2 off time 0.12 s ) and after the rotor
inertia up speed. continue rose 3 106 r / min.
reach extreme 3 106 r / min after 20.571 s, speed to low 2 995 r / min, the average
angular acceleration -0.565 1rad/s2. Because speed is lower than 3 000 r / min, at this
extreme point before 1.693 s, OPC 103% setting circuit release, 1.213s after the
pressure regulator valve IV1 starts to open, 1.240 s after the pressure regulator valve
begins to open IV2 , speed soaring again. 9.266 s up to third after the extreme 3 090 r /
min, the average angular acceleration 1.074rad/s2. In this extreme point before 0.360 s,
OPC103% setpoint loop due speed exceeds 3 090 r / min re-action, IV valve is closed,
IV1 off time 0.12 s, IV2 off time 0.094 s, the speed dropped.
16.967 s, the speed is reduced to 2 993 r / min, the average angular acceleration
-0.5987rad/s2. With the former principle, this extreme point reached before 1.214 s,
OPC1Z reset after 0.454 s IV1 starts to open, 0.520 s IV2 starts to open, but this time
by 85.325 s reheat steam boiler reheater time-to-air and low-pressure exhaust valve
Bypass release, has been reduced to a relatively low pressure level, the pressure
regulating valve is fully open, sufficient to fly the rotor speed increased to 3 090 r / min.
8.879 s after flying rose to a high point in the last extreme 3 007 r / min, 15.331 s after
the speed dropped to a low of 2 987 r / min. In the high-pressure regulator valve by DEH
instruction under the control of the speed stabilized at 2 993 r / min. 100% load rejection
transient reheated steam pressure shown in Figure 2, OPC, and the operation speed of
the relationship shown in Figure 3.
4.2 100% load rejection test results
eigenvalues eigenvalues calculated as follows:
a) dynamic speed overshoot = 4.66 %;
b) rotor angular acceleration r = 31.04rad / s;
c) the rotor time constant Tr = 10.13 s;
d) Rotor inertia J = 30 702.25 kg m2;
e) time constant steam volume Tv = 0.280 s.
4.3 100% load rejection Summary
generator main switch off after 5002, DEH OPC load anticipator circuit LDA action,
0.094 s after, OPC solenoid valve action, high pressure, medium pressure regulating
valve followed immediately quickly closed off time is less than 0.24 s.
100% load rejection after OPC and DEH joint action, to be effective in suppressing the
rotor speed soaring 4.66% (3 145r/min), less than the critical speed breaker Flyweight
action, and then stabilized at synchronous speed 2 994 r / min. By accurately
measuring the speed transient curve accurately obtain the time constant of the rotor
moment of inertia and other parameters.
LDA action 5.0 s after a preset delay time (measured as 4.811 s), its purpose is reset
when the LDA to ensure the speed is still 3 090 r / min or more, the OPC 103% setting
5/20/2014 Turbine load rejection N300-16.7/537/537 Study | Science and Technology
http://www.nt20.com/index.php/archives/1468 5/8
circuit continues to operate . Verified by experiment, 5 s delay time is appropriate. If
there is no valve DEH fast off function under the premise of the release of the LDA
logical conditions to until the speed is lower than 3 000 r / min, can achieve the same
purpose.
soaring in speed transient process, OPC common trigger three times, the first of which
is the LDA Since 5002 the main switch off while the pressure cylinder exhaust steam
pressure (IEP) is greater than 15% and 103% of rated joint action by To the other two by
the speed setpoint of 103% due to the role of the loop. From the domestic load rejection
test carried experience and information point of view, for the introduction of Harbin
Steam Turbine Plant Westinghouse technology to produce 300 MW units, because the
pressure regulating valve IV does not participate in speed adjustable to two valves
manner, in a 100% load rejection when, OPC 103% setpoint loop action only twice at 3
000r/min unit speed stability has not been reported. Accordingly, the second load
rejection test is successful, technically advanced. Jiaxing Power Plant Unit 2 is the
introduction of Shanghai Turbine Works Westinghouse technology to produce 300 MW
units, 50% of load rejection OPC operation 9 times 100% load rejection OPC operation
four times; Weihe Power Plant Unit 6 is produced by Harbin Turbine Works Imported
Type 300 MW units, 50% load rejection when the action four times, 100% load rejection
when the action five times; Waigaoqiao Power Plant Unit 3 is the introduction of
Shanghai Turbine plant of 300 MW Unit, 50% load rejection action six times , 100%
load rejection action 10 times; Songyu Power Plant Unit 2 (300 MW), 100% load
rejection action 13 times; Yiyang Power Plant Unit 1 Introduced (300 MW) accidental
load rejection, because there is no bypass design, OPC action 29 times.
5 Conclusions and recommendations
through the successful completion of Liyujiang Power Plant Unit 2 300 MW units 50%
and 100% load rejection test routine method to achieve the intended purpose test. The
results showed that:
a) Harbin Steam Turbine Plant type N300-16.7/537/537 subcritical, single reheat, twin
dual exhaust, uniaxial, condensing steam turbine with Control Engineering Co., Ltd.,
Harbin DEH overall design installed to meet the requirements of load shedding, the
dynamic characteristics of a good; various auxiliary and ancillary mechanical load
rejection condition for good adaptability.
b) LDA reset delay time of 2 ~ 3 s logic design, electrical power from the generator and
turbine mechanical power imbalance quick closing (fast valving) function, for after the
load rejection and target speed setpoint values were designed as 3 000 r / min for D EH,
whose role is reset when the LDA to ensure that speed is still 3 090 r / min or more, the
OPC 103% setting circuit continues to operate. Validated, 5 s delay time is appropriate,
but for the case of low load rejection was inappropriate, likely to cause secondary
soaring high speed. If there is no valve DEH fast off function under the premise of the
release of the LDA logical conditions to until the speed is lower than 3 000 r / min, can
achieve the same purpose. LDA action 5.0 s after the preset delay time (measured as 4.
811 s).
c) load rejection test conducted from the domestic experience and information point of
5/20/2014 Turbine load rejection N300-16.7/537/537 Study | Science and Technology
http://www.nt20.com/index.php/archives/1468 6/8
Large SBR process start characteristics and activity acclimation
Phenol-formaldehyde condensation and adsorption and treatment of phenolic
wastewater
Soy production wastewater treatment
Boiler control microcomputer control and
instrumentation control
Shajiao A 300 MW unit of peaking sliding
pressure operation of Economic Analysis
view, the introduction of Harbin Steam Turbine Plant Westinghouse technology to
produce imported type 300 MW units, because the pressure regulating valve IV does not
participate in speed adjustable to two way valve work, in a 100% load rejection when,
OPC 103% setting circuit only twice action unit speed and stability as 3 000 r / min has
not been reported. Accordingly, the second load rejection test is successful, technically
advanced.
d) Westinghouse steam turbine original design without bypass and reheat steam
pressure after the load rejection can not be released. DEH design pressure regulator
valve IV is to take two valve way of working, to reheat piping to vent the pressure, in
order to achieve a constant speed again, the purpose of synchronous speed, which is
two valve was originally designed . While the domestic introduction of universal design
type units bypass system, in this case, DEH should be designed to IV in speed and
part of the power control and well coordinated with the bypass system, which is the
elimination of post-OPC frequent load shedding actions a fundamental way.
e) Accordingly, Westinghouse introduced the first steam turbine overspeed protection
control system of 103% OPC in speeding instantaneous shut down the regulator valve
design, the design for other units in all cases to prevent excessive speed, especially
soaring is a very effective secondary soaring in China has been widely respected and
applied.
f) For the DEH hanging barrier pressure bypass not involved in the regulation of the
domestic imported type 300 MW units, so as soon as possible after the load rejection
reheat steam pressure reduction, inhibition of OPC is an effective means of frequent
movement.

December 5, 2013 in Science and Technology.
Related posts
5/20/2014 Turbine load rejection N300-16.7/537/537 Study | Science and Technology
http://www.nt20.com/index.php/archives/1468 7/8
Search
Recent Posts
Large SBR process start characteristics and activity acclimation
Phenol-formaldehyde condensation and adsorption and treatment of phenolic
wastewater
Soy production wastewater treatment
Optimal operation of chemical water treatment devices and improvement measures
Water reuse project MBR system design
Views
Nuclear power station conventional islands and design of auxiliary facilities autonomy
Discussion - 1,798 views
Fifteen renewable energy technology development strategy and policy measures
discussed - 1,518 views
Artificial neural network to relay Discussion - 1,489 views
480t / h circulating fluidized bed combustion boiler operation adjustment Discussion -
1,057 views
110kv and below substations discuss problems and solutions - 1,047 views
Yellow River water and sediment turbidity, sediment grain size between - 572 views
Foreign tariff system and tariff reform on Chinas revelation - 505 views
Living architecture, unusual landscape needs - 448 views
On the distribution network reactive power optimization - 369 views
Hydropower outlet Review of transformation and technological progress - 306 views
Archives
May 2014
April 2014
March 2014
February 2014
5/20/2014 Turbine load rejection N300-16.7/537/537 Study | Science and Technology
http://www.nt20.com/index.php/archives/1468 8/8
January 2014
December 2013
November 2013
October 2013
September 2013
May 2014
M T W T F S S
Apr
1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31
Proudly powered by WordPress | Theme: Expound by Konstantin Kovshenin

Anda mungkin juga menyukai