DONGRE ASSOCIATES

No. AHU room 1 Remark


1 Room Acoustic Insulation is balance. Balance
2 Installation and Termination of LCP for AHU is balance. In Progress
3 Installation of AHU drain pipe is balance. Done
4
Installation of Supply air duct up to the room wall with VCD
and Fire Damper.
In Progress
5
Installation of return air duct up to the room wall with VCD
and Fire Damper.
In Progress
6 Painting of Chilled water pipe line with flow direction. Balance
7 Commissioning of AHU. Balance
8 Integration of DDC with BMS is balance. Balance
9 Integration of LCP with BMS is balance. Balance
10 Water connection for filter washing is balance. Balance
11 Installation of Fire Extinguisher is balance. Balance
12 Cleaning is required. In Progress
No. AHU room 2
1 Room Acoustic Insulation is balance. Balance
2 Installation and Termination of LCP for AHU is balance. In Progress
3 Installation of AHU drain pipe is balance. Done
4
Installation of Supply air duct up to the room wall with VCD
and Fire Damper.
In Progress
5
Installation of return air duct up to the room wall with VCD
and Fire Damper.
In Progress
6 Painting of Chilled water pipe line with flow direction. Balance
7 Commissioning of AHU is balance. Balance
8 Integration of DDC with BMS is balance. Balance
9 Integration of LCP with BMS is balance. Balance
10 Water connection for filter washing is balance. Balance
11 Installation of Fire Extinguisher is balance. Balance
12 Cleaning is required. In Progress
No. AHU room 3
1 Room Acoustic Insulation is balance. Balance
2 Installation and Termination of LCP for AHU is balance. In Progress
3 Installation of AHU drain pipe is balance. Done
TOWER QC 2, GIFT CITY
Balance work/Snag list Snag Date:26.09.13
10th Floor DE SNAGS
1 of 6
DONGRE ASSOCIATES
TOWER QC 2, GIFT CITY
Balance work/Snag list Snag Date:26.09.13
10th Floor DE SNAGS
4
Installation of Supply air duct up to the room wall with VCD
and Fire Damper.
In Progress
5
Installation of return air duct up to the room wall with VCD
and Fire Damper.
In Progress
6 Painting of Chilled water pipe line with flow direction. Balance
7 Commissioning of AHU is balance. Balance
8 Integration of DDC with BMS is balance. Balance
9 Integration of LCP with BMS is balance. Balance
10 Water connection for filter washing is balance. Balance
11 Installation of Fire Extinguisher is balance. Balance
12 Cleaning is required. In Progress
No. AHU room 4
1 Room Acoustic Insulation is balance. Balance
2 Installation and Termination of LCP for AHU is balance. In Progress
3 Installation of AHU drain pipe is balance. Done
4
Installation of Supply air duct up to the room wall with VCD
and Fire Damper.
In Progress
5
Installation of return air duct up to the room wall with VCD
and Fire Damper.
In Progress
6 Painting of Chilled water pipe line with flow direction. Balance
7 Commissioning of AHU is balance. Balance
8 Integration of DDC with BMS is balance. Balance
9 Integration of LCP with BMS is balance. Balance
10 Water connection for filter washing is balance. Balance
11 Installation of Fire Extinguisher is balance. Balance
12 Cleaning is required. In Progress
Electrical Room
1 Integration of LDB with BMS is balance. Done
2 labelling of Switch Board/Power Plug is balance. Done
3 Installation of Rubber Mat is balance. Done
4 Pasting of SLD for Panel and DBs is balance. Done
5 Installation of Fire Extinguisher is balance. Done
6 Continuity of cable tray to be maintained. Done
7
Proper fixing of card reader and door lock position sensor is
to be done.
Done
2 of 6
DONGRE ASSOCIATES
TOWER QC 2, GIFT CITY
Balance work/Snag list Snag Date:26.09.13
10th Floor DE SNAGS
12 Cleaning is required. Balance
No. Male Toilet 1
1 labelling of Switch Board/Power Plug is balance. Done
2 Installation of Soap dispensor holder is balance. Balance
3 Installation of Toilet paper holder is balance. Balance
4 Installation of paper dispenser is balance. Balance
5 Installation of waste paper bin is balance. Balance
6 Installation of Hand dryer is balance. Balance
7 Switch board plate to be fixed properly in passage. Done
No. Female Toilet 1
1 labelling of Switch Board/Power Plug is balance. Done
2 Installation of Soap dispensor holder is balance. Balance
3 Installation of Toilet paper holder is balance. Balance
4 Installation of paper dispenser is balance. Balance
5 Installation of waste paper bin is balance. Balance
6 Installation of Hand dryer is balance. Balance
No. Male Toilet 2
1 labelling of Switch Board/Power Plug is balance. Done
2 Installation of Soap dispensor holder is balance. Balance
3 Installation of Toilet paper holder is balance. Balance
4 Installation of paper dispenser is balance. Balance
5 Installation of waste paper bin is balance. Balance
6 Installation of Hand dryer is balance. Balance
7 Switch board plate to be fixed properly in passage. Done
No. Female Toilet 2
1 labelling of Switch Board/Power Plug is balance. Done
2 Installation of Soap dispensor holder is balance. Balance
3 Installation of Toilet paper holder is balance. Balance
4 Installation of paper dispenser is balance. Balance
5 Installation of waste paper bin is balance. Balance
6 Installation of Hand dryer is balance. Balance
No. Male Toilet 3
3 of 6
DONGRE ASSOCIATES
TOWER QC 2, GIFT CITY
Balance work/Snag list Snag Date:26.09.13
10th Floor DE SNAGS
1 labelling of Switch Board/Power Plug is balance. Done
2 Installation of Soap dispensor holder is balance. Balance
3 Installation of Toilet paper holder is balance. Balance
4 Installation of paper dispenser is balance. Balance
5 Installation of waste paper bin is balance. Balance
6 Installation of Hand dryer is balance. Balance
No. Female Toilet 3
1 labelling of Switch Board/Power Plug is balance. Done
2 Installation of Soap dispensor holder is balance. Balance
3 Installation of Toilet paper holder is balance. Balance
4 Installation of paper dispenser is balance. Balance
5 Installation of waste paper bin is balance. Balance
6 Installation of Hand dryer is balance. Balance
No. Male Toilet 4
1 labelling of Switch Board/Power Plug is balance. Done
2 Installation of Soap dispensor holder is balance. Balance
3 Installation of Toilet paper holder is balance. Balance
4 Installation of paper dispenser is balance. Balance
5 Installation of waste paper bin is balance. Balance
6 Installation of Hand dryer is balance. Balance
7 Switch board plate to be fixed properly in passage. Done
No. Female Toilet 4
1 labelling of Switch Board/Power Plug is balance. Done
2 Installation of Soap dispensor holder is balance. Balance
3 Installation of Toilet paper holder is balance. Balance
4 Installation of paper dispenser is balance. Balance
5 Installation of waste paper bin is balance. Balance
6 Installation of Hand dryer is balance. Balance
No. Handicap Toilet
1 labelling of Switch Board/Power Plug is balance. Done
2 Installation of Soap dispensor holder is balance. Balance
3 Installation of Toilet paper holder is balance. Balance
4 of 6
DONGRE ASSOCIATES
TOWER QC 2, GIFT CITY
Balance work/Snag list Snag Date:26.09.13
10th Floor DE SNAGS
4 Installation of paper dispenser is balance. Balance
5 Installation of waste paper bin is balance. Balance
6 Installation of Hand dryer is balance. Balance
7 Installation of Grab rail is balance. Done
Lift lobbies and corridors
1 Fire exit signages and evacuation plan to be installed. In Progress
2 labelling of Switch Boards/Power Plugs. Done
Service Lift lobby
1 Labelling for intake hopper of garbage chute is balance. Done
2 labelling of Switch Board/Power Plug is balance. Done
3 Plate of switch board to be installed. Done
4 Intake hopper of chute not open/close. Balance
Tel.closet room
1 Cables are to be laid properly. Done
Office area
1 Paint touch up of fire fighting pipes wherever balance. Done
2
Proper connection of cable trays near SMDB to maintain
continuity of cable trays.
Done
3 Extra rods to be removed. In Progress
No. Fire Shafts
1 Supports to be painted wherever pending. Done
2 Red push button is missing in FHC near electrical room. Balance
3 Rubber grip to be placed at hose of fire extinguishers. Done
4 Cleaning is required. Done
5 63 mm dia. Hose reel of 30 mt. length to be provided. Done
No. ELV
1 Commissioning of HVAC System is balance. In Progress
2 Commissioning of Fire Alarm System is balance. In Progress
3 Commissioning of Access Control System is balance. Done
4 Commissioning of CCTV System is balance. Done
5 Integration of various services with BMS is balance. In Progress
No. Shafts
1
Identification tags with flow direction on the pipes is to be
provided.
In Progress
2
Tapping for RO water at easily access location for each
office.
Balance
3 Flooring not done at ELV shafts. In Progress
4 Cleaning is required. Done
5 of 6
DONGRE ASSOCIATES
TOWER QC 2, GIFT CITY
Balance work/Snag list Snag Date:26.09.13
10th Floor DE SNAGS
Remarks
De Snag Date 28.01.2014
ANC Representative: Praful
PMC Representative: Vanraj
6 of 6