The city of Caledonia, MS, has performed a preliminary

analysis and programing through GLM Collaborative


Partners to establish the base needs for a new Lowndes
County Volunteer Fire Department District 1 Fire Station. The
intent of the architect and constructor team is to create a
project delivery that is aimed to providing the owner with
the best building design to meet the needed requirements,
while maintaining the best value in construction and cost
effciency. The budget of the project depicts certain restraints
on what realistically can be designed and constructed. The
prefabricated industrial shed with a small mezzanine for the
administration building is the low-cost solution that most
communities have opted for because of the effciency. The
design intent was to take the prefabricated shed and make
it more visually appealing and functional for the surrounding
neighborhood.
Through the developing of the design with the intention of
reinterpreting the prefabricated shed design, we established
design objectives to further establish modularity, functionality,
sustainability, and constructability, with the use of logic and
proportionality.
Caledonia Fire Station 1
Carter Brown
Patrick Brown
Bryan Marks
Casey Walker
The city of Caledonia, MS, has performed a preliminary
analysis and programing through GLM Collaborative
Partners to establish the base needs for a new Lowndes
County Volunteer Fire Department District 1 Fire Station. The
intent of the architect and constructor team is to create a
project delivery that is aimed to providing the owner with
the best building design to meet the needed requirements,
while maintaining the best value in construction and cost
on what realistically can be designed and constructed. The
prefabricated industrial shed with a small mezzanine for the
administration building is the low-cost solution that most
design intent was to take the prefabricated shed and make
it more visually appealing and functional for the surrounding
neighborhood.
Through the developing of the design with the intention of
reinterpreting the prefabricated shed design, we established
design objectives to further establish modularity, functionality,
sustainability, and constructability, with the use of logic and
proportionality.
Caledonia FireStation 1
UP
01
02 04 06 08 01
01
07
05 03
C A
B
DN
C A
B
01
16 12 15 14
13 11 17
01
02
03
04
05
06
07
07
08
09
10
11
12
13
14
15
16
1st Floor Plan
1/8 : 1 0
2nd Floor Plan
1/8 : 1 0
2nd Floor Plan Detail
1 1/2 : 1 0
1st Floor Plan
1 1/2 : 1 0
Light Well : Perspective
No Scale
Standing Rib Panel Joints
Foam insulation
10 C-Channel
Weldid Steel Cleat
Portal Frame
Wood Slats
Masonry Tie
Standard Brick
2 Air Cavity
1 Rigid Board Insulation
Bituminous Coating
CMU non-load bearing wall
Kingzip Standing Rib Panel
UP
01
02 04 06 08 01
01
07
05 03
C A
B
DN
C A
B
01
16 12 15 14
13 11 17
01
02
03
04
05
06
07
07
08
09
10
11
12
13
14
15
16
1st Floor Plan
1/8 : 1 0
2nd Floor Plan
1/8 : 1 0
2nd Floor Plan Detail
1 1/2 : 1 0 1st Floor Plan
1 1/2 : 1 0
Standing Rib Panel Joints
Foam insulation
10 C-Channel
Weldid Steel Cleat
Portal Frame
Wood Slats
Masonry Tie
Standard Brick
2 Air Cavity
1 Rigid Board Insulation
Bituminous Coating
CMU non-load bearing wall
Kingzip Standing Rib Panel
Standing Rib Panel Joints
Foam insulation
10 C-Channel
Wood Blocking
Welded Steel Cleat
Portal Frame
Wood Slats
3 1/2 Aluminum Mullion
Panel Spreader
Polycarbonate Panel
Air Cavity
Kingzip Standing Rib Panel
Apparatus Bay
Training Room
Restroom
Stairs
Laundry Room / Elsctrical Room
Chiefs Office
Storage Room / Safe Room
Captains Office
DayRoom
Kitchen / Dinning Room
Womens Bathroom
Stairs
Mens Bathroom
Locker Room / Maintenance Room
Fitness Room
Mens Bunk Room
Womens Bunk Room
Plan Details
Structural Details
Defined Interior
Defined Exterior
UP
01
02 04 06 08 01
01
07
05 03
C A
B
DN
C A
B
01
16 12 15 14
13 11 17
01
02
03
04
05
06
07
07
08
09
10
11
12
13
14
15
16
1st Floor Plan
1/8 : 1 0
2nd Floor Plan
1/8 : 1 0
2nd Floor Plan Detail
1 1/2 : 1 0
1st Floor Plan
1 1/2 : 1 0
Standing Rib Panel Joints
Foam insulation
10 C-Channel
Weldid Steel Cleat
Portal Frame
Wood Slats
Masonry Tie
Standard Brick
2 Air Cavity
1 Rigid Board Insulation
Bituminous Coating
CMU non-load bearing wall
Kingzip Standing Rib Panel
Standing Rib Panel Joints
Foam insulation
10 C-Channel
Wood Blocking
Welded Steel Cleat
Portal Frame
Wood Slats
3 1/2 Aluminum Mullion
Panel Spreader
Polycarbonate Panel
Air Cavity
Kingzip Standing Rib Panel
Apparatus Bay
Training Room
Restroom
Stairs
Laundry Room / Elsctrical Room
Chiefs Office
Storage Room / Safe Room
Captains Office
DayRoom
Kitchen / Dinning Room
Womens Bathroom
Stairs
Mens Bathroom
Locker Room / Maintenance Room
Fitness Room
Mens Bunk Room
Womens Bunk Room
Plan Details
Structural Details
The metal plaques that fit
the same dimension of the
brick coursing to emphasis
the brick, contain the name
of all of the firefighters that
would have worked at the
fire station. The rank of the
firefighter is indicated by
the length of the offset from
the wall. The further away
the higher rank. The red
indicates the chiefs.
1
A
B
C
D
2 3 4 5 6 7 8 9 10 1
A
B
C
D
2 3 4 5 6 7 8 9 10
Kingzip Insulated Metal Panels
Wood blocking
Purlins
Drop Down Ceiling
Polycarbonate Spandrel Panel
Polycarbonate Panel
Wood Slats
W 36 x 135 Beam
Aluminum mullion
CMU Non-load bearing wall
Gypsum board
Insulating foam inserts in cores
Bituminous coating on face of CMU block
2 air cavity
Masonry ties
Brick facing
W 16 x 67 Beam
6 Concrete topping on
corrugated steel floor decking
1 Rigid board insulation
Continuous flashing
W 12 x 22 Column
Weep holes
J-bolt
Welded wire fabric
Polyethylene moisture barrier
2 layer of sand
4 Gravel base course
6 Concrete slab
Reinforced concrete grade beam
Isolated column footing
Filter fabric
Gravel
Perforated 4 drain pipe
Aluminum Mullion
5/8 Panel Batten
Polycarbonate Panels
Sill Frame w/ Fastener
Weep Notch
Window Flashing
Blocking
Standard Brick w/ 3/8 Mortar
Panel Threader
20 GA. Stainless steel top clip with thermal break
14 GA. Galvanized base clip
1/4 14 Hex head fasteners
Aluminum Mullion w/ Fastener
Steel cleat welded to steel beam
Wood slat
1/2 bolt
Drop down ceiling purlin clip
Polycarbonate Panel
5/8 Panel Batten
Wood blocking
10 Purlins
Panel Threader
2 Air Cavity
1 Rigid Board Insulation
Bituminous coating on face of CMU block
CMU non-load bearing wall
Insulating foam inserts in cores
Gypsum Board
Masonry Tie
Invisible Structure Inc. Gravelpave2 and
Grasspave2 are structural systems that provide
heavy load bearing support and containment of
gravel to create a porous surface with unlimited
traffic volume. The system can be used for
storage and filtration of rainwater.
ADA - Both systems create wheelchair
accessible surfaces.
Paths with Gravelpave2 and Grasspave2
systems eliminate the neccessity of concrete or
other impermeable surfaces and provides
porous surfaces that allow increased site
drainage and rainwater filtration.
Gravelpave2 system replaces the need of
concrete and asphalt driveways, and has been
specificly designed for traffic loads large enough
for firetrucks, while also having a permeable
surface that filters pollutants and provides
stormwater mitigation
Grass Gravel Grass
Two piece clip with thermal bridge
1/4 - 14x7/8 low profile tek screws
High eave trim
Wood Slats
Portal frame shoulder moment connection
Wall Girt
Strengthening plate
Metal hex screws for wood slats
Base trim
Flashing
Eave strut
Pop rivet
W 36x135
Crushed limestone
Grass
Gravelpave 2 system
Compact gravel
Grasspave 2 system
Perforated 4 drainage pipe
Grasspave2 / Gravelpave2 system fastener
Wall Section C
1 : 1
Steel base plate
J-bolts
Isolated footing
Grasspave2 / Gravelpave2 Plan View
1 : 1
Window Sill
3 : 1
Roof Detail
3 : 1
SOUTHWEST ELEVATION
1/8 = 1
TRANSVERSE SECTION
1/8 = 1
NORTHEAST ELEVATION
1/8 = 1
LONGITUDINAL SECTION
1/8 = 1
SOUTHEAST ELEVATION
1/8 = 1
NORTHWEST ELEVATION
1/8 = 1
1 2 3 4 5 6 7 8 9 10
Level 3 : 14 0
Level 5 : 22 10
Level 6 : 25 3
Level 1 : 0 2
Level 3 : 14 0
Level 5 : 22 10
Level 6 : 25 3
Level 1 : 0 2
Level 4 : 14 0
Level 5 : 21 3
Level 3 : 12 0
Level 2 : 9 11
9 11
7 3
Level 6 : 22 10
Level 7 : 25 3
Level 1 : 0 2
10 0 15 0 15 0 15 0 15 0 15 0 15 0 10 0 10 0
0 20 40 60 80 100 120 140
Project Close-Out
Building Sitework
Services
Interiors
Shell
Substructure
Site Prepara;on
General Condi;ons
Pre-Construc;on
Total Project Dura;on
Caledonia Fire Sta.on: Total Project Dura.on
132
Days
16 Days
3 Days
4 Days
35 Days
74 Days
14 Days
4 Days
5 Days
8 Days
Project Start Date
4/21/2014
Project Finish Date
10/21/2014
$0.00 $100,000.00 $200,000.00 $300,000.00 $400,000.00 $500,000.00 $600,000.00 $700,000.00 $800,000.00
Hard Cost
General Condi;ons
Fees
Total Project Cost
Caledonia Fire Sta.on: Total Project Cost
$ 703,048.10
$ 52,679.82
$ 48,901.40
$ 601,466.88
Hard Cost Breakdown
Substructure
Shell
Interiors
Services
Equipment
Building Sitework
9.5% of Hard Cost
59.8% of Hard Cost
5.3% of Hard Cost
20.0% of Hard Cost
3.0% of Hard Cost
2.4% of Hard Cost
Cost/Building S.F
$ 48.86/S.F
Constructability Analysis
Portal Frame BeamSystem:

Con;nuous Span (115) vs. 2-Part Span (70 & 45)
Advantages:
Cheaper material cost
Smaller size members
Disadvantages:
Thermal bridge between buildings
Structural columns are needed for bridge
Price Comparison:

Con;nuous Span - $ 195,545.00

2-part Beam - $ 154,678.00

Exterior Wall/Roof Paneling System:
PARKING LOT
STORAGE CONTAINERS
OFFICE TRAILER
PORTABLE TOILETS
TEMPORARY ROAD
CRANE AREA
LAY-DOWN AREA
DUMPSTER
WHEEL WASH AREA
PPE / FIRST AID STATION
TEMPORARY FENCE
SCAFFOLDING AREA
EROSION CONTROL FENCE
ONE-WAY TRAFFIC FLOW
SITE ENTRANCE
SITE EXIT
MOCK-UP AREA
Temporary Fence
6' High
Lay-Down Area
28' x 80'
Wheel Wash Area
20' x 50'
Storage Containers
8' x 10'
PPE/First Aid
8' x 8'
Parking Lot
40' x 80'
Office Trailer
8' x 28'
Crane Area
20' x 28'
Portable Toilets
3 1/2' x 3 1/2'
Dumpsters
8' x 20'
Mock-Up Area
25' x 35'
Print to PDF without this message by purchasing novaPDF (http://www.novapdf.com/)
PARKING LOT
STORAGE CONTAINERS
OFFICE TRAILER
PORTABLE TOILETS
TEMPORARY ROAD
CRANE AREA
LAY-DOWN AREA
DUMPSTER
WHEEL WASH AREA
PPE / FIRST AID STATION
TEMPORARY FENCE
SCAFFOLDING AREA
EROSION CONTROL FENCE
ONE-WAY TRAFFIC FLOW
SITE ENTRANCE
SITE EXIT
MOCK-UP AREA
Temporary Fence
6' High
Lay-Down Area
28' x 80'
Wheel Wash Area
20' x 50'
Storage Containers
8' x 10'
PPE/First Aid
8' x 8'
Parking Lot
40' x 80'
Office Trailer
8' x 28'
Crane Area
20' x 28'
Portable Toilets
3 1/2' x 3 1/2'
Dumpsters
8' x 20'
Mock-Up Area
25' x 35'
Print to PDF without this message by purchasing novaPDF (http://www.novapdf.com/)
SITE PLAN
1/32 = 1
SITE UTILIZATION PLAN
1/32 = 1