1.
ht
= 8,5 cm
= 100 cm
fc
= 300 kg / m2
fy
= 2400 kg / m3
= 12 cm
Pembebanan Pelat
A. Pembebanan Pelat
1.
Beban Mati ( DL )
kg / m2
2.
= 496 kg / m2
LL
= 250 kg / m2
Beban Hidup ( LL )
Beban Hidup
Setiawan (022113178)
II - 1
Struktur Beton 2
3.
Beban Terfaktor ( qU )
= 1,2 DL + 1,6 LL
= ( 1,2 x 496 ) + ( 1,6 x 250 )
= 995,2 kg/m2
Beban Mati ( DL )
Berat Sendiri Pelat ( t = 14 cm & = 2400 kg/m3)
2.
DL
= 544 kg / m2
LL
= 400 kg / m2
Beban Hidup ( LL )
Beban Hidup Pelat
3.
= 40 kg / m2
Beban terfaktor ( qU )
= 1,2 DL + 1,6 LL
= ( 1,2 x 544 ) + ( 1,6 x 400 )
= 1292,8 kg/m2
Bidang 1A
Setiawan (022113178)
II - 2
2,00 m
Struktur Beton 2
4,15 m
Ly / Lx = 4,15 / 2,00 = 2,1 c = 60
Mu = ( c / 1000 ) * qU * Lx2
= ( 60 / 1000 ) * 968,8 * 2,002
= 232,512 kg.m/m = 23251,2 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,016
= 0,016
= ( * 0,85 * fc ) / fy
= ( 0,016 * 0,85 * 300 ) / 2400
= 1,7 x 10-3
As = * b * d
= 1, 7 x 10-3 * 100 * 8,5
= 1,445
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,445
II - 3
Struktur Beton 2
Jarak = 100 / 1,840
= 54,35 cm 20 cm
2,00 m
Bidang 2A
3,2 m
Ly / Lx = 3,2 / 2,00 = 1,6 c = 49
Mu = ( c / 1000 ) * qU * Lx2
= ( 49 / 1000 ) * 968,8 * 2,002
= 189,885 kg.m/m = 18988,5 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,013
= 0,013
= ( * 0,85 * fc ) / fy
= ( 0,013 * 0,85 * 300 ) / 2400
= 1,381 x 10-3
As = * b * d
= 1,381 x 10-3 * 100 * 8,5
Setiawan (022113178)
II - 4
Struktur Beton 2
= 1,174
Untuk tulangan 10 mm Ab
= * * d2
= 0,785
As
1,174
2,20 m
Bidang 3A
4,15 m
Ly / Lx = 4,15 / 2,20 = 1,6 c = 55,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 55,5 / 1000 ) * 968,8 * 2,202
= 260,239 kg.m/m = 26023,9 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,017
= 0,017
= ( * 0,85 * fc ) / fy
= ( 0,017 * 0,85 * 300 ) / 2400
= 1,806 x 10-3
Setiawan (022113178)
II - 5
Struktur Beton 2
As = * b * d
= 1,806 x 10-3 * 100 * 8,5
= 1,535
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,535
2,20 m
Bidang 4A
3,20 m
Ly / Lx = 4,15 / 2,20 = 1,5 c = 45,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 45,5 / 1000 ) * 968,8 * 2,202
= 213,349 kg.m/m = 21334,9 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 21334,9 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
= 0,014
Setiawan (022113178)
II - 6
Struktur Beton 2
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,014
= 0,014
= ( * 0,85 * fc ) / fy
= ( 0,014 * 0,85 * 300 ) / 2400
= 1,488 x 10-3
As = * b * d
= 1,488 x 10-3 * 100 * 8,5
= 1,265
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,265
1,5 m
Bidang 5A
2,5 m
Ly / Lx = 2,5 / 1,5
= 1,7 c = 51
Mu = ( c / 1000 ) * qU * Lx2
= ( 51 / 1000 ) * 968,8 * 1,502
= 111,169 kg.m/m = 11116,9 kg.cm/m
Setiawan (022113178)
II - 7
Struktur Beton 2
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,007
= 0,007
= ( * 0,85 * fc ) / fy
= ( 0,007 * 0,85 * 300 ) / 2400
= 7,438 x 10-4
As = * b * d
= 7,438 x 10-4 * 100 * 8,5
= 5,373
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
5,373
2,50 m
Bidang 6A
Setiawan (022113178)
4,15 m
II - 8
Struktur Beton 2
Ly / Lx = 4,15 / 2,50 = 1,7 c = 51
Mu = ( c / 1000 ) * qU * Lx2
= ( 51 / 1000 ) * 968,8 * 2,502
= 308,805 kg.m/m = 30880,5 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,021
= 0,021
= ( * 0,85 * fc ) / fy
= ( 0,021 * 0,85 * 300 ) / 2400
= 2,231 x 10-3
As = * b * d
= 2,231 x 10-3 * 100 * 8,5
= 1,896
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,896
2,50 m
Bidang 7A
II - 9
Setiawan (022113178)
3,2 m
Struktur Beton 2
Ly / Lx = 3,2 / 2,50
= 1,3 c = 38
Mu = ( c / 1000 ) * qU * Lx2
= ( 38 / 1000 ) * 968,8 * 2,502
= 230,09 kg.m/m = 23009 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,016
= 0,016
= ( * 0,85 * fc ) / fy
= ( 0,016 * 0,85 * 300 ) / 2400
= 1,7 x 10-3
As = * b * d
= 1,7 x 10-3 * 100 * 8,5
= 1,445
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,445
II - 10
Struktur Beton 2
2,83 m
Bidang 10A
3,60 m
Ly / Lx = 3,60 / 2,83 = 1, c = 38
Mu = ( c / 1000 ) * qU * Lx2
= ( 38 / 1000 ) * 968,8 * 2,832
= 294,843 kg.m/m = 29484,3 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,020
= 0,020
= ( * 0,85 * fc ) / fy
= ( 0,020 * 0,85 * 300 ) / 2400
= 2,125 x 10-3
As = * b * d
= 2,125 x 10-3 * 100 * 8,5
= 1,806
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
Setiawan (022113178)
II - 11
Struktur Beton 2
As
1,806
3,60 m
Bidang 11A
4,15 m
Ly / Lx = 4,15 / 3,600 = 1,2 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 3,602
= 426,892 kg.m/m = 42689,2 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,028
= 0,028
= ( * 0,85 * fc ) / fy
= ( 0,028 * 0,85 * 300 ) / 2400
= 3,305 x 10-3
As = * b * d
= 3,305 x 10-3 * 100 * 8,5
Setiawan (022113178)
II - 12
Struktur Beton 2
= 2,809
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
2,809
1,4 m
Bidang 12A
2,7 m
Ly / Lx = 4,15 / 2,20 = 1,9 c = 55,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 55,5 / 1000 ) * 968,8 * 1,402
= 105,386 kg.m/m = 10538,6 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,007
= 0,007
= ( * 0,85 * fc ) / fy
= ( 0,007 * 0,85 * 300 ) / 2400
Setiawan (022113178)
II - 13
Struktur Beton 2
= 7,437 x 10-4
As = * b * d
= 7,437 x 10-4 * 100 * 8,5
= 0,632
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,632
2,25 m
Bidang 13A
2,6 m
Ly / Lx = 2,60 / 2,25 = 1,2 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 2,252
= 166,755 kg.m/m = 16675,5 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 16675,5 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
Setiawan (022113178)
II - 14
Struktur Beton 2
= 0,011
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,011
= 0,011
= ( * 0,85 * fc ) / fy
= ( 0,011 * 0,85 * 300 ) / 2400
= 1,168 x 10-3
As = * b * d
= 1,168 x 10-3 * 100 * 8,5
= 0,993
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,993
0,8 m
Bidang 14A
2,25 m
Ly / Lx = 2,25 / 0,8 = 2,8 c = 63,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 63,5 / 1000 ) * 968,8 * 0,802
Setiawan (022113178)
II - 15
Struktur Beton 2
= 39,372 kg.m/m = 3937,2 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,003
= 0,003
= ( * 0,85 * fc ) / fy
= ( 0,003 * 0,85 * 300 ) / 2400
= 3,188 x 10-4
As = * b * d
= 3,188 x 10-4 * 100 * 8,5
= 0,270
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,270
2,25 m
Bidang 15A
II - 16
Setiawan (022113178)
3,00 m
Struktur Beton 2
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,013
= 0,013
= ( * 0,85 * fc ) / fy
= ( 0,013 * 0,85 * 300 ) / 2400
= 1,381 x 10-3
As = * b * d
= 1,381 x 10-3 * 100 * 8,5
= 1,174
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,174
Setiawan (022113178)
II - 17
Struktur Beton 2
1,20 m
Bidang 16A
2,83 m
Ly / Lx = 2,83 / 1,20 = 2,4 c = 60
Mu = ( c / 1000 ) * qU * Lx2
= ( 60 / 1000 ) * 968,8 * 1,202
= 83,704 kg.m/m = 8370,4 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,006
= 0,006
= ( * 0,85 * fc ) / fy
= ( 0,006 * 0,85 * 300 ) / 2400
= 6,375 x 10-4
As = * b * d
= 6,375 x 10-4 * 100 * 8,5
= 0,542
Untuk tulangan 10 mm
Setiawan (022113178)
Ab = * * d2
II - 18
Struktur Beton 2
= 0,785
As
0,542
2,30 m
Bidang 17A
2,83 m
Ly / Lx = 2,83 / 2,30 = 1,2 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 2,302
= 174,248 kg.m/m = 17424,8 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,012
= 0,012
= ( * 0,85 * fc ) / fy
= ( 0,012 * 0,85 * 300 ) / 2400
= 1,275 x 10-3
Setiawan (022113178)
II - 19
Struktur Beton 2
As = * b * d
= 1,275 x 10-3 * 100 * 8,5
= 1,084
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,084
3,50 m
Bidang 18A
4,15 m
Ly / Lx = 4,15 / 2,20 = 1,2 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 3,502
= 403,505 kg.m/m = 40350,5 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 40350,5 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
= 0,027
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,027
Setiawan (022113178)
II - 20
Struktur Beton 2
= 0,027
= ( * 0,85 * fc ) / fy
= ( 0,027 * 0,85 * 300 ) / 2400
= 2,869 x 10-3
As = * b * d
= 2,869 x 10-3 * 100 * 8,5
= 2,438
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
2,438
3,20 m
Bidang 19A
3,50 m
Ly / Lx = 3,50 / 3,20 = 1,1 c = 29,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 29,5 / 1000 ) * 968,8 * 3,202
= 292,655 kg.m/m = 29265,5 kg.cm/m
Setiawan (022113178)
II - 21
Struktur Beton 2
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,019
= 0,019
= ( * 0,85 * fc ) / fy
= ( 0,019 * 0,85 * 300 ) / 2400
= 2,019 x 10-3
As = * b * d
= 2,019 x 10-3 * 100 * 8,5
= 1,716
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,716
1,33 m
Bidang 20A
2,20 m
Ly / Lx = 2,20 / 1,33 = 1,7 c = 51
Setiawan (022113178)
II - 22
Struktur Beton 2
Mu = ( c / 1000 ) * qU * Lx2
= ( 51 / 1000 ) * 968,8 * 1,332
= 87,399 kg.m/m = 8739,9 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,006
= 0,006
= ( * 0,85 * fc ) / fy
= ( 0,006 * 0,85 * 300 ) / 2400
= 6,375 x 10-4
As = * b * d
= 6,375 x 10-4 * 100 * 8,5
= 0,542
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,542
1,5 m
Bidang 21A
II - 23
Setiawan (022113178)
2,20 m
Struktur Beton 2
Ly / Lx = 2,20 / 1,5
= 1,5 c = 45,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 45,5 / 1000 ) * 968,8 * 1,52
= 99,181 kg.m/m = 9918,1 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,007
= 0,007
= ( * 0,85 * fc ) / fy
= ( 0,007 * 0,85 * 300 ) / 2400
= 7,437 x 10-4
As = * b * d
= 7,437 x 10-4 * 100 * 8,5
= 0,632
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,632
Setiawan (022113178)
II - 24
Struktur Beton 2
1,33 m
Bidang 22A
2,00 m
Ly / Lx = 2,00 / 1,33 = 1,5 c = 45,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 45,5 / 1000 ) * 968,8 * 1,332
= 77,974 kg.m/m = 7797,4 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,005
= 0,005
= ( * 0,85 * fc ) / fy
= ( 0,005 * 0,85 * 300 ) / 2400
= 5,313 x 10-4
As = * b * d
= 5,313 x 10-4 * 100 * 8,5
= 0,452
Setiawan (022113178)
II - 25
Struktur Beton 2
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,452
1,50 m
Bidang 23A
2,00 m
Ly / Lx = 2,00 / 1,50 = 1,33 c = 38
Mu = ( c / 1000 ) * qU * Lx2
= ( 38 / 1000 ) * 968,8 * 22
= 147,258 kg.m/m = 14725,8 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,009
= 0,009
= ( * 0,85 * fc ) / fy
= ( 0,009 * 0,85 * 300 ) / 2400
= 9,563 x 10-4
Setiawan (022113178)
II - 26
Struktur Beton 2
As = * b * d
= 9,563 x 10-4 * 100 * 8,5
= 0,813
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,813
2,50 m
Bidang 24A
2,83 m
Ly / Lx = 2,00 / 1,50 = 1,1 c = 29,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 29,5 / 1000 ) * 968,8 * 2,52
= 178,623 kg.m/m = 17862,3 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 17862,3 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
= 0,012
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,012
Setiawan (022113178)
II - 27
Struktur Beton 2
= 0,012
= ( * 0,85 * fc ) / fy
= ( 0,012 * 0,85 * 300 ) / 2400
= 1,275 x 10-3
As = * b * d
= 1,275 x 10-3 * 100 * 8,5
= 1,084
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,084
2,08 m
Bidang 25A
2,50 m
Ly / Lx = 2,50 / 2,08 = 1,2 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 2,082
= 142,508 kg.m/m = 14250,8 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 14250,8 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
Setiawan (022113178)
II - 28
Struktur Beton 2
= 0,009
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,009
= 0,009
= ( * 0,85 * fc ) / fy
= ( 0,009 * 0,85 * 300 ) / 2400
= 9,563 x 10-4
As = * b * d
= 9,563 x 10-4 * 100 * 8,5
= 0,813
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,813
2,13 m
Bidang 26A
2,50 m
Ly / Lx = 2,00 / 1,50 = 1,2 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 2,132
Setiawan (022113178)
II - 29
Struktur Beton 2
= 149,441 kg.m/m = 14944,1 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,010
= 0,010
= ( * 0,85 * fc ) / fy
= ( 0,010 * 0,85 * 300 ) / 2400
= 1,063 x 10-3
As = * b * d
= 1,063 x 10-3 * 100 * 8,5
= 0,903
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,903
1,33 m
Bidang 5B
Setiawan (022113178)
2,50 m
II - 30
Struktur Beton 2
Ly / Lx = 2,50 / 1,33 = 1,9 c = 51
Mu = ( c / 1000 ) * qU * Lx2
= ( 51 / 1000 ) * 968,8 * 1,332
= 87,399 kg.m/m = 8739,9 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,006
= 0,006
= ( * 0,85 * fc ) / fy
= ( 0,006 * 0,85 * 300 ) / 2400
= 6,375 x 10-4
As = * b * d
= 6,375 x 10-4 * 100 * 8,5
= 0,542
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,542
Setiawan (022113178)
II - 31
Struktur Beton 2
Setiawan (022113178)
II - 32
Struktur Beton 2
1,5 m
Bidang 5A
2,5 m
Ly / Lx = 2,5 / 1,5
= 1,7 c = 51
Mu = ( c / 1000 ) * qU * Lx2
= ( 51 / 1000 ) * 968,8 * 1,502
= 111,169 kg.m/m = 11116,9 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,007
= 0,007
= ( * 0,85 * fc ) / fy
= ( 0,007 * 0,85 * 300 ) / 2400
= 7,438 x 10-4
As = * b * d
Setiawan (022113178)
II - 33
Struktur Beton 2
= 7,438 x 10-4 * 100 * 8,5
= 5,373
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
5,373
2,50 m
Bidang 6A
4,15 m
Ly / Lx = 4,15 / 2,50 = 1,7 c = 51
Mu = ( c / 1000 ) * qU * Lx2
= ( 51 / 1000 ) * 968,8 * 2,502
= 308,805 kg.m/m = 30880,5 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,021
= 0,021
= ( * 0,85 * fc ) / fy
Setiawan (022113178)
II - 34
Struktur Beton 2
= ( 0,021 * 0,85 * 300 ) / 2400
= 2,231 x 10-3
As = * b * d
= 2,231 x 10-3 * 100 * 8,5
= 1,896
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,896
2,50 m
Bidang 7A
3,2 m
Ly / Lx = 3,2 / 2,50 = 1,3 c = 38
Mu = ( c / 1000 ) * qU * Lx2
= ( 38 / 1000 ) * 968,8 * 2,502
= 230,09 kg.m/m = 23009 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 23009 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
Setiawan (022113178)
II - 35
Struktur Beton 2
= 0,016
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,016
= 0,016
= ( * 0,85 * fc ) / fy
= ( 0,016 * 0,85 * 300 ) / 2400
= 1,7 x 10-3
As = * b * d
= 1,7 x 10-3 * 100 * 8,5
= 1,445
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,445
1,25 m
Bidang 8A
1,50 m
Ly / Lx = 1,50 / 1,25 = 1,2 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 1,252
Setiawan (022113178)
II - 36
Struktur Beton 2
= 51,467 kg.m/m = 5146,7 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,003
= 0,003
= ( * 0,85 * fc ) / fy
= ( 0,003 * 0,85 * 300 ) / 2400
= 3,188 x 10-4
As = * b * d
= 3,188 x 10-4 * 100 * 8,5
= 0,271
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,271
1,25 m
Bidang 9A
Setiawan (022113178)
1,33 m
II - 37
Struktur Beton 2
Ly / Lx = 1,33 / 1,25 = 1,1 c = 29,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 29,5 / 1000 ) * 968,8 * 1,332
= 50,554 kg.m/m = 5055,4 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,003
= 0,003
= ( * 0,85 * fc ) / fy
= ( 0,003 * 0,85 * 300 ) / 2400
= 3,188 x 10-4
As = * b * d
= 3,188 x 10-4 * 100 * 8,5
= 0,271
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,271
2,83 m
Bidang 10A
II - 38
Setiawan (022113178)
3,60 m
Struktur Beton 2
Ly / Lx = 3,60 / 2,83 = 1, c = 38
Mu = ( c / 1000 ) * qU * Lx2
= ( 38 / 1000 ) * 968,8 * 2,832
= 294,843 kg.m/m = 29484,3 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,020
= 0,020
= ( * 0,85 * fc ) / fy
= ( 0,020 * 0,85 * 300 ) / 2400
= 2,125 x 10-3
As = * b * d
= 2,125 x 10-3 * 100 * 8,5
= 1,806
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,806
II - 39
Struktur Beton 2
3,60 m
Bidang 11A
4,15 m
Ly / Lx = 4,15 / 3,600 = 1,2 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 3,602
= 426,892 kg.m/m = 42689,2 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,028
= 0,028
= ( * 0,85 * fc ) / fy
= ( 0,028 * 0,85 * 300 ) / 2400
= 3,305 x 10-3
As = * b * d
= 3,305 x 10-3 * 100 * 8,5
Setiawan (022113178)
II - 40
Struktur Beton 2
= 2,809
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
2,809
1,4 m
Bidang 12A
2,7 m
Ly / Lx = 4,15 / 2,20 = 1,9 c = 55,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 55,5 / 1000 ) * 968,8 * 1,402
= 105,386 kg.m/m = 10538,6 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,007
= 0,007
= ( * 0,85 * fc ) / fy
Setiawan (022113178)
II - 41
Struktur Beton 2
= ( 0,007 * 0,85 * 300 ) / 2400
= 7,437 x 10-4
As = * b * d
= 7,437 x 10-4 * 100 * 8,5
= 0,632
Ab = * * d2
Untuk tulangan 10 mm
= 0,785
As
0,632
2,25 m
Bidang 13A
2,6 m
Ly / Lx = 2,60 / 2,25 = 1,2 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 2,252
= 166,755 kg.m/m = 16675,5 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 16675,5 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
= 0,011
Setiawan (022113178)
= 1 - 1 2 * Rn
II - 42
Struktur Beton 2
= 1 - 1 2 * 0,011
= 0,011
= ( * 0,85 * fc ) / fy
= ( 0,011 * 0,85 * 300 ) / 2400
= 1,168 x 10-3
As = * b * d
= 1,168 x 10-3 * 100 * 8,5
= 0,993
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,993
0,8 m
Bidang 14A
2,25 m
Ly / Lx = 2,25 / 0,8 = 2,8 c = 63,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 63,5 / 1000 ) * 968,8 * 0,802
= 39,372 kg.m/m = 3937,2 kg.cm/m
Rn
Setiawan (022113178)
= Mu / ( * 0,85 * fc * b * d2 )
II - 43
Struktur Beton 2
= 3937,2 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
= 0,003
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,003
= 0,003
= ( * 0,85 * fc ) / fy
= ( 0,003 * 0,85 * 300 ) / 2400
= 3,188 x 10-4
As = * b * d
= 3,188 x 10-4 * 100 * 8,5
= 0,270
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,270
2,25 m
Bidang 15A
3,00 m
Ly / Lx = 3,00 / 2,25 = 1,3 c = 38
Mu = ( c / 1000 ) * qU * Lx2
Setiawan (022113178)
II - 44
Struktur Beton 2
= ( 38 / 1000 ) * 968,8 * 2,252
= 186,373 kg.m/m = 18637,3 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,013
= 0,013
= ( * 0,85 * fc ) / fy
= ( 0,013 * 0,85 * 300 ) / 2400
= 1,381 x 10-3
As = * b * d
= 1,381 x 10-3 * 100 * 8,5
= 1,174
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,174
1,20 m
Bidang 16A
II - 45
Setiawan (022113178)
2,83 m
Struktur Beton 2
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,006
= 0,006
= ( * 0,85 * fc ) / fy
= ( 0,006 * 0,85 * 300 ) / 2400
= 6,375 x 10-4
As = * b * d
= 6,375 x 10-4 * 100 * 8,5
= 0,542
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,542
Bidang 18A
Setiawan (022113178)
II - 46
3,50 m
Struktur Beton 2
4,15 m
Ly / Lx = 4,15 / 2,20 = 1,2 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 3,502
= 403,505 kg.m/m = 40350,5 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,027
= 0,027
= ( * 0,85 * fc ) / fy
= ( 0,027 * 0,85 * 300 ) / 2400
= 2,869 x 10-3
As = * b * d
= 2,869 x 10-3 * 100 * 8,5
= 2,438
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
2,438
II - 47
Struktur Beton 2
= 32,195 cm 25 cm
3,20 m
Bidang 19A
3,50 m
Ly / Lx = 3,50 / 3,20 = 1,1 c = 29,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 29,5 / 1000 ) * 968,8 * 3,202
= 292,655 kg.m/m = 29265,5 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,019
= 0,019
= ( * 0,85 * fc ) / fy
= ( 0,019 * 0,85 * 300 ) / 2400
= 2,019 x 10-3
As = * b * d
Setiawan (022113178)
II - 48
Struktur Beton 2
= 2,019 x 10-3 * 100 * 8,5
= 1,716
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,716
1,50 m
Bidang 27A
2,075 m
Ly / Lx = 2,075 / 1,50 = 1,4 c = 42
Mu = ( c / 1000 ) * qU * Lx2
= ( 42 / 1000 ) * 968,8 * 1,502
= 91,552 kg.m/m = 9155,2 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 9155,2 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
= 0,006
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,006
= 0,006
Setiawan (022113178)
II - 49
Struktur Beton 2
= ( * 0,85 * fc ) / fy
= ( 0,006 * 0,85 * 300 ) / 2400
= 6,375 x 10-4
As = * b * d
= 6,375 x 10-4 * 100 * 8,5
= 0,542
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,542
2,00 m
Bidang 28A
2,133 m
Ly / Lx = 2,133 / 2,00 = 1,1 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 2,1332
= 149,863 kg.m/m = 14986,3 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 14986,3 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
= 0,010
Setiawan (022113178)
II - 50
Struktur Beton 2
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,010
= 0,010
= ( * 0,85 * fc ) / fy
= ( 0,010 * 0,85 * 300 ) / 2400
= 1,063 x 10-3
As = * b * d
= 1,063 x 10-3 * 100 * 8,5
= 0,903
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,903
Setiawan (022113178)
II - 51
Struktur Beton 2
Setiawan (022113178)
II - 52
Struktur Beton 2
c)
1,5 m
Bidang 5A
2,5 m
Ly / Lx = 2,5 / 1,5
= 1,7 c = 51
Mu = ( c / 1000 ) * qU * Lx2
= ( 51 / 1000 ) * 968,8 * 1,502
= 111,169 kg.m/m = 11116,9 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,007
= 0,007
= ( * 0,85 * fc ) / fy
= ( 0,007 * 0,85 * 300 ) / 2400
Setiawan (022113178)
II - 53
Struktur Beton 2
= 7,438 x 10-4
As = * b * d
= 7,438 x 10-4 * 100 * 8,5
= 5,373
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
5,373
2,50 m
Bidang 6A
4,15 m
Ly / Lx = 4,15 / 2,50 = 1,7 c = 51
Mu = ( c / 1000 ) * qU * Lx2
= ( 51 / 1000 ) * 968,8 * 2,502
= 308,805 kg.m/m = 30880,5 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 30880,5 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
= 0,021
Setiawan (022113178)
= 1 - 1 2 * Rn
II - 54
Struktur Beton 2
= 1 - 1 2 * 0,021
= 0,021
= ( * 0,85 * fc ) / fy
= ( 0,021 * 0,85 * 300 ) / 2400
= 2,231 x 10-3
As = * b * d
= 2,231 x 10-3 * 100 * 8,5
= 1,896
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,896
2,50 m
Bidang 7A
3,2 m
Ly / Lx = 3,2 / 2,50 = 1,3 c = 38
Mu = ( c / 1000 ) * qU * Lx2
Setiawan (022113178)
II - 55
Struktur Beton 2
= ( 38 / 1000 ) * 968,8 * 2,502
= 230,09 kg.m/m = 23009 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,016
= 0,016
= ( * 0,85 * fc ) / fy
= ( 0,016 * 0,85 * 300 ) / 2400
= 1,7 x 10-3
As = * b * d
= 1,7 x 10-3 * 100 * 8,5
= 1,445
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,445
1,25 m
Bidang 8A
II - 56
Setiawan (022113178)
1,50 m
Struktur Beton 2
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,003
= 0,003
= ( * 0,85 * fc ) / fy
= ( 0,003 * 0,85 * 300 ) / 2400
= 3,188 x 10-4
As = * b * d
= 3,188 x 10-4 * 100 * 8,5
= 0,271
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,271
Setiawan (022113178)
II - 57
Struktur Beton 2
1,25 m
Bidang 9A
1,33 m
Ly / Lx = 1,33 / 1,25 = 1,1 c = 29,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 29,5 / 1000 ) * 968,8 * 1,332
= 50,554 kg.m/m = 5055,4 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,003
= 0,003
= ( * 0,85 * fc ) / fy
= ( 0,003 * 0,85 * 300 ) / 2400
= 3,188 x 10-4
As = * b * d
= 3,188 x 10-4 * 100 * 8,5
= 0,271
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,271
II - 58
Struktur Beton 2
Jarak = 100 / 0,345
= 289,855 cm 275 cm
2,83 m
Bidang 10A
3,60 m
Ly / Lx = 3,60 / 2,83 = 1, c = 38
Mu = ( c / 1000 ) * qU * Lx2
= ( 38 / 1000 ) * 968,8 * 2,832
= 294,843 kg.m/m = 29484,3 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,020
= 0,020
= ( * 0,85 * fc ) / fy
= ( 0,020 * 0,85 * 300 ) / 2400
= 2,125 x 10-3
Setiawan (022113178)
II - 59
Struktur Beton 2
As = * b * d
= 2,125 x 10-3 * 100 * 8,5
= 1,806
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,806
3,60 m
Bidang 11A
4,15 m
Ly / Lx = 4,15 / 3,600 = 1,2 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 3,602
= 426,892 kg.m/m = 42689,2 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 42689,2 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
= 0,028
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,028
Setiawan (022113178)
II - 60
Struktur Beton 2
= 0,028
= ( * 0,85 * fc ) / fy
= ( 0,028 * 0,85 * 300 ) / 2400
= 3,305 x 10-3
As = * b * d
= 3,305 x 10-3 * 100 * 8,5
= 2,809
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
2,809
1,4 m
Bidang 12A
2,7 m
Ly / Lx = 4,15 / 2,20 = 1,9 c = 55,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 55,5 / 1000 ) * 968,8 * 1,402
= 105,386 kg.m/m = 10538,6 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 10538,6 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
Setiawan (022113178)
II - 61
Struktur Beton 2
= 0,007
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,007
= 0,007
= ( * 0,85 * fc ) / fy
= ( 0,007 * 0,85 * 300 ) / 2400
= 7,437 x 10-4
As = * b * d
= 7,437 x 10-4 * 100 * 8,5
= 0,632
Ab = * * d2
Untuk tulangan 10 mm
= 0,785
As
0,632
2,25 m
Bidang 13A
2,6 m
Ly / Lx = 2,60 / 2,25 = 1,2 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 2,252
Setiawan (022113178)
II - 62
Struktur Beton 2
= 166,755 kg.m/m = 16675,5 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,011
= 0,011
= ( * 0,85 * fc ) / fy
= ( 0,011 * 0,85 * 300 ) / 2400
= 1,168 x 10-3
As = * b * d
= 1,168 x 10-3 * 100 * 8,5
= 0,993
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,993
0,8 m
Bidang 14A
Setiawan (022113178)
2,25 m
II - 63
Struktur Beton 2
Ly / Lx = 2,25 / 0,8
= 2,8 c = 63,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 63,5 / 1000 ) * 968,8 * 0,802
= 39,372 kg.m/m = 3937,2 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,003
= 0,003
= ( * 0,85 * fc ) / fy
= ( 0,003 * 0,85 * 300 ) / 2400
= 3,188 x 10-4
As = * b * d
= 3,188 x 10-4 * 100 * 8,5
= 0,270
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,270
2,25 m
Bidang 15A
II - 64
Setiawan (022113178)
3,00 m
Struktur Beton 2
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,013
= 0,013
= ( * 0,85 * fc ) / fy
= ( 0,013 * 0,85 * 300 ) / 2400
= 1,381 x 10-3
As = * b * d
= 1,381 x 10-3 * 100 * 8,5
= 1,174
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,174
II - 65
Struktur Beton 2
1,20 m
Bidang 16A
2,83 m
Ly / Lx = 2,83 / 1,20 = 2,4 c = 60
Mu = ( c / 1000 ) * qU * Lx2
= ( 60 / 1000 ) * 968,8 * 1,202
= 83,704 kg.m/m = 8370,4 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,006
= 0,006
= ( * 0,85 * fc ) / fy
= ( 0,006 * 0,85 * 300 ) / 2400
= 6,375 x 10-4
As = * b * d
= 6,375 x 10-4 * 100 * 8,5
= 0,542
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
Setiawan (022113178)
II - 66
Struktur Beton 2
As
0,542
3,50 m
Bidang 18A
4,15 m
Ly / Lx = 4,15 / 2,20 = 1,2 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 3,502
= 403,505 kg.m/m = 40350,5 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,027
= 0,027
= ( * 0,85 * fc ) / fy
= ( 0,027 * 0,85 * 300 ) / 2400
Setiawan (022113178)
II - 67
Struktur Beton 2
= 2,869 x 10-3
As = * b * d
= 2,869 x 10-3 * 100 * 8,5
= 2,438
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
2,438
3,20 m
Bidang 19A
3,50 m
Ly / Lx = 3,50 / 3,20 = 1,1 c = 29,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 29,5 / 1000 ) * 968,8 * 3,202
= 292,655 kg.m/m = 29265,5 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 29265,5 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
= 0,019
Setiawan (022113178)
= 1 - 1 2 * Rn
II - 68
Struktur Beton 2
= 1 - 1 2 * 0,019
= 0,019
= ( * 0,85 * fc ) / fy
= ( 0,019 * 0,85 * 300 ) / 2400
= 2,019 x 10-3
As = * b * d
= 2,019 x 10-3 * 100 * 8,5
= 1,716
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,716
1,50 m
Bidang 27A
2,075 m
Ly / Lx = 2,075 / 1,50 = 1,4 c = 42
Mu = ( c / 1000 ) * qU * Lx2
= ( 42 / 1000 ) * 968,8 * 1,502
= 91,552 kg.m/m = 9155,2 kg.cm/m
Rn
Setiawan (022113178)
= Mu / ( * 0,85 * fc * b * d2 )
II - 69
Struktur Beton 2
= 9155,2 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
= 0,006
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,006
= 0,006
= ( * 0,85 * fc ) / fy
= ( 0,006 * 0,85 * 300 ) / 2400
= 6,375 x 10-4
As = * b * d
= 6,375 x 10-4 * 100 * 8,5
= 0,542
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,542
2,00 m
Bidang 28A
2,133 m
Ly / Lx = 2,133 / 2,00 = 1,1 c = 34
Mu = ( c / 1000 ) * qU * Lx2
Setiawan (022113178)
II - 70
Struktur Beton 2
= ( 34 / 1000 ) * 968,8 * 2,1332
= 149,863 kg.m/m = 14986,3 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,010
= 0,010
= ( * 0,85 * fc ) / fy
= ( 0,010 * 0,85 * 300 ) / 2400
= 1,063 x 10-3
As = * b * d
= 1,063 x 10-3 * 100 * 8,5
= 0,903
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,903
Setiawan (022113178)
II - 71
Struktur Beton 2
Setiawan (022113178)
II - 72
Struktur Beton 2
1,5 m
Bidang 5A
2,5 m
Ly / Lx = 2,5 / 1,5
= 1,7 c = 51
Mu = ( c / 1000 ) * qU * Lx2
= ( 51 / 1000 ) * 968,8 * 1,502
= 111,169 kg.m/m = 11116,9 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 11116,9 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
= 0,007
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,007
= 0,007
Setiawan (022113178)
II - 73
Struktur Beton 2
= ( * 0,85 * fc ) / fy
= ( 0,007 * 0,85 * 300 ) / 2400
= 7,438 x 10-4
As = * b * d
= 7,438 x 10-4 * 100 * 8,5
= 5,373
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
5,373
2,50 m
Bidang 6A
4,15 m
Ly / Lx = 4,15 / 2,50 = 1,7 c = 51
Mu = ( c / 1000 ) * qU * Lx2
= ( 51 / 1000 ) * 968,8 * 2,502
= 308,805 kg.m/m = 30880,5 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 30880,5 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
= 0,021
Setiawan (022113178)
II - 74
Struktur Beton 2
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,021
= 0,021
= ( * 0,85 * fc ) / fy
= ( 0,021 * 0,85 * 300 ) / 2400
= 2,231 x 10-3
As = * b * d
= 2,231 x 10-3 * 100 * 8,5
= 1,896
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,896
2,50 m
Bidang 7A
3,2 m
Ly / Lx = 3,2 / 2,50 = 1,3 c = 38
Mu = ( c / 1000 ) * qU * Lx2
Setiawan (022113178)
II - 75
Struktur Beton 2
= ( 38 / 1000 ) * 968,8 * 2,502
= 230,09 kg.m/m = 23009 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,016
= 0,016
= ( * 0,85 * fc ) / fy
= ( 0,016 * 0,85 * 300 ) / 2400
= 1,7 x 10-3
As = * b * d
= 1,7 x 10-3 * 100 * 8,5
= 1,445
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,445
1,25 m
Bidang 8A
II - 76
Setiawan (022113178)
1,50 m
Struktur Beton 2
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,003
= 0,003
= ( * 0,85 * fc ) / fy
= ( 0,003 * 0,85 * 300 ) / 2400
= 3,188 x 10-4
As = * b * d
= 3,188 x 10-4 * 100 * 8,5
= 0,271
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,271
Bidang 9A
Setiawan (022113178)
II - 77
1,25 m
Struktur Beton 2
1,33 m
Ly / Lx = 1,33 / 1,25 = 1,1 c = 29,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 29,5 / 1000 ) * 968,8 * 1,332
= 50,554 kg.m/m = 5055,4 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,003
= 0,003
= ( * 0,85 * fc ) / fy
= ( 0,003 * 0,85 * 300 ) / 2400
= 3,188 x 10-4
As = * b * d
= 3,188 x 10-4 * 100 * 8,5
= 0,271
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,271
II - 78
Struktur Beton 2
= 289,855 cm 275 cm
2,83 m
Bidang 10A
3,60 m
Ly / Lx = 3,60 / 2,83 = 1, c = 38
Mu = ( c / 1000 ) * qU * Lx2
= ( 38 / 1000 ) * 968,8 * 2,832
= 294,843 kg.m/m = 29484,3 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,020
= 0,020
= ( * 0,85 * fc ) / fy
= ( 0,020 * 0,85 * 300 ) / 2400
= 2,125 x 10-3
As = * b * d
= 2,125 x 10-3 * 100 * 8,5
= 1,806
Untuk tulangan 10 mm
Setiawan (022113178)
Ab = * * d2
II - 79
Struktur Beton 2
= 0,785
As
1,806
3,60 m
Bidang 11A
4,15 m
Ly / Lx = 4,15 / 3,600 = 1,2 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 3,602
= 426,892 kg.m/m = 42689,2 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,028
= 0,028
= ( * 0,85 * fc ) / fy
Setiawan (022113178)
II - 80
Struktur Beton 2
= ( 0,028 * 0,85 * 300 ) / 2400
= 3,305 x 10-3
As = * b * d
= 3,305 x 10-3 * 100 * 8,5
= 2,809
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
2,809
1,4 m
Bidang 12A
2,7 m
Ly / Lx = 4,15 / 2,20 = 1,9 c = 55,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 55,5 / 1000 ) * 968,8 * 1,402
= 105,386 kg.m/m = 10538,6 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 10538,6 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
= 0,007
Setiawan (022113178)
II - 81
Struktur Beton 2
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,007
= 0,007
= ( * 0,85 * fc ) / fy
= ( 0,007 * 0,85 * 300 ) / 2400
= 7,437 x 10-4
As = * b * d
= 7,437 x 10-4 * 100 * 8,5
= 0,632
Ab = * * d2
Untuk tulangan 10 mm
= 0,785
As
0,632
2,25 m
Bidang 13A
2,6 m
Ly / Lx = 2,60 / 2,25 = 1,2 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 2,252
= 166,755 kg.m/m = 16675,5 kg.cm/m
Setiawan (022113178)
II - 82
Struktur Beton 2
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,011
= 0,011
= ( * 0,85 * fc ) / fy
= ( 0,011 * 0,85 * 300 ) / 2400
= 1,168 x 10-3
As = * b * d
= 1,168 x 10-3 * 100 * 8,5
= 0,993
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,993
0,8 m
Bidang 14A
2,25 m
Ly / Lx = 2,25 / 0,8 = 2,8 c = 63,5
Setiawan (022113178)
II - 83
Struktur Beton 2
Mu = ( c / 1000 ) * qU * Lx2
= ( 63,5 / 1000 ) * 968,8 * 0,802
= 39,372 kg.m/m = 3937,2 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,003
= 0,003
= ( * 0,85 * fc ) / fy
= ( 0,003 * 0,85 * 300 ) / 2400
= 3,188 x 10-4
As = * b * d
= 3,188 x 10-4 * 100 * 8,5
= 0,270
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,270
2,25 m
Bidang 15A
II - 84
Setiawan (022113178)
3,00 m
Struktur Beton 2
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,013
= 0,013
= ( * 0,85 * fc ) / fy
= ( 0,013 * 0,85 * 300 ) / 2400
= 1,381 x 10-3
As = * b * d
= 1,381 x 10-3 * 100 * 8,5
= 1,174
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,174
Setiawan (022113178)
II - 85
Struktur Beton 2
1,20 m
Bidang 16A
2,83 m
Ly / Lx = 2,83 / 1,20 = 2,4 c = 60
Mu = ( c / 1000 ) * qU * Lx2
= ( 60 / 1000 ) * 968,8 * 1,202
= 83,704 kg.m/m = 8370,4 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,006
= 0,006
= ( * 0,85 * fc ) / fy
= ( 0,006 * 0,85 * 300 ) / 2400
= 6,375 x 10-4
As = * b * d
= 6,375 x 10-4 * 100 * 8,5
= 0,542
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,542
II - 86
Struktur Beton 2
Jarak = 100 / 0,690
= 144,927 cm 150 cm
3,50 m
Bidang 18A
4,15 m
Ly / Lx = 4,15 / 2,20 = 1,2 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 3,502
= 403,505 kg.m/m = 40350,5 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,027
= 0,027
= ( * 0,85 * fc ) / fy
= ( 0,027 * 0,85 * 300 ) / 2400
= 2,869 x 10-3
As = * b * d
= 2,869 x 10-3 * 100 * 8,5
= 2,438
Setiawan (022113178)
II - 87
Struktur Beton 2
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
2,438
3,20 m
Bidang 19A
3,50 m
Ly / Lx = 3,50 / 3,20 = 1,1 c = 29,5
Mu = ( c / 1000 ) * qU * Lx2
= ( 29,5 / 1000 ) * 968,8 * 3,202
= 292,655 kg.m/m = 29265,5 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 29265,5 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
= 0,019
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,019
= 0,019
Setiawan (022113178)
II - 88
Struktur Beton 2
= ( * 0,85 * fc ) / fy
= ( 0,019 * 0,85 * 300 ) / 2400
= 2,019 x 10-3
As = * b * d
= 2,019 x 10-3 * 100 * 8,5
= 1,716
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
1,716
1,50 m
Bidang 27A
2,075 m
Ly / Lx = 2,075 / 1,50 = 1,4 c = 42
Mu = ( c / 1000 ) * qU * Lx2
= ( 42 / 1000 ) * 968,8 * 1,502
= 91,552 kg.m/m = 9155,2 kg.cm/m
Rn
= Mu / ( * 0,85 * fc * b * d2 )
= 9155,2 / ( 0,8 * 0,85 * 300 * 100 * 8,52 )
Setiawan (022113178)
II - 89
Struktur Beton 2
= 0,006
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,006
= 0,006
= ( * 0,85 * fc ) / fy
= ( 0,006 * 0,85 * 300 ) / 2400
= 6,375 x 10-4
As = * b * d
= 6,375 x 10-4 * 100 * 8,5
= 0,542
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,542
2,00 m
Bidang 28A
2,133 m
Ly / Lx = 2,133 / 2,00 = 1,1 c = 34
Mu = ( c / 1000 ) * qU * Lx2
= ( 34 / 1000 ) * 968,8 * 2,1332
Setiawan (022113178)
II - 90
Struktur Beton 2
= 149,863 kg.m/m = 14986,3 kg.cm/m
= Mu / ( * 0,85 * fc * b * d2 )
Rn
= 1 - 1 2 * Rn
= 1 - 1 2 * 0,010
= 0,010
= ( * 0,85 * fc ) / fy
= ( 0,010 * 0,85 * 300 ) / 2400
= 1,063 x 10-3
As = * b * d
= 1,063 x 10-3 * 100 * 8,5
= 0,903
Untuk tulangan 10 mm
Ab = * * d2
= 0,785
As
0,903
Setiawan (022113178)
II - 91
Struktur Beton 2
Setiawan (022113178)
II - 92